evm for cngs

16
CNGS Review 15 July 2003 M. Meddahi 1 EVM for CNGS • Definitions • Pre-requisites • Application to CNGS

Upload: summer

Post on 19-Jan-2016

45 views

Category:

Documents


0 download

DESCRIPTION

EVM for CNGS. Definitions Pre-requisites Application to CNGS. Definitions. EVM : E arned V alue M anagement -> Measure amount of work performed -> Estimate total costs and duration. PV Planned Value. EV Earned Value. AC Actual Cost. BC Budget at complete. Schedule Variance - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: EVM for CNGS

CNGS Review15 July 2003

M. Meddahi 1

EVM for CNGS

• Definitions

• Pre-requisites

• Application to CNGS

Page 2: EVM for CNGS

CNGS Review15 July 2003

M. Meddahi 2

Definitions

EVM: Earned Value Management-> Measure amount of work performed-> Estimate total costs and duration

PVPlanned Value

EVEarned Value

ACActual Cost

Schedule Variance

SV = EV-PV

Cost VarianceCV = EV-AC

BCBudget at complete

Page 3: EVM for CNGS

CNGS Review15 July 2003

M. Meddahi 3

time

Money

PV

Today

AC

EV

Cost variance

Schedule variance

Page 4: EVM for CNGS

CNGS Review15 July 2003

M. Meddahi 4

EVM at CERN

- EVM for LHC- Much work done for implementing EVM for LHC- CNGS decided to also apply this management tool- Autumn 2002 started to implement EVM for CNGS

Page 5: EVM for CNGS

CNGS Review15 July 2003

M. Meddahi 5

Pre-requisites

Work BreakdownStructure

ProjectProgressTracking

Data collectionfrom project

engineers

Page 6: EVM for CNGS

CNGS Review15 July 2003

M. Meddahi 6

Work Breakdown Structure

Page 7: EVM for CNGS

CNGS Review15 July 2003

M. Meddahi 7

WBS layers

Page 8: EVM for CNGS

CNGS Review15 July 2003

M. Meddahi 8

Data collection

Page 9: EVM for CNGS

CNGS Review15 July 2003

M. Meddahi 9

PPT: Project progress tracking

• EVM project baseline frozen 9 May 2003

• 1st phase of utilisation and learning for the users:Project engineers are getting used to the system and the reporting.Analysing the results obtained from the EVM tools and proposing correcting actions.

Page 10: EVM for CNGS

CNGS Review15 July 2003

M. Meddahi 10

Page 11: EVM for CNGS

CNGS Review15 July 2003

M. Meddahi 11

Status of Work Units

Page 12: EVM for CNGS

CNGS Review15 July 2003

M. Meddahi 12

Work unit reporting

Page 13: EVM for CNGS

CNGS Review15 July 2003

M. Meddahi 13

Staff plan

Page 14: EVM for CNGS

CNGS Review15 July 2003

M. Meddahi 14

Planned cash Flow

Page 15: EVM for CNGS

CNGS Review15 July 2003

M. Meddahi 15

EVM summaries: an example

Proton Beam dump

WindowsShieldingHelium tubes

Target station

ShutterHadron Stop

Page 16: EVM for CNGS

CNGS Review15 July 2003

M. Meddahi 16

Summary

Organised the CNGS tasks in a Work Breakdown Structure

Defined the Work Units required to complete the project(313 Work Units for CNGS)

EVM CNGS baseline frozen on 9 May 2003

Earned Value Management applied to CNGS- Work is in progress- Monitoring of the project’s progress started (one report per month requested)