executive summary english - mppcb.nic.in summary of environment impact assessment for 2 laning with...
TRANSCRIPT
Executive Summary of Environment Impact Assessment for 2 laning with Paved
shoulders Gwalior to Bhind NH-92 from 0.00 Km to 108.00 Km.
1
Introduction
Executive Summary of Environment Impact Assessment for 2 laning with Paved
shoulders Gwalior to Bhind NH-92 from 0.00 Km to 108.00 Km.
2
A. Introduction
The Govt. of India (GOI) through Ministry of Roads & Highways (MORT&H) is
contemplating to enhance the traffic capacity and safety for efficient transshipment of
Goods as well as passenger traffic on few of the Selected heavily trafficked
stretches/paved shoulder of National Highways. The National Highways Authority of
India (NHAI) has been entrusted for the development. Maintenance and
management of National Highways, under NHDP Phase –IV programme.
The Project under consideration aims at converting existing 2-lane NH 92 from
Gwalior to Bhind 2 lane divided carriageway to be executed by private entrepreneurs
as BOT projects. The Madhya Pradesh Road Development Corporation (MPRDC)
has assigned Holtec Consulting Private Limited (HCPL) to prepare Feasibility
Report.
Location
The Paved shoulder starts from Km 0.00 of NH 92 at Gwalior traverses through of
Gwalior District to Bhind of Bhind District and further runs across Chambal river and
enters into Gwalior & Bhind taluka of Gwalior District, further runs through MP&UP
border & ends at Km108.000 of NH-92 Major settlements along the paved shoulder
are Gwalior & Bhind, other important towns/villages are Malanpur, Moharajpur,
Gohad, Mehgaon, Phoop and Barhi. Total length of the paved shoulder is
approximately 108 Km. The location map of the project is given in figure 1.
Salient Features of the project
Project Name: Two laning with paved shoulder of the section Km 0.00 to Km
108.00 of NH-92 (Gwalior-MP/UP border) in the state of Madhya Pradesh by
Madhya Pradesh Road Development Corporation ltd. (MPRDC), Government of
Madhya Pradesh.
Start: Km 0.000 (Gwalior)
End: Km 107.500 (UP/MP Border)
Length: Km 107.500
Important Towns: Gwalior and Bhind, other important towns/villages are Malanpur,
Executive Summary of Environment Impact Assessment for 2 laning with Paved
shoulders Gwalior to Bhind NH-92 from 0.00 Km to 108.00 Km.
3
Moharajpur, Gohad, Mehgaon, Phoop and Barhi.
Terrain: Plain
Road Formation (existing): 9 m to 13m.
Carriageway (existing): 0 5 m to 10 m. Poor to Good
Traffic Volume: 15,000 PCU.
Culverts (Existing): 96 nos (less numbers, week and inadequate).
Minor Bridges: 35 nos (require up gradation by way of special repairs /
rehabilitation, widening, reconstruction and retention with repairs).
Major Bridges: 1 no. satisfactory condition.
ROB: 1 No: at Km 7.043 Satisfactory condition.
Flyover (under construction): 1 Nos. at Km 19.740
Junction/Intersection: 8 nos major and 7 nos minor.
B. Project Influence Area
i) Direct Area of Influence
The direct influence area of the project is restricted to proposed Right of way (RoW)
only, since the project involves widening of existing highway and all construction and
operation stage activities will be contained within it. The proposed RoW is 60m for
open country road & 45m for semi urban areas.
ii) Indirect Area of influence
As per MoEF guidelines for conducting EIA (EIA notification, S O 1533 dated 14th
Sept, 2006); the geographical scope of the EIA study has been considered as 15 km
radius for highway projects for major environmental features like national park,
wildlife sanctuary, Critically Polluted Area, Notified Eco-Sensitive Zone, Inter-state
Boundaries and International Boundaries (10 km), Coastal Zones, Areas protected
under international convention, defense installations etc. Physical features like
Executive Summary of Environment Impact Assessment for 2 laning with Paved
shoulders Gwalior to Bhind NH-92 from 0.00 Km to 108.00 Km.
4
physiography, hydrology were also studied/ recorded within 15 km radius of the
project road.
C. Statutory clearance requirement
S.
