environmental scoping and management plan for …eia.met.gov.na/screening/116_esmp for...

112
1 ENVIRONMENTAL SCOPING AND MANAGEMENT PLAN FOR A 1000 SOW PIGGERY PROJECT AT STAMPRIED FARM STAMPRIET VILLAGE - HARDAP REGION. FOR ROOTS PIGGERY (PTY) LTD PREPARED BY P. O. Box 70822 Khomasdal, Windhoek, Namibia. +264 812 683 578 [email protected]

Upload: others

Post on 24-Mar-2020

4 views

Category:

Documents


0 download

TRANSCRIPT

1

ENVIRONMENTAL SCOPING AND MANAGEMENT PLAN FOR A 1000 SOW PIGGERY PROJECT AT STAMPRIED FARM – STAMPRIET VILLAGE - HARDAP

REGION.

FOR

ROOTS PIGGERY (PTY) LTD

PREPARED BY

P. O. Box 70822 Khomasdal, Windhoek, Namibia.

+264 812 683 578 [email protected]

2

PROJECT DETAILS

TITLE: ENVIRONMENTAL SCOPING AND MANAGEMENT PLAN FOR A

PIGGERY PROJECT AT STAMPRIED FARM – STAMPRIET VILLAGE –

HARDAP REGION.

TERMS OF REFERENCE

AND SCOPE OF THE PROJECT: ROOTS PIGGERY (PTY) LTD

AUTHORS: OUTRUN CONSULTANTS CC

CLIENT: ROOTS PIGGERY (PTY) LTD

REPORT STATUS: FINAL ENVIRONMENTAL SCOPING AND MANAGEMENT PLAN

DATE: 25 April 2019

AUTHORISED SIGNATURE:

JOSIAH T. MUKUTIRI

EIA PRACTITIONER

3

ACKNOWLEDGEMENT

We would to take this opportunity to thank all the stakeholders for their

technical support and input during the consultation process that shaped the

scope of this study and enlightened the grey areas for sound decision making.

4

ABBREVIATIONS BID Background and Invitation to Participate Document

DEA Directorate of Environmental Affairs

EIA Environmental Impact Assessment

EMA Environmental Management Act

EMP Environmental Management Plan

IAPs Interested and Affected Parties

MAWF Ministry of Agriculture, Water & Forestry

MET Ministry of Environment & Tourism

5

Table of Contents LIST OF FIGURES ...................................................................................................................................... 8

1. INTRODUCTION ............................................................................................................................... 9

1.1. Environmental Impact Assessment Practitioner’s Details .................................................... 10

1.1.1. Details of Environmental Assessment Practitioner....................................................... 10

1.2. Project Description and Location ............................................................................................... 12

2. DESCRIPTION OF THE ENVIRONMENT .......................................................................................... 15

2.1. Topography ........................................................................................................................... 15

2.2. Geology and Hydrology ......................................................................................................... 15

2.3. Climate .................................................................................................................................. 15

2.3.1. Temperature ................................................................................................................. 15

2.3.2. Wind .............................................................................................................................. 15

2.3.3. Rainfall .......................................................................................................................... 16

2.4. Evaporation and Evapotranspiration .................................................................................... 16

2.5. Demographics ....................................................................................................................... 17

2.6. Water Supply and Sanitation ................................................................................................ 17

2.6.1. Water Supply ................................................................................................................. 17

2.6.2. Sanitation ...................................................................................................................... 17

2.6.3. Water and water use in the area .................................................................................. 18

2.7. Vegetation ............................................................................................................................. 18

2.8. Economic Activities ............................................................................................................... 19

2.8.1. Agriculture:-Crop and Livestock Production ................................................................. 19

2.9. Access road ........................................................................................................................... 19

2.10. Other site infrastructure/requirements............................................................................ 20

3. PUBLIC CONSULTATION ................................................................................................................ 21

3.1. Public Consultation Process .................................................................................................. 21

3.2. Summary of Issues Raised During the Public Meeting ......................................................... 22

3.3. Need and Desirability of the Proposed Project..................................................................... 23

3.3.1. Relevance of economic viability .................................................................................... 23

3.3.2. Economic and non-economic benefits and costs ......................................................... 23

3.4. Assessment of Project Alternatives ...................................................................................... 25

3.4.1. The No-Go Option / Consequences of not proceeding ................................................. 25

3.4.2. Alternative site (s) ......................................................................................................... 26

3.4.3. Strategic Alternatives .................................................................................................... 26

6

3.5. Technical Alternatives ........................................................................................................... 26

3.5.1. Waste Management Technologies ............................................................................... 26

3.5.2. Benefits associated with good waste management practices ...................................... 28

3.6. Assessment models of agricultural projects (Alternatives) .................................................. 29

3.6.1. Ecological Footprint ...................................................................................................... 29

3.6.2. Nutrient Balance ........................................................................................................... 30

3.6.3. Environmental Risk Mapping ........................................................................................ 30

3.6.4. Multi-Agent System ...................................................................................................... 31

3.6.5. Multi Linear Programming ............................................................................................ 31

3.6.6. Life Cycle Assessment ................................................................................................... 32

4. LEGAL AND POLCY ENVIRONMENT ............................................................................................... 34

4.1. Legal and policy instruments relevant to the proposed project ........................................... 34

4.1.1. Namibia’s National Constitution ................................................................................... 34

4.1.2. Environmental Management Act (2007) and Regulations (2012) ................................ 34

4.1.3. Soil Conservation Act (1969) ......................................................................................... 35

4.1.4. The Forest Act (2001) .................................................................................................... 35

4.1.5. The Water Act (1956) .................................................................................................... 35

4.1.6. The Water Resources Management Act (2004) ............................................................ 35

4.1.7. Water Legislations and Water Quality Requirements .................................................. 36

4.2. Legalisation Compliance by Proponent ................................................................................ 37

5. IDENTIFYING AND ASSESSING POTENTIAL ENVIRONMENTAL IMPACTS ...................................... 39

5.1. Assessing the Stampried Farm’s Proposed 1000 Sow Piggery project ................................. 39

5.1.1. Defining project scope .................................................................................................. 39

5.2. Inventory analysis ................................................................................................................. 41

5.2.1. General description of the system ................................................................................ 41

5.3. Pig housing design and environmental consideration .......................................................... 44

6. ENVIRONMENTAL MANAGEMENT PLAN ...................................................................................... 46

6.1. Planning and Design .............................................................................................................. 46

7. CONCLUSION ................................................................................................................................. 81

Works Cited ........................................................................................................................................... 82

Annex 1: Risk assessment model results .............................................................................................. 83

Annex 2: Background information and invitation to participate document ........................................ 84

1. PURPOSE OF THE DOCUMENT AND CONTENTS ................................................................... 86

2. PROJECT DESCRIPTION ............................................................................................................ 86

7

2.1. Terms of Reference ........................................................................................................... 86

2.1.1. Activities planned for the scoping phase .............................................................. 86

2.1.2. Project Location ......................................................................................................... 87

3. PROPOSED STUDIES.................................................................................................................. 87

a. Biodiversity Study ................................................................................................................. 87

b. Waste management .............................................................................................................. 88

c. Assessment Of Alternatives ..................................................................................................... 88

i. No-Go Option .......................................................................................................................... 88

ii. Sites .......................................................................................................................................... 88

iii. Technological Alternatives ............................................................................................. 88

4. THE ENVIRONMENTAL IMPACT ASSESSMENT PROCESS ................................................... 89

a. Project elements to be covered by the EIA. ...................................................................... 89

b. Scope Of The Work ................................................................................................................ 91

Scoping Activities .......................................................................................................................... 91

c. Draft EIA Report .................................................................................................................... 92

d. Legal Framework .................................................................................................................. 92

5. PUBLIC CONSULTATION AND DISCLOSURE PLAN ............................................................... 92

a. How you can be involved? ................................................................................................... 93

Annex 3: List of registered Interested and Affected Parties and Neighbours’ questionnaires. ........... 96

Annex 4: Advertisements and posters ................................................................................................ 109

Annex 5: EIA Practitioner’s details ...................................................................................................... 110

8

Table 1: List of experts and their areas of responsibility in the EIA process. ....................................... 11

Table 2: Water use and slurry production. ........................................................................................... 42

Table 3: Gross nutrient production in manure and feed efficiency. ..................................................... 43

Table 4: Overall risk assessment results. .............................................................................................. 45

Table 5: EMP: general environmental factors. ..................................................................................... 47

Table 6:EMP: geology and soil fcators. ................................................................................................. 54

Table 7: EMP: atmosphere and noise factors. ...................................................................................... 57

Table 8: EMP: soil, surface water, storm water and groundwater factors. .......................................... 63

Table 9: EMP: biosecurity factors. ........................................................................................................ 71

Table 10: EMP: resource usage factors. ................................................................................................ 75

Table 11: EMP: infrastructure factors. .................................................................................................. 78

Table 1: IAP REGISTRATION AND COMMENTS FORM ......................................................... 94

LIST OF FIGURES Figure 1: The location of the proposed site at Stampried Farm. .......................................................... 14

Figure 2: Average wind speeds and directions. .................................................................................... 16

Figure 3: Average temperature and rainfall. ........................................................................................ 16

Figure 4: Stampried Farm locality Map. Source: Own map. ......................................................... 87

Figure 5: The EIA process that will be followed. ................................................................................... 90

Figure 6: The EIA process to be followed. ............................................................................................. 90

9

1. INTRODUCTION

Stampried Farm is proposing to establish a 1000 sow piggery on a portion of

Stampried Farm located at Stampriet in Hardap Region. The proposed project will

cover an aerial extent of approximately 5 Ha for a development footprint of 1000

sows, 7 Boars, 86 Breeding, 272 for farrowing, 1760 piglets, 3255 weaners, 4501

Growers and 2251 Finishers. In order to realize this project an environmental impact

assessment (EIA) process must be undertaken by the relevant applicant and

authorised by the Ministry of Environment and Tourism (MET) as prescribed in the

Environmental Management Act, (2007) and Regulations (2012). Stampried Farm

appointed Outrun Consultants CC as its environmental assessment practitioner

(EAP) for this environmental impact assessment process.

This report comprises of the environmental scoping and management plan for the

proposed project. The scoping section includes the terms of reference (plan of study)

that sets out the proposed approach to the relevant environmental impact

assessment, inter alia, a description of tasks undertaken for the environmental

impact assessment process, an indication of the stages for competent authority

consultation, a description of the assessment methodology used and particulars of

the public participation process that was followed. Finally, the terms of reference also

proposed the relevant investigations for the EIA study. The important aspects that

allowed the practitioners to assess the project objectively were:

Climate;

Geology;

Topography;

Soils;

Land-use capabilities;

Hydrology;

Air quality;

Natural vegetation; and

Occupational health and safety

As required in the EIA regulations the components of this report are set out below:

details and expertise of the EAP who prepared this report;

description of the proposed activity;

10

description of the property on which the activity is to be undertaken and the

activity’s location on the property;

description of the environment that may be affected by the activity and the

manner in which the physical, biological, social, economic and cultural

aspects of the environment may be affected by the proposed activity;

description of the property on which the activity is to be undertaken and the

activity’s location on the property;

description of the environment that may be affected by the activity and the

manner in which the physical, biological, social, economic and cultural

aspects of the environment may be affected by the proposed activity;

details of the public participation process;

description of the need and desirability of the proposed activity;

identified potential alternatives, inclusive of associated advantages and

disadvantages;

indication of the methodology used in determining significance of potential

environmental impacts;

description and comparative assessment of alternatives;

environmental issues identified during the EIA process, assessments of

significance and mitigation measures;

assessment of identified potentially significant impacts;

description of assumptions, uncertainties and gaps in knowledge;

reasoned opinion of whether activity should be authorised and any

prescriptive conditions;

environmental impact assessment scope;

proposed environmental management plan;

health and safety issues;

conclusions and recommendations.

1.1. Environmental Impact Assessment Practitioner’s Details

1.1.1. Details of Environmental Assessment Practitioner

Outrun Consultants CC is a privately owned consultancy company doing various

projects in Southern Africa Development Community (SADC) countries. Our core

services are:

11

Environmental Impact Assessment

Environmental Investigations

Research and Training

Feasibility Studies

Agronomy

Monitoring and Evaluation

Outrun draws its experts from regional and international universities such as

University of Zimbabwe (Zimbabwe), National University of Science and Technology

(Zimbabwe), University of Namibia (Namibia) and Polytechnic of Namibia (Namibia).

Outrun declares that we have no interests in this project and are independent and

acted as such during the EIA process as required by the EIA regulations. The key

team members who carried out this EIA are presented in Table 1 below.

Table 1: List of experts and their areas of responsibility in the EIA process.

ORGANIZATION AREA OF RESPONSIBILITY

/ FIELD OF EXPERTISE

TEAM MEMBERS

OUTRUN Project management

EIA coordination

Josiah T. Mukutiri

OUTRUN EIA process Josiah T. Mukutiri

PROPONENT Development of the project

concept

Stampried Farm

OUTRUN Literature review / Desk study Emmerencia Montzinger

OUTRUN Legislation & Policy Review Josiah T. Mukutiri

OUTRUN Development of

Environmental Management

Plan (EMP)

Josiah Mukutiri

OUTRUN Public Consultation and

Facilitation

Josiah Mukutiri and the

Proponent

12

1.2. Project Description and Location

Stampried Farm is putting up infrastructure for a 1000 sow piggery unit on a portion

of the farm currently having at least 100 Ha of land under irrigation for the following

crops:

Lucerne;

Maize;

citrus comprising of apples; and

grape vines etc.

