In This Issue
——————————————–—
Events & Updates
Land Acquisition Status & Critical Issues
Civil Works & Progress photos at a Glance
What's’ Happening beneath the Ground
Track Works at a Glance
E-News Letter for BMRCL Website only
https://english.bmrc.co.in/News/NewsSection
Shri Durga Shanker Mishra, IAS
Secretary to GoI, Ministry of Housing & Urban Affairs, &
Chairman, Bangalore Metro Rail Corporation Limited
Shri Ajay Seth, IAS
Managing Director
Bangalore Metro Rail Corporation Limited
Address: Bangalore Metro Rail Corporation Limited
3rd Floor, BMTC Complex, K H Road, Shanthinagar,
Bengaluru - 560 027. Web: www.bmrc.co.in
1
July 2020 Issue 123
Events & Updates
HON’BLE CHIEF MINISTER GOVERNMENT OF KARNATAKA LAUNCHED
THE COMMENCEMENT OF TUNNELLING WORK ON 30.07.2020
Shri B.S. Yeddiyurappa, Hon’ble Chief Minister along with other Cabinet Ministers, Government of Karnataka Launched
the Tunnelling work by the TBM named URJA to tunnel between Cantonment & Shivajinagar Underground Stations.
Under Phase-2 of the project, Reach-6 line consists of 13.9 kms of Underground Section with 12 Underground Stations.
Shri Ajay Seth, Managing Director, BMRCL & other officials were present on the occasion.
2
2
Sl. No
Reaches
No. of properties Required
No. of properties Acquired
[As per 28(4) & 3(1)]
Handed over to Eng. Section up to
July - 2020
Balance to be Handed over to Engg. Section
Govt. Priv. Total Govt. Priv. Total Govt. Priv. Total Govt. Priv. Total
1
Reach-1 Extn 38 522 560 38 522 560 38 485 523 0 37 37
Forest Land 21 0 21 0 0 0 21 0 21 0 0 0
2
Reach-2 Extn Station & Viaduct
25 99 124 25 97 122 25 97 122 0 2 2
Challaghatta Depot 10 24 34 10 24 34 10 24 34 0 0 0
3 Reach-3C Extn 3 111 114 3 105 108 3 105 108 0 6 6
4
Reach-4B Extn. 12 294 306 12 294 306 12 294 306 0 0 0
Anjanapura Depot 1 20 21 1 20 21 1 20 21 0 0 0
5
Reach-5 New Line 46 798 844 46 798 844 46 798 844 0 0 0
Hebbagodi Depot 1 57 58 1 57 58 1 57 58 0 0 0
6
Reach-6 (Elevated) 34 222 256 34 222 256 34 222 256 0 0 0
Reach - 6 (UG) 52 281 333 52 276 328 49 270 319 3 11 14
Kothnur Depot 4 64 68 4 64 68 4 64 68 0 0 0
Total 247 2492 2739 226 2479 2705 244 2436 2680 3 56 59
7 ORR Line 31 56 87 30 55 85 29 54 83 2 2 4
8 Airport line 61 280 341 61 229 290 14 63 77 47 217 264
Total 92 336 428 91 284 375 43 117 160 49 219 268
Grand Total 339 2828 3167 317 2763 3080 287 2553 2840 52 275 327
Land Acquisition Status for the month of July, 2020 of Phase-2, ORR -2A & Airport -2B Line
3
3
Critical issues faced regarding Land Acquisition for Phase-2 of the Project
Reach-6 Underground Section
Langford Town Station:- Local Military Authorities (LMA) have sent the proposal for
transfer of 2137.334. sqm of land on permanent basis and 5866.569 sqm on
temporary basis to Army Head Quarters. Matter is being pursued with Defence
Authorities.
Lakkasandra Village Sy. No. 14 and 15:- The re-location of 101 encroachers at
Lakkasandra land is under consideration of Deputy Commissioner, Bangalore
Urban and Karnataka Slum Development Board.
