estimation qms training. objective to arrive at accurate estimates for the project mahindra satyam...
TRANSCRIPT
![Page 1: Estimation QMS Training. Objective To arrive at accurate estimates for the project Mahindra Satyam Confidential2](https://reader036.vdocuments.site/reader036/viewer/2022082713/5697bf811a28abf838c8568d/html5/thumbnails/1.jpg)
Estimation
QMS Training
![Page 2: Estimation QMS Training. Objective To arrive at accurate estimates for the project Mahindra Satyam Confidential2](https://reader036.vdocuments.site/reader036/viewer/2022082713/5697bf811a28abf838c8568d/html5/thumbnails/2.jpg)
Objective
• To arrive at accurate estimates for the project
Mahindra Satyam ConfidentialMahindra Satyam Confidential 22
![Page 3: Estimation QMS Training. Objective To arrive at accurate estimates for the project Mahindra Satyam Confidential2](https://reader036.vdocuments.site/reader036/viewer/2022082713/5697bf811a28abf838c8568d/html5/thumbnails/3.jpg)
Estimation
Mahindra Satyam ConfidentialMahindra Satyam Confidential 33
Accurate Estimates areAccurate Estimates are
![Page 4: Estimation QMS Training. Objective To arrive at accurate estimates for the project Mahindra Satyam Confidential2](https://reader036.vdocuments.site/reader036/viewer/2022082713/5697bf811a28abf838c8568d/html5/thumbnails/4.jpg)
Estimation
• For a Project, the Estimates are computed several times– At Project Acquisition Phase– At Project Planning Phase– During Project Execution Phase
Mahindra Satyam ConfidentialMahindra Satyam Confidential 44
![Page 5: Estimation QMS Training. Objective To arrive at accurate estimates for the project Mahindra Satyam Confidential2](https://reader036.vdocuments.site/reader036/viewer/2022082713/5697bf811a28abf838c8568d/html5/thumbnails/5.jpg)
Estimation at Project Acquisition Phase
• The Proposal team performs the estimation based on the inputs available at that phase
Mahindra Satyam ConfidentialMahindra Satyam Confidential 55
![Page 6: Estimation QMS Training. Objective To arrive at accurate estimates for the project Mahindra Satyam Confidential2](https://reader036.vdocuments.site/reader036/viewer/2022082713/5697bf811a28abf838c8568d/html5/thumbnails/6.jpg)
Estimation at Project Planning Phase
The PL • Performs the estimation based on
– the estimates at the Acquisition phase– further requirements obtained later
• Documents these estimates in the Broad Estimates section of the project plan
• Records the discrepancy, if any, between these estimates and the commitments made to the customer, along with the actions to be taken
Mahindra Satyam ConfidentialMahindra Satyam Confidential 66
![Page 7: Estimation QMS Training. Objective To arrive at accurate estimates for the project Mahindra Satyam Confidential2](https://reader036.vdocuments.site/reader036/viewer/2022082713/5697bf811a28abf838c8568d/html5/thumbnails/7.jpg)
Estimation at Project Planning Phase
The PL • Defines the phases / milestones / events at which
the estimates are to be re-visited• Documents these in the Estimation Schedule
section of the project plan
Mahindra Satyam ConfidentialMahindra Satyam Confidential 77
![Page 8: Estimation QMS Training. Objective To arrive at accurate estimates for the project Mahindra Satyam Confidential2](https://reader036.vdocuments.site/reader036/viewer/2022082713/5697bf811a28abf838c8568d/html5/thumbnails/8.jpg)
Estimation during Project Execution Phase
• The PL re-visits the estimates– Following the schedule documented in the project
plan, and/or– When any anomaly such as a slipped schedule or a
large change request, occurs in the project
• The PL performs the estimation based on– the current project requirements– the estimates from the earlier phases
Mahindra Satyam ConfidentialMahindra Satyam Confidential 88
![Page 9: Estimation QMS Training. Objective To arrive at accurate estimates for the project Mahindra Satyam Confidential2](https://reader036.vdocuments.site/reader036/viewer/2022082713/5697bf811a28abf838c8568d/html5/thumbnails/9.jpg)
Estimation
• The process for all these instances of Estimation is the same
• Different Estimation methods can be used for different instances in the same project, based on– Inputs Available – Past Data Available– Assumptions of method to match with those of
the project
Mahindra Satyam ConfidentialMahindra Satyam Confidential 99
![Page 10: Estimation QMS Training. Objective To arrive at accurate estimates for the project Mahindra Satyam Confidential2](https://reader036.vdocuments.site/reader036/viewer/2022082713/5697bf811a28abf838c8568d/html5/thumbnails/10.jpg)
Process
Mahindra Satyam ConfidentialMahindra Satyam Confidential 1010
Select an Estimation Method
Perform the Estimation
Review the Estimates
Approve the Estimates
![Page 11: Estimation QMS Training. Objective To arrive at accurate estimates for the project Mahindra Satyam Confidential2](https://reader036.vdocuments.site/reader036/viewer/2022082713/5697bf811a28abf838c8568d/html5/thumbnails/11.jpg)
Select an Estimation Method
• PL/PM selects an appropriate method to be followed in the project based on the criteria defined
• Obtains the corresponding Estimation WorkSheet from QUALIFY
• If a different method is to be used, prepares the Estimation WorkSheet in line with the Formats available in QUALIFY– The Cover Page should be exactly the same as in the case of
available WorkSheets
Mahindra Satyam ConfidentialMahindra Satyam Confidential 1111
![Page 12: Estimation QMS Training. Objective To arrive at accurate estimates for the project Mahindra Satyam Confidential2](https://reader036.vdocuments.site/reader036/viewer/2022082713/5697bf811a28abf838c8568d/html5/thumbnails/12.jpg)
Perform the Estimation• PL/PM
– computes the estimates for size, effort, schedule and resources based on selected Estimation Method using the Estimation WorkSheet
– uses the following inputs and document them in the Estimation WorkSheet:
• Appropriate past data from Mahindra Satyam’s Project Knowledge Base
• Data from the previous phases / work requests of the project
Mahindra Satyam ConfidentialMahindra Satyam Confidential 1212
![Page 13: Estimation QMS Training. Objective To arrive at accurate estimates for the project Mahindra Satyam Confidential2](https://reader036.vdocuments.site/reader036/viewer/2022082713/5697bf811a28abf838c8568d/html5/thumbnails/13.jpg)
Review the Estimates
• PM and/or another PM/PL having sufficient knowledge on similar projects reviews the estimates – The Estimation Review Checklist and the
Review Report are used for recording and tracking this review
– These are attached to the Estimation WorkSheet
Mahindra Satyam ConfidentialMahindra Satyam Confidential 1313
![Page 14: Estimation QMS Training. Objective To arrive at accurate estimates for the project Mahindra Satyam Confidential2](https://reader036.vdocuments.site/reader036/viewer/2022082713/5697bf811a28abf838c8568d/html5/thumbnails/14.jpg)
Approve the Estimates
• Pre-sales approves the estimates during pre-project stage
• PM approves the estimates during Project Planning and Project Execution
• This approval is recorded in the Estimation WorkSheet
Mahindra Satyam ConfidentialMahindra Satyam Confidential 1414
![Page 15: Estimation QMS Training. Objective To arrive at accurate estimates for the project Mahindra Satyam Confidential2](https://reader036.vdocuments.site/reader036/viewer/2022082713/5697bf811a28abf838c8568d/html5/thumbnails/15.jpg)
Objective met
• The accurate estimates for the project are arrived at, when required
Mahindra Satyam ConfidentialMahindra Satyam Confidential 1515