Experiences with SAP Quality Award –
Project B2B Ecommerce @ HANA
April 26, 2016
Günther Lanner - Senior Technology Consultant
TEC 237 – Günther Lanner
Agenda
Project Review
Key Challenges and Success Factors
Follow Up Projects
What did the quality award change?
Project Introduction
TEC 237 – Günther Lanner
Introduction of the Swarovski B2B E-Commerce Platform
TEC 237 – Günther Lanner
Initial Situation
The initial situation is...
• General Performance issues in the Catalogue (Navigation, Attribute Values,
Stock Information, …), but also in calling ERP functions
• Risk and instability with current set-up for Catalogue usage with SAP Shared
Memory Technology
• B2B shop scenario is the best starting scenario at the moment for getting
experience with SAP HANA (benefits for IT and Business)
TEC 237 – Günther Lanner
Project Goals
Objective KPI Target Value
General high availability of Web Shop (reduction of
downtimes because of shared memory issues, …)
System
Availability via SIL
99.9% (excluding Maintenance
Windows)
Performance improvement – comparison of response times
before and after HANA
Response
timeSignificant improvement
Possibility to switch between HANA and old shop even for
specific Customers/Businesses only sidecar installation
possible
Switch back
time15 min.
Generally reduce Complexity (especially in the area of
catalogue maintenance) IT Maintenance effort Reduction by 10 % p.a.
TEC 237 – Günther Lanner
2014
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Project Schedule Overview Legend:
Project Preparation
HW vendor decision, purchase
HW/SW installation and synch
test system
Development for Catalogue +
Testing
HW/SW installation and synch
productive system
Gate for decision
about further
developments and
purchase of
productive HW.
DoneMilestone Go LivePhase
Efforts (PD) by end of September 2014
Internal External
Development / Testing 110 8
Project Management, SLT,
Infrastructure and Basis tasks
130 14
TEC 237 – Günther Lanner
System Architecture (Sidecar Approach)
Results
TEC 237 – Günther Lanner
Performance examples – B2B shop catalogue navigationCollection / Round stones
* Analyzed with SAP Solution Manager EEM in Productive System after Go Live
TEC 237 – Günther Lanner
Performance examples – B2B shop catalogue navigationclick on stone 1088 and select color and size
* Analyzed with SAP Solution Manager EEM in Productive System after Go Live
TEC 237 – Günther Lanner
Performance examples – B2B shop searchsearch for an article list (a few hundred selective articles)
* Analyzed with SAP Solution Manager EEM in Productive System after Go Live
Key Challenges and Success
Factors
TEC 237 – Günther Lanner
Key Challenges and Success Factors
Key challenges faced
Get familiar with HANA, as this was our first HANA implementation we had a lot of
things to learn do a start workshops, involve several SAP experts
Replication of data was also very challenging, to find the tradeoff between source
systems influence and an acceptable latency time
Information to all relevant stakeholders, as SAP HANA is a topic with max
attention from all areas (IT colleagues from application and infrastructure teams,
business, and also SAP) stakeholder analysis and communication plan, several
info presentations
TEC 237 – Günther Lanner
Key Challenges and Success Factors
Key lessons learnt
What went well?
Objectives were achieved; less technical issues with HANA than expected; Especially
stability could now be achieved with HANA (live since 18 months – only one minor issue)
Project was managed professionally – information flow was sufficient;
Project Team was highly motivated and eager to work with HANA and achieve great results.
What could be improved?
Too many experts from SAP involved; (some were less experts than expected and some
only in a particular area). Next time better to have SAP consultants with a broader Know
How.
Significant PM efforts because of new technology and high management / stakeholder
(SAP) attention
Improvement is possible, also in areas we thought it was not possible (e.g. ABAP
performance improvement)
TEC 237 – Günther Lanner
Key Challenges and Success Factors
Key contributors to the success of your project
Involve all stakeholders during the project
Detailed project planning and controlling
SCRUM as success factor for the developments/testing part of the project
Doing an assessment with SAP before project start which included:
Collect business requirements and calculate a business case
Define technical requirements by workshops with SAP and some customer reference visits
Follow up projects
TEC 237 – Günther Lanner
Follow up projects
• CRM on HANA 2015
• POC for ERP (+ S/4 HANA Finance) and ERP on HANA in autumn 2015
• ERP and BW migration w/o any major problems
• Simple finance migration ended with some 100.000 erros which neeed to be corrected in a followup
project in 2016
• ERP on HANA Go Live in May 2016
• BW on HANA Go Live in June 2016
• New systems will be installed on HANA
• Midterm all SAP systems on HANA
What did the quality award
change?
TEC 237 – Günther Lanner
What did the quality award change?
• Establish the PM approach for all further HANA projects, esp. the stakeholder
analysis and communication matrix
• Communication is now done in a better and more efficient way. Important because SAP HANA has a
very high attention in our company
• SAP AGS involvement is standard procedure now
• Further rollout of SCRUM
• More business awareness for HANA, potential for further HANA business projects
• Motivation of project team
• Further quality awards participation planned
• Project leader has now lots of followup projects to choose of ;-)
TEC 237 – Günther Lanner