Phase-2 Progress up to 31st July, 2020
29
31
68
59
95
65
95
95
90
72
0 10 20 30 40 50 60 70 80 90 100
REACH-6-ELEV (GOTTIGERE TO SWAGATH CROSS ROAD)
REACH-5-P-3 (BOMMANAHALLI TO R V ROAD)
REACH-5-P-2 (HOSA ROAD TO BOMMANAHALLI)
REACH-5-P1 (BOMMASANDRA TO HOSA ROAD)
REACH-4B (PUTTENAHALLI CROSS TO ANJANAPURA TOWNSHIP)
REACH-3C (HESSARAGHATTA CROSS TO BANGALORE INTERNATIONAL EXHIBITION CENTER)
REACH-2B (PATTANAGERE TO CHELLAGHATTA DEPOT)
REACH-2A (MYSURU ROAD TO PATTANAGERE)
REACH-1B (VISVESVARAYA INDUSTRIAL AREA TO WHITEFIELD)
REACH-1A (BAIYAPPANAHALLI TO VISVESVARAYA INDUSTRIAL AREA)
CIVIL WORK PROGRESS IN PERCENTAGE
4
Phase– 2 Progress Photos at a glance
R-1A: Progress of works at Garudacharpalya Station R-1B : Whitefield Station – I Girder Erection completed,
Central slab work in progress
R-2A: Track Casting work in progress R-2B: View of Mailasandra Station finishing work in Progress
R-3C: Hand Railing Works from Pier 558 to Pier 568 R-4B: Road level views of Konanakunte Cross Station
4
5
Phase– 2 Progress Photos at a glance:
R-5-P1: Huskur Station Pier and Pier arm erection R-5-P2: Basapura Station-At Platform level Pier Arm PP3
erection work in progress
R-5-P3: Rail Segment erection in progress near R V Road R-6-Ele: Viaduct work in progress
R-6-UG-RT1: East to West Aerial view of Lakkasandra Station R-6-UG-RT1: Both TBM’s assembled at Shivajinagar Station
5
6
6
UNDERGROUND WORKS - REACH 6
DAIRY CIRCLE TO NAGAWARA -TOTAL LENGTH -13.9 KMS
Contractor - M/s Afcons Infrastructure Limited—RT-01
Sl No
RT-01 Progress Details as on 31.07.2020
1 Alignment of RT-1 Between South Ramp to Vellara Junction.
2 UG Works are divided into 4 Packages
Package-1
3 Station Works Progress
South Ramp:
Utility diversion work is in progress (95% completed).
Barricading board installation work is in progress (23% completed).
Secant Pile Construction work is in Progress (08% completed).
Retaining wall construction work completed.
Drain construction work is in progress (60% completed).
Road diversion work is in progress (65 % completed).
Trial trench excavation for utility identification is completed.
Dairy Circle Station:
Utility diversion work is in progress (82% completed).
Barricading board installation work is in progress (90% completed).
Secant Pile Construction work is in Progress (18% completed).
Drain construction work is in progress (16% completed).
Trial trench for utility identification is in progress.
Lakkasandra Station:
Building demolition work is in progress (88% completed).
Work area barricading is in progress (74% completed).
Secant Pile Construction work is in Progress (07% completed).
Langford Station:
Work area barricading 5% completed.
Vellara Launching Shaft:
Secant Pile Construction work is in progress (99% completed).
Casting Yard (Baiyappanahalli):
Work area barricading is in progress (85% completed).
Tunnel segment moulds calibration work completed.
Casting of temporary Tunnel rings (segments) in progress (17% completed).
Fabrication work of Trusses for shed work in progress.
RCC beam for rail of overhead Gantry crane is in progress.
