erp implementation in saa

Upload: shrutibag

Post on 07-Apr-2018

269 views

Category:

Documents


10 download

TRANSCRIPT

  • 8/4/2019 Erp Implementation in Saa

    1/21

    Click to edit Master subtitle style

    4/15/12

    Presented By-:

    Aishwary shuklaAnirban Kaushik

    Anisha RRaj kumarShruti Bag

    ERP Implementation In

    SAA

  • 8/4/2019 Erp Implementation in Saa

    2/21

    4/15/12

    Project Overview

    Implementing an ERP Project for South African

    Airlines @ Johannesburg. The Project involves

    following parameters:

    The Budget is US$ 1,00,00,000

    The Time frame is 12 months

    Team members - 7 and Native of Johannesburg.

  • 8/4/2019 Erp Implementation in Saa

    3/21

    4/15/12

    South African Airlines

    South African Airways is Africas leading airline serving

    more than 700 destinations throughout the world

    carrying more than 6.5 million passengers each year to

    34 cities in 26 countries on 6 continents, employing close

    to 11, 000 people worldwide

  • 8/4/2019 Erp Implementation in Saa

    4/21

    4/15/12

    Industry overview - Global

    Since 2000, aviation industry - profit of US$5,6-billion (as

    on 2007)

    Major concern rise in oil prices

    Airlines are seeking to cut costs by grounding aircraft,

    scrapping unprofitable routes and merging

    Further casualties are expected in the airline industry if the

    oil price remains high, and a decline in industry profitability

  • 8/4/2019 Erp Implementation in Saa

    5/21

    4/15/12

    Companys Concern

    Vision and Mission - delivering sustainable profits and

    growing our market share by offering world class service

    to our customers

    SAA is mostly concentrating on high density routes to

    improve its opportunities.

    The focus is on ensuring profits and sustain in the

    competitive industry

  • 8/4/2019 Erp Implementation in Saa

    6/21

    4/15/12

    CASE 1

    You are the Project Manager goingfrom India and how will you go aboutthe Project?

  • 8/4/2019 Erp Implementation in Saa

    7/21

    4/15/12

    Resource AllocationName Competencies

    A ERP specialist/Testing & Implementation

    B System Analysis & Network Engineer

    C Hardware & Software Engineer

    D Network & Hardware Engineer

    E Design & Implementation

    F Analysis & Testing

    G Design &Testing

  • 8/4/2019 Erp Implementation in Saa

    8/21

    Click to edit Master subtitle style

    4/15/12

    REPORTING CHART

  • 8/4/2019 Erp Implementation in Saa

    9/21

    4/15/12

    Task Allocation

    CompetenciesAishwaryA nirban Anisha Rajkumar Shruti Sudhir Koustu

    Ana lys is Yes No No yes No No A l t

    Netw ork EngineerN o N o Ye s N o A LT N o N o

    Softw are EngineerN o N o A LT Ye s N o N o N o

    H ardw are EngineerN o N o N o A LT Y es N o N o

    System An a lys is N o yes No Yes No ALT N o

    Design an d

    Implementat i

    AL T N o N o N o N o N o Y es

    Testin g N o Yes N o N o N o N o A LT

  • 8/4/2019 Erp Implementation in Saa

    10/21

    4/15/12

    Planning

    Project ScheduleWork Percentage Time in days

    As-Is process 5 9

    To be process 6 12

    Detail Des. &

    Dep.

    30 70

    Gap Analysis 3.5 2

    Realization 4.5 8

    Preparation ForGoing Live

    48 100

    Execution 2 3

    Sign Off 1 2

    Total

    209

    Lead 40

  • 8/4/2019 Erp Implementation in Saa

    11/21

    4/15/12

    COST ALLOCATIONPhase Planned Budget Allocation (in $)

