epa’s proposed geologic sequestration rule administrator johnson signed july 15, 2008 120 day...

15
EPA’s Proposed Geologic Sequestration Rule Administrator Johnson signed July 15, 2008 120 day comment period Final rule in 2010 or 2011

Upload: holly-ray

Post on 12-Jan-2016

221 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: EPA’s Proposed Geologic Sequestration Rule  Administrator Johnson signed July 15, 2008  120 day comment period  Final rule in 2010 or 2011

EPA’s Proposed Geologic Sequestration RuleEPA’s Proposed Geologic Sequestration Rule Administrator Johnson signed July 15, 2008

120 day comment period

Final rule in 2010 or 2011

Page 2: EPA’s Proposed Geologic Sequestration Rule  Administrator Johnson signed July 15, 2008  120 day comment period  Final rule in 2010 or 2011

2

Key Points Regarding SDWA

SDWA UIC – 42 USC § 300h et seq.

Establishes minimum federal standards to protect USDWs

USDW – any aquifer capable of supplying water to a public water system with < 10,000 mg/L TDS

EPA has broad emergency powers under “imminent and substantial endangerment” 42 USC § 300i

contaminant which is present or is likely to enter a USDW (i.e., “endangerment”)

EPA can order shut down of wells, remediation, replacement of water supplies

Violations – administrative orders, civil actions and criminal enforcement

UIC Regulations – 40 CFR Part 144 - 148

Page 3: EPA’s Proposed Geologic Sequestration Rule  Administrator Johnson signed July 15, 2008  120 day comment period  Final rule in 2010 or 2011

3

UIC Program

Collective State/Federal Experience

Over 9B gallons of hazardous waste injected each year

Over 2B gallons of brine from oil & gas every day

Over 1B gallons of municipal wastewater every day

Well Classes

I – deep haz waste/industrial non-haz/municipal (500)

II – oil & gas fluids/brines/hydrocarbon storage (147,500)

III – mineral extraction (17,000)

IV – shallow haz/radioactive wastes (subject to 1984 ban)

V – experimental technology (650,000)

VI – geologic sequestration (NEW)

Page 4: EPA’s Proposed Geologic Sequestration Rule  Administrator Johnson signed July 15, 2008  120 day comment period  Final rule in 2010 or 2011

4

UIC – Delegated State Primacy

Page 5: EPA’s Proposed Geologic Sequestration Rule  Administrator Johnson signed July 15, 2008  120 day comment period  Final rule in 2010 or 2011

5

UIC Progam Elements

Site Characterization

Area of Review and Corrective Action

Well Construction

Well Operation

Site Monitoring

Well Plugging and Post-Injection Site Care

Financial Assurance

Public Participation

Page 6: EPA’s Proposed Geologic Sequestration Rule  Administrator Johnson signed July 15, 2008  120 day comment period  Final rule in 2010 or 2011

6

GS Rule - Overview

EPA considered 4 alternatives: opted for “tailored requirements approach”

Applicable to all U.S. and up to 3 miles offshore

Beyond scope: risks to air, human health, ecosystems

State primacy for Class VI

must promulgate regulations at least as stringent as the final rulemaking

Targeted formations: below lowermost USDW (deep saline, depleted oil/gas, unmineable coal seams, basalt)

Page 7: EPA’s Proposed Geologic Sequestration Rule  Administrator Johnson signed July 15, 2008  120 day comment period  Final rule in 2010 or 2011

7

GS Rule - Overview

Plans required AoR and Corrective Action Monitoring and Testing Emergency and Remedial Response Post-injection Site Care and Site Closure Plan

Increased frequency of mechanical integrity monitoring from 5 to 1 year

Tracers (odorants) not required but recommended to detect leaks

Multi-barrier, continuous monitoring (confining zone, USDW, surface air, soil gas) with alarms and automatic shut-off valves

State discretion to require monitoring for CO2 in surface air Raises question whether federally enforceable

Page 8: EPA’s Proposed Geologic Sequestration Rule  Administrator Johnson signed July 15, 2008  120 day comment period  Final rule in 2010 or 2011

8

GS Rule - Overview

Permit issued through post-injection site care (50+ years)

Periodic updates to AoR models and corrective action status

States/Tribes may be more stringent than EPA

Estimated cost of commercial scale GS well

$3.40/t CO2 of which $1.20/t is attributable to new GS rule

(compared to $42/t CO2 for capture at IGCC plant)

Page 9: EPA’s Proposed Geologic Sequestration Rule  Administrator Johnson signed July 15, 2008  120 day comment period  Final rule in 2010 or 2011

9

Liability Concerns - RCRA

“. . . EPA cannot make a categorical determination as to whether injected CO2 is hazardous under RCRA. . .”

