mliveexisting trees / bushes legend fence historical river channel location notes huron river bank...

1
EXISTING TREES / BUSHES LEGEND FENCE HISTORICAL RIVER CHANNEL LOCATION NOTES HURON RIVER BANK EXISTING MONITORING WELL LOCATION AND NUMBER 1. BASE MAP DEVELOPED FROM SITE PLAN PROVIDED BY MICHCON, DATED OCTOBER 2007 AND UPDATED USING AERIAL PHOTOS AND DATA FROM A LIMITED SITE SURVEY CONDUCTED IN JUNE 2009, APRIL 2010, AND JULY 2011 (NAVD88), AND SITE TOPO DATED AUGUST 2011. 2. OFF-SITE FEATURES ARE DEPICTED CONCEPTUALLY. RIVER WIDTH AND BOUNDARY APPROXIMATE. 3. PLANTING ZONE A TO BE SEEDED AND PLANTED WITH SHRUBS, SEDGES AND GRASSES. SEE SPECIFICATIONS ON SHEET 17. 4. PLANTING ZONE B TO BE SEEDED AND PLANTED WITH NATIVE TREES AND OTHER LARGE ROOT STRUCTURE PLANTS. SEE SPECIFICATIONS ON SHEET 17. 5. SEE SEEDING, ROAD GRAVEL , RIP RAP AND PLANTING SECTIONS IN SPECIFICATIONS ON SHEETS 16 AND 17. 6. APPROXIMATE LOCATION OF WHITEWATER FEATURES AS PLANNED BY THE CITY OF ANN ARBOR. 7. SALVAGED FENCE TO BE INSTALLED FROM EXISTING FENCE TO EDGE OF RIVER. POSTS TO BE INSTALLED MAXIMUM 1-FOOT DEEP OVER CAP AREA. FENCE POST INSTALLATION CANNOT PENETRATE SELECT CRUSHED STONE BED. 8. EROSION CONTROL AND REVEGETATIVE MAT TO BE INSTALLED FROM THE UPSLOPE EDGE OF RIP RAP TO THE DOWNSLOPE EDGE OF PLANTING ZONE B AS WELL AS ANY DISTURBED AREA WITHOUT RIP RAP WITHIN 30' OF THE RIVER BANK AS SHOWN ON THIS DRAWING. SEE DETAIL 1, SHEET 14. 9. ALL DISTURBED AREAS MUST BE STABILIZED WITH SEEDING OR AGGREGATE IN ACCORDANCE WITH SOIL EROSION CONTROL PERMIT. 10. SEE DETAIL 6, SHEET 12 FOR NAPL TRAPPING CAP RESTORATION. 11. PERMANENT MARKERS TO BE MINIMUM 3' DIAMETER BOULDERS INSTALLED AS PART OF CAP RESTORATION. MW-6 RAILROAD TRACKS APPROXIMATE SITE BOUNDARY FORMER RAILROAD TRACKS (SPUR) APPROXIMATE CITY STORM DRAIN LOCATION SEEDING AREA OF NAPL TRAPPING CAP ROAD GRAVEL RIP RAP PLANTING ZONE A PLANTING ZONE B DETAIL NUMBER SHEET NUMBER 4 11 765 PROPOSED FINAL GRADE (5' CONTOUR) PROPOSED FINAL GRADE (1' CONTOUR) EXISTING GROUND SURFACE CONTOUR (5') EXISTING GROUND SURFACE CONTOUR (1') PERMANENT MARKER LOCATION EXISTING FLOOD PLAIN BOUNDARY APPROXIMATE EXISTING FLOOD PLAIN ELEVATION 766.8 DRAINAGE PATTERN See Note 10 APPROXIMATE LOCATION OF ORIGINAL HURON RIVER CHANNEL (FILLED ~1915) GATE TW-6R TW-2 W-3 TW-8 MW-1 TW-1 ET-04 ET-05 ET-06 W-7 TW-9 W-8 TW-11 MW-2 F L O W D I R E C T I O N FORMER SERVICE CENTER BUILDING FOUNDATION H U R O N R I V E R W-4 W-6 AMTRAK STATION ENTRANCE GATE FORMER MICHCON BROADWAY STREET MGP SITE TW-3 GATE SHEET PILE WALL DEPOT STREET NORTH 4th AVENUE ARGO DAM AMTRAK PARKING LOT (EASTERN PARCEL) (WESTERN PARCEL) GATE GATE DOCKING BAY W-10 ET-02 W-2 TW-5 TW-10 ALLEN CREEK DRAIN BROADWAY STREET ET-03 CONCRETE CONCRETE See Note 4 See Note 3 BACKFILL FOR PRE-EXISTING GRASSY AREAS (TYP) 3 11 BACKFILL FOR PRE-EXISTING PAVED AREAS (TYP) 4 11 MW-3 See Note 8 See Note 8 SALVAGED FENCE (See Note 7) 765 760 770 PERMANENT MARKER (See Note 11) BUILDING DECONSTRUCTED TO AVERAGE FOUNDATION ELEVATION OF 766.68'. INCREASED FLOODPLAIN STORAGE VOLUME ~55 CUBIC YARDS RIVERBANK GRADED PER DESIGN. NET INCREASED FLOODPLAIN STORAGE VOLUME ~1,155 CUBIC YARDS. 766.1 766.8 767.8 779.5 WHITEWATER FEATURE HURON RIVER STRUCTURE 2 (SEE NOTE 6) WHITEWATER FEATURE HURON RIVER STRUCTURE 1 (SEE NOTE 6) 0 APPROXIMATE SCALE IN FEET 50' 100' 150' 200' 1540 Eisenhower Place Ann Arbor, MI 48108 Phone: 734.971.7080 Fax: 734.971.9022 FILE NO. SCALE: DATE PRINTED: PROJ. NO. PROJECT: SHEET TITLE: DATE: DRAWN BY: CHECKED BY: APPROVED BY: REVISION DATE 2. 1. NO. 3. BY APP'D. APRIL 2012 AS INDICATED 192363.0000.01 FIGURE 10 FORMER MICHCON BROADWAY STREET MGP ANN ARBOR, MICHIGAN SITE RESTORATION PLAN DGS CWD VEB DGS 04/26/12 SITE PLAN FOR PLANNING COMMISSION REVIEW VEB