    As-Is-Process 10,000

    To-be-Process 1,00,000

    Detailed Design & Development ForExecution

    30,40,000

    Gap-Analysis 20,000

    Realization 10,00,000

    Preparation for Going Live 5,30,000

    Going Live 20,00,000

    Sign-off 1,00,000

    For Contingencies 30,00,000

    Total 1,00,00,000

  • 8/4/2019 Erp Implementation in Saa

    12/21

    4/15/12

    Project Schedule

    Projectschedule.mpp

    http://var/www/apps/conversion/current/tmp/scratch10651/Project%20schedule.mpphttp://var/www/apps/conversion/current/tmp/scratch10651/Project%20schedule.mpphttp://var/www/apps/conversion/current/tmp/scratch10651/Project%20schedule.mpphttp://var/www/apps/conversion/current/tmp/scratch10651/Project%20schedule.mpp
  • 8/4/2019 Erp Implementation in Saa

    13/21

    4/15/12

    Risk Management

    Risk RegisterActions Consequences

    Fast Track -Add Risk- Add cost

    Crashing -Adds Cost- May add management time

    Reduce/Add Scope -Lead to save/add cost and time- negatively/positively impact customersatisfaction

    Cut-quality -Negatively impact customer satisfaction- may increase risk-Could possibly save cost

    http://var/www/apps/conversion/current/tmp/scratch10651/Project%20schedule.mpphttp://var/www/apps/conversion/current/tmp/scratch10651/Project%20schedule.mpphttp://var/www/apps/conversion/current/tmp/scratch10651/Project%20schedule.mpphttp://var/www/apps/conversion/current/tmp/scratch10651/Project%20schedule.mpphttp://var/www/apps/conversion/current/tmp/scratch10651/Project%20schedule.mpphttp://var/www/apps/conversion/current/tmp/scratch10651/Project%20schedule.mpphttp://var/www/apps/conversion/current/tmp/scratch10651/Project%20schedule.mpphttp://var/www/apps/conversion/current/tmp/scratch10651/Project%20schedule.mpphttp://var/www/apps/conversion/current/tmp/scratch10651/Project%20schedule.mpphttp://var/www/apps/conversion/current/tmp/scratch10651/Project%20schedule.mpphttp://var/www/apps/conversion/current/tmp/scratch10651/Project%20schedule.mpphttp://var/www/apps/conversion/current/tmp/scratch10651/Project%20schedule.mpphttp://var/www/apps/conversion/current/tmp/scratch10651/Project%20schedule.mpphttp://var/www/apps/conversion/current/tmp/scratch10651/Project%20schedule.mpphttp://var/www/apps/conversion/current/tmp/scratch10651/Project%20schedule.mpphttp://var/www/apps/conversion/current/tmp/scratch10651/Project%20schedule.mpphttp://var/www/apps/conversion/current/tmp/scratch10651/Project%20schedule.mpphttp://var/www/apps/conversion/current/tmp/scratch10651/Project%20schedule.mpphttp://var/www/apps/conversion/current/tmp/scratch10651/Project%20schedule.mpphttp://var/www/apps/conversion/current/tmp/scratch10651/Project%20schedule.mpphttp://var/www/apps/conversion/current/tmp/scratch10651/Project%20schedule.mpphttp://var/www/apps/conversion/current/tmp/scratch10651/Project%20schedule.mpphttp://var/www/apps/conversion/current/tmp/scratch10651/Project%20schedule.mpphttp://var/www/apps/conversion/current/tmp/scratch10651/Project%20schedule.mpphttp://var/www/apps/conversion/current/tmp/scratch10651/Project%20schedule.mpphttp://var/www/apps/conversion/current/tmp/scratch10651/Project%20schedule.mpp
  • 8/4/2019 Erp Implementation in Saa

    14/21

    4/15/12

    Situational AnalysisSituation Actions

    Change in project scopeduring the project Risk and resources associated . Eitherfast-tracking or crashing depending ondays left.

    Team member(s) notavailable

    Alternate resource

    Conflict among teammembers

    Cause , confront by 1-to-1, orinterfering

    Conflict with client Meeting

    Delay of H/W, S/W supply Informing management, find alternatesupplier which may add cost for its

    responsiveness.SAA employees Union strike Doing tasks which are independent or

    not related to employees

    70% Budget over in first 2-3months

    Reduce scope, crashing/fast-tracking.

