evolving markets and potential for the future - energy.gov · 2017-05-10 · 6 key questions...
TRANSCRIPT
1
Evolving Markets and Potential for the Future
Greg Brinkman
National Renewable Energy Laboratory
May 4, 2017
ENHANCED REVENUE AND MARKET STRUCTURES
2
Background
• In 1980s and before, one company owned transmission, generation, and distribution, and was responsible for keeping lights on – Generators provided many services: Inertia, governor response, frequency
regulation, spinning and non-spin reserve, reactive power/voltage support, capacity, energy, load-following, flexibility, etc.
– Almost all generators provided almost all of these services
• Today there are more markets – Lines between “market” and
“non-market” are blurred
– Services must still be provided, but providers (usually generators) are sometimes not paid for these services, or only for cost of service
– FERC and system operators are working to improve transparency
----------------TIMES ARE CHANGING----------------
3
Background
• In 1980s and before, one company owned transmission, generation, and distribution, and was responsible for keeping lights on – Generators provided many services: Inertia, governor response, frequency
regulation, spinning and non-spin reserve, reactive power/voltage support, capacity, energy, load-following, flexibility, etc.
– Almost all generators provided almost all of these services
----------------TIMES ARE CHANGING----------------
(non-hydro)
Lazard (2016) levelized cost of: • Wind: $32-62/MWh • PV: $46-56/MWh • Gas CC: $48-78/MWh
(All unsubsidized)
4
Why does it matter if these services aren’t compensated?
1. It’s not fair
2. It could cause real problems (and higher-cost electricity)
5
Example: Declining frequency response in the East
• Generators do not get paid to provide governor frequency response – System operators are beginning to find
ways to mandate or provide some incentive (e.g., must have governor to play in regulation market)
• Generators can make more money in the market if they do not provide frequency response – Operate at max capacity
– Reduced wear and tear (maybe)
• Some generators are blocking or reducing governor function
Ingleson and Allen (2010), IEEE
• Shows size of disturbance required to produce 1 mHz reduction in frequency
Slow frequency recovery to a very large event in the EI
FERC, NERC, ISOs working
to improve this
6
Key questions relevant to hydropower
• Hydro provides value to the grid in: – Services for which markets are common today
• Energy, capacity, frequency regulation (AGC), spinning (and non-spinning) reserves
• How can hydropower resources be better optimized to play in these (evolving) markets?
– How can constraints be adjusted to meet water/river/reservoir requirements while allowing more ability for electricity market revenue?
• Renewable / low carbon “markets”
– How does hydropower reduce carbon emissions?
– How can hydropower be used flexibly to help grid accommodate more renewables more efficiently?
– Services for which markets are not common today
• Inertia, governor response, reactive power/voltage support, load-following, flexibility, etc.
• How can these services be quantified?
• How can they be valued ($$$)?
• How can this turn into an actual revenue source?
• None of these questions are simple (all must be done transparently)
7
Types of relevant projects and examples
• New Markets – GMLC Metrics analysis (PNNL-led)
– GMLC Grid Valuation (ORNL-led)
– GMLC Markets work (NREL-led)
– Argonne exploration of markets
• Analysis of future grid planning scenarios (e.g., grid integration studies) – E.g., NARIS (NREL-led)
– Carbon impacts of hydropower, benefits of hydropower flexibility for accommodating renewables
• Optimizing grid operations and river systems together (mostly next session) in existing markets – RiverWare-PLEXOS (NREL)
– WM-PLEXOS (PNNL-led)
– WAPA (Argonne)
– EMCAS (Argonne)
• Other projects
Relationships with industry are very important for all of these studies
8
• Note that the unit commitment (UC) and economic dispatch (ED) problem used by energy markets is not well-suited to estimating prices for inertia, etc.
• Precedent – Ancillary services markets are a metric inserted into the UC/ED problem as a
constraint
– Capacity markets are a metric turned into a market outside the UC/ED
New Markets Section
9 9
Expected Outcomes
Enhance existing metrics to enable:
DOE to better set priorities on
modernization R&D
Congress to better monitor progress on
regional and national levels
Report on metrics definition and
approaches and baseline
Validation of metrics and approaches
with stakeholders and regional partners
Adoption of metrics by key partners Project Participants and Roles ANL – Security and synthesis lead, resilience contributor
BNL – Reliability contributor
LANL – Synthesis contributor
LBNL – Reliability lead
LLNL – Flexibility lead
NREL – Sustainability and stakeholder engagement lead,
flexibility contributor
ORNL – Affordability contributor
PNNL – Affordability lead and project manager
SNL – Resilience lead ---------------------------------------------------------------------------------------------
Working partners:
APPA, DHS, EIA, EPA, EPRI, FERC, NARUC, NERC, NRECA, ERCOT
Project Description The objective of the project is to assess the
feasibility and usefulness of metrics for
measuring change in the evolving electricity
infrastructure. The effort will develop
metrics and associated methods to assess
the power grid’s evolution with respect to
characteristics that are organized into the
following 6 categories: reliability,
resilience, flexibility, sustainability,
affordability, and security.
GMLC Metrics Analysis
10
Project Description Development of a valuation framework
that will allow electricity-sector stakeholders
to conduct, interpret, and compare valuation
studies of existing and emerging grid
services and technologies with high levels
of consistency, transparency,
repeatability, and extensibility.