The farm is located at Stampriet, approximately km from Windhoek along the B1

Highway towards Mariental. There is an existing gravel road connecting the plot

earmarked for the piggery project and the controlled main access to the farm. The

proposed infrastructure and approximate dimensions is presented below:

Fresh water reservoir;

Slurry dam;

Pig shed;

Dead animal disposal area;

Whey dam; and

Canteen

The pigs are housed in fully slatted floors. No bedding or sawdust is used. The

manure (solids and liquids) excreted by the animals falls through the slatted floor.

The manure is temporally stored under the slatted floor in an effluent holding pit until

the “flushing plug” is opened daily to release the effluent, which flows in a pipe to a

slurry sump. It is then pumped from the slurry sump through a fixed separator which

separates any solids from the sludge. The liquid is pumped to a holding pond to be

recycled while the solids are concentrated and composted, and then sold to local

farmers as manure.

The pigs produce 28,000 litres of effluent per day. The effluent is a mixture of faeces,

urine, and wash water. This effluent is separated into solids and liquids, using a

rotary or static separator. The solids are loaded to a large compost heap, where it is

broken down by various microorganisms to produce a nutrient-rich organic material

13

which is used to grow feed crops and citrus on the farm. The liquid is transferred to a

reservoir.

Liquid from the reservoir is recycled back to the pig pens, and is flushed under the

slatted area where they are kept. It gathers faeces and urine again, and goes

through the separator, eventually ending in the reservoir. Some liquid evaporates,

and is replaced with water from a nearby borehole. Pig mortalities estimated to be

between 1,000 and 2,000 kg/month are expected at the facility and will be dealt with

by donating the carcasses to lion parks or burial on a portion of land within the

facility.

The process involved can be summarized as follows:

1. Slurry is removed from the building by way of 315mm class 4 drain pipes.

2. Slurry is then deposited in a slurry pump sump with a capacity of 78m3.

3. The slurry sump is 1m higher than the slurry pipe to prevent spill.

4. From this sump the slurry is pumped with a slurry pump with a capacity of

45m3 per hour to a fixed separator with a capacity of 50m3 per hour.

5. The separator filters solids from the slurry through a screen of 250 microns.

6. The screened water is then deposited into the water storage dam with

1,000m3 volume.

7. The solid is deposited on a concrete slab and composted.

8. The water is recycled i.e. used to flush the pig pens again.

Pigs that die are rendered or incinerated at a facility in Mariental on an out sourcing

arrangement in which the Proponent will be paying for the disposal services

rendered.

14

Figure 1: The location of the proposed site at Stampried Farm.

15

2. DESCRIPTION OF THE ENVIRONMENT

2.1. Topography

The project site lies on the Stampriet Transboundary Aquifer System (STAS) which

is a very large transboundary aquifer system covering an area of 86 647 km2 on a

generally flat topography with a gentle NW to SE slope. Altitude ranges from about 1

500 m to 900 m above sea level. Namibian area covers approximately two thirds of

the aquifer covering the whole Stampriet area.

2.2. Geology and Hydrology

The project site lies on the Stampriet Transboundary Aquifer System (STAS) which

covers a large arid region stretching from Central Namibia into Western Botswana

and South Africa’s Northern Cape Province. This aquifer system consists of an

unconfined Kalahari aquifer units that overly two confined sandstone aquifers. The

delineation of the STAS area follows the outer boundary of the so-called Ecca Group

of geological formations within the catchments of the Auob and Nossob rivers.

It has a hot and dry climate, with an annual mean temperature of 19-22 oC and mean

rainfall ranging from 140 mm/yr in the SW to 300 mm/year along the northern and

north-eastern border. During the period May through September there is hardly any

rainfall.

2.3. Climate

2.3.1. Temperature

The project area under study is characterised by a hot and dry climate with an

annual mean temperature of 19 – 22oC. Annual mean temperature variation is small.

During the summer period mean maximum temperature varies between 26 and

36°C, while in winter, the temperature pattern is reversed with mean minimum

temperatures of 1°C in the western, southern and eastern boundaries of the STAS

and of 12°C in the STAS northern central area, Stampriet area).

2.3.2. Wind

16

Figure 2: Average wind speeds and directions.

2.3.3. Rainfall

High intensity and short duration rainfall events are common in the Stampriet area

and normally occurs in the months from October to April. Most rainfall is usually

received from the months of January to March whilst the lowest rainfall months are

from June to September. The average annual rainfall within the study area varies

from 140 - 310 mm/y.

Figure 3: Average temperature and rainfall.

2.4. Evaporation and Evapotranspiration

Evaporation and evapotranspiration form the main water outflow component in the

study area. High potential evaporation rates result in huge losses from open water

bodies and high potential evapotranspiration rates because the water demands of

crops to be considerably high.

17

In all parts of the study area, mean annual rainfall is much smaller than annual

potential evapotranspiration, and indicates aridity.

2.5. Demographics

Stampriet is a small settlement surrounded by commercial farms and administered

by a Village Council. It is served by a supermarket, a fuel station, church and a

school. Houses are either brick houses with iron roof or corrugated iron shacks.

Approximately 60 % of the population is the working age group while 22% and 18%

are below the age of 15 and above the age of 60, respectively. Regarding literacy,

around 85% of the population is literate, 15% of the population has never attended

school, and 23% are currently at school and approximately 60% left school.

2.6. Water Supply and Sanitation

2.6.1. Water Supply

It is estimated that at least 90% of people in the Stampriet settlements have access

to safe drinking water. The water is provided by NAMWATER and the Ministry of

Agriculture, Water and Forestry (MAWF). Water losses and water unaccounted for

represent more than 60% of the water exploited for water supply in Stampriet.

Households without direct household water connections (mainly population in the

informal areas) in the study area accesses water from communal standpipes. The

burden of collecting water to meet the household water needs from the communal

standpipes mainly lies with women and girls. The distances travelled by household

members vary between one and two kilometres. A prepaid token system is used to

access water from the communal standpipes.

2.6.2. Sanitation

In contrast to access to drinking water over 65 % of households in the Stampriet

Basin and approximately 54% of Stampriet settlement households do not have

access to any toilet facilities. The sanitation gap is most dire in other villages and

settlements such as Kries (90% of the population without access to sanitation) and

Hoachanas (80% of the population without access to sanitation). Information also

points out to the use of pit latrines in some settlements households, which may have

18

implications on groundwater pollution, particularly in the shallow Kalahari aquifers.

34% of settlements households have flush toilets and use septic tanks and

soakaways systems because of the lack of sewer reticulation networks. It is

estimated that on average, 80% of water used in households becomes wastewater.

2.6.3. Water and water use in the area

Given the climatic and other geographic features, there are no permanent rivers in

the Stampriet area but some ephemeral rivers that provide some water during the

rainy season, there are surface water pans scattered over the area that collect and

store water for livestock watering.

These reserves can last a few months after the rains leaving groundwater as the

only permanent and dependable water resource in the project area. Groundwater is

withdrawn from the Kalahari, Auob and Nossob aquifers, by means of dug wells and

boreholes. It is estimated that at least 20 million cubic metres per year is abstracted;

65% of this volume comes from Kalahari aquifers, 33% from the Auob aquifer and

2% from the Nossob aquifer. The breakdown of overall water use is as follows: 52%

for irrigation, 32% for stock watering and 16% for domestic use.

2.7. Vegetation

The agricultural practices in this area are typically integrated crop and livestock

systems were water is used for irrigation and watering livestock. Crops are

dominated by fodder (lucerne), although some farmers have started switching to

horticulture (e.g. vegetables and fruits). Such crops cannot be grown without

irrigation because of the arid climate. Since irrigation needs higher investment, crop

production is dominated by commercial farmers that can invest in irrigation systems.

It is estimated that approximately 80 commercial farms are irrigating 619 ha of land

of a total of approximately 1000ha of irrigable land. Irrigated areas in farms usually

do not exceed 20 ha. Drip irrigation is widely applied in the study area. Other

methods in use are center pivots, sprinklers and mixed applications (sprinkler, drip

and others). Farms applying only flood irrigation are very few.

19

2.8. Economic Activities

2.8.1. Agriculture:-Crop and Livestock Production

The agricultural practices in this area are typically integrated crop and livestock

systems were water is used for irrigation and watering livestock. Crops are

dominated by fodder (Lucerne), although some farmers have started switching to

horticulture (e.g. vegetables and fruits). Such crops cannot be grown without

irrigation because of the arid climate. Since irrigation needs higher investment, crop

production is dominated by commercial farmers that can invest in irrigation systems.

It is estimated that approximately 80 commercial farms are irrigating 619 ha of land

of a total of approximately 1000ha of irrigable land. Irrigated areas in farms usually

do not exceed 20 ha.

Drip irrigation is widely applied in the study area. Other methods in use are centre

pivots, sprinklers and mixed applications (sprinkler, drip and others). Farms applying

only flood irrigation are very few. Lucerne represents approximatively 50% of the

irrigated area (310 ha) and 38% of crop production (6200 tons/year). It is primarily

produced for farmers’ own use as feed for livestock, and consequently may not

directly generate income for farmers; but reduces expenditure on inputs for livestock

farming and is likely more cost effective than importing it from, for example, the

Hardap scheme near Mariental, or South Africa. Some farmers have started

switching to vegetables (e.g. tomatoes, beans) and fruits (e.g. citrus, grapes,

melons, pumpkins). Vegetables and fruits together represent 50% and 8% of total

crop production, respectively.

Potential income from vegetables and fruits are greater than other crops (e.g. oats

and maize), however they are deemed to have higher labour and initial investment

costs, and to be riskier in terms of their yield (mainly due to climatic conditions) and

value.

2.9. Access road

The most acceptable access road to the piggery site is the existing road leading off

the main road into the farm. However, a second gate / access control point to the

piggery site will be needed to control movement of people on the farm. This is critical

20

for security and disease control as well.

2.10. Other site infrastructure/requirements

In the proposed site layout allowance has been made for the following buildings and

facilities within the project area:

slurry dam and ponds;

Ablution house;

electrical substations and motor control centres;

central control room;

workshop; and

a staff cafeteria.

All buildings will be “modular” type structures placed on an engineered terrace with a

concrete floor slab, with adequate sanitary facilities and air conditioning as required.

Steel structures will include the general workshop and stores building, pipe and

cable racking and miscellaneous access platforms and walkways. No need for onsite

housing is foreseen for either the construction or operation phase of the project.

Housing would be located in Stampriet.

General waste will be deemed to consist of domestic waste (comprising primarily of

food wastes from the cafeteria and office waste) and industrial waste consisting of

construction waste (concrete, wood, metal, and other scraps), empty non-hazardous

reagent containers, tyres, and other waste products from the construction and

operations stages. General provision will be made for disposal of all waste material

at offsite licenced refuse/disposal sites at Stampriet.

21

3. PUBLIC CONSULTATION

3.1. Public Consultation Process

Public participation forms an integral part of any present day environmental

assessment process. The objectives of public participation can be summarised as

follows:

informing stakeholders;

sharing of views, concerns and values;

minimising risks and maximising on potential benefits;

influencing project design;

obtaining local knowledge useful in the project planning phase;

creating buy-in from the public and stakeholders;

transparency and accountability in decision-making; and

Reducing conflict (decision-making through consensus).

The Consultant and the Proponent conducted a public consultation meeting held at

Stampriet Village Council board room on the 20th of February 2019. The meeting

was chaired by the Councillor for Stampriet, Honourable S. Dukeleni, and

attended by other Councillors and community members. The meeting was

publicised through posters pinned at the local supermarket, fuel station and the

Village Council Notice Board. Advertisements were also published in 2 local

newspapers and announcements on the local radio station. Questionnaires were

also distributed in the community and neighbouring farmers to solicit their input.

22

3.2. Summary of Issues Raised During the Public Meeting

Table 2: Issues and / or concerns raised during the public consultations and actions taken / recommended.

Issues / Concern(s) Raised Response and / or Recommendation

What will happen to the solid waste or

residue and the smell?

All solid waste generated will be

separated from the water through

dewatering and composted. The organic

manure will be used in the crop fields and

surplus can be sold.

Can a biogas plant be erected? Biogas is a possibility but is not under

consideration at this moment in time.

How many job opportunities will be

created?

At most 150 direct permanent jobs will

be created and many others in the

downstream.

We are happy because the project will

contribute to meet social needs.

This is achievable through corporate

social responsibility

How will the community benefit? There are direct and indirect benefits in

which case the direct benefit are the

employment opportunities created, while

the economic spin offs will benefit the

community indirectly.

How will you prevent pollution of ground

water?

All ponds collecting waste water will be

lined using impermeable geotechnical

fabric or poly vinyl chloride material.

We would want to have continued

information sharing.

The consultations held ensured that we

have the contact details of the IAPs and

will be used for future correspondence in

support of other media such as the

community radio and print media.

23

3.3. Need and Desirability of the Proposed Project

3.3.1. Relevance of economic viability

Uncertainties or substantial fluctuations in production levels, or the actual failure of

resource projects, potentially create adverse social and environmental impacts. This

is particularly so in the case of large scale projects involving major supporting

physical and social infrastructure. Therefore the analysis of the broad economic

viability of a project forms a relevant important component of an environmental

impact assessment.

