esrpp 2009 regional studies initial results
DESCRIPTION
ESRPP 2009 Regional Studies Initial Results. ESRPP Stakeholder Meeting August 12, 2009 Astor Crown Plaza New Orleans, Louisiana. Selected ESRPP Study Projects. Turk-McNeil 345 kV Spadra-Russellville 161 kV Turk-Fulton-El Dorado 345 kV Messick 500/230 kV Autotransformer - PowerPoint PPT PresentationTRANSCRIPT
![Page 1: ESRPP 2009 Regional Studies Initial Results](https://reader035.vdocuments.site/reader035/viewer/2022062519/568150a9550346895dbebc8a/html5/thumbnails/1.jpg)
SPP.org 1
![Page 2: ESRPP 2009 Regional Studies Initial Results](https://reader035.vdocuments.site/reader035/viewer/2022062519/568150a9550346895dbebc8a/html5/thumbnails/2.jpg)
ESRPP 2009 Regional StudiesInitial Results
ESRPP Stakeholder MeetingAugust 12, 2009Astor Crown PlazaNew Orleans, Louisiana
![Page 3: ESRPP 2009 Regional Studies Initial Results](https://reader035.vdocuments.site/reader035/viewer/2022062519/568150a9550346895dbebc8a/html5/thumbnails/3.jpg)
SPP.org 3
Selected ESRPP Study Projects
• Turk-McNeil 345 kV
• Spadra-Russellville 161 kV
• Turk-Fulton-El Dorado 345 kV
• Messick 500/230 kV Autotransformer
• Flint Creek-Chamber Spr-Fort Smith-ANO 345 kV
![Page 4: ESRPP 2009 Regional Studies Initial Results](https://reader035.vdocuments.site/reader035/viewer/2022062519/568150a9550346895dbebc8a/html5/thumbnails/4.jpg)
SPP.org 4
Regional Study Overview Map
3
1
3
52
345 kV
161 kV
![Page 5: ESRPP 2009 Regional Studies Initial Results](https://reader035.vdocuments.site/reader035/viewer/2022062519/568150a9550346895dbebc8a/html5/thumbnails/5.jpg)
SPP.org 5
General Study Assumptions for Step 1 High-Level Analysis
• MUST DC analysis of FCITC
• Monitored and Contingent Elements
• 115 kV and above elements within:
1. Entergy Zones adjacent to SPP
2. SPP Areas adjacent to Entergy
• All elements 345 kV and above in SPP and Entergy
• N-1 Contingency Scan (no breaker-to-breaker scan)
![Page 6: ESRPP 2009 Regional Studies Initial Results](https://reader035.vdocuments.site/reader035/viewer/2022062519/568150a9550346895dbebc8a/html5/thumbnails/6.jpg)
SPP.org 6
General Study Assumptions for Step 1 High-Level Analysis, cont.
• MDWG MOD Model 2014 Summer Peak
• Incorporate Entergy’s Construction Plan Projects
• Identical Source/Sink Transfer Analyses will be performed for all study projects
• FCITC Changes from the Base Case will be identified
• Planning-level cost estimates and construction timelines provided
![Page 7: ESRPP 2009 Regional Studies Initial Results](https://reader035.vdocuments.site/reader035/viewer/2022062519/568150a9550346895dbebc8a/html5/thumbnails/7.jpg)
SPP.org 7
AEPW
CLECO
SWPAEMDE
OGE
WOTABAmite
South
SPP Areas
SPP (all)
AEP West
CLECO
OG&E
Empire District
SWPA
Entergy Areas
Entergy (all)
Amite South
WOTAB
18 Combinations, bi-directionally = 36 Combinations
Source/Sink Areas for Transfer Analysis
![Page 8: ESRPP 2009 Regional Studies Initial Results](https://reader035.vdocuments.site/reader035/viewer/2022062519/568150a9550346895dbebc8a/html5/thumbnails/8.jpg)