7
7
Piling work in progress at Shivajinagar Station
UNDERGROUND WORKS - REACH 6
DAIRY CIRCLE TO NAGAWARA -TOTAL LENGTH -13.9 KMS
Contractor - M/s Larson & Toubro Ltd—RT-02
Sl No
RT-02 Progress Details as on 31.07.2020
1 Alignment of RT-2 Between Vellara to Shivajinagar.
2 UG Works are divided into 4 Packages
Package-2
3 Station Works Progress
Rastriya Military School Station: Secant Piles are being provided as temporary support structures. 48.8% of the piles for station box and 45% of the piles for entry exit have been completed. 14538 Cum (12.2%) of excavation for the station have been completed.
M G Road Station: Secant Piles are being provided as temporary support structures. 100% of the piles for station box and 38.1% of the piles for entry exit have been completed. 37241 Cum (38.3%) of excavation for the station have been completed.
Shivajinagar Station: Secant Piles are being provided as temporary support structures. 100.1% of the piles for station box and 67.2% of the piles for entry exit have been completed. 83956 Cum (73.1%) of excavation for the station have been completed .
4 Tunnel Works Progress
TBM 1: AVNI -(Tunnel Boring Starts at Shivajinagar & Ends at Vellara Junction)
Filter press connection work is in progress.
Area development to install allied equipment of TBM in progress.
TBM 2: VINDHYA-(Tunnel Boring Starts at Shivajinagar & Ends at Vellara Junction)
Tail shield joint alignment completed
Decking Rebar Cutting Bending works in progress at MG Road Station
Piling work in progress at Vellara Station
Front shield Fixing for the TBM
Finishing work for Main store at
Lakkasandra Yard
8
8
Commencement of Tunneling works at Cantonment Station
UNDERGROUND WORKS - REACH 6
DAIRY CIRCLE TO NAGAWARA -TOTAL LENGTH -13.9 KMS
Contractor - M/s Larson & Toubro Ltd—RT-03
Sl No
RT-03 Progress Details as on 31.07.2020
1 Alignment of RT-3 Between Shivajinagar to Pottery Town.
2 UG Works are divided into 4 Packages
Package-3
3 Station Works Progress
Cantonment Station:
Hard rock Excavation using Controlled blasting Technique is in progress. 42% of total
excavation, i.e. 67,700Cum of excavation is completed out of 1,62,000Cum.
1078 Sqm. of PCC has been done on south side of the station and a length of 90m has been made ready for launching of Tunnel Boring Machine.
Urja TBM (TBM No 1) was Commissioned by Hon’ble Chief Minister of Karnataka on
30.07.2020. This marks the commencement of Tunneling works from Cantonment station towards Shivaji Nagar station.
Vindhya TBM (TBM No – 2) has been assembled and testing of various components is in
progress.
Installation of Slurry Treatment plant is completed, testing of Slurry Treatment plant and
Laying of Slurry pipelines is in progress.
Pottery Town Station:
Temporary support system using Secant Piles are being provided; about 91.9% of the
secant piles for station box and 100% of the secant piles for Ancillary Building have been completed.
Excavation work for station box construction is in progress and so far 10% i.e. 16,735 Cum
of excavation has been completed out of 1,72,889 Cum.
Fabrication & Installation of first layer struts and waler beams are in progress.
4 Peenya Casting Yard Precast Tunnel segment casting is in progress. Casting of 18.3% of tunnel rings has been
completed so far, i.e. 594 Nos. of tunnel rings have been casted out of the total scope of 3244Nos.
Erection of 1st Ring at Cantonment Station
9
9
Track Works at a Glance
Contractor - M/s Texmaco Rail & Engineering Limited
Sl No Item Description Unit Track Plinth Casting
Sections Track Meters Reach 4
(July 2020) Reach 2
(July 2020)
1 Scope of Work Trm 12580 17628
2 Progress for the month Trm Nil 540
3 Cumulative progress Trm 11700 5967
4 Access Handed over Trm 11700 14900
R-1 Extn: Flash Butt Welding of Rail Joints
between K R Puram & Whitefield in progress
R-2 Extn: Track work in progress along the
viaduct between Nayadanahalli & Kengeri