In the case of the proposed piggery project, assessing economic viability involves

consideration of the forecast demand for pork products, and its anticipated price

relative to the proposed investment in its production. However, for this project

fluctuations in the rate of production will have only a minor impact on the socio-

economic structure of the region, compared with larger resource projects that involve

the establishment of townships and the provisions of a wide range of support

services. The proposed project places minimal demands on government services

and the interaction with the local community will be relative modest and

predominantly beneficial.

3.3.2. Economic and non-economic benefits and costs

Social and economic impacts of the proposed piggery project forms part of the

environmental impact assessment undertaken for the project. Naturally new job

opportunities will be created at the Stampried Farm, coupled with economic benefits

to the Namibian government and the Stampriet area. Economic costs to the

Stampriet community will be minimal, particularly with regard to infrastructure, water

infrastructure for the project will be developed on site, and electricity will be drawn

from and existing line on the farm.

Significant non-economic benefits can be expected to emanate from increased

employment opportunities in skilled and semi-skilled jobs, including the associated

training and experience, in the neighbouring community, including social upliftment

24

programmes and through an employment multiplier of about two hundred per cent.

Namibia has a total of about 600 pig producers, most of them i.e. about 500 farmers

having between three and 10 pigs making them subsistence farmers. There are

about 100 commercial farmers producing about 50 % of pork in the Namibian market

while the rest is imported from South Africa and Europe. The pig production sector

provides resilience in a dynamic and economically difficult situation for farmers for

example the pig sector was never affected during the livestock export and drought

challenges experienced in the past years. Farmers are also enjoying the pig

protection scheme and the Pork Market Share Promotion Scheme. Pig farming

remains attractive because of the lower input costs, especially cheaper feeding costs

for pigs.

25

3.4. Assessment of Project Alternatives

3.4.1. The No-Go Option / Consequences of not proceeding

At the moment, Namibia imports at least 50 % of the pork products consumed.

Stampried Farm will be capable of producing significant quantities and supplying it to

the local market. The advantage is that Namibia will save on foreign exchange and

local companies will save on the transport costs. Failure to proceed (no-go

alternative) will negate these benefits and savings for the country.

The construction phase of the proposed piggery project will create up to jobs in the

country. Although many of these newly created job opportunities will occur in the

farming industry, additional job creation effects will take place in various other

sectors as well; for example, personnel services, transport and equipment

manufacturing. There will be no employment benefit if the piggery project does not

proceed.

The proposed piggery will generate new income opportunities for the Namibian

government. These income derived sources will include:

indirect government taxes,

pay as you earn (PAYE) taxes, and

Company taxes paid to government.

Benefits for not proceeding with the project can be summarised as the following

primary benefits:

the resource will remain in place for possible future development,

there will be no further visual impact of development,

there will be no disruption to local communities arising from construction and

operation, and

there will be no alteration to local biodiversity arising from construction and

operation.

26

3.4.2. Alternative site (s)

The proposed site, a portion of the Stampried Farm considered for this development

is ideal given that it is fairly flat and will not require extensive ground works to erect

the required infrastructure. No other potential sites were considered. On the other

note it is farther away from the existing farm houses and thus no potential noise or

air pollution is foreseen in the context of the existing farm layout.

3.4.3. Strategic Alternatives

The proposed project site is easily accessible and has all the necessary utilities such

as water, electricity and access gravel road which forms part of the farm road

network servicing the different sections of the farm. Although there are other pig

farms in Namibia the market is still dominated by foreign suppliers. Hence the

Namibian market has a huge opportunity for piggery and the Proponent can

potentially apply for infant industry protection from the GRN.

3.5. Technical Alternatives

3.5.1. Waste Management Technologies

Site-specific, nutrient management strategies will be required to prevent and / or

minimize potential water pollutants from confinement facilities and land application of

manure and organic by-products. Using environmentally safe alternatives to land

application of manure should be an integral part of the overall Environmental

Management Plan (EMP). These alternative uses are needed in areas where nutrient

supply exceeds the nutrient requirements of crops, and/or where land application

would cause significant environmental risk. More efficient and cost effective methods

are needed for manure handling, treatment, and storage. Options that are available

include but are not limited to the following:

Improved systems for solids removal from liquid manure;

Improved manure handling, storage, and treatment methods to reduce

ammonia volatilization;

Treatment systems that transform and/or capture nutrients, trace elements,

and pharmaceutically active compounds from manure;

Improved composting and other manure stabilization techniques; and

27

Treatment systems to remediate or replace anaerobic ponds.

Modern trends show a shift from municipal treatment methods in the near past to a

new body of knowledge with methods adapted to the specific characteristics of these

wastes and a different purpose for treatment as detailed below:

Option 1

Is to develop dry systems such as the deep bedding where fresh manure is mixed

with a bulking agent or use inclined belts under the slatted floor to separate urine and

solids so that all or part of the manure leaving a building is directly handled as a solid.

Option 2

The second option is to improve or retrofit existing liquid systems so that volatile

solids and organic nutrients are separated from the fresh manure and transported

and/or treated with a variety of technologies to generate value-added products. Solid-

liquid separation of the raw manure increases the capacity of decision making and

opportunities for treatment. The separation up-front allows recovery of the organic

compounds, which can be used for the manufacture of compost materials and other

value-added products or energy production. These products include stabilized peat

substitutes, humus, bio-chars, organic fertilizers, soil amendments, and energy. The

remaining liquid needs to be treated on the farm. A variety of biological, physical or

chemical processes can be used to achieve specific nutrient management goals and

environmental standards.

Option 3

A third option is to use anaerobic digesters (AD) to recover methane and energy from

the carbon in the liquid manure (EPA, 2012). The biogas recovery systems collect

methane from the manure and burn it to generate electricity or heat. Production of

biogas from manure using anaerobic digesters is projected to be important worldwide.

However, in areas of intensive livestock production, new technologies need to be

developed in conjunction with AD to address surplus nitrogen and nitrogen removal

and/or recovery of concentrated phosphorus from AD effluents in a form that can be

removed from the watershed.

Over and above all it is vital to take heed that nutrients (e.g., nitrogen and

28

phosphorus), manure and wastewater from animal feeding operations have the

potential to contribute other pollutants such as organic matter, sediments, pathogens,

heavy metals, and ammonia if discharged uncontrollably into the environment.

Anaerobic ponds are widely used to treat and store liquid manure from confined

piggery production facilities. However they have their inherent environmental and

health concerns which include emissions of ammonia, odours, pathogens, and water

quality deterioration. Thus, there is a major interest in considering various options as

much as possible depending on the socio-economic setting. Choice of options should

be technically, operationally, and economically feasible, and meet the following five

environmental performance standards:

Eliminate the discharge of animal waste to surface waters and groundwater

through direct discharge, seepage, or runoff;

Substantially eliminate atmospheric emissions of ammonia;

Substantially eliminate the emission of odour that is detectable beyond the

boundaries of farm;

Substantially eliminate the release of disease-transmitting vectors and airborne

pathogens; and

Substantially eliminate nutrient and heavy metal contamination of soil and

groundwater.

3.5.2. Benefits associated with good waste management practices

The quality of the air is improved significantly through the reduction of odours

compounds (phenol, p-cresol, p-ethylphenol, indole, and skatole). Substantial animal

production advantages can be realized through good manure management practices.

Many Researchers have documented with many examples the direct linkage between

improved manure management and animal productivity and health. Indicators of

better productivity and health were healthier pigs, reduced mortality, increased daily

gain, improved feed conversion, and substantial economic benefits to the producer.

The reuse of cleaner, sanitized water (ammonia free) to refill barn pits reduced

ammonia concentration in the air and improved the growing environment. Ambient

ammonia levels in the barns dropped an average of 75 percent, from 11.3 to 2.8 ppm.

As a result, animal health and productivity were enhanced. Daily weight gain

increased 6.1 percent, and feed conversion improved 5.1 percent. Animal mortality

decreased 47 percent. Such results are consistent with the substantial animal

production advantages that can be realized through good manure management

practices in swine production buildings.

29

Value-added Products

Composting of the separated manure solids is done in a centralized facility where the

solids are combined with a rich carbon source to optimize the composting process.

The produced composts conserve 95-100% of the nitrogen and other nutrients and

meet EPA Class A bio-solids quality standards due to low pathogen levels. The high-

quality composts are used for the commercial manufacture of soil amendments,

organic fertilizers, and potting soil. Using the United Nations Convention on Climate

Change (UNFCCC) protocols from separation and composting realized and estimated

96.9% reduction in GHG emissions by sing solid separation, composting and

biological N treatment.

3.6. Assessment models of agricultural projects (Alternatives)

Environmental assessment models are a means to quantify the environmental

impacts associated with production systems. Several types of environmental

assessments have been applied in different industry sectors whereby each of the

method implements different approaches and levels of detail. Known assessment

methods are: Ecological Footprint, Nutrient Balance, Environmental Risk Mapping,

Multi Agent System and Multi Linear Programming Approach. This section will

summarize each of the methods and discuss the advantages and disadvantages

followed by qualifying the Life Cycle assessment (LCA) combined with the Risk

Assessment Model as the appropriate method for this type of project.

3.6.1. Ecological Footprint

Ecological Footprint is an environmental assessment method developed by (Mathis

Wackernagel, 1997). It is used to indicate the human demand on the environment

by quantifying the amount of nature they occupy in order to live. The assessment

method is used to quantify the human populations demand for natural resources and

the ability of the biosphere to regenerate the consumed resources, (Mathis

Wackernagel, 1997). The method considers five categories: consumed land,

gardens, crop land, pasture land and productive forest. It also considers the

potential sustainability of manufacturing the product(s). However, local, regional or

global differences are not included, thus, the assumption is made that all land and

30

water areas are the same. The method also only considers CO2 and leaves other

Greenhouse Gases (GHGs) which may have a profound effect on the environment

outside the assessment. These are the identified weaknesses in the assessment,

although there maybe scope to enhance the methodology to include other GHGs to

give a more complete assessment of a system. Consequently, (Jeroen van der

Bergh, April, 1999) suggest that the potential environmental impacts of a production

process are generally underestimated within the current method of Ecological

Footprint.

3.6.2. Nutrient Balance

Another method of environmental analysis is Nutrient Balance (de Boer 2003). This

is carried out to identify inefficiencies within a production system. At farm level, this

approach assesses nutrient losses, erosion and leaching from a system. Nutrient

Balance focuses mainly on the assessment of N, P and K (macro - nutrients),

therefore it can be useful when considering the environmental effects of crop

production with regards to losses from applied fertilizers (nutrient loss = input –

output). However, other inputs into the system are not considered, for example, fossil

energy required for the manufacture of fertilizers. Nutrient Balance does not take into

account site specific conditions. For instance, an assumption is included in the model

for equal efficiencies of N, P and K applied to crops on different sites (Sheldrick &

Lingard 2004). The success of Nutrient Balance varies, depending on the detail

included in the assessment and the construction of the analysis for nutrient losses at

farm level (de Boer 2003). It is not suitable, however, for assessment of all

environmental burdens.

3.6.3. Environmental Risk Mapping

Another more holistic approach is Environmental Risk Mapping. This defines the

environmental risks resulting from human pressure (for example farming practices)

and from the vulnerability of the environment in a given region. However, it only

assesses one impact category at a time, for example nitrate leaching or the transfer

of phosphorus (Assimakopoulos et al. 2003; Payraudeau & van der Werf 2005). The

assessment is constructed using several variables, and has the ability to include

output data from simulation models. This assessment could be applied to determine

31

the environmental impacts arising from a particular aspect of the farm system, for

example manure management but it is not a useful tool to quantify several

environmental impacts in the same assessment (Payraudeau & van der Werf 2005).

3.6.4. Multi-Agent System

The Multi-Agent System is an environmental assessment method that assesses the

economic, social and environmental interactions of an agricultural system. The aim

of this approach is to represent the behaviour of a defined group towards a limited

resource and to calculate the use of resources within a system. It also allows

different potential situations to be modelled. The parameters included can be

controlled to determine the best possible scenarios for the management of the

assessed product. Courdier et al (2002) and Payraudeau & van der Werf (2005)

applied this method to analyze the management systems of manure and the overall

impacts this caused to the sustainability of the environment. The aim of their study

was to show different ‘what if’ scenarios for management of animal wastes. This

approach is therefore advantageous when determining ways to reduce

environmental impacts in a theoretical approach. However, the results are focused

not on the environmental impacts per se, but rather directed at the social and

economic impacts. Therefore, to make a thorough environmental assessment of a

production system, Multi-Agent System may not be the most appropriate approach.

3.6.5. Multi Linear Programming

Multi Linear Programming is an approach that is applied to determine potential ways

to minimize the environmental impacts of a system by optimizing production by

considering its technical, economic and social aspects (Bouman et al. 1999;

Payraudeau & van der Werf 2005). Linear optimization techniques are used to

identify the management method(s) which maximizes profitability with minimal

environmental emission (Payraudeau & van der Werf 2005). Indicators within the

assessment can be adjusted to determine (theoretically) the best scenario within the

system to reduce the environmental burdens. This approach is constructed in

stages. Initially, the production system is described to include all inputs and outputs

and all associated emissions. All environmental (also if required economic,

agronomic and social) constraints are then incorporated which limit the management

32

of the system. Finally, to determine the best possible scenario, linear optimization

techniques are applied to determine the most appropriate management scenario

which has the lowest environmental impact. Applicability is limited due to data

unavailability shortage of skills.