    Cost baseline overshoot Crashing activities with affecting cost

    http://var/www/apps/conversion/current/tmp/scratch10651/Project%20schedule.mpphttp://var/www/apps/conversion/current/tmp/scratch10651/Project%20schedule.mpphttp://var/www/apps/conversion/current/tmp/scratch10651/Project%20schedule.mpphttp://var/www/apps/conversion/current/tmp/scratch10651/Project%20schedule.mpphttp://var/www/apps/conversion/current/tmp/scratch10651/Project%20schedule.mpphttp://var/www/apps/conversion/current/tmp/scratch10651/Project%20schedule.mpphttp://var/www/apps/conversion/current/tmp/scratch10651/Project%20schedule.mpphttp://var/www/apps/conversion/current/tmp/scratch10651/Project%20schedule.mpphttp://var/www/apps/conversion/current/tmp/scratch10651/Project%20schedule.mpphttp://var/www/apps/conversion/current/tmp/scratch10651/Project%20schedule.mpphttp://var/www/apps/conversion/current/tmp/scratch10651/Project%20schedule.mpphttp://var/www/apps/conversion/current/tmp/scratch10651/Project%20schedule.mpphttp://var/www/apps/conversion/current/tmp/scratch10651/Project%20schedule.mpphttp://var/www/apps/conversion/current/tmp/scratch10651/Project%20schedule.mpphttp://var/www/apps/conversion/current/tmp/scratch10651/Project%20schedule.mpphttp://var/www/apps/conversion/current/tmp/scratch10651/Project%20schedule.mpphttp://var/www/apps/conversion/current/tmp/scratch10651/Project%20schedule.mpphttp://var/www/apps/conversion/current/tmp/scratch10651/Project%20schedule.mpphttp://var/www/apps/conversion/current/tmp/scratch10651/Project%20schedule.mpphttp://var/www/apps/conversion/current/tmp/scratch10651/Project%20schedule.mpphttp://var/www/apps/conversion/current/tmp/scratch10651/Project%20schedule.mpphttp://var/www/apps/conversion/current/tmp/scratch10651/Project%20schedule.mpphttp://var/www/apps/conversion/current/tmp/scratch10651/Project%20schedule.mpphttp://var/www/apps/conversion/current/tmp/scratch10651/Project%20schedule.mpphttp://var/www/apps/conversion/current/tmp/scratch10651/Project%20schedule.mpphttp://var/www/apps/conversion/current/tmp/scratch10651/Project%20schedule.mpp
  • 8/4/2019 Erp Implementation in Saa

    15/21

    4/15/12

    CASE 2

    You are one of the Team members under another

    project Manager who is native Johannesburg

    person. In this situation how will you go with the

    Project?

    Assumption- She/he has a

    competency of Design and

    http://var/www/apps/conversion/current/tmp/scratch10651/Project%20schedule.mpphttp://var/www/apps/conversion/current/tmp/scratch10651/Project%20schedule.mpphttp://var/www/apps/conversion/current/tmp/scratch10651/Project%20schedule.mpphttp://var/www/apps/conversion/current/tmp/scratch10651/Project%20schedule.mpphttp://var/www/apps/conversion/current/tmp/scratch10651/Project%20schedule.mpphttp://var/www/apps/conversion/current/tmp/scratch10651/Project%20schedule.mpphttp://var/www/apps/conversion/current/tmp/scratch10651/Project%20schedule.mpphttp://var/www/apps/conversion/current/tmp/scratch10651/Project%20schedule.mpphttp://var/www/apps/conversion/current/tmp/scratch10651/Project%20schedule.mpphttp://var/www/apps/conversion/current/tmp/scratch10651/Project%20schedule.mpphttp://var/www/apps/conversion/current/tmp/scratch10651/Project%20schedule.mpp
  • 8/4/2019 Erp Implementation in Saa

    16/21

    4/15/12

    Cont..

    Be hospitable to PM and Bring adhesion to theteam

    Understanding the scope & objective of theproject.

    Go through WBS & WBS dictionary

    Analysing the current process(As-Is) &documentation.