SPP.org 8
Entergy Net Interchange
• 1471 MW Net Export to all areas
• 1033 MW Net Export to SPPArea MW
CLECO 596LAFA -91LEPA 53SWPA -253AEPW -49OGE 744EMDE 33
Positive number indicates EXPORTNegative number indicates IMPORT
![Page 9: ESRPP 2009 Regional Studies Initial Results](https://reader035.vdocuments.site/reader035/viewer/2022062519/568150a9550346895dbebc8a/html5/thumbnails/9.jpg)
SPP.org 9
FCITC Results: Baseline
SOURCE SINK SOURCE SINK SOURCE SINKFCITC (347) 1767 (1097) 1180 (999) (1212)
FCITC (2434) 761 (1024) 696 (975) (1318)
FCITC (768) (293) (536) (344) (1115) (418)
FCITC (570) 1041 (1253) 1041 (1000) (1006)
FCITC (676) 625 (1172) 625 (992) (1070)
FCITC (939) 1204 (1262) 1207 (1001) (1005)SWPA
AEPW
CLECO
EMDE
OGE
EES ALL AMITE SOUTH WOTAB
SPP ALL
![Page 10: ESRPP 2009 Regional Studies Initial Results](https://reader035.vdocuments.site/reader035/viewer/2022062519/568150a9550346895dbebc8a/html5/thumbnails/10.jpg)
SPP.org 10
(#1) Turk – McNeil 345 kV
Turk
McNeil
New 345 kV Line
![Page 11: ESRPP 2009 Regional Studies Initial Results](https://reader035.vdocuments.site/reader035/viewer/2022062519/568150a9550346895dbebc8a/html5/thumbnails/11.jpg)
SPP.org 11
FCITC Results: Turk-McNeil 345 kV
SOURCE SINK SOURCE SINK SOURCE SINKFCITC (241) 1917 (1086) 1226 (996) (1166)Change 105 150 11 46 3 46FCITC (2545) 810 (1053) 728 (975) (1245)Change (111) 49 (28) 32 0 73FCITC (752) (291) (523) (342) (1110) (415)Change 16 2 13 2 5 2FCITC (543) 1041 (1234) 1041 (995) (977)Change 27 0 19 0 4 29FCITC (189) 625 (1163) 625 (990) (1032)Change 487 (0) 9 (0) 3 39FCITC (920) 1204 (1238) 1207 (997) (980)Change 19 (0) 24 (0) 5 25
SWPA
AEPW
EES ALL AMITE SOUTH WOTAB
SPP ALL
CLECO
EMDE
OGE
![Page 12: ESRPP 2009 Regional Studies Initial Results](https://reader035.vdocuments.site/reader035/viewer/2022062519/568150a9550346895dbebc8a/html5/thumbnails/12.jpg)
SPP.org 12
(#2) Spadra – Russellville 161kV Line
Little Spadra
Russellville East
New 161 kV Line
![Page 13: ESRPP 2009 Regional Studies Initial Results](https://reader035.vdocuments.site/reader035/viewer/2022062519/568150a9550346895dbebc8a/html5/thumbnails/13.jpg)
SPP.org 13
FCITC Results: Spadra-Russellville 161 kV
SOURCE SINK SOURCE SINK SOURCE SINKFCITC (802) 1765 (1096) 1177 (999) (1211)Change (455) (2) 1 (3) 0 1FCITC (2433) 759 (1024) 694 (975) (1317)Change 1 (2) 1 (2) 0 1FCITC (768) (293) (535) (344) (1115) (418)Change 0 0 0 0 0 0FCITC (690) 1041 (1253) 1041 (999) (1006)Change (120) 0 1 0 0 1FCITC (627) 625 (1172) 625 (992) (1070)Change 49 0 0 (0) 0 1FCITC (961) 1204 (1261) 1207 (1001) (1004)Change (23) (0) 1 (0) 0 1
AMITE SOUTH WOTAB
SPP ALL
AEPW
CLECO
EMDE
EES ALL
OGE
SWPA
![Page 14: ESRPP 2009 Regional Studies Initial Results](https://reader035.vdocuments.site/reader035/viewer/2022062519/568150a9550346895dbebc8a/html5/thumbnails/14.jpg)
SPP.org 14
(#3) Turk – Fulton – El Dorado 345 kV
Turk
El Dorado345 kV
Fulton
New 345 kV Line