3.6.6. Life Cycle Assessment

Although the methods above can be useful on a smaller scale, with the exception of

Ecological Foot printing, to identify environmental problems within a particular

aspect of the pig industry, a more comprehensive environmental assessment is

required to assess the environmental impacts of a complete production system. This

identified approach is called Life Cycle Assessment (LCA).

Life Cycle Assessment is a tool for assessing the environmental impact caused by a

product or a service. The basic principle for LCA is to follow the product through its

entire life cycle, from cradle to grave. The product system is delimited from the

surrounding environment by a system boundary. The energy and material flows

crossing the boundaries are accounted for as input-related (e.g. resources) and

output-related (e.g. emissions to air) flows.

The procedure for performing an LCA consists of four phases:

Phase 1

In phase 1, the goal and scope is definition, the aim and the range of the study is

defined. Important decisions are made concerning definition of functional unit (i.e.

reference unit), choice of allocation methods and system boundaries.

Phase 2

In the inventory analysis, information about the system is gathered and relevant

inputs and outputs are identified and quantified.

Phase 3

In the impact assessment, the data and information from the inventory analysis are

linked with specific environmental parameters so that the significance of these

potential impacts can be assessed.

33

Phase 4

In the final interpretation phase, the findings of the inventory analysis and the impact

assessment are combined and interpreted to meet the previously defined goals of

the study.

In the light of the above the LCA and risk assessment models were chosen and

used jointly to assess the potential environmental impacts of the proposed piggery

project.

34

4. LEGAL AND POLCY ENVIRONMENT

4.1. Legal and policy instruments relevant to the proposed project

This section describes the policy and legal environment in which the project will be

implemented, the relevant ones in line with the project throughout its life cycle.

4.1.1. Namibia’s National Constitution

The Namibian Constitution Article 95(1) of the Namibian Constitution commits the

state to actively promote and maintain the welfare of the people by adopting policies

aimed at the “… maintenance of ecosystems, essential ecological processes and

biological diversity of Namibia and utilisation of living natural resources on a

sustainable basis for the benefit of all Namibians, both present and future…”

4.1.2. Environmental Management Act (2007) and Regulations (2012)

Under the Environmental Management Act, agricultural activities require

authorisation and the Proponent should apply for an ECC in order to comply. This

act is administered by the Environmental Commissioner in the Department of

Environmental Affairs (DEA) in the Ministry of Environment and Tourism (MET).

Normally, to get Environmental Clearance, an Environmental Impact Assessment

(EIA) has to be completed, together with an Environmental Management Plan

(EMP). An EIA is an assessment of the environmental damage that a project might

cause, and the EMP provides advice on how the negative impacts can be avoided or

reduced. An EIA should be carried out by an independent environmental practitioner.

The EIA report is evaluated by the DEA, and if the Environmental Commissioner is

satisfied that the negative impacts are minimised, an Environmental Clearance

Certificate is issued. The certificate requires the project proponent to diligently

implement the EMP. Violations of the Environmental Management Act are

punishable by law. In a nutshell this is the basis upon which Outrun Consultants CC

was contracted to carry out the EIA.

35

4.1.3. Soil Conservation Act (1969)

This Act promotes the combating and prevention of soil erosion and aims to

conserve, protect, and improve the soil, vegetation, and water supply. Under the Act,

the Minister of Agriculture, Water & Forestry may regulate cultivation as a means to

prevent soil degradation. Specifically, the Minister may direct an owner or occupier of

land regarding: the cultivation of land (including ploughing, the protection,

stabilization, or withdrawal of land from cultivation, the application of crop rotation,

the disposal of crop remnants and plant residues), and the stabilizing of any soil

surface to prevent erosion.

4.1.4. The Forest Act (2001)

The Forest Act (No. 12 of 2001), as amended by the Forest Amendment Act (No. 13

of 2005), guides the Forest Policy implementation. Basically, the Act stipulates how

forest resources should be utilized and the Users’ responsibilities.

It aims to prevent deforestation by making it illegal to clear woody vegetation on

more than 15 hectares of land or remove more than 500 cubic meters of forest

produce per year. Removal of forest produce on any piece of land requires approval

by the Director of Forestry.

4.1.5. The Water Act (1956)

It is currently administered by the Ministry of Agriculture, Water and Forestry and

remains in force until the new Water Resources Management Act (No 24 of 2004,

under amendment) is signed and gazetted. The act does not enforce legislative

controls in respect of the use of water for industrial purposes, but controls the

discharge of used water and effluent originating from industrial enterprises. It also

makes provision for the protection of river catchments, drilling of boreholes and the

digging of wells.

4.1.6. The Water Resources Management Act (2004)

This Act declares that water resources are owned by the State, i.e. for both ground

and surface water. The law was put in place to ensure that water resources are

36

managed and used to the benefit of all people. It is therefore illegal for any person to

pollute either surface or groundwater and it is illegal to discharge effluent without a

permit. It makes provision for the protection of river catchments, drilling of boreholes

and the making of wells; it controls effluent discharge; and exercises certain aspects

of water quality and water pollution monitoring.

4.1.7. Water Legislations and Water Quality Requirements

Legislations governing environmental and water resources have been revised and

passed as bills and laws in parliaments due to the increasing concerns for safer and

cleaner environment and drinking water. Guidelines to drinking water have been

passed which are suitable for human consumption, domestic use and industry use,

represented by guideline values (World Health Organization Geneva, 1993). The

guideline values represent concentration of a constituent that does not result in any

significant risk to the health of the consumer over a lifetime of consumption. The

World Health Organization (WHO) has put guidelines to water quality standards for

water use in a way to try and make sure that everyone has potable water, Annex 1

(Vander Leeden, et al., 1991). The World Health Organization has formed sub-

bodies to monitor that the water quality standards are adhered to. For example,

South Africa has put water quality standards which are termed the Water Quality

Guidelines (Department of Water Affairs and Forestry (DWAF), 1996) which are a

guide to water quality requirements for domestic use, agricultural use (irrigation and

livestock, aquaculture), aquatic ecosystems use, recreational use and industrial use.

Similarly the Namibia Department of Water Affairs (DWA) has got its drinking water

standards and livestock watering, which were passed in July 1991.

37

Table 3: Namibia's Directorate of Water Affairs Standards (1991)(drinking water - human consumption and livestock use)

for selected elements - values are in ppm (mg / L) unless otherwise stated.

Recommended maximum limits

Human consumption Livestock watering Parameter Group A Group B Group C

p H 6-9 5.5-9.5 4-11

Electrical Conductivity (mS/m) 150 300 400

Turbidity 1 5 10

Total Dissolved Solids (calc.) 6000

Total Hardness as CaCO3 300 650 1300

Ca-Hardness as CaCO3 375 500 1000 2500

Mg-Hardness as CaCO3 290 420 840 2057

Chloride as Cl- 250 600 1200 1500-3000

Fluoride as F- 1.5 2.0 3.0 2.0-6.0

Sulphate as SO42-

200 600 1200 1000

Nitrate as N 10 20 40 100

Nitrite as N 10

Sodium as Na 100 400 800 2000

Potassium as K 200 400 800

Magnesium as Mg 70 100 200 500

Calcium as Ca 150 200 400 1000

Manganese as Mn 0.05 1.0 2.0 10

Iron as Fe 0.1 1.0 2.0 10

4.2. Legalisation Compliance by Proponent

Below is a summary of the legalisations that govern project and it is suggested

compliance by the proponent to them. It is advised that the proponent be well

versed/ familiarise with these laws and regulations so that he/she may not face

problems in the future.

38

Table 4: Compliance summary for legislation governing agriculture.

Act/Regulation Compliance

Environmental Management Act Chapter

20:27

Produce biannual reports; adhere to the EMP

outline in EIA and renewal of EIA certificate.

Soil Conversation Act (1969) Practice good farming methods and implement

soil erosion control measures.

Forest Act (2001) Adhere to the regulations and re-vegetate any

areas were vegetation has been destroyed /

should be maintained.

Water Act (1956) Acquire water permits and pay the designated

fees as prescribed.

Water Resources Management Act (2004) Monitor water quality and pay for any

discharge of effluent

39

5. IDENTIFYING AND ASSESSING POTENTIAL ENVIRONMENTAL

IMPACTS

5.1. Assessing the Stampried Farm’s Proposed 1000 Sow Piggery

project

5.1.1. Defining project scope

Purpose

The goal of this study is to perform an environmental system analysis of the

proposed 1000 sow piggery facility at Stampried Farm using LCA methodology.

The purpose of the study is to gain increased knowledge about the environmental

impacts of this particular project and to illustrate environmental benefits and

disadvantages that are integrated in the production system. The study will also

help to illustrate relevant conflicts of interests when different aspects of

sustainability are prioritised. The analysis will be based upon 3 key aspects in pig

farming:

Animal welfare;

Environment; and

Product quality

Scope of the study

The analysis deals with all phases of the life cycle of pig meat as shown below

including production of materials and energy used. Transport steps are also taken

into account.

Descriptions of the production scenario and assumptions

Environmental care, productivity and quality are the priority of the pig production

facility. Feed efficiency is high and the dominant part of the feed is cultivated at the

farm site. The farm buildings are equipped with ammonia collectors in the ventilation

system and the manure is stored and spread with best technique available in order

to reduce emissions. Cereals and legume crops are used in the cultivation and the

crop rotation is strictly planned to minimise fertilizer and pesticide use. Mechanical

regulation of weeds is used frequently.

40

Delimitations

Production of farm buildings and farm machinery is excluded in the LCA

study. The production, use and emissions of medicines are not included due

to lack of knowledge of the environmental impact from medicine residues in

the ecosystems.

The production and use of pesticides are included in the inventory analysis

but a toxic assessment of the fate of pesticide residues is not included in this

study.

Production of synthetic amino acids used in pig production is not included due

to lack of data.

Production of the enzyme phytase is excluded due to lack of data. This

enzyme is used to improve the utilisation of phosphorous in the feed

components making it possible to reduce the need for mineral feed

complement.

Disinfectants, washing detergents and minor stable equipment are not taken

into account.

The various limitations of the LCA were compensated for in the Risk Assessment

Model which also took consideration of the design factors in combination with

environmental setting.

Units used in the Study: Functional units

The functional unit (FU) in the study is “one kg of bone- and fat free meat”. This

functional unit was selected to measure the final function at the consumer, i.e. the

eatable parts from meat production. When data on meat production and

consumption are presented in statistics it is mostly as carcass weight. The amount of

meat finally consumed will however differ since the consumer does not eat the

bones of the chop and most often not the fat; this is the basis for the choice of the

FU in the study. Emissions of ammonia and nitrate are the source of local as well as

regional environmental impact. The concentrations of the emissions are therefore of

interest and consequently the impacts of these emissions are also referred to the

functional unit “one hectare of arable land”. Pesticide use is also assessed per

41

hectare of arable land.

Chosen impact categories

The environmental impact categories considered in this study are:

Resources – energy, material, land use

Toxicity – the use of pesticides is included, pesticide risk indicators

Ecological effects

Climate change

Soil acidification

Groundwater contamination

Air pollution

5.2. Inventory analysis

5.2.1. General description of the system

Animal production

There will be 1000 sows at any one time on the farm and data on the total

animals are summarised in the following table.

42

Table 2: Water use and slurry production.

Estimate on water use/requirement and slurry production (water m3 / year)

Animals Drinking Total

Boars 7 15 105

Breeding 86 12 1032

Early gestation 950 14 13300

Farrowing 272 30 8160

Piglets 1757 1 1757

Weaners 3255 4 13020

Growers 4501 8 36008

Finishers 2251 11 24761

Cleaning 13079 0.5 6539.5

Grand Total 104 682.5

N.B. Total slurry produced is about 60 000 tonnes per year.

Meat production

The functional unit is one kg bone-and fat free meat. This functional unit was

selected to measure the final function at the consumer, i.e. the eatable part from

meat production. The meat percentage out of the carcass weight is estimated at

about 59 %.

Feed consumption

The total feed consumption is presented in table below. The composition of feed

rations is shown. It should be observed that the sows´ consumption of feed is

included per produced slaughter pig and is estimated at 250 kg per slaughter pig

maximum.

Manure production and nutrient balances in the stable

The manure production and the nutrient composition of the manure were calculated

through balances of input of nutrients in the feed and output of nutrients in the

43

produced pigs. All manure is handled as slurry and the dry matter content of the

slurry is 8.8 % (Steineck et al, 1999). All the pigs are fed intensively and the manure

produced during this time is composted and ultimately applied in the field.

Table 3: Gross nutrient production in manure and feed efficiency.

N P K

Nutrients in manure,

kg/slaughter pig

6.9 2.4 2.8

Feed efficiency 0.39 0.25 0.12

Emissions of ammonia

Emissions of ammonia take place in animal housing, during manure storage. The

ammonia losses in the barn are calculated to be 14 % of the excreted nitrogen. If the

ventilation system has a filter to catch discharged ammonia and it is estimated that

approximately 75 % of the ammonia emission in the stable can be caught in the filter

and washed out as ammonium-sulphate and led into the slurry store. Thus, ammonia

emission in this case would be calculated to be 5 % of excreted N. The slurry is

stored in a well-covered tank. The ammonia losses are low from this storage system,

1 % of total nitrogen in the manure is estimated to be lost during the storing period.