GMLC Grid Valuation Framework
Project Objectives Produce a framework—not another new
model: a systematic approach to
conducting, and interpreting valuation to:
Ask the right questions and produce
credible answers
Increase transparency in modeling
assumptions and methods used in
evaluating grid technologies and services
Identify value beyond monetary savings
and costs (sustainability, reliability, etc)
Simple Complexity Involved
Coarse Purpose:ScreeningDatarequired:Low
Purpose:Multi-regionevaluationof technologiesandservicesDatarequired:Geographicor technologyhigh
Accuracy
Purpose:SingleProjectdeveloperDatarequired:Highforproject,low forrestofgrid
Purpose:Rate-setting,majorproject constructiondecisionDatarequired:HighPrecise
Project Participants and Roles ORNL – Project manager
PNNL – Review state of valuation
ANL – Taxonomy and glossary
NREL – Case studies
LBNL – Review and taxonomy support
SNL – Framework development support
LANL – Framework development support
NARUC – Stakeholder Advisory Group support
Affordability Sustainability
Resilience Reliability Flexibility Security
Economic Impact
11
GMLC Markets Analysis
Bi-level expansion model
Wholesale electricity markets exist to schedule and
dispatch generating units, given demand and the
transmission network configuration, at minimum
cost to the system.
The goal of this project is to create a multi-
timescale market and reliability modeling
framework, encompassing both the planning
(decades) and operational time frames (seconds),
to assess reliability and revenue sufficiency
challenges and solutions under a wide range of
market design options and revenue sources. Key
research questions include:
How do essential reliability service needs
evolve with different system fleets?
As the system evolves, how well does the
system meet needs?
What are the options to meet those needs?
12
Extensive Analysis of Electricity Market Designs
• Review of current and proposed market designs
• What are the new fundamental challenges and promising solutions to create better incentives and improved market design?
• How to achieve capacity adequacy and revenue sufficiency in the long-run?
• How to ensure and incentivize flexibility in short-run operations?
13
Power Market Analysis with Agent-Based Models
• Argonne developed Electricity Market Complex Adaptive System (EMCAS)
• EMCAS utilizes agent-based modeling to simulate the behavior of market participants in restructured power markets (e.g., various bidding strategies in day-ahead and hour-ahead markets)
• Agents have learning and adaptation capabilities
• Includes VALORAGUA (Value of Water) model to optimize hydropower and pumped-storage (PSH) plant and reservoir operations
• EMCAS has been licensed to companies in 14 countries
14
Future Grid Scenario Planning
15
NARIS: North American Renewable Integration Study
• Partnership between US DOE, NRCan (Canada), and SENER (Mexico) – Work led by NREL
• Analyze pathways to modernize the power systems in the US, Mexico, and Canada through efficient infrastructure planning and system operations
• Extensive stakeholder technical review
• Study potential interconnection of Canada, Mexico, and US power systems, from planning through operation and balancing at 5-minute resolution
PLEXOS (operations) ReEDS (generation and transmission planning)
dGen
(distributed
generation
market
model)
16
NARIS: North American Renewable Integration Study
• Partnership between US DOE, NRCan (Canada), and SENER (Mexico) – Work led by NREL
• Analyze pathways to modernize the power systems in the US, Mexico, and Canada through efficient infrastructure planning and system operations
• Extensive stakeholder technical review
• Study potential interconnection of Canada, Mexico, and US power systems, from planning through operation and balancing at 5-minute resolution
PLEXOS (operations) ReEDS (generation and transmission planning)
dGen
(distributed
generation
market
model)
Benefits of hydro
flexibility will be studied in
the context of these
scenarios
17
Optimizing hydro in current market framework (more in panel #2)
18
Developed Numerous Power Marketing EIS
• Colorado River Storage Projects - Glen Canyon - Flaming Gorge - Blue Mesa - Morrow Point - Crystal
• Collbran Project - Upper Molina - Lower Molina
• Rio Grande Project - Elephant Butte
• Seedskadee Project - Fontanelle
• Dolores Project - McPhee Dam - Towaoc Canal
• Provo Project - Deer Creek
How Do Power Marketing
Contracts and Glen Canyon
Operating Constraints
Impact Western’s
Customers?
19
Flexibility and Energy Imbalance Market (EIM)
• Energy imbalance (EI) – deviations of actual values from scheduled values
• Deviations increase with higher variable renewables
• Operational flexibility (e.g., fast ramping) helps balance deviations
Current Practice CAISO EIM
Single BA Multiple BAs
Federal Resources
and Purchase
Optimize Participating
Resources Dispatch
Footprint
Balancing
Hourly Hourly, 15 min, 5 min Time Step
Settlement Financial or
Energy Payback
Locational Marginal Price
(LMP) & Neutrality Accounts
Resolving EI
20
Financial Risk Software Evaluates Market Impacts on Hydropower
Fin
ancia
l B
enefit
($)
Fin
ancia
l B
enefit
($)
Hydropower System Energy Production
• Software forecasts financial probability distributions as basin hydrology and water depletions change over time
• Thousands of hydropower model optimization runs are preformed in parallel for a range of hydrological and market conditions
• Financial costs and benefits are evaluated for each run
• Risks are evaluated monthly and annually over several years
• Key forcing variables that impact financial outcomes are identified and summarized