EPC activitiesduring LS2
PROJECTS1) Beam dump relocation2) SPS TCDI3) CIS consolidation Mains SPS4) Controls SMQ Electronics5) EIS PPS upgrade6) Ncod to MACAO7) Converter controls TI2 TI88) Power transformers consolidation9) BEQ1 dismantling10) RF powering
L. De Oliveira TE-EPCPresentation 28-11-2018
No EPC activities the last 2 months
SPS consolidation
LIU SPS
![Page 3: EPC activities - Indico€¦ · Ncod MACAO 1872299 MACAO today Start of LS2 END of LS2 IST 04/2019 Decabling Install of new racks Modification of the 400V electrical distribution](https://reader033.vdocuments.site/reader033/viewer/2022042410/5f276e9f336f1141075181f9/html5/thumbnails/3.jpg)
Typical sequence for converter’s installation: to take in account for planning
1. Disconnection – Decabling (in case of renovation)2. Removal (old) – Tansport (new)3. Mechanical works (support frame)4. Installation5. Cabling (except DC)6. IST (Individual System Test)7. DC connection8. Hardware tests
https://edms.cern.ch/document/2001154/1
Groups involvesEPC - EL-CVHE – EPCSMBEPCEL-COEPCELEPC-OP
![Page 4: EPC activities - Indico€¦ · Ncod MACAO 1872299 MACAO today Start of LS2 END of LS2 IST 04/2019 Decabling Install of new racks Modification of the 400V electrical distribution](https://reader033.vdocuments.site/reader033/viewer/2022042410/5f276e9f336f1141075181f9/html5/thumbnails/4.jpg)
JOB title - PROJECT
Responsible: WHERE: BA1 (868)E.COULOT ECR:
§ Done:§ ECR APPROVED and Integration validated§Activities planned by EN-ACE (Draft on indico 731388)
Removed: 1x N06ARPPEO.BA1.MDHD11832
Installed: 2 x SIRIUS_SRPAEJ.BA1.RMDPH.11757RPAEJ.BA1.RMDHW.1157M
1874303
BA1 ConvertersModifications
Task :Recomissioning
SPS LSS5 Beam Dump Upgrade project
PLAN: 11103
WP: 11103
todayStart
of LS2END
of LS2Comissioning
14-08-2019
Task 1Send JOB andImpact Requests
23-10-19
LIU SPS
4Q[20A / 160V]
4Q[200A / 900V]
![Page 5: EPC activities - Indico€¦ · Ncod MACAO 1872299 MACAO today Start of LS2 END of LS2 IST 04/2019 Decabling Install of new racks Modification of the 400V electrical distribution](https://reader033.vdocuments.site/reader033/viewer/2022042410/5f276e9f336f1141075181f9/html5/thumbnails/5.jpg)
BA5 ConvertersModifications
Responsible: WHERE: BA5 (872)E.COULOT ECR: 1874304
PLAN: 11103
WP: 11103
Removed:RPPAY.BA5.MDHW5183M (34)
RPPAO.BA5.MDPH51753 (kept asspare, N07)
RPPBK.BA5.BBLR5177M (46x)
Installed: 1 x N06A and 1xN07RPPEO.BA5.RMDHD51832RPPAO.BA5.SPARE.1
todayStart
of LS2END
of LS2Comissioning
24-10-2019
Task 1Send JOB andImpact Requests
15-01-20
§ Done:§ ECR APPROVED§Activities planned by EN-ACE (Draft on indico 731388)
Task :Recomissioning
4Q[20A / 160V][125A /125V]
![Page 6: EPC activities - Indico€¦ · Ncod MACAO 1872299 MACAO today Start of LS2 END of LS2 IST 04/2019 Decabling Install of new racks Modification of the 400V electrical distribution](https://reader033.vdocuments.site/reader033/viewer/2022042410/5f276e9f336f1141075181f9/html5/thumbnails/6.jpg)
JOB title - PROJECT
Responsible: WHERE: 2275 (SR2)Mutin ECR:
Name oldequipmentRQIF.80400RQID.80500
Names newequipments
RPADA.SR2.RQIF.28800RPADA.SR2.RQIF.29000
RPADA.SR2.SPARE1
1871488
LIU SPS
todayStart
of LS2END
of LS2ComissioningJan.