No
Clearance Required for Statute under which
clearance is required
Statutory Authority
1 Environmental Clearance EIA notification, 2006
issued under EP Act
1986
Ministry of Environment &
Forest, GOI, New Delhi
2 Wildlife Clearance Wildlife protection Act
1972
State Wildlife Board, Dept
of Forest, Govt. of M.P. &
Central Empowered
Committee, MoEF
3 Forest Clearance Forest Conservation
Act 1980
Dept. of Forest, Govt. of
M.P. & MoEF
4 Permission for filling of
roadside trees
- Revenue Department
5 Consent to Establish
(CTE)
Water (P & CP) Act,
1974 & Air (P & CP)
Act, 1981
Madhya Pradesh Pollution
Control Board
D. Project interventions
The existing 2-lane NH-92 shall be widened to 4-lane divided carriageway. There are
two short bypasses. The detail information of the short bypasses are as follows,
Executive Summary of Environment Impact Assessment for 2 laning with Paved
shoulders Gwalior to Bhind NH-92 from 0.00 Km to 108.00 Km.
5
Sl.No. Chainage Length (Km)
1 40.300 – 41.000 0.700
2 106.000 – 106.800 0.800
Total 1.500
Proposed features include 1 no major bridge, 35 nos minor bridges, 1no RoB, 1 no
fly over, 8 nos junction, 96 nos culverts, 2 nos toll plaza (Km 22 & Km 105),
Intersections / Junctions (Major 8 + Minor 7) are 15 nos, 1 no Truck Lay-Byes, 6 nos
Bus Bays.
Executive Summary of Environment Impact Assessment for 2 laning with Paved
shoulders Gwalior to Bhind NH-92 from 0.00 Km to 108.00 Km.
6
Executive Summary of Environment Impact Assessment for 2 laning with Paved
shoulders Gwalior to Bhind NH-92 from 0.00 Km to 108.00 Km.
7
Description of the
Environment
Executive Summary of Environment Impact Assessment for 2 laning with Paved
shoulders Gwalior to Bhind NH-92 from 0.00 Km to 108.00 Km.
8
Description of the Environment
A) Physical Environment
i) Meteorology
Climate: Study area has three distinct seasons like most of north India, it has a hot
dry summer (April–June) followed by monsoon rains (July–September) and a cool
and relatively dry winter.
Temperature: Gwalior has extreme climatic conditions, scorching summer and chilly
winter. Summer (March to June) temperature rises to 47°C and has a minimum of
16°C. Monsoon rainy season during July to October is humid and temperature within
25°C to 32°C. Winter (December to February) is chilly and can drop down to
subzero. Day time in winter can have temperature up to 27°C. The temperature of
Bhind ranges from 46°C in summer & 2°C in winter.
Humidity: Relative humidity in both districts varies from 26 % to 83 %. In Bhind
district, relative humidity generally exceeds 83% (August month). In the rest of the
period is dry. The driest period is summer season, when relative humidity is less
than 26%.
Rainfall: The average rainfall is about 1,370 mm (53.9 inch). It decreases from east
to west. The south-eastern districts have the heaviest rainfall, some places receiving
as much as 2,150 mm (84.6 inch), while the western and north-western districts
receive 1,000 mm (39.4 inch) or less.
Wind speed: In Gwalior, the northwestern wind blows, predominantly, over the city
of Gwalior and the wind speed generally ranges from 8 km per hour in summer to 2
km per hour in winter time. In Bhind district, wind velocity is higher during the pre
monsoon period as compared to the post monsoon period. The maximum wind
velocity is 11.3 km/h during the month of June and minimum is 3.1 km/h during the
month of November. Average normal annual wind velocity is 6.4 km/h.
(ii) Physiographic & Terrain:
The project region falls in the Western Satpura plateau. Of the project influenced
area 80% is plain terrain, 20% undulating.
Executive Summary of Environment Impact Assessment for 2 laning with Paved
shoulders Gwalior to Bhind NH-92 from 0.00 Km to 108.00 Km.
9
(iii) Land use
The mean elevation above the sea is about 2000 ft. The entire stretch is essentially a
highland tract, divided naturally into three distinct portions, differing in their
superficial aspects, the character of their soil and their geological formation. The
northern part of the Bhind district forms an irregular plain of the sandstone formation.