    Study the requirement according to the "To Be

    Process".

    http://var/www/apps/conversion/current/tmp/scratch10651/Project%20schedule.mpphttp://var/www/apps/conversion/current/tmp/scratch10651/Project%20schedule.mpphttp://var/www/apps/conversion/current/tmp/scratch10651/Project%20schedule.mpphttp://var/www/apps/conversion/current/tmp/scratch10651/Project%20schedule.mpphttp://var/www/apps/conversion/current/tmp/scratch10651/Project%20schedule.mpphttp://var/www/apps/conversion/current/tmp/scratch10651/Project%20schedule.mpphttp://var/www/apps/conversion/current/tmp/scratch10651/Project%20schedule.mpphttp://var/www/apps/conversion/current/tmp/scratch10651/Project%20schedule.mpphttp://var/www/apps/conversion/current/tmp/scratch10651/Project%20schedule.mpphttp://var/www/apps/conversion/current/tmp/scratch10651/Project%20schedule.mpphttp://var/www/apps/conversion/current/tmp/scratch10651/Project%20schedule.mpphttp://var/www/apps/conversion/current/tmp/scratch10651/Project%20schedule.mpphttp://var/www/apps/conversion/current/tmp/scratch10651/Project%20schedule.mpphttp://var/www/apps/conversion/current/tmp/scratch10651/Project%20schedule.mpphttp://var/www/apps/conversion/current/tmp/scratch10651/Project%20schedule.mpphttp://var/www/apps/conversion/current/tmp/scratch10651/Project%20schedule.mpphttp://var/www/apps/conversion/current/tmp/scratch10651/Project%20schedule.mpp
  • 8/4/2019 Erp Implementation in Saa

    17/21

    4/15/12

    Situational Analysis

    Situation Actions

    If he has to act as alternativeduring his work time

    Check the priorities of activitiesi.e,whether that activity is dependentor independent

    Conflict among teammembers

    Try to resolve by yourself

    Delay of H/W, S/W supply Informing PM

    http://var/www/apps/conversion/current/tmp/scratch10651/Project%20schedule.mpphttp://var/www/apps/conversion/current/tmp/scratch10651/Project%20schedule.mpphttp://var/www/apps/conversion/current/tmp/scratch10651/Project%20schedule.mpphttp://var/www/apps/conversion/current/tmp/scratch10651/Project%20schedule.mpphttp://var/www/apps/conversion/current/tmp/scratch10651/Project%20schedule.mpphttp://var/www/apps/conversion/current/tmp/scratch10651/Project%20schedule.mpphttp://var/www/apps/conversion/current/tmp/scratch10651/Project%20schedule.mpphttp://var/www/apps/conversion/current/tmp/scratch10651/Project%20schedule.mpphttp://var/www/apps/conversion/current/tmp/scratch10651/Project%20schedule.mpphttp://var/www/apps/conversion/current/tmp/scratch10651/Project%20schedule.mpphttp://var/www/apps/conversion/current/tmp/scratch10651/Project%20schedule.mpphttp://var/www/apps/conversion/current/tmp/scratch10651/Project%20schedule.mpphttp://var/www/apps/conversion/current/tmp/scratch10651/Project%20schedule.mpp
  • 8/4/2019 Erp Implementation in Saa

    18/21

    4/15/12

    Case 3

    You are one of the team members and the Project Manager leaves

    the project in the last phase of the Project. How you will go about

    the project along with other team member?

    Assumption-PM left at Going Live

    http://var/www/apps/conversion/current/tmp/scratch10651/Project%20schedule.mpphttp://var/www/apps/conversion/current/tmp/scratch10651/Project%20schedule.mpphttp://var/www/apps/conversion/current/tmp/scratch10651/Project%20schedule.mpphttp://var/www/apps/conversion/current/tmp/scratch10651/Project%20schedule.mpphttp://var/www/apps/conversion/current/tmp/scratch10651/Project%20schedule.mpphttp://var/www/apps/conversion/current/tmp/scratch10651/Project%20schedule.mpphttp://var/www/apps/conversion/current/tmp/scratch10651/Project%20schedule.mpphttp://var/www/apps/conversion/current/tmp/scratch10651/Project%20schedule.mpphttp://var/www/apps/conversion/current/tmp/scratch10651/Project%20schedule.mpphttp://var/www/apps/conversion/current/tmp/scratch10651/Project%20schedule.mpp
  • 8/4/2019 Erp Implementation in Saa

    19/21

    4/15/12

    Cont.