201
9
Task 0 Decabling and remove two power converter of TI2 RQIF.28800 and RQIF.29000 (EPC-OMS)
Task 2 Add 1 new AC cable and connection to spare converter (EN-EL)Task 3 Pull 2 new AC cables and connection to power converter (EN-EL)
Task 1 Installation x3 power converters (EPC+EN-HE)
Task 4 Connect existing DC cables to power converter (EN-EL)
Task 6 Cabling of control (CCE)
Task 5 Update WIC cable for FGC3 (MPC)
TCDI - Target Collimator Dump Injection
Mar
ch. 2
019
Ap. 2
019
summer. 2019
Task
7C
omm
issi
ng(E
PC)
Installation of x3 news COMET 2p converters(TI2)
Switch mode CVSFGC3 platform
4Q [500A / 120V]
![Page 7: EPC activities - Indico€¦ · Ncod MACAO 1872299 MACAO today Start of LS2 END of LS2 IST 04/2019 Decabling Install of new racks Modification of the 400V electrical distribution](https://reader033.vdocuments.site/reader033/viewer/2022042410/5f276e9f336f1141075181f9/html5/thumbnails/7.jpg)
Responsible: WHERE: 2875 (SR8)Mutin ECR:
Name oldequipmentsRQIF.80400RQID.80500
Name new equipmentRPPEC.SR8.RQIF.87000RPPEC.SR8.RQID.87100
1866204
todayStart
of LS2END
of LS2Comissioning
Task 1 Decabling 2 converters of TI2 RQIF.28800 and RQIF.29000 (TE-EPC-OMS)
Task 2 Transport this 2 converters from bat.2275 to bat.2875 (EN-HE)
Task 3 Remove empty racks RYIC04, RYIC05 and RYIC06
Task 4 Install 2 converters (TE-EPC-OMS) + (EN-HE)
Task 5 Add 2 news AC cables and connection to power converter (EN-EL)
Task 6 Pull DC cables and connect to power converter (EN-EL)
Task 7 Connection to the WIC using standard FGC3 (TE-EPC-MPC)
Jan.
201
9
Feb.
201
9
Mar
ch 2
019
Task
8C
omm
issi
ng(E
PC)
summer. 2019
Thyristor CVSmugef platform
Installation of x2 new RB6 converters (TI8)
![Page 8: EPC activities - Indico€¦ · Ncod MACAO 1872299 MACAO today Start of LS2 END of LS2 IST 04/2019 Decabling Install of new racks Modification of the 400V electrical distribution](https://reader033.vdocuments.site/reader033/viewer/2022042410/5f276e9f336f1141075181f9/html5/thumbnails/8.jpg)
JOB title - PROJECT
Responsible: WHERE: BA2-6, BEJ.M. De Paco ECR:
CIS
EDMS tbd
Control andInterlock System
Mains SPS
SPS consol
todayStart
of LS2END
of LS2Comissioning
02/2019
Task 1 Specification
Task 2Systemdesign
04/2019 04/2020
CIS consolidation
https://wikis.cern.ch/display/TEEPCCCS/SPS+Mains+-+CIS+consolidation
09/2020
Task 3 Software development
Task 4 HW installation
01/2020
Task 5 Systemcommissioning
S7-300GTD dev 1998 CERN standard system
![Page 9: EPC activities - Indico€¦ · Ncod MACAO 1872299 MACAO today Start of LS2 END of LS2 IST 04/2019 Decabling Install of new racks Modification of the 400V electrical distribution](https://reader033.vdocuments.site/reader033/viewer/2022042410/5f276e9f336f1141075181f9/html5/thumbnails/9.jpg)
Start of LS2
Studies f(cvs)+
Crate fab.
JOB title - PROJECT
Responsible: WHERE: All BAs & TI2/8De Oliveira L.
Voie PLC (Ext. chain)+ Voie cablée
today
Modifications on converters MCB 400V + 18kV
Interface on spare converter blg 269
EIS-PPS upgrade
jan. 19
Out of chain (SPS complex)
Jan. 20 Jun. 20 Sept. 20
In operationfor hardwarecomissioning
Jul.
20
EIS commissioning
Aug.
20
June 20
Modifications on particular converters (RBI.81607M and MBE.2103M)
Modification on SPS Mains
Rac
cord
emen
tau
sytè
me
EIS-
PSS
Hardwarecommissioning
BB4
EIS-SPS-PPS schedule:01/19 Ap.
BA2
may
BA1
Jul-aug
BA80-81
Nov..
BA7
01/20
BA5
Feb-march
BA4-3
Apr.
BA6
ENDof LS2
Condamnation
x2 types of interface crates(EL & EPC)
SPS consolIntegration depending:Þ Topology (Electronics)Þ Power of cvsÞ Particularities (Mains / load switch)
Concerning:x12 power converters with 400V MCBx22 converters with 18kV MCB
Voie A+ Voie B
![Page 10: EPC activities - Indico€¦ · Ncod MACAO 1872299 MACAO today Start of LS2 END of LS2 IST 04/2019 Decabling Install of new racks Modification of the 400V electrical distribution](https://reader033.vdocuments.site/reader033/viewer/2022042410/5f276e9f336f1141075181f9/html5/thumbnails/10.jpg)
JOB title - PROJECT
Responsible: WHERE: BA1-BA7,BB4, SR2, SR8.Serge PITTET ECR:
Ncod
MACAO
1872299
MACAO
todayStart
of LS2
ENDof LS2
IST
04/2019
Decabling
Install of new racks
Modification of the 400V electrical distribution
DC, Ethernet, interlocks re-cabling
Install 354 new converters
EN-EL ?? 12/2019
Correction dipoles convertersconsolidation
Remove old converters/racks
False floors (reworks SMB)
Hardwarecomissioning
OP ????