The land use of Gwalior is classified into four types – viz. forests, area under
cultivation, culturable waste and the area not available for cultivation. The land under
cultivation is further sub-divided into two types viz. irrigated and un-irrigated.
Land Use Pattern of Gwalior:
Forest Land 118.10 Sq. Km
Land under Cultivation
a) Irrigated Land
b) Un irrigated Land
54.29 Sq. Km
33.18 Sq. Km
Culturable Waste Land 16.76 Sq. Km
Area not available for
cultivation
27.09 Sq. Km
Total Area 249.42 Sq. Km
Land Use Pattern of Bhind:
Forest area 89.05 Sq Km
Net area sow 3298.8 Sq Km
Cultivable area 3406.2 Sq Km
(iv) Water Resources
Surface Water: Project stretch crosses six rivers. Chambal, Sindh, Londara,
Pawaya, Kunwari, Swarnrekha river. & small rivulets & storm channels cut across at
many places, most of which are non-perennial and drain only for few days/weeks
during & after the monsoons.
Ground Water: Ground water is the major source of the drinking water in Gwalior &
Bhind area. The villages are dependent on ground water for their everyday
Executive Summary of Environment Impact Assessment for 2 laning with Paved
shoulders Gwalior to Bhind NH-92 from 0.00 Km to 108.00 Km.
10
requirement. Ground water is fetched from open dug- as well as bore wells which are
both mechanized and manual. There are 1325 numbers of ground water observation
wells present in project area.
(v) Water Quality
The surface water samples ware collected from 2 rivers viz. Suarnrekha River (at Km
3.750) & Chambal River (Km 120.200) for monitoring the surface water quality.
Environmental survey was conducted & 24 sampling locations for ground water were
selected along the project highway in order to find out the primary data of existing
water quality scenario.
Surface Water Quality Results: The pH value ranges between 7.74 to 8.40. TDS
content ranged between 198-263 mg/I. while chloride values ranged from 104 to 172
mg/I respectively, well below the tolerance limits. Iron content is found to be varying
between 0.08-0.23 mg/I. There is no significant presence of trace metals in the
surface waters. There is no faecal contamination where as the total coliform bacteria
recorded as < 2.0 mg/I. Total Hardness varies from 100.12 to 130.00 mg/l.
Ground Water Quality Results: The ground water sources have agreeable color
taste and odour. The pH values ranged between 7.2-7.80, generally above the
neutral mark and within the permissible limits for drinking water. TDS values ranged
between 375-488 mg/I, and is within the permissible limits for drinking water (500
mg/I). Chloride values ranged from 15 mg/I to 30 mg/I, iron content varies between
0.10-0.21 mg/I, thus within permissible limits. . BOD is <2 mg/I .There is no
signification bacteriological contamination of these sources. Total Hardness ranged
between 230-300 mg/l. Heavy metals like arsenic, mercury are BDL.
(vi) Air Quality
The air polluting sources in the project region primarily consists of industries and the
vehicles playing on the roads. A total of six (6) ambient air monitoring stations were
identified based on the different existing and land use pattern along the project road.
Ambient air quality was monitored as per GSR 826 (E) dated 16th November 2010.
All the station falls in residential and rural zone. The on-site monitoring result shows
that RPM (ug/m3) varies between 68 to 178, SO2 (ug/m3) varies between 6.8 49-75,
NO2 (ug/m3) varies between 15.6 to 17.2, CO (mg/m3) found <1.0 and Ammonia
Executive Summary of Environment Impact Assessment for 2 laning with Paved
shoulders Gwalior to Bhind NH-92 from 0.00 Km to 108.00 Km.
11
(ug/m3) recorded as <10 at all station, Thus, all the parameters are found be within
the permissible limits at all the stations.
(vii) Noise Quality
Noise level monitoring was conducted at 2 locations. Day time noise was found to
vary between 67 to 81 levels [dB (A)] wherein night time noise was found to vary
between 41 to 48 level [dB (A)]. The detail monitoring report is given below:
Pollution Parameter Location Parameter
Test
Existing
Levels
Standard
Levels
Bhind Day level 81 dB (A) 55 dB (A
Night Levels 48 dB (A) 45 dB (A)
Gwalior Day levels 67 dB (A) 59 dB (A)
Noise
Night Levels 41 dB (A) 45 dB (A)
(B) Ecological Environment
Forest
Flora: In the project affected districts mainly mixed miscellaneous forest are found.