Upload: others

Post on 02-Feb-2021

1 views

Category:

Documents


0 download

TRANSCRIPT

  • EXISTING TREES / BUSHES

    LEGEND

    FENCE

    HISTORICAL RIVER CHANNEL LOCATION

    NOTES

    HURON RIVER BANK

    EXISTING MONITORING WELL LOCATION AND NUMBER

    1. BASE MAP DEVELOPED FROM SITE PLAN PROVIDED BY MICHCON, DATEDOCTOBER 2007 AND UPDATED USING AERIAL PHOTOS AND DATA FROM ALIMITED SITE SURVEY CONDUCTED IN JUNE 2009, APRIL 2010, AND JULY 2011(NAVD88), AND SITE TOPO DATED AUGUST 2011.

    2. OFF-SITE FEATURES ARE DEPICTED CONCEPTUALLY. RIVER WIDTH ANDBOUNDARY APPROXIMATE.

    3. PLANTING ZONE A TO BE SEEDED AND PLANTED WITH SHRUBS, SEDGES ANDGRASSES. SEE SPECIFICATIONS ON SHEET 17.

    4. PLANTING ZONE B TO BE SEEDED AND PLANTED WITH NATIVE TREES ANDOTHER LARGE ROOT STRUCTURE PLANTS. SEE SPECIFICATIONS ON SHEET 17.

    5. SEE SEEDING, ROAD GRAVEL , RIP RAP AND PLANTING SECTIONS INSPECIFICATIONS ON SHEETS 16 AND 17.

    6. APPROXIMATE LOCATION OF WHITEWATER FEATURES AS PLANNED BY THECITY OF ANN ARBOR.

    7. SALVAGED FENCE TO BE INSTALLED FROM EXISTING FENCE TO EDGE OFRIVER. POSTS TO BE INSTALLED MAXIMUM 1-FOOT DEEP OVER CAP AREA.FENCE POST INSTALLATION CANNOT PENETRATE SELECT CRUSHED STONEBED.

    8. EROSION CONTROL AND REVEGETATIVE MAT TO BE INSTALLED FROM THEUPSLOPE EDGE OF RIP RAP TO THE DOWNSLOPE EDGE OF PLANTING ZONE BAS WELL AS ANY DISTURBED AREA WITHOUT RIP RAP WITHIN 30' OF THERIVER BANK AS SHOWN ON THIS DRAWING. SEE DETAIL 1, SHEET 14.

