ETCS Level 1 Deployment in Luxembourg

UIC ERTMS CONFERENCE 2006

BUDAPEST 05.04.2006

François JAEGER

Director CFL

Member of the CFL board of Directors

05.04.06 2

ETCS LEVEL 1 DEPLOYMENT IN LUXEMBOURGETCS LEVEL 1 DEPLOYMENT IN LUXEMBOURG

SUMMARY

0 - LUXEMBOURG GENERAL INFORMATIONS

1 - LUXEMBOURG NETWORK

2 - INFRASTRUCTURE

3 - PILOT PHASE

4 - ROLLING STOCK

5 - ACHIEVEMENTS AND LESSONS

6 - OPEN POINTS AND QUESTIONS

7 - CONCLUSIONS

05.04.06 3

0 0 -- LUXEMBOURG LUXEMBOURG General InformationGeneral Information

Luxembourg

Territory: 2586 km2

Population: ~ 451.000

Border countries: BelgiumFranceGermany

LUXEMBOURG

05.04.06 4

è270 km lines

è95% electrified

è70 % of the railway traffic is cross-border

ètraction units needs several CCSystems

TROISVIERGES

LUXEMBURG

KLEINBETTINGEN

PETANGEBETTEMBURG

ESCHsur

ALZETTE

ETTELBRUCK

Germany:- INDUSI / PZB- LZB

Luxembourg:- MEMOR II+- ETCS Level 1Belgium:

- Crocodile- TBL

France:- Crocodile- KVB / TVM

WASSERBILLIG

1 1 -- LUXEMBOURG NETWORKLUXEMBOURG NETWORKCharacteristics Characteristics -- CCSystemsCCSystems in Luxembourg / Neighbourhoodsin Luxembourg / Neighbourhoods

05.04.06 5

Ø 1973 CFL introduced crocodile system

Ø 1997 the implementation of MEMOR II+ (improvement of the crocodile system)

Ø 1999 CFL decided to introduce ETCS Level 1 on the complete Luxembourg railway network and to equip the whole whole rolling stock fleetfleet

Ø 2002 a German suppliera German supplier got the order to install ETCS Level 1 on the whole network, including including Infill functionality based onbased on Balise

Ø 2002 a French suppliera French supplier got the order for the ETCS equipment of a pre-series of 10 engines

1 1 -- LUXEMBOURG NETWORKLUXEMBOURG NETWORKCCSystemCCSystem in Luxembourg in Luxembourg -- HistoryHistory

Project supported by EU

05.04.06 6

1 1 -- LUXEMBOURG NETWORKLUXEMBOURG NETWORKTechnical migration for ETCS LEVEL 1Technical migration for ETCS LEVEL 1

Ø No direct interface between LEU* and the InterlockingØ Signal information picked up by 2 current sensors for each lampØ LEU also controls during migration MEMOR II+Ø Onboard ETCS EVC** controls the transitions between ETCS

and MEMOR II+ (cut off in/out interface of MEMOR II+ system)

* LEU Line-side Electronic Unit ** EVC European Vital Computer

Balises

MEMOR II+LEU

Antenna EVC

05.04.06 7

2 2 -- INFRASTRUCTURE INFRASTRUCTURE ETCS Level 1 and estimated costsETCS Level 1 and estimated costs

Ø ETCS increases safety level on the network

Ø ETCS achieves interoperability between Luxembourg and neighbouring countries

Ø Same standard on the whole network

Ø Fully compatible with TSI

Ø Luxembourg takes a whole network approach(European wide a corridor approach, the Corridor C Antwerp -Basle/Lyon will accelerate ETCS development in the area and the RS onboard migra tion)

Ø Total estimated costs for the entire network:for the entire network:24.665.406 € (1999)

05.04.06 8

2 2 -- INFRASTRUCTUREINFRASTRUCTUREMigrationMigration

Ø Migration duration : 5 years from 2003

Ø Started with SRS* Version 2.2.2. + several change requests applied in first phase (pilot line)

Ø 9 phases are foreseen for ETCS deployment Deployment is line oriented

Ø All main signals (v>40km/h) and distant signals are also equipped with Infill functionality (Balises)

Ø Determination of the national values

Ø Several changes introduced in the national operational rules due to ETCS migration

* SRS System Requirement Specification

05.04.06 9

2 2 -- INFRASTRUCTUREINFRASTRUCTURENational Values National Values -- Changes in National Operation RulesChanges in National Operation Rules