These forests mainly have Shisham (Dallbergia Sisso), Ashok (saraca Asoca), Neem
(Azadirachta indica) etc. There are also Non wood forest products (NWFP) like
Tendu leaves or Bidi leaves (DiospyrosmeloNO2ylon), Sal Seed (Shorea robusta),
Chebulic Myrobolan or Harra (Terminaliachebula), Gum, Chirobji (Buchanania
lanzan), flower and seeds of Mahua Madhuca indica) and flowrs, seeds, bark & roots
of various plants species.
Fauna: Common animal like dog, cats, monkey, pig and cattle are also present. The
presence of wild animals in the project areas is not reported and may be considered
very rare.
Executive Summary of Environment Impact Assessment for 2 laning with Paved
shoulders Gwalior to Bhind NH-92 from 0.00 Km to 108.00 Km.
12
(C) Cultural Environment
The Gwalior Fort has changed hands many times, from the Tomaras in the 8th
century it passed on to the Mughals, then the Marathas under the Scindia's (1754),
followed briefly by Lakshmi Bai of Jhansi, Tatiya Tope and the British. The city has
several important educational institutions including the Indian Institute of Information
Technology and Management, Indian Institute of Travel and Tourism Management,
Scindia School, and Laxmibai National Institute of Physics. Bhind district is
surrounded by Agra and Etawa districts of Uttar Pradesh in the north and Gwalior
and Datia districts in the south. The economy of Bhind is mainly agriculture.
Dairy is the main source of income of the farmers in the district. Traditional cropping
practices along with old conventional tools are still used commonly but the farmers
have readily adopted new agricultural machinery as well. The crops cultivated in the
Kharif season are soyabean, paddy, cotton, jowar, maize, bajra, pulses, sesamum,
and sunflower. During the Rabi season, the crops cultivated are wheat, gram, peas,
lahat and toria. There are about 417 Small Scale Industries in Bhind. About 2340
people are employed in these industries. The incurred establishment expenditure is
up to Rs.70 lakhs. Ghee manufacturing in Bhind had been an important industry,
along with rearing of livestock for milk and other milk product.
Executive Summary of Environment Impact Assessment for 2 laning with Paved
shoulders Gwalior to Bhind NH-92 from 0.00 Km to 108.00 Km.
13
ANTICIPATED ENVIRONMENTAL
IMPACT AND MITIGATION
MEASURES
Executive Summary of Environment Impact Assessment for 2 laning with Paved
shoulders Gwalior to Bhind NH-92 from 0.00 Km to 108.00 Km.
14
Air Environment
Impact Measures
Generation of
Dust
• Sprinkling of water
• Earth handling, Asphalt mixing site, borrow areas, construction
site
• Air Pollution control at stone crusher site
• Masks for workers of stone crushing units
• Regulation of construction timings near sensitive receptors and
settlements
• Regular Air Quality Monitoring
Gaseous
Pollution
• Vehicles and machineries - regularly maintained to conform to
the emission standards
• Asphalt mixing sites at least 500 m away from residential
quarters.
• Workers in asphalt mixing, application of asphalt mix will be
provided with masks.
• Supervising officers will ensure that the worker use the masks
Noise Environment
Impact Measures
Noise
• Noise levels of machineries used shall conform to relevant
standard
• Workers shall not be exposed to noise level more than 90 dB (A)
(Leq) for 8 hours.
• Workers will be provided ear plugs
• Regulation of timings of construction work generating noise
pollution near the sensitive and residential areas.
• Regular Noise Level Monitoring
Executive Summary of Environment Impact Assessment for 2 laning with Paved
shoulders Gwalior to Bhind NH-92 from 0.00 Km to 108.00 Km.
15
Water Environment
Impact Mitigation Measures
Loss or
impacts on
water bodies
Precautions need to be taken during the construction work of
culverts and bridges across the rivers and canals such that the flow
in these water bodies is not obstructed thus affecting the cross
drainage. Further, attention to be paid so that no waste, debris is
discharged into surface water body.