4Q[3.5A / 150V]
4Q[3.5A / 80V]
MAGtests
SPS consol
![Page 11: EPC activities - Indico€¦ · Ncod MACAO 1872299 MACAO today Start of LS2 END of LS2 IST 04/2019 Decabling Install of new racks Modification of the 400V electrical distribution](https://reader033.vdocuments.site/reader033/viewer/2022042410/5f276e9f336f1141075181f9/html5/thumbnails/11.jpg)
JOB title - PROJECT
Responsible: WHERE:SR2 – 2275SR8 – 2875José María Fernández ECR:
Crate SPS RénoFGC3 - Type 7
Backplane
1894658
today
Startof LS214 jan. 19
ENDof LS21st trimester
2019
Disassembly of OldCrates and DCCTs
Cabling adaptations
Installation new Crates & DCCTs
Power Test
Summer2019
Thyristor Power Converter Controls TI2-TI8
Test of Type 7 Cratesand Boards (FSU)
Test CCC
Mid-july2020
18th sept.2020Date from
test planning??
Comissioning
??
SPS consolDeployment of the FGC3 control electronics to replace mugef electronics (from 80’s)Þ 36 power converters (Thyristor)
![Page 12: EPC activities - Indico€¦ · Ncod MACAO 1872299 MACAO today Start of LS2 END of LS2 IST 04/2019 Decabling Install of new racks Modification of the 400V electrical distribution](https://reader033.vdocuments.site/reader033/viewer/2022042410/5f276e9f336f1141075181f9/html5/thumbnails/12.jpg)
JOB title - PROJECT
Responsible: David Cid WHERE: BA2, BA6, BB4, b.250 ECR: In preparation
• RMT112/A2• RMT310/B4• RMT116/A6• RMT115/A6• RMT108*7 (not SPS)
• RMT304/A4 (not fully decided yet)
Oil-Filled Transformersreplaced by Cast resin
todayStart
of LS2END
of LS2Jun.19
Designstudies andTMC Txspurchasing
TMC CRTransformersmanufacturingand FAT
Replacementandcommissioningof RMT108*7
Jul.19 Aug.19
Oil-Filled Transformers
Replacementandcommissioningof RMT112/A2 Replacement
andcommissioningof RMT116/A6
Sept.19
Replacementandcommissioningof RMT310/B4
Nov.19
Replacementandcommissioningof RMT304/A4
Feb.20
Cast-Resin RMT304/A4 design, manufacturing and testing
Replacementandcommissioningof RMT115/A6
IMPACT: 119446
Needs: Scaffolding + Transport + Free space around
* Lockouts
SPS consol
![Page 13: EPC activities - Indico€¦ · Ncod MACAO 1872299 MACAO today Start of LS2 END of LS2 IST 04/2019 Decabling Install of new racks Modification of the 400V electrical distribution](https://reader033.vdocuments.site/reader033/viewer/2022042410/5f276e9f336f1141075181f9/html5/thumbnails/13.jpg)
JOB title - PROJECT
Responsible: G McTague WHERE: All BAs IMPACT 119464
Maintenance of x24 units on sitex2 units sent to factory for refurbishment
todayStart
of LS2END
of LS2May 19
Contractawardand
Planning
CRTransformerMaintenance
Final ProtectionChain tests withnew 18kV (BA4
and BA6)
Aug. 19 Jan. 20
MAINTENANCE - Oil & Cast-Resin Transformers
Removal and offsiterefurbishment of
RMT115/A2 (BA2) andRMT117/A6 (BA6)
Jun.20
Oil CR
BA1 4
BA2 8
BA3 7 10
BA4 5 6
BA5 4
BA6 2 4
BA7 2
LS2 Maintenance Activity (site)
OTHER – Offsite refurbishment of 2 Transformers (BA2 and BA6)
Oil TransformerMaintenance (BA4
and BA6transformers transfer
to new EN-EL 18kVJan 2020)
Return and Re-commissioning ofRMT115/A2 (BA2)and RMT117/A6
(BA6)
Needs: Scaffolding + Transport + Free space around
* Lockouts
SPS consol
![Page 14: EPC activities - Indico€¦ · Ncod MACAO 1872299 MACAO today Start of LS2 END of LS2 IST 04/2019 Decabling Install of new racks Modification of the 400V electrical distribution](https://reader033.vdocuments.site/reader033/viewer/2022042410/5f276e9f336f1141075181f9/html5/thumbnails/14.jpg)
JOB title - PROJECT
Responsibles:WHERE: Bdg. 884K. Kahle / F. Blánquez
Existing SVCBEQ1 (1974)
will berenovatedduring LS2
SVC BEQ1
today
ENDof LS2
Comissioning
Task 1Dismantling ofBEQ1 (fromMid. Dec. 2018)
Task 2 Civilengineering
Task 3 electricalcomponent installation,cooling.