    9. ALL DISTURBED AREAS MUST BE STABILIZED WITH SEEDING OR AGGREGATEIN ACCORDANCE WITH SOIL EROSION CONTROL PERMIT.

    10. SEE DETAIL 6, SHEET 12 FOR NAPL TRAPPING CAP RESTORATION.

    11. PERMANENT MARKERS TO BE MINIMUM 3' DIAMETER BOULDERS INSTALLEDAS PART OF CAP RESTORATION.

    MW-6

    RAILROAD TRACKS

    APPROXIMATE SITE BOUNDARY

    FORMER RAILROAD TRACKS (SPUR)

    APPROXIMATE CITY STORM DRAIN LOCATION

    SEEDING

    AREA OF NAPL TRAPPING CAP

    ROAD GRAVEL

    RIP RAP

    PLANTING ZONE A

    PLANTING ZONE B

    DETAIL NUMBER

    SHEET NUMBER

    411

    765 PROPOSED FINAL GRADE (5' CONTOUR)

    PROPOSED FINAL GRADE (1' CONTOUR)

    EXISTING GROUND SURFACE CONTOUR (5')

    EXISTING GROUND SURFACE CONTOUR (1') PERMANENT MARKER LOCATION

    EXISTING FLOOD PLAIN BOUNDARY

    APPROXIMATE EXISTING FLOODPLAIN ELEVATION

    766.8DRAINAGE PATTERN

    SeeNote 10

    APPROXIMATELOCATION OF

    ORIGINALHURON RIVER

    CHANNEL(FILLED ~1915)

    GATE

    TW-6R

    TW-2

    W-3

    TW-8

    MW-1

    TW-1

    ET-04

    ET-05

    ET-06

    W-7

    TW-9

    W-8

    TW-11

    MW-2

    F L O W D I R E C T I O N

    FORMERSERVICE CENTER

    BUILDINGFOUNDATION

    H U R O NR I V E

    R

    W-4

    W-6

    AMTR

    AK ST

    ATION

    ENTR

    ANCE

    GATE

    FORMER MICHCONBROADWAY STREET

    MGP SITE

    TW-3

    GAT

    E

    SHEET PILE WALL

    DEPOT STREET

    NORT

    H 4t

    h AV

    ENUE

    ARGO DAM

    AMTRAK PARKING LOT

    (EASTERN PARCEL)

    (WESTERN PARCEL)

    GATE

    GATE

    DOCKINGBAY

    W-10

    ET-02

    W-2

    TW-5

    TW-10

    ALLENCREEKDRAIN

    BROA

    DWAY

    STRE

    ET

    ET-03

    CONC

    RETE

    CONCRETE

    See Note 4

    See Note 3

    BACKFILL FORPRE-EXISTINGGRASSY AREAS (TYP)

    311

    BACKFILL FORPRE-EXISTING

    PAVED AREAS (TYP)

    411

    MW-3

    See Note 8

    See Note 8

    SALVAGEDFENCE

    (See Note 7)

    765

    760

    770

    PERMANENTMARKER

    (See Note 11)

    BUILDING DECONSTRUCTED TOAVERAGE FOUNDATION ELEVATION OF

    766.68'. INCREASED FLOODPLAINSTORAGE VOLUME ~55 CUBIC YARDS

    RIVERBANK GRADED PER DESIGN. NETINCREASED FLOODPLAIN STORAGE

    VOLUME ~1,155 CUBIC YARDS.

    766.1

    766.8

    767.8

    779.5

    WHITEWATERFEATURE HURONRIVER STRUCTURE 2(SEE NOTE 6)

    WHITEWATERFEATURE HURONRIVER STRUCTURE 1(SEE NOTE 6)

    0

    APPROXIMATE SCALE IN FEET

    50' 100' 150' 200' 1540 Eisenhower PlaceAnn Arbor, MI 48108Phone: 734.971.7080Fax: 734.971.9022

    FILE NO.

    SCALE:

    DATE PRINTED:

    PROJ. NO.

    PROJECT:

    SHEET TITLE:

    DATE:

    DRAWN BY:

    CHECKED BY:

    APPROVED BY:

    REVISIONDATE

    2.

    1.

    NO.

    3.

    BY APP'D.

    APRIL 2012

    AS INDICATED

    192363.0000.01

    FIGURE 10

    FORMER MICHCON BROADWAY STREET MGPANN ARBOR, MICHIGAN

    SITE RESTORATION PLAN

    DGS

    CWD

    VEB

    DGS 04/26/12 SITE PLAN FOR PLANNING COMMISSION REVIEW VEB