Siltation of
water bodies
• Turfing or pitching of embankments where possible to prevent
erosion.
• Slopes of embankments - modified and re-channelised so that
contaminants may not enter the water body
• No solid waste will be dumped in or near the water bodies or
rivers
Flooding due
to siltation of
drainages
channel
Excavated earth and other construction materials shall be stored
away to prevent washing away
Water for
construction
Water sources would be selected such that local availability is not
affected
Contamination
from wastes
• Septic tanks and oil interceptors will be provided to prevent any
uncontrolled effluent discharge from workers camps and
storages.
• The camp site will be provided with proper drainage connected
with local drain
Contamination
from fuel
• Vehicle maintenance will be carried out in a confined area,
away from water sources.
• It will be ensured that used oil or lubricants are not disposed to
watercourses.
Sanitation and
Water use in
Construction
Camps
• Construction camp will be organized in a planned manner.
• Workers shall be provided proper sanitation facilities including
toilets.
• Camps will have water supply facilities like tube wells
Executive Summary of Environment Impact Assessment for 2 laning with Paved
shoulders Gwalior to Bhind NH-92 from 0.00 Km to 108.00 Km.
16
Impact Mitigation Measures
Rain Water
Harvesting
• Rain Water Recharge Pits at every 500 m of the project road
will be provided.
Impact on Solid Waste Generation
Item Management Strategy
Top Soil to be disposed off in low lying
areas within ROW
Completely used in Green Belt
Development
Overburden – 245100 m3
To be utilized in median
(Below layers) -- 144,000 m3
To be utilized for construction
of Roads to quarries -- 150,000 m3
In road embankment for
additional 2 lanes -- 200,000 m3
Used for strengthening of slopes of
embankments, construction of haul roads to
quarries & median filling
Construction debris 17000 m3
Bituminous material
removed from existing
pavement -- 65000 m3
Total 6,20,000 m3
Construction Debris – Mostly reused for
filling of low lying areas and in road
construction. Remaining dumped after
requisite permission in designated disposal
grounds
Domestic Solid Waste – 0.20 m3 /
day
Disposed in Municipal / Grampanchayat at
Dumping grounds after requisite permission
Executive Summary of Environment Impact Assessment for 2 laning with Paved
shoulders Gwalior to Bhind NH-92 from 0.00 Km to 108.00 Km.
17
Land Environment
Impacts Mitigation Measures
Loss of topsoil
Total land requirement for
Project (Available ROW
land & land to be
acquired) : 550 ha
• Removed and stockpiled on sides and used on the
side slopes & shoulder, for top cover of borrow areas
and in green belt development.
• Turfing of road embankment slopes with herbs,
shrubs and grasses
Loss of topsoil from
borrowing
• Arable lands will be avoided for earth borrowing. If
needed, topsoil will be separated and refilled after
excavation
Borrowing of fill materials
• Excavation from pre-selected locations. After
excavation the borrow pits will be dressed to match
with the surrounding.
• Borrow pits - depth regulated. Slope of Sides of the
excavation not steeper than 1 vertical to 4 horizontal
from the edge of the final section of bank.
Ecological
Impacts Mitigation Measures
Loss of trees
• A large number of tree will be planted as per the
compensatory afforestation.
• Shrubs to be planted in median.
• Arjuna, Pipal, Nili gulmohar, Mango, Kachnar, Siris,
Neem are the predominant tree species along the
project corridor and same species will be planted
Executive Summary of Environment Impact Assessment for 2 laning with Paved
shoulders Gwalior to Bhind NH-92 from 0.00 Km to 108.00 Km.
18
Public Health / Occupational Safety
Impacts Mitigation Measures
Safety to Public Signs on road before construction areas
Restriction to Access
Safe and convenient passage for vehicles, pedestrians
and live stocks to and from the side roads and property
across the road.
Occupational safety for
workers
Contractor will arrange all safety measures for workers
as per factories Act
Occupational safety for
Asphalt plant workers and
crusher plant
• All workers employed on mixing asphaltic material,
cement, lime mortars, concrete etc., will be provided
with protective footwear and protective goggles.
• For crusher workers masks should be provided.
