erke group, vibratory hammer 52hv driving casings near a railway canada
TRANSCRIPT
-
7/29/2019 ERKE Group, Vibratory hammer 52HV driving casings near a railway Canada
1/1
The project on the West Toronto Diamond consists o a rail-to-rail and rail-to-road grade separation, in the
Georgetown South Corridor. When completed the GO commuter line will run underneath the Canadian
Pacic reight line and provide saer, more efcient trafc. The project also contains a new Air Rail Link
rom Union Station to Pearson International Airport and uture expanded service to Milton, Barrie, and
Georgetown.
A division of Metrolinx, GO Transit is the regional public transit service for the Greater
Toronto and Hamilton Area. With the objective of increasing and improveing the
network of rail lines, the government decided to build a grade separation on the
West Toronto Diamond (WTD), the busiest railway intersection in Canada.
The 52HV buildinga grade separation onthe West Toronto Diamond,Canada.
The ollowing work was accomplished while
maintaining rail operations or CN, CP, VIA and GO
Transit service :
Aloweredcorridorfor4setsofGOTransittracks.
A bridge to carry CP tracks, and vehicles/
pedestrians on Old Weston and junction roads,
crossing over the lowered GO tracks .
AsecondbridgethatwillcarrytheCPtracksover
the lowered GO tracks.
ThegroundconditionsaresiltyclaywithSPTvalues
upto65.Thistypeofhardsoilisnormallytreated
with hydraulichammers,butin thisprojecttheir
useislimitedtoavoidvibratorydisturbancetothe
housesandnoisedisturbancetotheinhabitants.
To overcome the work under these strict demands
and difcult soil conditions, the contractor Geo
Foundations, chose to do the oundation work with
aPTC52HVVibrodriver.
ThisVibratoroersaperfectmixbetweendriving
powerand vibrationcontrol, becauseits variable
moment technology (PTC patent) allows the
adjustment of the vibration amplitude at any
moment during the driving.
Furthermore, the Vibmaster monitoring system,
permitsastrictcontrolofthesoilparticlevelocity
emitted in the soil, guaranteeing that oundation
worksrespectthelimitxedbythelocalauthorities.
Project phases
Phase 1
Utilityrelocationandretainingwallconstruction.
Phase 2
Installation o interlocking pipe piles to orm the
walls o the lowered rail corridor.
The 52HV was mounted free hanging on a 150 t
Manitowaccranetodrivethetubesthatwillsupport
thenewraillines.Thetubesdrivenbythe52HV
had36 diameter(915 mm),0.5 wallthickness
(12.7mm),and40long(12.2m).
Phase 3
Pipe pile wall validation: removing soil rom within
piles and lling them with concrete and other
sealing compounds to ensure water- tight walls.
The 52HV was used to drive the piles and to remove
them once the concrete was poured.
Phase 4
Excavationoftheloweredrailcorridorandbridgeinstallation.
Thisprojectstartedin2010,andiscurrentlyunder
phasenumber3.Itisexpectedtobecompletedin
2014.
Crdit images:
www.gotransit.com/gts.
Project presentation:
Georgetown South.
PTC - Job report - Free hanging piling
KEY FACTS
Go transit carries more than
62 million passengers a year.
The 52HV Vibrodriver isequipped with Patented
Variable Moment Technology.
Vibmaster monitoring system
controlled the soil particle
velocity during the Vibrodrivers
work.
Tubes: 915mm diameter
and 12 m long.
Duplex clamp 120 t.
View of the works required for the grade separation project on the West Toronto Diamond.