Emissions of nitrous oxide

The manure is transported daily to the slurry tank, thus no losses of nitrous oxide in

the stable are calculated. IPCC (1997, 2000) gives emission factors for losses of

nitrous oxide during storing corresponding to 0.001 kg N2O-N/kg N in slurry (after

deduction for N emitted as ammonia). For estimations of indirect N2O emissions due

to deposit of ammonium, IPCC gives the EF of 0.01 kg N2O-N/kg NH4-N deposited.

So far, there is very little data behind this emission factor and due to the great

uncertainty, IPCC recommends this factor to be used rather than country-specific

data (IPCC 2000).

Emissions of methane

The discharges of methane due to enteric fermentation are 1.5 kg CH4/pig according

to IPCC (1997). Due to differences in the intensity as well as choice of slaughter

weight, the total life time of the slaughter pigs varies from 16.6 weeks/pig to about

44

23.7 weeks/pig and we use the higher figure for calculations (waste case always

applies). The emission of methane from manure storage is calculated according to

IPCC (1997):

Emission of CH4 = VS * Bo * 0.67 kg/m3 * MCF

VS stands for volatile solids excreted from animals. VS are 87 % of the dry

matter in the manure (Dustan 2002). The average dry matter of the slurry is

estimated to 8.8 % which has been recorded as an average for pig slurry.

Bo is the methane generation potential, IPCC (1997) suggests 0.45 CH4/kg

VS for swine; this factor was also suggested by Naturvårdsverket (2002).

MCF is the methane conversion factor. For slurry in hot climates, IPCC (1997)

suggested MCF to be 20 %.

Given the proposed production scenario at Stampried it is evident that there are

significant resources input into the system. Based on the first law of conservation of

energy the various input conversion pathways were followed and potentially the

following aspects emerged important for environmental management:

Waste water

Manure (major components being, N, P and K)

Gaseous emissions

Dead pigs carcasses

5.3. Pig housing design and environmental consideration

Key design aspects informed the risk assessment and included the following:

Slated floor design to allow solid waste to drop off the floor

Waste water collection, centrifugation and pumping to solid separation plant;

Piping contained in concrete lined drain lines that collect waste in the event of

leakages;

Very low water table;

Sandy loam soils;

Distance from sensitive receptors of 1 km plus.

45

Table 4: Overall risk assessment results.

46

6. ENVIRONMENTAL MANAGEMENT PLAN

6.1. Planning and Design

This section outlines how environmental considerations have informed and been

incorporated into the planning and design phases of the 1000 sow piggery project at

Stampried Farm as proposed by Roots Piggery (Pty) Ltd. The following design

related mitigation measures have been recommended to reduce the environmental

impacts and gave rise to the EMP that follows. This EMP has been structured so as

to provide its various intended recipients (Proponent, Environmental Control Officer,

Construction Contractors and Engineers) with mitigation measures immediately

applicable to their respective scopes of work. The management requirements for the

various recipients carrying out work for this project are divided according to the main

project phases.

47

Table 5: EMP: general environmental factors.

General environment

Activity:

Design and planning of the proposed piggery.

Design and planning of the wastewater management system.

Aspect

Inadequate planning and design of the piggery.

Inadequate design and planning of the wastewater management system.

Construction X

Project Phase Applicability Operation X

Decommissioning

Impact Description

Environmental

Objective

Management / Mitigation/ Monitoring

Measures

Monitoring

compliance and

reporting

Time frames Responsible

Party

Harm to watercourses due to

inadequate design

To prevent

harm to land /

soil and

watercourses

through

effective and

thorough

planning and

design, taking

the

environment

into

consideration.

Development planning, including storm

water and wastewater management, must

ensure that the construction and operation

of the piggery will not impact on the land or

watercourses.

Project engineers should compile a method

statement, outlining the construction

methodologies. Mitigation measures should

be included in this method statement that

must be approved by the ECO and be

available on site.

Proponent must

verify

implementation of

the mitigation

measures

proposed in this

EMP.

During the

Planning

Planning and

Design

Engineers,

Proponent

48

Soil and groundwater pollution

from effective containment of the

piggery wastewater and

irresponsible application of

wastewater sludge to land.

To ensure

effective design

of the

wastewater

system, in

order to ensure

no

environmental

harm occurs

when the

waste water

system

becomes

operational.

The wastewater management system

should be properly designed and installed

so that the piggery waste is effectively

removed from the houses.

• Plastic / geotechnical fabric lined holding

dams/ponds for wastewater (liquid fraction)

should be designed to contain the

maximum amount of wastewater that could

be stored at any given time.

Any eventualities resulting in land

application not being possible should be

taken into account when designing the

storage facilities.

The holding dam/pond must be lined with a 1.5mm HDPE liner or impermeable concrete floor.

The wastewater management system must be positioned so that it is not subject to flooding and must be situated above the 1:100 year flood line.

Overflow of the wastewater management system must be prevented.

Ensure sufficient freeboard to guarantee facility integrity during heavy rainfall events.

The solid fraction of the wastewater must be stored on an impermeable surface that is properly drained, with drains leading back to the separator.

Determining the amount of land required for

the effective and responsible application of

the wastewater sludge must take the

Proponent must

verify

implementation of

the mitigation

measures

proposed in this

EMP.

During the

design and

Planning of the

Wastewater

management

system.

Planning and

Design

Engineers,

Proponent

49

following into consideration:

Susceptibility to waterlogging, erosion and surface water runoff;

Climatic conditions (evapotranspiration, wind speed and rainfall);

The potential effect on surface and groundwater resources;

The nature of the crop or pasture to be irrigated;

Agricultural practices on the farm;

Soil properties, such as infiltration rate;

The quantity and quality of the wastewater;

Trace element loading (Cu, Zn and Cd); and

The maximum operational life of the application sites in terms of phosphorous sorption capacity and predicted salt accumulation (ARMCANZ/ANZECC, 1999).

It must be ensured that the soils where the

wastewater will be irrigated have the

following characteristics, or as many of

them as possible:

A structure that permits water penetration and air movement;

Adequate drainage;

Sufficient depth for crop root development;

Sufficient capacity to hold water for plant use between irrigations;

A moderate pH;

Nutrients in sufficient quantities to promote plant growth; and

50

Ease of cultivation. Suitable soils are generally deep, well

drained, well-structured soils with loam to

clay loam textures (ARMCANZ/ANZECC,

1999).

Land application rates must take into

consideration the following:

Wastewater salinity;

Wastewater nutrient content;

Wastewater pH;

Wastewater BOD;

Hydraulic loading;

Salt loading; and

Nutrient loading (P, N and K) (ARMCANZ/ANZECC, 1999).

Land application of wastewater should not

occur on land which is:

Waterlogged or saline;

Subject to flooding;

Sloping with inadequate groundcover;

A highly impermeable soil type; and

Rocky or highly erodible (ARMCANZ/ANZECC, 1999).

The following groundwater

factors must be considered

when designing the wastewater

irrigation system:

Groundwater quality;

Depth to the groundwater; and

The current and potential future uses of the groundwater (ARMCANZ/ANZECC,1999).

The following surface water factors must

51

be considered when designing the

wastewater irrigation system:

The distance to watercourses; and

Hydrological features such as drainage patters and catchment areas.

52

Activity: Construction activities for the establishment of a new piggery. Operational activities at the piggery.

Aspect: Lack of knowledge amongst workers and contractors in terms of the impact their actions may have on the environment.

Construction X

Project Phase Applicability Operation X

Decommissioning

Impact Description

Environmental Objective

Management / Mitigation/ Monitoring Measures

Monitoring compliance and reporting

Time frames Responsible Party

Harm to the environment in general (including pollution of soil and water resources, as well as harm to employees).

To prevent harm to the Environment due to lack of knowledge.

Compliance to the Environmental Clearance terms and conditions and Environmental Management Plan (EMP) must form part of agreements with all construction or operational phase contractors. The contractor is to ensure that all employees, including sub-contractors and their employees, attend onsite Environmental Awareness Training prior to commencing work onsite. Follow-up Environmental Awareness Training may be required from time to time as new subcontractors, crews or employees commence work or for specific activities that may potentially impact upon the environment. The contractor and facility manager is to maintain accurate records of any training undertaken. The Environmental Control Officer (ECO) shall monitor the contractor’s compliance

Construction Phase: ECO to verify implementation of the Mitigation measures proposed in this EMP. ECO to submit monthly compliance reports to the competent authority. Operational Phase: Regular site inspections. Internal audits against this EMP must be

During the construction and operational phases.

Construction Contractor, Facility Manager and ECO

53

with the requirement to provide sufficient environmental awareness training to all site staff. All construction workers shall be issued with ID badges and clearly identifiable uniforms. Training is to cover all aspects of the EMP and procedures to be followed.

conducted every 6 months and records kept onsite. Shortcomings must immediately be addressed.

54

Table 6:EMP: geology and soil fcators.

Geology and soils

Activity: Construction and operation of the new piggery. Stockpiling of topsoil and cleared vegetation. Site clearance. Replacement of topsoil and re-vegetation. Vegetation establishment as part of the rehabilitation.

Aspect: Soil erosion. Topsoil being exposed to the elements. Prolonged exposure of cleared areas. Poor topsoil replacement and establishment of vegetation. Unsatisfactory establishment of vegetation.

Construction X

Project Phase Applicability Operation X

Decommissioning

Impact Description

Environmental Objective

Management / Mitigation/ Monitoring Measures

Monitoring compliance and reporting

Time frames

Responsible Party

Exposure of soil to erosion. Erosion can lead to destruction of natural habitats and sedimentation of the proximate watercourses.

To prevent soil erosion subsequent sedimentation of proximate watercourses.

The contractor is to ensure that all reasonable measures are taken to limit erosion during the construction phase. All areas susceptible to erosion should be protected. Erosion protection measures include sand bags, cut-off drains and/or berms.

Do not allow erosion to develop to a large scale before taking action.

Existing roads and tracks should be used as far as possible.

Retain vegetation and soil in position as long as possible. It should only be removed immediately ahead of construction.

Remove only the vegetation essential for construction. No

Construction Phase: • ECO to verify implementation of the mitigation measures proposed in this EMP. ECO to submit monthly compliance reports to the competent authority. Operational Phase: Regular site inspections. Internal audits against this EMP must be conducted every 6 months and records kept onsite. Shortcomings should immediately be addressed.

During the construction phase.

Construction Contractor’ Facility Manager, and ECO

55

disturbance of adjoining vegetation should be allowed.

Colonisation of the disturbed areas should be monitored to ensure that vegetation cover is sufficient within one growing season. If not, the area has to be rehabilitated.

Storm water Management Measures should be implemented.

Degradation and loss of valuable resource (topsoil) due to exposure of topsoil to the weather elements.

To reduce the extent of exposure of topsoil in order to preserve and protect it as a resource.

Topsoil is to be stockpiled in discrete areas and retained for future landscaping. Any sub-soil or rocks removed should also be stockpiled separately and be used during rehabilitation. The length and steepness of the slopes should be minimised. If sterilisation of the topsoil has occurred during stockpiling, inorganic fertilisers can be used to supplement the soils before seeding of the areas takes place. Replace topsoil concurrent with construction, whenever possible. Cordon off areas under rehabilitation using danger tape or similar demarcation to prevent vehicular, pedestrian and livestock access. Aim to replace topsoil to its original depth. If there is not enough topsoil available from a particular soil zone, topsoil of a similar quality may be used to replace it. The suitability of substitute topsoil should be determined by a soil analysis and approved by the ECO.

Compacted soil should be ripped to ensure effective re-vegetation.

Work necessary additives, as indicated by the soil analysis, into the soil.

Construction Phase: ECO to verify implementation mitigation measures proposed in this EMP. ECO to submit monthly compliance reports to the competent authority. Operational Phase: Regular site inspections. Internal audits against this EMP must be conducted every 6 months and records kept onsite. Shortcomings should immediately be addressed.

During the construction and operational phases.

Construction Contractor, Facility Manager, and ECO

56

Re-vegetation by indigenous grass species.

If areas show no specific vegetation growth within three months, the areas shall receive additional topsoil, ripped to a depth of 100mm and re-planted.

Soil stabilising measures could include rotovating in straw bales (at a rate of 1

bale/20m²), applying mulching or brush packing, or creating windbreaks using brush or bales.

The site must have an adequate and effective storm water management system in place.

Storm water measures should be inspected on a regular basis in order to ensure that the structures are functional and not causing soil erosion.

Where necessary, place culverts underneath road foundations.

Vegetation establishment, as part of the rehabilitation cleared areas and the construction site, may not be effective and this may lead to erosion of bare areas.

To prevent erosion of bare areas ensuring vegetation establishment.

Re-vegetated areas should be continuously monitored to verify whether the vegetation is growing and covering bare areas. If areas show no specific vegetation growth within three months, areas must receive additional topsoil, ripped to a depth of 100mm and re-planted. Fertilisers can also be used to promote vegetation growth.

Construction Phase: ECO to verify implementation of the mitigation measures proposed in this EMP. ECO to submit monthly compliance reports to the competent authority. Operational Phase: Regular site inspections. Internal audits against this EMP must be conducted every 6 months and records Kept onsite. Shortcomings must immediately be addressed.

During the operational phase.

Facility Manager, ECO

57

Table 7: EMP: atmosphere and noise factors.