Explosive use
Contractor shall obtain such permission as required
from all Government Authorities, public bodies and
private parties whatsoever concerned or affected or
likely to be concerned or affected by blasting operations.
Cultural Properties / Roadside Amenities / Archeological Sites
Impacts Mitigation Measures
Affected roadside
amenities and cultural
properties
• Affected religious structures will be relocated.
Alternative sites will provide and appropriate
enhancement will be done.
• All common property resources will be replaced
before the start of construction. Relocation site
identification will be in accordance to the choice of
the community / concerned agency.
Executive Summary of Environment Impact Assessment for 2 laning with Paved
shoulders Gwalior to Bhind NH-92 from 0.00 Km to 108.00 Km.
19
ENVIRONMENTAL MONITORING
PROGRAMME
Executive Summary of Environment Impact Assessment for 2 laning with Paved
shoulders Gwalior to Bhind NH-92 from 0.00 Km to 108.00 Km.
20
Environmental Monitoring Programme
Provisions have been made for monitoring of environmental attributers during
construction and operation phase of the project. The details of the parameters,
frequency and duration are given in Table.3.
Table .3 Details of Environmental Monitoring
Rehabilitation and Upgardation to 4 lane configuration of Gwalior-Bhind section of
NH-92 in the State of Madhya Pradesh.
Attribute
d
Project
Stage Parameter Frequency Duration
Locatio
n
Constru
ction
PM10, PM2.5,
SO2, No2, O3,
Pb, CO& NH 3.
Once in a season
( excluding
monsoon)
throughout the
construction period)
24-hours for
SPM
,RSPM,SO2
and NOx: 8
Hours for
CO and HC
6
locations
along
the
paved
shoulder
and
plant
sites
Air
Operati
on
PM10, PM2.5,
SO2, No2, O3,
Pb, CO& NH 3.
Once in a season
( excluding
monsoon) season
for 2 years of
Operating period)
24-hours for
SPM
,RSPM,SO2
and NOx: 8
Hours for
CO and HC
6
location
along
the
paved
shoulder
Water Constru
ction
(i) pH ,DO, BOD
,COD, TDS, CI ,
Pb, Oil &
Grease, As
Hg,Cn, total
Coliform , faecal
Coliform and
Detergents for
Once in a season
( excluding
monsoon)
throughout the
construction period)
Composite
Sample
6
locations
including
3
drinking
Water
sources
at
Executive Summary of Environment Impact Assessment for 2 laning with Paved
shoulders Gwalior to Bhind NH-92 from 0.00 Km to 108.00 Km.
21
surface water
(ii) pH , TDS,
Total Hardness,
Sulphate
Chloride , Fe,
Pb, Cn,Oil&
Grease ,As ,Hg,
Total Coliform ,
faecal Coliform
for Ground water
Constru
ction
camps.
Noise level on
dB (A) Scale.
Once in a season
( excluding
monsoon)
throughout the
construction period)
Reading to
be taken at
15 seconds
interval for
15 minutes
every hour
and for 24
hours.
Wherev
er the
Contract
or
decides
to locate
the
equipme
nt yard
(5
Location
s).
Noise
Constru
ction
Noise level on
dB (A) Scale
Once in a season
( excluding
monsoon)
throughout the
construction period)
Reading to
be taken at
15 seconds
interval for
15 minutes
every hour
and for 24
hours.
2
locations
along
the
Paved
shoulder
and
plant
location.
Executive Summary of Environment Impact Assessment for 2 laning with Paved
shoulders Gwalior to Bhind NH-92 from 0.00 Km to 108.00 Km.
22
Operati
on
Noise level on
dB (A) Scale
Once every season
(except monsoon)
for 2 years after
completion of
construction activity
Reading to
be taken at
15 seconds
interval for
15 minutes
every hour
and for 24
hours.
10
locations
along
the
Project
paved
shoulder
Soil Constru
ction
Monitoring of Pb,
SAR and oil
Grease
Once in a season
(excluding)
monsoon season )
throughout the
construction period
Grab
Sampling
-2
Location
at
producti
ve
agricultu
ral lands
close to
intersect
ion
- any
accident
or spills
location
involving
bulk
transport
carrying
hazardo
us
material
s.