Task 4 TCR system andelectrical infrastructurework Task 6
Powering andperformancetests
Task 5Commissioning
Dismantling of existing BEQ1 (with reactor)
Worksite Resp. D. Denuziere
New SVCBEQ1
Environmental risk!
• Removal of Reactor• Bldg destruction
SPS consol
![Page 15: EPC activities - Indico€¦ · Ncod MACAO 1872299 MACAO today Start of LS2 END of LS2 IST 04/2019 Decabling Install of new racks Modification of the 400V electrical distribution](https://reader033.vdocuments.site/reader033/viewer/2022042410/5f276e9f336f1141075181f9/html5/thumbnails/15.jpg)
JOB title - PROJECT
Responsible: WHERE: BA3/BAE3I. Josifovic ECR: 1853335
SPS_RF_Cavities
SPS 200 Concrete platforms and 400 V cabling
Tests of seriesSYRACUSE
rectifiers in A7
Installation and cablingof equipment atA7 test-platform
Manufacturing of seriesSYRACUSE rectifiers
Manufacturing ofseries
18 kV trans. boxes
Building of sixconcrete platforms
for 18 kV trans. boxes
Placement of 18 kV trans.boxes on concrete platforms
and400 V auxiliaries cabling
Manufact. of pre-series18 kV trans. box
Tests of pre-seriesunitsin A7
Manufact. ofpre-seriesSYRACUSE
rectifier
<--------------------------------------- LS 2 --------------------------------------->
Q420202018 2019
Q2 Q3 Q4 Q1 Q2Q3 Q4 Q1 Q3
A7 test platform
Concrete platforms
![Page 16: EPC activities - Indico€¦ · Ncod MACAO 1872299 MACAO today Start of LS2 END of LS2 IST 04/2019 Decabling Install of new racks Modification of the 400V electrical distribution](https://reader033.vdocuments.site/reader033/viewer/2022042410/5f276e9f336f1141075181f9/html5/thumbnails/16.jpg)
Project Responsible ContactSPS Beam Dump Upgrade E. Coulot 169191CIS consolidation J.M. De Paco 163483EIS PPS upgrade L. De Oliveira 164707Correction dipole converters S. Pittet 165205FGC3 control electronics (THY converters) J-M Fernandez 160909Oil filled transformer’s consolidation D. Cid Fernandez 162807Maintenance of 18kV transformers G. McTague 163782RF powering I. Josifovic 167618SPS TCDI C. Mutin 162953BEQ1 dismantling F. Blánquez 168365
Persons in charge
![Page 17: EPC activities - Indico€¦ · Ncod MACAO 1872299 MACAO today Start of LS2 END of LS2 IST 04/2019 Decabling Install of new racks Modification of the 400V electrical distribution](https://reader033.vdocuments.site/reader033/viewer/2022042410/5f276e9f336f1141075181f9/html5/thumbnails/17.jpg)
Transformers Consolidation project activities NEED:Areas accessible for personnel, vans, trucks and cranes all along the LS2,or at least during the specified period for each area.
ü Areas / requirements identifiedü Periods defineü Requests DONEü Some PB for transport (BM4, BA6)
CONSTRAINT - Free space needed
![Page 18: EPC activities - Indico€¦ · Ncod MACAO 1872299 MACAO today Start of LS2 END of LS2 IST 04/2019 Decabling Install of new racks Modification of the 400V electrical distribution](https://reader033.vdocuments.site/reader033/viewer/2022042410/5f276e9f336f1141075181f9/html5/thumbnails/18.jpg)
CONSTRAINT - Impacts of other activities
Can involved huge impacts on EPC jobs / planning:
Exemple: Programme de rénovation des infrastructures EN-EL:® Cabling consideration for EIS upgrade project® Consider test period as a 1st COMISSIONING® Renaming of all EPC 18kV transformers (on site identification, database, docs)
ü In accordance with EL - Planning in preparationDates / Durations / Manpower resources)
ü New modifications identifiedü Additional tasks take in account
(from others groups)
IST / Hardware tests:
® Periods for Individual System Test still have to be clearly defined® Clarification for Hardware tests with OP-ACE (period, safety rules, etc…)® Converters restart after LS2 must be planed ASAP