ewec forum windfarms projects in morroco milan- 9 may, 2007
TRANSCRIPT
EWEC Forum
WINDFARMS PROJECTS IN MORROCO
MILAN- 9 MAY, 2007
The Office National de l'Electricité (ONE)
Creation August 1963
Total installed capacity 5312 MW - Steam power plants (coal/oil/diesel) 3469 MW
- Hydro electric plants 1265 MW
- Wind farms 114 MW
Until march 2007
ACTORS IN THE ELECTRIC SYSTEM
ONE in charge of production, transmission and distribution
Regis or Municipal Distributors are in charge of 55% of the electricity distribution
Privates actors are entring in the system :
- Private Generators (Jorf Lasfar & Al Koudia Al Baïda Projects, Tahaddart),
- Private Distributors in Casablanca ( LYDEC) and in Rabat ( REDAL), etc.
LEGAL FRAMEWORK
ONE is allowed to : « …. Make agreements, after competition, with private operators for the production of electrical power… under the following conditions :
- All the production should be exclusively oriented to the satisfaction of ONE ’s needs;
- The initial conditions of the economical equilibrium stipulated by the agreement must be maintained during the execution of this convention ». (the 23rd sept. 1994 decree, art. 6).
MAIN STRATEGIC ORIENTATIONS
I- Renewables into Morocco’s energy mix by targeting the development of 1000 MW wind installed capacity by 2012;
II- Private sector involvement in the power sector by providing for long term off take agreements through modern and sustainable power purchase agreements;
III- The Emergence of mature Moroccan energy players through numerous actions including EnergiPro (Autoproduction), an initiative launched by ONE towards its large customers;
IV- Morocco’s position as a regional energy hub by encouraging energy export through the strong electric interconnexion infrastructures with neighboring countries.
OPERATING WINDFARMES
PROJECT UNDER THE CONSTRUCTION
FUTURS PROJECTS
Adelkhalek Torres Wind farm in Tangier Adelkhalek Torres Wind farm in Tangier 50,4 MW50,4 MW
Model wind farm in Tangier Model wind farm in Tangier 3,5 MW 3,5 MW
Amougdoul Wind farm in EssaouiraAmougdoul Wind farm in Essaouira
140 MW140 MW
60 MW60 MW
Tanger Wind farm (under construction)Tanger Wind farm (under construction)
200 - 300 MW200 - 300 MWTarfaya Wind farm Tarfaya Wind farm
ONE’S PROJECT OWNER
O&Mcontract
O&Mcontract
ONEDeveloper / Operator/ Owner
ONEDeveloper / Operator/ Owner
EPCTurn key
EPCTurn key
FinancementFinancementLandLandnetworknetworkEnvironment
studies
Environment studies
Wind dataWind dataCDER
Manufactor
Manufactor
IgCConsulting Consulting
IPP ONE’S PROJECT
ONEUnique supplier
ONEUnique supplier
Building contractsBuilding contracts O&M contractO&M contract
FinancementFinancement
-PPA - LTR
-PPA - LTR
PROJECT SOCIETYInvestisseur/Opérateur
PROJECT SOCIETYInvestisseur/Opérateur
developmentdevelopment
landland
Network Network
SITES DE PARCS EOLIENS
TAZA
Operating windfarmers
Windfarmers under construction
Windfarmers on development
Initiative 1000 MW
Tarfaya
TahTiskrad
Boujdour
My Bouzerktoun
ENERGY PRO OFFER
Private OwnerDeveloper / Operator/ supplier
Private OwnerDeveloper / Operator/ supplier
EPCTurn key
EPCTurn key
O&Mcontract
O&Mcontract
FinancementFinancement
LandLand
ONEnetwork
ONEnetwork
Wind dataWind dataONE
Manufactor
Manufactor
IgCConsulting Consulting
Actually, private can develop only 10 MW.
ENERGY PRO OFFER
In September 2006, ONE issued the “EnergiPro” offer to large industrial customers aimed at promoting renewable based auto-production. The offer includes three aspects:
- Wheeling all energy produced from renewable power project to any point of consumption using ONE high-voltage transmission grid. The Wheeling tariff has been put at 6cMAD/kWh (post stamp basis) for any project commissioned before 2009 and 8cMAD/kWh thereafter;
- Purchasing of all excess energy by ONE with a tariff structure that has been revised (Average 20% increase amounting to an average weighted tariff of about 41cMAD/kWh).