Executive Summary of Environment Impact Assessment for 2 laning with Paved
shoulders Gwalior to Bhind NH-92 from 0.00 Km to 108.00 Km.
23
PROJECT BENEFIT
Executive Summary of Environment Impact Assessment for 2 laning with Paved
shoulders Gwalior to Bhind NH-92 from 0.00 Km to 108.00 Km.
24
Project Benefit
Implementation of the Project will have following benefit:
1. Accelerate regional economic development in term of industry, tourism and
agriculture
2. Reduce vehicle operating and maintenance costs by improving road conditions
3. Reduce vehicle travel time by minimizing congestion in settlement areas and
providing a four lane facility
4. Minimize road accidents by increasing road width, improving intersection and
road geometry
5. The project may also generate local employment opportunities through the
construction activities and local business
6. Abatement of ambient air and noise pollution in comparison to a do- nothing
situation
7. Increase in safety due to construction of median between two direction of traffic
flow and plantation of shrub in median
8. Provision of pedestrian and cattle underpasses shall provide safe movement from
one side of the project road to other side of the Project road
9. Construction of Road Over Bridge (ROBs) shall reduce travel time and enhance
smooth flow of the traffic
10. Project facilities included in the project preparation are Rest Area , Bus Bays,
Truck Lay Bye, Road Side Furniture, Street lighting, Traffic Aid Post Patrolling,
Medical Aid post, vehicles Resource posts etc.
Executive Summary of Environment Impact Assessment for 2 laning with Paved
shoulders Gwalior to Bhind NH-92 from 0.00 Km to 108.00 Km.
25
ENVIRONMENTAL MANAGEMENT
PLAN
Executive Summary of Environment Impact Assessment for 2 laning with Paved
shoulders Gwalior to Bhind NH-92 from 0.00 Km to 108.00 Km.
26
Environmental Management Plan
Several mitigation measures have been suggested along with the agency
responsible for planning, execution , supervision and monitoring of the
Environmental Management Plan for pre- construction , construction and operation
stages to avoid or mitigation the adverse impacts.
Pre- Construction Phase
Pre-construction activities include acquisition of land and structure, relocation of
utilities, removal of trees, and relocation of common property resources viz. temple,
hand pump, obtaining Environmental clearance Forest Clearance and wildlife
clearance from MoEF, Consent to Establish from MPPCB etc. NHAI Concessionaire
and concerned department shall be responsible for those activities.
Construction Phase
Concessionaire activities during this phase include setting up of construction Camp,
setting up of plants namely crusher plant, concrete batching plant, hot mix plant;
clearing and grubbing, collection storage and utilization of topsoil, identification of
borrow pit & aggregated quarry (if other than those identified by design consultant),
operation of the quarry, plantation along the road side & at median, environmental
protection & monitoring. Concessionaire shall also be responsible for implementation
of the Environmental protection measures during construction’s The Independent
Engineer shall be responsible for monitoring & supervision of the Concessionaire’s
activities as per Contract & report it to PIU, NHAI time to time. Project
implementation Unit (PIU), NHAI shall be regulatory compliance.
Operation Phase
Operation phase activities include environmental monitoring of survival rate of the
plantation etc. The PIU and Concessionaire shall be responsible for those activities.
Environmental costs:
The costs for mitigation and management measures have been estimated for
inclusion into the Economic Analysis. These costs along with the social costs have to
be incurred by the implementing agency to include environmental and social
safeguard measure into the proposed project. Environmental Mitigation Cost is INR
3.961 crore.
Executive Summary of Environment Impact Assessment for 2 laning with Paved
shoulders Gwalior to Bhind NH-92 from 0.00 Km to 108.00 Km.
27
CORPORATE SOCIAL
RESPONSIBILY
Executive Summary of Environment Impact Assessment for 2 laning with Paved
shoulders Gwalior to Bhind NH-92 from 0.00 Km to 108.00 Km.
28
Corporate Social Responsibility
The project proponent will generate direct as well as indirect employment facilities in
the nearby areas and also determined to provide clean and green environment. The
widening of project demands more manpower for its operation. This already
generates basic needs. This will generate opportunity for indirect employment, basic
commodity, dhabas, road side shops & many other facilities in the junction areas as
transportation will increase. This will boost the size of existing market. Villagers have
opportunity to sell their commodities to nearby area only. This will also boost the
consumption for opening new fast food corner.