Atmosphere and Noise

Activity: • Construction activities of the piggery • Excavation activities, loading and offloading activities and vehicles travelling to and from the site. • Increased traffic to and from the site. • Operational activities on the piggery • Waste management on site

Aspect: • Release of emissions and odours from the piggery, mortalities and wastewater management system, and subsequent nuisance. • Dust generation • Generation of noise and nuisance

Construction X

Project Phase Applicability Operation X

Decommissioning

Impact Description

Environmental Objective

Management / Mitigation/ Monitoring Measures Monitoring compliance and reporting

Time frames

Responsible Party

Degradation of ambient air quality and nuisance due to odour Generation from the piggery, ammonia emissions, its Waste water management practices and mortality management. The generation of odours depends on the design of the piggery, the wastewater collection and disposal system as well as how the piggery is managed. The impact of any odours that are generated depends upon the topography and climate of the site, (Forestry, 2018). The main sources of odours at intensive piggery operations

To minimise atmospheric emissions, odour generation and the subsequent nuisance it causes.

Ventilation points on the piggery houses must be as high as possible so that the exiting gases enter the air column as high as possible.

Covering the wastewater collection pond can reduce odorous emissions. The released gas can also be captured as part of a bio-gas plant.

Spillages must be prevented.

Effective housekeeping and best management practices must be implemented.

Houses should be cleaned and maintained on a regular basis.

Drains and treatment systems should be well maintained.

Disposal of wastewater should be done in accordance with Directorate of Water Affairs

Construction Phase: ECO to verify implementation of the mitigation measures proposed in this EMP. ECO to submit monthly compliance reports to the competent authority. Operational Phase: Regular site inspections. Internal audits against this EMP must be conducted every 6 months and records kept onsite. Shortcomings must immediately be addressed.

During the construction and operational phases.

CC,FM,ECO

58

include the following: Poorly maintained pig houses; Inadequate housekeeping; and Inadequate or poorly maintained wastewater treatment systems, storage of wastewater and land application of wastewater and solids (ARMCANZ/ANZECC, 1999). Odours are also generated from the decomposition of manure and waste food at the piggery (www.daf.qld.gov.au/environment/intensive-livestock/piggeries/managing-environmental-impacts/odour). The main constituents of piggery wastewater that need to be considered from an environmental protection perspective include potassium, dissolved solids, sodium, ammoniacal compounds, organic matter, phosphorous and nitrogen from urine and faeces. The wastewater generally has elevated levels of volatile organic solids, nutrients and possibly salts and can also contain disinfectants used to wash the houses, veterinary chemicals and metals such as copper and zinc. The organic components are readily biodegradable (ARMCANZ/ANZECC, 1999). Toxic compounds in the wastewater sludge, such as heavy metals and pathogens, can,

guidelines.

Disposal of the liquid fraction on agricultural land should be avoided in adverse weather conditions (windy days).

Wind rows for drying the solid fraction should be located as far as possible from sensitive receptors.

Disposal of wastewater on agricultural land should be avoided on weekends and public holidays, as far as possible.

The following buffer zone is required to protect the public from possible vectors and odours: Application to land: >500m away from dwellings.

o The production of biogas from the wastewater slurry and its use in generating heat and/or electricity can reduce the greenhouse gas emissions per kg pig raised at the piggery, ( (Forestry, 2018).

o Ensure adequate ventilation of houses. o Keep wastewater drains clean. o Avoid ponding and irrigation with wastewater

slurry during wet conditions. o Avoid excessive build-up of manure within

the houses and below the floor area. o Regularly flush wastewater from the houses. o Plant trees around the piggery to act as

buffers. o A bio-digester is proposed for the disposal of

mortalities on the farm. Alternatively a mortality/compost pit can also be used.

o Mortalities must be stored in enclosed areas prior to being taken to the bio-digester or mortality/compost pit.

o The bio-digester or mortality/compost pit must be adequately designed and regularly maintained.

o It must be ensured that the capacity of the

59

however, also be detrimental to the environment. The proposed management of the piggery wastewater will include a deep pit flush system as described earlier in this report. Should any pipes within the system burst, the wastewater will enter into the main channel and from there into the collection sump. The entire system is a closed system and no wastewater can be released into the environment. The introduction of a separator stage will have the following benefits:

The N utilisation (% of total N) by crops of the liquid fraction is higher compared to application of raw, unseparated pig slurry (Birkmose, 2009). More of the liquid fraction is therefore considered to enter the soil, resulting in the generation of less odours following land application.

The storage of the separated liquid fraction in should also have a lower potential to produce persistent odours as the solid fraction has been removed. Also, as the liquid fraction should contain no solids/fibres, less crust should form in

bio-digester or mortality/compost pit is not exceeded.

o The bio-digester or mortality/compost pit

must be well managed and monitored. o The bio-digester or mortality/compost pit

must be located away from sensitive environmental receptors, including wetlands, rivers, streams and drainage lines.

o The design of the mortality/compost pit must ensure that water does not enter upstream of the pit. This can be achieved by locating the pit at or near the crest of a hill.

o The addition of Carbon to the mortality/compost pit is necessary to ensure that the required Carbon-Nitrogen ratio is present, allowing for optimal composting. Sawdust is the preferable source of Carbon. Straw can also be used.

o The composting process will be more efficient if the correct ingredients are placed in composting “bins” in the correct proportions, allowed to compost for a period of time (a minimum of three months from when the last mortality is placed in the bin) and then moved to a second bin for a secondary composting phase of at least three months. The composting bins can be constructed using large round or square bales of hay. The bales are placed end-to-end to create three-sided enclosures (bins). Two adjacent bins are required as a minimum. The bins must be constructed on top of a layer of at least 300mm of sawdust.

o Each mortality must be placed in the pit and covered with at least 300mm of sawdust or straw.

o Mortalities must be inspected daily and re-covered where necessary.

60

the ponds. o Any runoff from the pits should be contained and taken to the wastewater management system.

o Inform neighbours in advance of any maintenance activities that may lead to odour nuisance.

o The bio-digester or mortality/compost populations and odours.

o A complaints register should be kept onsite. The register must record the following:

o Date when complaint was received, name of person who reported the complaint, details of the complaint and when and how the concern was addressed.

Degradation of ambient air quality due to dust and exhaust emissions generation.

To minimise the impact of construction activities, excavation activities, loading and offloading activities and increased traffic to and from the site on the ambient air quality.

A dust automobile should be onsite to water down dusty roads.

Speed bumps and traffic signs should be erected to reduce speeding onsite.

A complaints register should be kept onsite. The register must record the following:

Date when complaint was received, name of person who reported the complaint,

Details of the complaint and when and how the concern was addressed.

Open areas should be re-vegetated. If the soil is compacted, it should be ripped, and fertilised.

Regular maintenance of vehicles and equipment should be undertaken.

Optimal engine combustion will allow for ‘cleaner’ exhaust emissions.

Construction Phase: ECO to verify implementation of the mitigation measures proposed in this EMP. ECO to submit monthly compliance reports to the competent authority. Operational Phase: Regular site inspections. Internal audits against this EMP must be conducted every 6 months and records kept onsite. Shortcomings must immediately be addressed.

During the construction and operational phases.

CC, FM, ECO

Noise According to Jorgensen & Johnson (1981), the noise levels created by general construction activities on a building site can reach levels of approximately 70 dB, caused by for instance heavy

To minimise noise generation on the site.

Activities that will generate the most noise should be scheduled during times of the day that will result in least disturbance to neighbours.

Site workers and contractors will adhere to the requirements of the Occupational

Construction Phase: ECO to verify implementation of the mitigation measures proposed in this EMP. ECO to submit monthly compliance reports to the

During the construction and operational phases.

CC, FM,ECO

61

machinery. It can therefore be assumed that the proposed development will have a negative impact on the environmental noise of the area once construction starts. Sound is inversely proportional to the distance from the source and can get absorbed by buildings and vegetation barriers. Noise intensities (dB) will be at their highest on site and will decrease as one moves away from their sources. The noise decline curve gives an indication of how noise generated at the site will decrease with distance. It gives an indication of the distance that the sound would have travelled upon reaching a level of 60 dB, prescribed by the SABS as being the acceptable limit for environmental noise. According to noise decline curve, at a distance of 27 metres from the construction site, the generated noise would have decreased to a level of 60 dB and at a distance of 45 metres it would have decreased to approximately 55dB. It can therefore be said that noise travelling further than 45 metres will have a low impact on neighbouring farms and residential areas. The distance to sensitive noise receptors (residences) is more than 45 metres in all cases.

Health and Safety standards stipulated in the Labour Act regarding hearing protection and noise control measures.

Regular maintenance of vehicles, equipment and fans should be done.

Conveyors/augers should not be run when empty.

Working hours should be restricted to daylight hours.

No sound amplification equipment such as sirens, loud halers or hooters are to be used on site except in emergencies.

No amplified music is permitted on site.

If work is to be undertaken outside normal work hours, permission must be obtained from the ECO and the facility manager.

No noisy work is to be conducted over the weekends or on public holidays.

Unnecessary disturbance of the pigs should be avoided. This will ensure that the pigs are not excessively noisy.

Vehicles travelling to and from the site during night time hours must be kept to a minimum.

A complaints register should be kept onsite. The register must record the following:

Date when complaint was received, name of person who reported the complaint, details of the complaint and when and how the concern was addressed.

competent authority. Operational Phase: Regular site inspections. Internal audits against this EMP must be conducted every 6 months and records kept onsite. Shortcomings must immediately be addressed.

62

During the operational phase, noise will be generated by the Ventilation equipment, transport vehicles and the pigs themselves. Noise levels at the piggery should not exceed 55dB during daytime hours and 45dB during night time hours. Increased noise levels during the operational phase can be caused by the animals, when they are unsettled, disturbed or excited. For example, pigs that are fed at designated times during the day become excited when the feed cart approaches. At the proposed piggery, the pigs will have permanent access to feed and will therefore not routinely become excited during the day. The piggery houses will be solidly constructed and will largely contain noise generated by the pigs.

63

Table 8: EMP: soil, surface water, storm water and groundwater factors.

Soil, surface water, storm water and groundwater

Activity:

The handling, storage, mixing and disposal of cement and concrete.

The cleaning of equipment and construction areas.

Handling, storage and disposal of general, domestic and hazardous waste.

Installation and use of ablution facilities.

Storage and handling of hazardous chemical substances including fuel, greases and oils.

Vehicle and equipment maintenance and fueling.

Construction and operation of the piggery, its wastewater management system and mortality management system.

Storm water runoff on site.

Management of the solid wastewater fraction.

Aspect:

Concrete and cement spillage.

Generation and runoff of contaminated wash water.

Poor waste management.

Unsanitary conditions on site.

Poor management and spills of hazardous chemical substances including fuel, greases and oils.

Leaking and/or spilling of fuels, greases and oils.

Inadequate construction and management of the piggery, its wastewater management system and mortality management system.

Contamination of clean runoff water.

Poor containment and management of the solid wastewater fraction.

Construction X

Project Phase Applicability Operation X

Decommissioning

Impact Description

Environmental Objective

Management / Mitigation/ Monitoring Measures Monitoring compliance and reporting

Time frames

Responsible Party

Soil and surface water pollution as a result of spillage, improper handling, storage, mixing or disposal of cement and concrete.

To prevent pollution of soil and surface water.

Cement may only be mixed on an impermeable surface (not bare soil).

Dry cement must be removed from the soil surface to prevent an impermeable layer forming on top of the soil. The cement must be disposed of with building rubble.

Construction Phase: ECO to verify implementation of the mitigation measures

During the construction phase.

CC, FM, ECO

64

Ready-mix trucks are not permitted to clean chutes onsite. Cleaning into foundations

or a dedicated cleaning pit is permitted.

Bricklayers and plasterers are to minimise any cement spill or runoff in their work area.

They also have to ensure that the work area is cleaned of all cement spillage at the

end of each workday.

Both used and unused cement bangs are to be stored in weatherproof containers so

as not to be affected by rain or runoff.

Soil contaminated by cement or concrete, including residue produced by the washing

of cavities, are to be removed immediately after the spillage has occurred and disposed of appropriately.

Measures must be taken to prevent dirty water (wash water) from contaminating a watercourse. Water has to be contained by excavations or berms.

Should a concrete batching plant be required, the following measures should be implemented:

Concrete may only be mixed in designated and demarcated areas.

The batching plant must be erected on a compacted earth platform.

The batching plant must be sited within a bund wall.

Storm water must be diverted around the batching plant.

Any concrete spillages must be removed by the contractor and disposed of at a

licensed disposal site.

After use, all waste remaining at the batching plant must be removed and

disposed of at a licensed disposal site.

proposed in this EMP. ECO to submit monthly compliance reports to the competent authority. Operational Phase: Regular site inspections. Internal audits against this EMP must be conducted every 6 months and records kept onsite. Shortcomings must immediately be addressed.

Soil and surface water pollution through contaminated wash water.

To prevent soil and surface water pollution.

No vehicles are permitted to be washed on site.

A dedicated, temporary cleaning area (such as a plastic lined pit, plastic or metal drums located close

Construction Phase: ECO to verify implementation of

During the construction and

Construction contractor

65

to a water point) is to be identified to facilitate washing of cement and painting equipment.

No wastewater/wash water may be disposed of on site, onto the soil or into any water body.