Defined “carbon dioxide stream” to exclude hazardous wastes

CO2 stream composition will depend on flue gas scrubbing technology, additives, CO2 capture technology.

Test as hazardous per 40 CFR 261 (characteristic wastes: reactive, ignitable, corrosive and toxic)

If hazardous, cannot use Class VI

Page 10: EPA’s Proposed Geologic Sequestration Rule  Administrator Johnson signed July 15, 2008  120 day comment period  Final rule in 2010 or 2011

10

Liability Concerns - CERCLA

“. . . whether or not there is a ‘hazardous substance’ that may result in CERCLA liability from a sequestration facility depends entirely on the make-up of the specific CO2 stream and of the environmental media (e.g., soil, groundwater) in which it is stored.”

Impurities in CO2 stream that are hazardous substances, e.g., mercury

Chemical reactions with groundwater that create hazardous substances after injection, e.g., sulfuric acid, carbonic acid

Dissolution of minerals that may liberate heavy metals

Page 11: EPA’s Proposed Geologic Sequestration Rule  Administrator Johnson signed July 15, 2008  120 day comment period  Final rule in 2010 or 2011

11

CERCLA (cont’d)

Potential for case-by-case claim for Natural Resource Damages or response costs – Trustees (U.S., State, Tribes) may pursue

Defense to liability – “federally-permitted release” Expressly applies to UIC (42 USC 9601(10) and 9707(j))

courts have construed narrowly – nicknamed “disappearing exemption”

N/A if release is (1) not expressly permitted; (2) exceeds the limitations established in the permits; or (3) occurs during a time period when there were no permits.

Page 12: EPA’s Proposed Geologic Sequestration Rule  Administrator Johnson signed July 15, 2008  120 day comment period  Final rule in 2010 or 2011

12

CERCLA (cont’d)

“Class VI permits will need to be carefully structured to ensure that they do not ‘authorize’ inappropriate hazardous releases . . . include clarifying if there are potential releases from the well which are outside the scope of the Class VI permit.”

What releases and “potential” releases should be included in a permit application and permit?

What is an “inappropriate” release?

Page 13: EPA’s Proposed Geologic Sequestration Rule  Administrator Johnson signed July 15, 2008  120 day comment period  Final rule in 2010 or 2011

13

Practical Challenges

Phased corrective action/monitoring wells Negotiating site access agreements What happens if access denied? EPA recommends monitoring groundwater for

heavy metals and organics to track plume and pressure front.

- How much sampling? - What are the risks? - What happens if contamination is

identified unrelated to UIC?

Page 14: EPA’s Proposed Geologic Sequestration Rule  Administrator Johnson signed July 15, 2008  120 day comment period  Final rule in 2010 or 2011

14

Post-Injection Site Care

50 years (possibly longer) or less time if demonstration of no endangerment (monitoring and modeling in sync)

“. . .could be 100 years (or longer) if monitoring and modeling information suggest that the plume may still endanger USDWs. . .”

Deed recordation for the facility property (in perpetuity)- What about other properties below plume?

Financial Assurance

Terminates after completed P-I site care approved and no longer endangerment

Specifies only a “general duty” to obtain financial care (guidance to be provided later)

May allow bi-furcated approach (well plugging v. P-I site care)

Page 15: EPA’s Proposed Geologic Sequestration Rule  Administrator Johnson signed July 15, 2008  120 day comment period  Final rule in 2010 or 2011

15

Long-Term Liability Transfer

“SDWA does not provide EPA with the authority to transfer liability from one entity to another.”

UIC regulations allow permit to be transferred

Trust responsibilities for owner/operator are in perpetuity

EPA says owner/operator may still be held responsible after post-injection site care for unanticipated migration that endangers USDW

although parties may agree to contractually shift liability, such agreements may not be binding on the government