Variable Packet 3 ‚National Values‘ National Values

NID_C 56V_NVSHUNT 30km/hV_NVSTFF 40km/hV_NVONSIGHT 30km/hV_NVUNFIT 100km/hV_NVREL 25km/hD_NVROLL 2mQ_NVSRBKTRG 1 = YesQ_NVEMRRLS 0 = only at standstillV_NVALLOWOVTRP 40km/hV_NVSUPOVTRP 40km/hD_NVOVTRP 200mT_NVOVTRP 150sD_NVPOTRP 300mM_NVCONTACT 10 = no reactionT_NVCONTACT 1111 1111 = unlimitedM_NVDERUN 0 = NoD_NVSTFF 32767 = unlimitedQ_NVDRIVER_ADHES 1 = Yes

EXIGENCEFONCTIONNELLE ETCS

MESURE PRISE OU A PRENDRE PARLE GI LUXEMBOURGEOIS (REGLE

D’EXPLOITATION OU ADAPTATIONINFRASTRUCTURE)

STATUTDE

TRANSPOSITION

ETCS ne contrôle pas lesréductions de vitesse imposéespar des conditions de freinageforfaitaire

le GI luxembourgeois a pris tout un train demesures pour supprimer ces réductions devitesses:

déterminer la vitesse maximale autoriséepar les conditions de freinage en fonctionde la vitesse-limite de la ligne, si cettevitesse est inférieure à la vitesse autoriséepar la catégorie de circulation

R

déterminer la vitesse maximale autoriséepar les conditions de freinage en fonctiondes distances d’implantation réelles desSFAv et des déclivités réelles,

R

adapter la distance d’implantation decertains SFAv à la distance d’arrêtnécessaire

AT

augmentation des pourcentages de freinageforfaitaires minimaux de certainescatégories de trains : celui des MA 90 ⇒63%, celui des V120 ⇒ 100%, celui desV140 ⇒ 120%

AT

définition de nouveaux pourcentages defreinage minimaux pour les Hlp, les Hpv etles trains de locomotives

AT

nouvelle distance de protection desobstacles de 1500 m

R

National Values Changes in National Operation Rules

05.04.06 10

2 2 -- INFRASTRUCTURE INFRASTRUCTURE LinesideLineside Electronic Unit and Electronic Unit and EurobaliseEurobalise

Line-side Electronic Unit

Switch-able Balise

Signal Electronic Unit

05.04.06 11

TROISVIERGES

ETTELBRUCK

LUXEMBURG

KLEINBETTINGEN

PETANGEBETTEMBURGESCH /

ALZETTE

WASSERBILLIG

Phase 1 completed(Pilot phase)

2 2 -- INFRASTRUCTURE INFRASTRUCTURE State of playState of play

Phase 2 completed

LORENTZWEILER

SANDWEILERDOMMELDANGE

WALFERDANGE

MERSCH

LINTGEN

HEISDORF

CENTS-HAMM

COLMAR-US

BÜRDEN

ETTELBRUCK

DIEKIRCH

SCHIEREN

BISSEN

COLMARBERG

CRUCHTEN

Phases 3 and 4

05.04.06 12

3 3 -- PILOT PHASEPILOT PHASESUMM UP of the pilot lineSUMM UP of the pilot line

Ø ~50 km line equipped with ETCS level 1Ø 10 traction units equipped with ETCS level 1Ø ETCS Version 2.2.2. + several change requests

corresponding to subset 108Ø All problems solved on an international level, no

national solution (UNISIG Group)Ø First tests with CFL D-railcar: December 2003Ø Commercial service: March 2005

Ø Commercial train kilometres: ~ 16.600 km

05.04.06 13

3 3 -- PILOT PHASEPILOT PHASERolling stock Rolling stock -- First migration phase achieved 2003First migration phase achieved 2003--20052005

Pilot phase started in 2004 with 10 engines

3 D-Railcar CFL 2100 (same as SNCF X73500)

Equipped with ETCS: 12/2003 - 04/2004Use: Passenger trains cross-border and on corridor

Cost per engine: 227 074,- €

4 EMU CFL 2000 (same as SNCF Z11500)

Equipped with ETCS: 09/2004 - 12/2004 Use: Passenger trains cross-border and on corridor (needs two equipments per EMU due to the length of the EMU)

Cost per engine: 353 284,- €

3 E-Locos CFL 3000 (same as SNCB T13)

Equipped with ETCS: 05/2004 - 07/2005Use: Freight / passengers trains cross-border and on corridor

Cost per engine: 260 144,- €

3 0 0 1

Total costs for the 10 engines: 3 035 000,-€

05.04.06 14

3 3 -- PILOT PHASEPILOT PHASEMain goals achievedMain goals achieved

Ø Test components on- Infrastructure- Rolling Stock

Ø Test of the system ETCS level 1Ø Validation of the systemØ Reduction of maintenance costsØ Improved safetyØ High reliability level Ø No major train delays