The proponent will provide all socio economic growth opportunity for its workers and
villagers. This will boost the demand of skilled and unskilled worker. The villagers
have opportunity to work in road area when there is slack period in harvesting.
Employment
The most benefit due to the proposed road project will be in the sphere of generating
employment for a large number of people in that area during construction period.
The project activities will lead to generation of commercial activities in construction
as well as service sector. These activities will generate huge employment potential
which will benefit local population.
Transportation
There will also be increase in the vehicular traffic due to passenger transport. This
increase in traffic will not have any consequence to warrant special mention. One
should expect that the increased passenger load in the sector would prompt the
state government to start new and frequent public transport services to this area,
bringing upliftment to the whole locality.
Other Benefits
Besides faster connectivity and commercial, economic upsurge, the project will
provide:
• More Plantation and Greenery.
• Highways accident hazards considerably reduced by four laning.
• Medical aid available across the highway.
• More safety of users assured through curve improvements, reconstruction of
bridges, crash barriers, roadside furniture.
Executive Summary of Environment Impact Assessment for 2 laning with Paved
shoulders Gwalior to Bhind NH-92 from 0.00 Km to 108.00 Km.
29
• Substantial Saving in vehicle operation cost & less pollution.
• Creation of beautiful Water Bodies.
• Economic upliftment due to faster, better accessibility & saving in vehicle
operation cost.
Executive Summary of Environment Impact Assessment for 2 laning with Paved
shoulders Gwalior to Bhind NH-92 from 0.00 Km to 108.00 Km.
30
CONCLUSION
Executive Summary of Environment Impact Assessment for 2 laning with Paved
shoulders Gwalior to Bhind NH-92 from 0.00 Km to 108.00 Km.
31
CONCLUSION
The location of the project site selected based on its socio, techno economical
suitability. As a positive impact the entire socio economical status of the region will
be improved to the better level. The potential environmental, social and economic
impacts have been assessed. The proposed project has certain level of marginal
impacts on the local environment. With effective implementation of proposed
environment management plan, these effects will be insignificant. Implementation of
the project has beneficial impact in terms of providing direct and indirect employment
opportunities. This will be a positive socio-economic development in the region.
Quality of life of the people will improve. No displacement of people from the project
site is involved.
The improvement of this highway will provide the following technological benefits
� Providing better level of service in terms of improved riding quality and smooth
traffic flow.
� Faster transportation will ultimately lead to massive savings in the form of
reduced wear & tear vehicles, reduced vehicles operating costs and total
reduction in transportation costs etc.
� With the improvement of road surface, the traffic congestion due to obstructed
movements of vehicles will be minimized and thus wastage of fuel emissions
from vehicles will be reduced.
� Introduction of additional safety measures like crash barrier, road illumination,
retro-eflective signage, delineators etc. will result in lesser accident.
Socio economic benefits
The improvement of this highway will provide the following socio economic benefits
to the regions:
� It will increase access of the villages and other small settlements to urban areas,
thus providing connectivity of rural produce to urban markets, there by enhancing
the reach and export of perishable farm-products, leading to better remuneration
for the producer.
� By reducing the transportation costs, it will be more feasible to transfer
construction materials which are important for many economic activities (house
building, small hydro-electric projects etc.) to hinterland. This will in turn, lead to
direct as well as indirect strenthing of local economics.
Executive Summary of Environment Impact Assessment for 2 laning with Paved
shoulders Gwalior to Bhind NH-92 from 0.00 Km to 108.00 Km.
32
� Access to social infrastructure like schools, colleges, health centers will improve,
providing many benefits from increased education and health facilities and
improved social interaction and mobility.
� During the execution of the project i.e. during the construction period,
employment will be provided to workers from the local communities.
� The educated as well as uneducated people from villages will obtain access new
employment centers.
� The improvement of the road will prevent single vehicle collision as the road will
be two lanes with paved shoulders. This would be very beneficial from the safety
point of view and will thus, reduce accident rate. The proposed project will attract
more & more domestic & international tourists. Thus tourism is likely to flourish.
� Overall improved quality of life for the lesser developed areas in the
neighborhood.