TRANSCRIPT

Page 1: Expenditure   some topics
Page 2: Expenditure   some topics

Measurement Book, On

account bills, Contractors

Ledger & Works Register

2

ByM.Nageswara Rao,

Sr.SO(A)/SC

Page 3: Expenditure   some topics

Maintenance of Measurement Book-para E1322

The pages of the book should be machine-numbered

no page should on any account be torn out, nor should any entry be erased or deffaced so as to be illegible

.If mistake be made, it should be corrected by crossing out the incorrect words or figures, and rewriting the correct words or figures, and the correction thus made should be initialed.

Page 4: Expenditure   some topics

Maintenance of Measurement Book-para E1322

The entries must be made directly in the measurement books at the site of work.

The copying of entries from another rough note book or similar record is strictly forbidden.

A reliable record is the object to be aimed at, as it may have to be produced as evidence in a Court of Law.

The entries must be made directly in the measurement books at the site of work.

The copying of entries from another rough note book or similar record is strictly forbidden.

A reliable record is the object to be aimed at, as it may have to be produced as evidence in a Court of Law.

Page 5: Expenditure   some topics

Maintenance of Measurement Book-para E1323

The entries in the "contents or area" column should, however, be invariably made in ink.

Page 6: Expenditure   some topics

Maintenance of Measurement Book-para E1324

• Entries should be recorded continuously in the measurement book.

Page 7: Expenditure   some topics

On Account Bill

Form No. E-1337

For use in Contract works only, not supplies of

materials.

On account means , before completion of the final

work.

Page 8: Expenditure   some topics

On Account Bill

Form No. E-1337

For use in Contract works only, not supplies of materials.

On account means , before completion of the final work.

Page 9: Expenditure   some topics

Passing of Contractor’s Bills1. Agmt should be vetted by SSO/A of finance section.

3. The items and amounts claimed are in accordance with the Schedule of contract

Page 10: Expenditure   some topics

Passing of Contractor’s Bills5. Contractor has signed duly accepting the measurements recorded.

6. Test check - The measurements recorded by the suboridnates are test checked by the Exe.Engineers.

Page 11: Expenditure   some topics

Passing of Contractor’s Bills7. Competent authority has approved and signed the Bill.

8. Necessary deductions incl: Income Tax are made in the Bill.

9. Variations in the Schedule quantity(beyond permissible limits) if any are concurred by Finance and sanctioned by Competent authority.

Page 12: Expenditure   some topics

Passing of Contractor’s Bills10. Prescribed form, are written in ink and are in original,

11. Total in words and figures,

12.No erasures and alterations, if any attested as many times as they are made,

Page 13: Expenditure   some topics

Passing of Contractor’s Bills13. Certify services for which payment is claimed actually rendered.

14.Correct allocation is furnished in the bill

15.Income tax deductions where applicable

Page 14: Expenditure   some topics

Enclosures to the Bill

Orignial W.O./P.O./Agreement/subsidary agt./MOU vetted by Finance

MOS – Designation and reference of authority ie item of SOP etc.

Copy of finance concurrence, wherever necessary..

Amendment to the purchase order, if any by competent authority.

Page 15: Expenditure   some topics

Enclosures to the Bill

Delivery date extension for material/equipment by competent authority.

Original 'Misc. Cash Receipt (MCR)' for release of EMD and S.D.

Specimen Signature of Bill Drawing Officer

Page 16: Expenditure   some topics

Contractor’s Ledger

It is a personal account of the Contractor

Records all the payments made to the Contractor and the quantity of the work executed.

Page 17: Expenditure   some topics

Contractor’s Ledger

Form No. E-1483It should be closed and balanced monthly

Page 18: Expenditure   some topics

Contractors Ledger – F-1483- An example

Dr. DEBITS Cr. CREDITSDate Particulars Amt.

(Rs.)Date Particulars Amt.

(Rs.)01.01.15 To Advance payment 10000 10.01.15 By Quantity of work

done20000

05.01.15 To Materials provided 5000

18.01.15 To On A/c Bill No.01 2000

31.01.15 Closing Balance c/d 3000

Total for Jan 15 20000 Total for Jan 15 20000

01.02.15 Opening Balance B/d 3000

Page 19: Expenditure   some topics

Contractors Ledger

The accounts of each contractor is covers one or several works pertains to him

Page 20: Expenditure   some topics

Contractors Ledger

A copy of his account in the Ledger may be furnished to Contractor on

request.

On completion of Contract, Contractors account should be

closed without delay

Page 21: Expenditure   some topics

If contractor declines to accept final payment ?

The final payment should be credited to “Deposit Misc”, if Contractor delays to receive final payment for more than one month.

Asked to state his objections in writing.

Warned that no claim to interest would be admitted by Railways.

Page 22: Expenditure   some topics

If contractor declines to accept final payment ?

The objections raised or claims put forward by contractors should be investigated and settled with reasonable period.

If investigation is prolonged due to obstructive tactics on part of contractor, railways should refer the matter to arbitration as provided in the Contracts.

Page 23: Expenditure   some topics

Works Register

Objects

Control of Expenditure

w.r.t Estimates

Budgetary control by comparison between

Grant allotted and expenditure incurred

To spot any material modification

occurred

Page 24: Expenditure   some topics

Works Register- Is a collective record of expenditure

At the end of every month, the register should be totalled up the 1.Monthly 2. yearly & 3. “Up-to –date” totals for each work struck.

Page 25: Expenditure   some topics

Works Register- Form No – E-1473

At the end of every month, the register should be totalled up the 1.Monthly 2. yearly & 3. “Up-to –date” totals for each work struck.

Page 26: Expenditure   some topics

Works Register

Last column always “TOTAL CHARGES”

Last but one column always “ Value of materials recd. In advance of payment to Contractors”

Page 27: Expenditure   some topics

Works Register

Last column but two will show the value of the “Materials at site”

Last column but three will show” advance payment for supply of materials”

Page 28: Expenditure   some topics

Works Register – F-1473 – pro forma

• Form E.1473• .............................Railway• WORKS REGISTER • Name of work ...............• Authority ................…….• Capital........... .Rs. case……………Rs…………. Budget allotment for the year• Depreciation Fund.............................Rs. Stores.................. Rs. Original

Estimate No…………..• Development Fund .......................... Rs. Total ....................Rs. Revised Estimate

No....• Accident Compensation............................• Passenger Amenities Fund ................... ......• Open Line Works Revenue ................• Revenue ................. Rs.

Page 29: Expenditure   some topics

Works Register – F-1473 – pro formaDate of Commencement__________________

Date of completion _____________________

Items of Estimate Head of Accounts

Date No. of Vr..

Particulars

Amt. Amt. Amt Capital DRF DF Rev.

Advance payment for supply of materials.

Materials at site Value of materials received in advance of payment of contractor

Total Charges

Page 30: Expenditure   some topics