![Page 15: ESRPP 2009 Regional Studies Initial Results](https://reader035.vdocuments.site/reader035/viewer/2022062519/568150a9550346895dbebc8a/html5/thumbnails/15.jpg)
SPP.org 15
FCITC Results: Turk-Fulton-El Dorado 345 kV
SOURCE SINK SOURCE SINK SOURCE SINKFCITC (274) 1895 (1089) 1229 (997) (1178)Change 73 128 8 49 2 35FCITC (2510) 803 (1053) 726 (976) (1263)Change (77) 41 (28) 30 (0) 54FCITC (756) (291) (526) (342) (1111) (415)Change 12 2 9 2 4 3FCITC (553) 1041 (1240) 1041 (997) (984)Change 17 0 13 0 3 23FCITC (641) 625 (1166) 625 (991) (1041)Change 34 (0) 6 (0) 1 29FCITC (927) 1204 (1246) 1207 (998) (985)Change 12 0 16 (0) 3 20
WOTAB
AEPW
EES ALL AMITE SOUTH
SPP ALL
SWPA
CLECO
EMDE
OGE
![Page 16: ESRPP 2009 Regional Studies Initial Results](https://reader035.vdocuments.site/reader035/viewer/2022062519/568150a9550346895dbebc8a/html5/thumbnails/16.jpg)
SPP.org 16
(#3) Messick 500/230kV Autotransformer
New 500/230kV Autotransformer
at Messick
Existing Mt. Olive-Hartburg 500 kV
Line
![Page 17: ESRPP 2009 Regional Studies Initial Results](https://reader035.vdocuments.site/reader035/viewer/2022062519/568150a9550346895dbebc8a/html5/thumbnails/17.jpg)
SPP.org 17
FCITC Results: Messick 500/230 kV Auto
SOURCE SINK SOURCE SINK SOURCE SINKFCITC (341) 1809 (1097) 1197 (997) (1203)Change 6 43 0 17 2 9FCITC (2496) 782 (1029) 711 (972) (1300)Change (62) 20 (5) 14 4 17FCITC (783) (140) (541) (164) (1099) (197)Change (15) 152 (6) 180 4 221FCITC (568) 1041 (1246) 1041 (1000) (1002)Change 1 0 7 0 (0) 5FCITC (673) 625 (1169) 625 (992) (1064)Change 3 0 3 (0) 1 6FCITC (938) 1204 (1253) 1207 (1002) (1001)Change 1 0 9 0 (1) 4
AMITE SOUTHEES ALL
OGE
SPP ALL
WOTAB
AEPW
CLECO
EMDE
SWPA
![Page 18: ESRPP 2009 Regional Studies Initial Results](https://reader035.vdocuments.site/reader035/viewer/2022062519/568150a9550346895dbebc8a/html5/thumbnails/18.jpg)
SPP.org 18
(#5) Flint Creek – Chamber Springs – Fort Smith – ANO 345kV Line
Flint CreekChamber
Springs
Fort Smith
ANO
New 345 kV Line
![Page 19: ESRPP 2009 Regional Studies Initial Results](https://reader035.vdocuments.site/reader035/viewer/2022062519/568150a9550346895dbebc8a/html5/thumbnails/19.jpg)
SPP.org 19
FCITC Results: Flint Creek-Chamber Spr-Ft Smith-ANO 345 kV
SOURCE SINK SOURCE SINK SOURCE SINKFCITC 132 1741 (1101) 1151 (998) (1220)Change 479 (26) (4) (29) 1 (8)FCITC (2441) 739 (1029) 675 (975) (1326)Change (7) (23) (4) (22) 1 (8)FCITC (772) (296) (538) (348) (1114) (422)Change (4) (3) (3) (4) 1 (4)FCITC (400) 1041 (1256) 1041 (999) (1014)Change 170 0 (3) 0 1 (7)FCITC 115 625 (1178) 625 (992) (1077)Change 791 0 (5) 0 1 (7)FCITC (853) 1204 (1267) 1206 (1000) (1011)Change 86 (1) (5) (1) 1 (6)
OGE
SPP ALL
SWPA
WOTAB
AEPW
CLECO
EMDE
AMITE SOUTHEES ALL
![Page 20: ESRPP 2009 Regional Studies Initial Results](https://reader035.vdocuments.site/reader035/viewer/2022062519/568150a9550346895dbebc8a/html5/thumbnails/20.jpg)
SPP.org 20
Next Steps
• Continue Transfer Analysis
• Next Meeting: Draft Report, Stakeholder Input
• Post Final Report
• First Meeting of Next Cycle:
• Select Step 2 Studies
• Select Step 1 Studies