    Gather all the required information from PM before he leaves

    Have a meeting with the team members and also ask my team

    member to show me the daily updates

    As we will be in the Going Live phase. We will prepare risk list,

    risk management & user manual

    Control & review by checking the required

    deliverables after the completion of phase

    Sign Of

    http://var/www/apps/conversion/current/tmp/scratch10651/Project%20schedule.mpphttp://var/www/apps/conversion/current/tmp/scratch10651/Project%20schedule.mpphttp://var/www/apps/conversion/current/tmp/scratch10651/Project%20schedule.mpphttp://var/www/apps/conversion/current/tmp/scratch10651/Project%20schedule.mpphttp://var/www/apps/conversion/current/tmp/scratch10651/Project%20schedule.mpphttp://var/www/apps/conversion/current/tmp/scratch10651/Project%20schedule.mpphttp://var/www/apps/conversion/current/tmp/scratch10651/Project%20schedule.mpphttp://var/www/apps/conversion/current/tmp/scratch10651/Project%20schedule.mpphttp://var/www/apps/conversion/current/tmp/scratch10651/Project%20schedule.mpphttp://var/www/apps/conversion/current/tmp/scratch10651/Project%20schedule.mpphttp://var/www/apps/conversion/current/tmp/scratch10651/Project%20schedule.mpphttp://var/www/apps/conversion/current/tmp/scratch10651/Project%20schedule.mpphttp://var/www/apps/conversion/current/tmp/scratch10651/Project%20schedule.mpphttp://var/www/apps/conversion/current/tmp/scratch10651/Project%20schedule.mpphttp://var/www/apps/conversion/current/tmp/scratch10651/Project%20schedule.mpphttp://var/www/apps/conversion/current/tmp/scratch10651/Project%20schedule.mpp
  • 8/4/2019 Erp Implementation in Saa

    20/21

    4/15/12

    Situational Analysis

    Situation Actions

    Team member(s) not available Alternate resource

    If 75% Budget got over Reduce scope, crashing/fast-

    tracking.Cost baseline overshoot Crashing activities with affecting

    cost

    Scope change at last phase Consider lead time and costanalysis

    http://var/www/apps/conversion/current/tmp/scratch10651/Project%20schedule.mpphttp://var/www/apps/conversion/current/tmp/scratch10651/Project%20schedule.mpphttp://var/www/apps/conversion/current/tmp/scratch10651/Project%20schedule.mpphttp://var/www/apps/conversion/current/tmp/scratch10651/Project%20schedule.mpphttp://var/www/apps/conversion/current/tmp/scratch10651/Project%20schedule.mpphttp://var/www/apps/conversion/current/tmp/scratch10651/Project%20schedule.mpphttp://var/www/apps/conversion/current/tmp/scratch10651/Project%20schedule.mpphttp://var/www/apps/conversion/current/tmp/scratch10651/Project%20schedule.mpphttp://var/www/apps/conversion/current/tmp/scratch10651/Project%20schedule.mpphttp://var/www/apps/conversion/current/tmp/scratch10651/Project%20schedule.mpphttp://var/www/apps/conversion/current/tmp/scratch10651/Project%20schedule.mpp
  • 8/4/2019 Erp Implementation in Saa

    21/21

    4/15/12

    THANK YOU

    Questions ?

    http://var/www/apps/conversion/current/tmp/scratch10651/Project%20schedule.mpphttp://var/www/apps/conversion/current/tmp/scratch10651/Project%20schedule.mpphttp://var/www/apps/conversion/current/tmp/scratch10651/Project%20schedule.mpphttp://var/www/apps/conversion/current/tmp/scratch10651/Project%20schedule.mpphttp://var/www/apps/conversion/current/tmp/scratch10651/Project%20schedule.mpp