Project supported by EU

05.04.06 15

4 4 -- ROLLING STOCKROLLING STOCKOnboard MigrationOnboard Migration

20062006

20072007

20082008

18 EMU CFL 2000 (same as SNCF Z11500)CCS-system: MEMOR II+ Use: Passenger trains cross-border and on corridor*

Cost per engine: ~300.000,- €

12 EMU CFL 2200 (same as SNCF Z 24500)CCS-system: MEMOR II+, KVBUse: Passenger trains cross-border and on corridor*

16 E-Locos CFL 3000 (same as SNCB T13)CCS-system: MEMOR II+, KVB, TBLUse: Freight / passengers trains cross-border and on corridor*

3001

18 Control trailer CFL DABpbdzfa A14CCS-system: MEMOR II+, PZB (same as DB AG DBpbzfa 766)Passenger trains cross-border and on corridor*

20 E-Locos CFL 4000 (same as DB AG 185)CCS-system: MEMOR II+, KVB, PZBUse: Passenger / freight trains cross-border and on corridor*

* corridor C Antwerp - Basle/Lyon

05.04.06 16

4 4 -- ROLLING STOCKROLLING STOCKOnboard MigrationOnboard Migration

Roll-out phase will start when:- equipment prices are acceptable !

- and financing is secured !(Railway Undertaking and MS + EU Funds)

05.04.06 17

4 4 -- ROLLING STOCKROLLING STOCKOnboard MigrationOnboard Migration

Equipment of the Electric Multiple Unit 2000

DM I Driver

Machine Interface

EVC European

Vital Computer

Radar

Antenna

Speed Sensor

Accelerometer

05.04.06 18

5 5 -- ACHIEVEMENTS AND LESSONS (1/2)ACHIEVEMENTS AND LESSONS (1/2)

+ ~100 km (double/single track) equipped with ETCS + 10 traction units equipped with ETCS + No major problem to equip (INFRA + RS)+ ETCS version 2.2.2. + several change requests

corresponding to subset 108+ No national solution implemented + Changing operation rules to introduce ETCS+ Commercial service from March 2005

(no major train delays due to the introduction of ETCS)

+ Commercial train kilometres: ~ 27.100 km+ Increased safety level (MEMOR II+)

05.04.06 19

5 5 -- ACHIEVEMENTS AND LESSONS (2/2)ACHIEVEMENTS AND LESSONS (2/2)

+ No relevant failures (INFRA + RS) + No interoperability problems between INFRA + RS

(two different suppliers)

+ No interferences with actual system Memor II++ End of MEMOR II+ by 2017

- Multiple Units need two equipments (additional costs)

- Problems with homologation of ETCS RS on other networks (costs and time)

- ETCS equipment for RS increases costs currently (costs of prototype and series)

- Combined ETCS/National System are not helpful for Interoperability

05.04.06 20

6 6 -- OPEN POINTS and QUESTIONS (1/2)OPEN POINTS and QUESTIONS (1/2)

Ø Cross acceptance !Re-examination of the rolling stock authorisation for the modified engines in the

bordering countries (long lasting process and high additional co sts)

Ø Braking curves not unified !

Ø Transition between the different CCSystems ! (No specific STM available in the worst case standing transition)

Ø 70% of the trains in Luxembourg are cross-border, traction units need several CCSystems !

Ø Several data recorders within one engine to pass border (JRU, ATESS, DSK) !

05.04.06 21

6 6 -- OPEN POINTS and QUESTIONS (2/2) OPEN POINTS and QUESTIONS (2/2)

Ø Compatibility problems between ETCS balises and KVB on board equipment !

Ø State of play of the RS migration of other RUsoperating in the area ?

Ø Retrofitting ETCS on RS is actually a high invest for CFL and other "ETCS RUs" !

Ø State of play of MS and EU funding?

Ø Funding prototype (fix costs) and series?

Ø All traction units should qualify for EU funds?(Locomotives, multiple units, control trailers, .....)

05.04.06 22

7 7 -- MAIN CONCLUSIONSMAIN CONCLUSIONS

ETCS:Ø in Luxembourg is aligned on the EU policies

Ømigration phase for Luxembourg INFRA assured

Ømigration phase on RS is challenging(high costs, cross acceptance and different migration strategies of other RUs)

Øon the Corridor C Antwerp- Basle/ Lyon will certainly accelerate the migration in the area (INFRA +RS)

Ø is expensive on INFRA and particularly on RS side

Øneeds MS and EU funds for INFRA and RS

Ø insures interoperability and is an important projectfor Luxembourg and Europe