Runoff form the washing activities is to be contained against the building by excavations of berms around the foundations.

the mitigation measures proposed in this EMP. ECO to submit monthly compliance reports to the competent authority. Operational Phase: Regular site inspections. Internal audits against this EMP must be conducted every 6 months and records kept onsite. Shortcomings must immediately be addressed.

operational phases.

Facility Manager ECO

Soil, surface water and groundwater pollution due to poor waste management including biological waste generated on-site).

To prevent soil, surface water and groundwater pollution.

Building waste must be disposed of at a landfill site.

Sufficient waste bins, skips or bulk containers should be installed. Containers must be available on site at all times.

All containers (bins, skips and bulk containers) must be kept clean and hygienic.

Containers (bins, skips and bulk containers) utilised for the disposal of general and hazardous waste must be demarcated accordingly.

Waste material may only be temporarily stored in areas demarcated for such storage.

General waste must be stored in a manner that prevents the harbouring of pests.

Construction Phase: ECO to verify implementation of the mitigation measures proposed in this EMP. ECO to submit monthly compliance reports to the competent authority.

During the construction and operational phases.

CC, FM,ECO

66

General waste should always be stored or disposed of separately from hazardous

waste.

Skips or bulk containers should be removed to a licensed landfill site on a weekly basis or more often if required. No build-up of waste is permitted onsite.

A waste management plan should be implemented. The waste management plan should consider the type of waste, description, source, storage, disposal method, disposal facility and responsible person.

No incineration of any kind of waste will be permitted onsite.

The facility should be fenced off in order to ensure high health herd status.

Strict biosecurity measure should be employed. Such measures include:

o Limit nonessential access and traffic to the farm. o Clean and disinfect livestock and feed haulers. o Keep a record of all visitors and deliveries. o Have one combined entrance and exit. o Provide disinfectant and appropriate footwear. o Implement policies with regards to visiting livestock

facilities. o Take precaution when buying livestock, feed and

equipment. o Prevent contact between healthy and sick animals. o Implement pest control measures. o Prevent contact between livestock and waste

generated on the site.

The piggery should consist of platforms in which specific categories of pigs are housed.

Animal housing should have slatted floors that capture waste in a sealed slurry store facility of 50 – 60cm deep with a storage capacity of at least 28 days.

All slurry receiving and conducting canals should be concrete canals with flow regulators.

The concrete slurry collection pit to which slurry is

Operational Phase: Regular site inspections. Internal audits against this EMP must be conducted every 6 months and records kept onsite. Shortcomings must immediately be addressed.

67

fed should have an additional 10 days collection capacity.

The liquid fraction that will be applied to agricultural land should be handled in accordance with DWA recommended guidelines.

Soil, surface water and groundwater pollution due to unsanitary conditions onsite.

To prevent soil, surface water and groundwater pollution.

Sufficient ablution facilities shall be provided – minimum of 1 toilet per 30 workers.

Ablution facilities must be on impermeable surfaces and at least 50m from wetlands, drainage lines or places where storm water may accumulate.

The location of the ablution facilities is to be approved by the ECO prior to site establishment, but shall be located within 100m of any work point.

Ablating anywhere other than in the toilets shall not be allowed.

Ablution facilities are to be secured.

The contractor shall ensure that no chemicals and/or waste form the ablution facilities are spilled on the ground at any time.

Ablution facilities are to be serviced weekly or more frequently if required.

Contents are to be removed from site on a regular basis.

Ablution facilities should be inspected and maintained to prevent and minimise blockage and leakages.

Toilets should have properly closing doors and be supplied with toilet paper.

Awareness of the importance of proper hygiene should be created among employees.

The septic tank should be cleaned and de-sludged at least once a year.

Construction Phase: ECO to verify implementation of the mitigation measures proposed in this EMP. ECO to submit monthly compliance reports to the competent authority. Operational Phase: Regular site inspections. Internal audits against this EMP must be conducted every 6 months and records kept onsite. Shortcomings must immediately be addressed.

During the construction and operational phases.

CC, FM, ECO

Soil, surface water and groundwater pollution due to poor management and accidental spills of hazardous chemical substances including fuel, greases and oils used onsite.

To present soil, surface water and groundwater pollution by hazardous

Identify all hazardous chemical substances used onsite including fuel, greases and oils.

Obtain the material safety data sheet of each of the hazardous chemical substances.

Ensure that the material safety data sheets have

Construction Phase: ECO to verify implementation of the mitigation measures

During the construction and operational phases.

CC, FM, ECO

68

chemical substances.

sufficient information to enable the user to take the necessary measures to protect his/her health and safety and that of the environment.

Material Safety Data Sheets for all hazardous chemical substances must be readily available on site.

Keep a stock inventory register of all chemicals in the store.

Powders must be stored above liquids.

Proper storage of chemicals in a lockable, well ventilated building.

Use chemicals with low toxicity and low water contamination potential, as far as possible.

Ensure adequate access control for the storage area.

Storage areas for hazardous chemicals are to comply with standard fire regulations.

Safety signage including “No Smoking”, “No Naked Lights” and “Danger”, and product identification signs, are to be clearly displayed in areas housing chemicals.

Appropriate equipment to deal with emergency spill incidents is to be readily available on site. This includes fire extinguishers, spill kits for hydrocarbon spills, drip trays for equipment and/or machinery leaks, drums or containers for contaminated water.

Chemicals are to be properly labelled and handled in a safety conscious manner.

All personnel handling hazardous chemicals and hazardous materials are to be issued with the appropriate Personal Protective Equipment (PPE).

Ensure that diesel/fuel tanks are in a bunded area with capacity of holding 110% of the total storage volume.

The removal of only the daily-required amount of chemicals to be used from the shed.

If refuelling on site or from drums, the ground must be protected and dispensing equipment is to be used i.e. hand pumps and funnels. Drums may

proposed in this EMP. ECO to submit monthly compliance reports to the competent authority. Operational Phase: Regular site inspections. Internal audits against this EMP must be conducted every 6 months and records kept onsite. Shortcomings must immediately be addressed.

69

not be tipped to dispense fuel.

Use of drip trays during filling of machinery or equipment. Drip trays should be emptied into secondary containers on a regular basis.

Ensure that any spilled chemical cannot exit the designated storage area by constructing a berm or bump at the exit, or store chemicals in a spill tray.

Immediately clean all spillage of fuels, lubricants and other petroleum based products.

The contaminated material must be disposed of in accordance with the management procedure.

No hazardous chemical must be discarded in the sewage or storm water system.

Train staff on the use of chemicals in accordance with the risks as described in the material data sheets.

Soil contaminated with hazardous chemical substances shall be treated as hazardous waste and removed from site.

Soil, surface water and groundwater pollution due to the incorrect management of the solid fraction of wastewater on site. Nuisance due to management of the solid fraction.

To prevent soil, surface and groundwater pollution and Nuisance as a result of poor management of the solid wastewater fraction.

The solid fraction of the piggery wastewater may only be temporarily stored in designated areas, on impermeable surfaces.

The temporary storage must occur in such a manner as to prevent the harbouring of pests. The composting process must occur on a bunded area of land that is impermeable.

No wastewater from the composting area may be discharged or allowed to run into the environment or into any drainage lines or other water systems.

A collection pit/sump must be installed to contain any runoff from the composting area.

The captured water can be re-used to moisten the compost piles.

Manage every active compost pile such that the initial carbon to nitrogen ratio is at least 25:1. The ideal C:N ratio is between 25:1 and 30:1.

Any solid or liquid waste generated at the facility, including contaminated products and process

Construction Phase: ECO to verify implementation of the mitigation measures proposed in this EMP. ECO to submit monthly compliance reports to the competent authority. Operational Phase: Regular site inspections. Internal audits

During the operational phase.

SM

70

residuals that cannot be processed at the facility must be stored in such a manner as to prevent water pollution and amenity impacts.

The quantities of incoming and processed organics must not exceed the design requirements of the storage and processing areas.

All organic compost intended for use as fertilisers must be registered with MAWF and meet all the necessary requirements as per the Regulations Regarding Fertilisers and Farm remedies, including

any other amended version(s) thereof.

No incineration of any kind of waste will be permitted onsite.

Implement a surface- and groundwater monitoring programme.

against this EMP must be conducted every 6 months and records kept onsite. Shortcomings must immediately be addressed.

71

Table 9: EMP: biosecurity factors.

Biosecurity

Activity Operation of the piggery

Aspect The attraction of flies, mice and rats to the piggery. The use of vaccines at the piggery.

Construction X

Project Phase Applicability Operation X

Decommissioning

Impact Description

Environmental Objective

Management / Mitigation/ Monitoring Measures

Monitoring compliance and reporting

Time frames Responsible Party

Flies, mice and rats can carry infectious vectors that are detrimental to the health of pigs. Flies are attracted to moist and decaying organic matter. A risk exists of fly populations increasing in the vicinity of the piggery.

To prevent the attraction of lies to the piggery and the harbouring of pests such as mice and rats.

Mortalities must be removed from the houses on a daily basis.

The feed storage and distribution systems must be designed and maintained in a manner that deters the presence and breeding of vermin.

Attention to effective sanitation at the piggery will minimise the area where flies can rest and breed.

Regular flushing of the wastewater from the houses will minimise fly breeding.

Regularly clean the feeding areas and collect wasted feed. This will prevent the attraction of flies to the piggery.

Construction Phase: ECO to verify implementation of the mitigation measures proposed in this EMP. ECO to submit monthly compliance reports to the competent authority. Operational Phase: Regular site inspections. Internal audits against this EMP must be conducted every

During the operational phase.

FM

72

6 months and records kept onsite. Shortcomings must immediately be addressed.

Potential injury to employees working with biological waste. Biological or bio-hazard waste includes syringes for vaccines.

To ensure the correct handling and management of biological waste.

The collection and disposal of biological waste must be conducted in a responsible manner, in conjunction with a consulting veterinarian. Recognised safe storage equipment/containers must be used for the collection of this waste. Awareness must be created amongst employees on the safe placing of this material into the designated containers.

Construction Phase: ECO to verify implementation of the mitigation measures proposed in this EMP. ECO to submit monthly compliance reports to the competent authority. Operational Phase: Regular site inspections. Internal audits against this EMP must be conducted every 6 months and records kept onsite. Shortcomings must immediately be addressed.

During the operational phase.

FM

Unauthorised access to the site, via foot or vehicles, as well as the entry of other animals into the biosecurity zone of the piggery can

To ensure that there is no unauthorised access to the

A security fence must be erected around the piggery.

Access to the piggery must be

Construction Phase: ECO to verify implementation of

During the operational phase.

FM

73

compromise its biosecurity buffer.

site. controlled via one access point.

Access to the property itself must also be controlled.

Entrance gates must be manned during operational hours and locked outside of operational hours.

Access to the premises should only be by prior arrangement.

The condition of the fence around the piggery must be inspected every six months.

the mitigation measures proposed in this EMP. ECO to submit monthly compliance reports to the competent authority. Operational Phase: Regular site inspections. Internal audits against this EMP must be conducted every 6 months and records kept onsite. Shortcomings must immediately be addressed.

Death of pigs at the piggery, including mass mortalities and the potential spread of the disease to other farms.

To ensure that any outbreak of disease is contained and does not spread to neighbouring farms or further afield.

Should there be an outbreak of disease at the piggery, the cause or source of the

disease should be identified as soon as possible, in consultation with a veterinarian.

Neighbouring landowners should be informed of the outbreak.

The diseased animals should be separated/isolated and treated (when possible).

Sealable containers must be used for mortalities.

Construction Phase: ECO to verify implementation of the mitigation measures proposed in this EMP. ECO to submit monthly compliance reports to the competent authority. Operational

During the operational phase.

FM

74

Inform the relevant state department of the outbreak.

Bait stations should be used for rodent control and can also be used for fly control.

Bait stations must be placed where they cannot be reached by the pigs. They must

be placed where rodents and flies are active and should have sufficient levels of bait.

Emergency plans/procedures must be developed to deal with outbreaks of diseases.

Mass mortalities must be managed in a responsible manner, in consultation with a

Veterinarian.

Phase: Regular site inspections. Internal audits against this EMP must be conducted every 6 months and records kept onsite. Shortcomings must immediately be addressed.

75

Table 10: EMP: resource usage factors.

Resource Usage

Activity Usage of resources, such as electricity and water (groundwater).

Aspect Inefficient and redundant use of valuable resources (electricity and groundwater).

Construction X

Project Phase Applicability Operation X

Decommissioning

Impact Description

Environmental Objective

Management / Mitigation/ Monitoring Measures

Monitoring compliance and reporting

Time frames Responsible Party

Wastage or depletion of valuable resources (electricity and groundwater) due to inefficient or redundant usage.

To prevent the wastage or depletion of valuable resources (electricity and groundwater).

Ensure that all employees have been informed of the importance of natural resources (proper environmental training and awareness).

Regular site inspection by supervisors should be conducted.

Inspect operations regularly to determine areas of improvement with regards to resource consumption.

Regular maintenance and inspection of equipment such as hose pipes to prevent leaks.

Monitor resource consumption especially water.

Identify areas where resource consumption can be minimised.

Set targets to minimise resource consumption.

Identify and implement technologies and practices that may reduce resource consumption.

Construction Phase: ECO to verify implementation of the mitigation measures proposed in this EMP. ECO to submit monthly compliance reports to the competent authority. Operational Phase: Regular site inspections. Internal audits against this EMP must be conducted every 6 months and records kept

During the construction and operational phases.

CC, FM, ECO

76

Regular inspection and maintenance of all boreholes, tanks, reservoirs, toilets, water pipes, valves and taps should be conducted.

Leaking tanks, reservoirs, taps, toilets and pipes must be repaired immediately.

Running water taps and pipes may not be left unattended.

All pipe, hose and tap connections are to be fitted with correct and appropriate plumbing fittings.

The quantity of groundwater abstracted on a daily basis must be metered or gauged. Records must be kept of all abstractions.

The recommended groundwater abstraction rates should be adhered to, to ensure sustainable use of the resource.

It is advised that water level monitoring is conducted on the boreholes used for the piggery as well as any surrounding boreholes.

All measuring devices must be properly maintained, must be in good working order and must be easily accessible. This shall include a programme of checking, calibration and/or renewal of measuring devices.

Electricity

Houses should face north for optimal temperature control within the houses.

Save electricity by turning off lights

onsite. Shortcomings must immediately be addressed.

77

and computers when not in use.

Energy saving light bulbs should be used.

The flow of wastewater through the wastewater management system should be by gravity flow, rather than pumps, as far as possible.

78

Table 11: EMP: infrastructure factors.

Infrastructure

Activity Increased traffic frequency on road infrastructure during construction activities. Increased traffic on road infrastructure during operation of the piggery (loading and offloading of pigs and feed).

Aspect Wear of access roads and insufficient vehicle inspections. Visibility of the piggery to adjacent land owners.

Construction X

Project Phase Applicability Operation X

Decommissioning

Impact Description

Environmental Objective

Management / Mitigation/ Monitoring Measures

Monitoring compliance and reporting

Time frames Responsible Party

Wear of access roads, accidents on access roads, unpermitted transport of pigs and loss of pigs being transported on access roads.

To minimise the impact of the increase in traffic on access roads to the site.

Ensure that all construction vehicles using access roads are roadworthy.

All loads are to be securely fastened when being transported.

All vehicles are to adhere to the tonnage limitation and acquire a permit as required.

All speed limits and other traffic regulations on the roadways must be adhered to.

Safety signage should be erected along the construction site.

Construction Phase: ECO to verify implementation of the mitigation measures proposed in this EMP. ECO to submit monthly compliance reports to the competent authority. Operational Phase: Regular site inspections. Internal audits against this EMP must be conducted every

During the Construction and operational phase.

CC, FM, ECO

79

6 months and records kept onsite. Shortcomings must immediately be addressed.

Visual impact upon receptors surrounding the piggery, including adjacent land owners. The residential dwellings of all adjacent properties are further than 2km from the four alternative sites.

To minimise the visual impact of the piggery on receptors in the vicinity of the site.

Trees should be planted around the periphery of the piggery, outside of the piggery fence, to reduce the visibility of the piggery to receptors in the vicinity of the piggery.

Directional lighting can be used at the piggery, but must be directed inwards (towards the piggery) and not outwards towards the neighbouring properties.

No high floodlights may be erected at the piggery.

Construction Phase: ECO to verify implementation of the mitigation measures proposed in this EMP. ECO to submit monthly compliance reports to the competent authority. Operational Phase: Regular site inspections. Internal audits against this EMP must be conducted every 6 months and records kept onsite. Shortcomings must immediately be addressed.

During the construction and operational phase.

CC, FM, ECO

CC – Construction Contractor; FM – Facility Manager; ECO – Environmental Control Officer

80

CLOSURE PHASE

Decommissioning of the piggery is not anticipated for the foreseeable future. Should

the piggery be decommissioned, a detailed closure and rehabilitation plan will be

submitted to the Ministry prior to decommissioning.

81

7. CONCLUSION

The construction of a 1000 sow piggery facility at Stampried Farm in the Hardap

Region has negative environmental impacts. The EIA study findings showed

negative environmental impacts to the environment to varying degrees depending on

the nature of the activity and impacts arising thereof. The key impact identified relate

to the following categories:

Resource use and specifically water given that the area relies on lots on

groundwater while the project utilizes a lot of water for both drinking and

waste management.

Solid and liquid waste, the planned facility generates large quantities of

nutrient rich (N, P, K) solid and liquid waste which if not management properly

can pollute the environment (soil, groundwater and air) with serious resultant

environmental impacts.

Management and corrective measures were formulated and implementation

timelines proposed depending on the gravity of threat to human life and the

environment. The identified impacts, mitigation and monitoring activities, indicators,

responsible parties and monitoring frequency are indicated in the EMP. The EMP

should form the obligatory conditions upon which the EIA clearance certificates will

be issued and non-compliance attracts prosecution. The EMP should be

implemented throughout the project lifecycle and an Environmental Management

System formulated and implemented based on the EIA study findings. Environmental

monitoring and performance evaluations should be conducted and targets for

environmental improvement set and monitored throughout the project lifespan. It is

also our determination that the findings should be incorporated earlier and sound

SHE policies and supportive programmes implemented.

82

Works Cited Forestry, D. o. (2018). Livestock Piggeries: Management of Environemntal Impacts: odour.

Queensland: (www.daf.qld.gov.au/environment/intensive livestock/piggeries/managing-

environmental-impacts/odour).

Jeroen van der Bergh, V. a. (April, 1999). Spatial sustainability, trade and indicators: An evaluation of

the ecological footprint. Research gate volume 29, 61-72.

Mathis Wackernagel, L. O. (1997). Ecological footprints of nations. Mexico: Universidad Anahuac de

Xalapa Apdo.

83

Annex 1: Risk assessment model results

84

Annex 2: Background information and invitation to participate

document

BACKGROUND AND INVITATION TO PARTICIPATE DOCUMENT (BID)

FOR

A PIGGERY PROJECT AT STAMPRIED FARM, STAMPRIET, HARDAP REGION.

PROPONENT: STAMPRIED FARM

DECEMBER 2018

PREPARED BY

Number 34 Old Power Station Building, Windhoek, Namibia. Cell Number: +264 812 683 578

E.Mail Add: [email protected]

85

PROJECT DETAILS

TITLE BACKGROUND AND INVITATION TO PARTICIPATE

DOCUMENT

AUTHORS OUTRUN CONSULTANTS CC

CLIENT STAMPRIED FARM

REPORT STATUS FINAL BID REPORT

DATE DECEMBER 2018

AUTHORISED SIGNATURE: __________________________________________

JOSIAH T. MUKUTIRI LEAD CONSULTANT / ENVIRONMENTAL IMPACT

ASSESSMENT

PRACTITIONER

86

1. PURPOSE OF THE DOCUMENT AND CONTENTS

The purpose of this Background Information Document (BID) is to provide

stakeholders with the opportunity to register as Interested and Affected Parties

(I&APs) in the scoping exercise for the Environmental Impact Assessment (EIA)

Study for a piggery project at Stampried Farm. We will share with you the process

being followed and also obtain your initial comments on the project. The document

also gives you information on the benefits of the proposed project, potential impacts

of the project and proposed environmental studies needed. Further to that we

advise you on how you can become involved in the project, raise concerns which

you may have or receive information which may be of interest to you. This is the core

of public participation during the EIA process. Information sharing is the cornerstone

of successful Public Participation and your input will help ensure that all potential

issues are taken into consideration before critical decisions are made.

2. PROJECT DESCRIPTION

The applicant, Stampried Farm (Pty) Ltd plans to embark on a piggery project at

Stampriet, Hardap Region. The piggery facilities will be set up to accommodate one

thousand sows at any one time. This is an intensive large scale activity making it a

prescribed activity under the Environmental Management Act (2007) and requires

environmental clearance before implementation. It is against this background that

an independent environmental consultant, Outrun Consultants cc was contracted by

the Proponent to carry out the EIA study and apply for an environmental clearance

certificate.

2.1. Terms of Reference The proponent, (Stampried Farm Pty Ltd) hired Outrun Consultants CC to carry out

an Environmental Impact Assessment Study for the piggery project in Hardap

Region. The EIA process will consist of two phases, the scoping phase and the

detailed EIA phase.

2.1.1. Activities planned for the scoping phase The scoping process undertaken includes the following activities:

87

Policy and legislation relevant to construction and operation of a pig production

facility.

Description of the proposed project

Description of the affected environment

The public participation process

A detailed description of the potential impacts associated with the proposed

project

Evaluation of the significance of the potential impacts

Submission of the final scoping report to MET: DEA for consideration and

decision making.

2.1.2. Project Location

Figure 4: Stampried Farm locality Map. Source: Own map.

3. PROPOSED STUDIES

a. Biodiversity Study A biodiversity study is necessary given that vegetation will be destroyed

during land clearing to make way for the construction of the pigster and

other associated infrastructure.

88

b. Waste management A huge amount of organic solid and liquid waste will be generated daily

and this warrants a study on the handling and management of waste.

c. Assessment Of Alternatives

i. No-Go Option The “no-go” option means maintaining the status quo. This option will be

explored to assess the implications of not implementing the project.

ii. Sites Sites within the project that pose minimal impact on the environment will

be chosen for putting up the infrastructure. Similarly access routes will be

assessed and those with minimal environmental impacts chosen.

iii. Technological Alternatives There are different technologies available that are used in waste

management and environmental monitoring. The various options will be

explored and appropriate recommendations made for the sustainability of

the project.

89

4. THE ENVIRONMENTAL IMPACT ASSESSMENT PROCESS

An EIA is the process of identifying, predicting, evaluating and mitigating

the biophysical, social, health and other relevant effects of development

projects prior to major decisions being taken and commitments made.

The objectives of the EIA will be to:

Provide you with adequate information to understand the potential

environmental and socio-economic impacts of the proposed project

and opportunities to comment on the project and the process.

Provide information that will assist the consultants to incorporate

effective mitigation measures into the design and implementation of

the project.

Provide the regulatory authorities with sufficient information to

serve as a basis for sound decision making.

a. Project elements to be covered by the EIA.

The EIA will cover the following elements:

Planning and design;

Construction;

Operation and maintenance;

90

PHASE 1: SCOPING

Determine scoping of EIA

Policy, regulatory review

Desk review of previous studies

Reconnaissance site visit

Scoping workshop

Draft scoping report with terms of reference & work plan for phase 2

PHASE 2: Environmental Impact

Aseessment

Biophysical, Socio-economic and Specialist Studies

Impact Assessment

Mitigation Plan

Draft EIA Report

Decision making

Implementation

On-going consultations

Including Public Meetings

Public Consultation & Disclosure

Includes community consultation

& Public Meeting

Draft Public Consultation &

Disclosure Plan (PCDP)

Development not approved Environmental

Impact Assessment

Development not approved

Development approved

Figure 5: The EIA process that will be followed. Figure 6: The EIA process to be followed.

91

b. Scope Of The Work

The EIA will focus on the issues related to biodiversity-land clearing,

waste management (solid and liquid), operation and management of the

piggery. The EIA will be done in 2 phases (See Figure.2).

PHASE 1 – SCOPING

It is a formal requirement during the EIA process to carry out a scoping

study and this is in-line with the Namibian Environmental Management

Act (2007). The purpose of this study is to direct the assessment on the

key issues for assessment and at the same time eliminate those that do

not require detailed intensive studies.

Scoping Activities

Consultations with key stakeholders, government

departments etc.

Advertising and carrying out public meetings.

Distribution of project information to the public.

Producing draft scoping report.

Gathering public comments on draft scoping report.

Submission of final scoping report to Ministry of Environment

& Tourism (MET).

92

PHASE 2

Issues that are raised during the scoping study will be used to develop

terms of reference for specialist studies. Experts within the Consultancy

Team will be assigned to carry out the specialist studies. The results from

the specialist studies will be incorporated into the Draft EIA report.

c. Draft EIA Report The draft EIA report will reflect all the identified issues, mitigation

measures and the proposed environmental management plan. The draft

EIA document will be made available to the public for comments on issues

of interest and can also raise any concerns they may feel require further

attention.

d. Legal Framework

The Namibian Government gazetted the Environmental Management Act

in 2007 and is supported by a set of guidelines and regulations. The EIA

process will follow the EIA Policy and the Environmental Management Act

& its regulations. The EIA will also take cognizance of applicable

international standards and guidelines, conventions and treaties.

5. PUBLIC CONSULTATION AND DISCLOSURE PLAN

According to the Environmental Management Act (2007), public

participation forms an integral part of the EIA process. Adequate public

consultation is important to identify issues relevant to the project,

evaluating their significance and deciding measures to mitigate these

impacts. A public consultation plan has been developed in line with the

Environmental Management Act (2007) and seeks to achieve the following

objectives:

To ensure all stakeholders are included in the consultation and

disclosure process;

93

To ensure initial information disclosure about the project is

appropriate and understandable to the non-technical stakeholders

and the local population;

To ensure that adequate and timely information is provided to the

public;

To ensure that all stakeholders are given sufficient opportunity to

express their issues, concerns and opinions;

To ensure that stakeholders’ opinions and concerns influence

project decisions;

To ensure regular feedback is given to the public;

To ensure that effective communication will continue during the

construction and operational phases of the project;

Stampried Farm (Pty) Ltd and the Outrun Team are committed to active

and ongoing communication and consultation with all members of the

public with regards to the Piggery Project.

a. How you can be involved?

Attend public meetings that will be advertised in the press.

Contact the EIA consultants for further information.

Review the draft reports when you are invited to do so within the

timeframes provided.

Please ensure that you are registered on the project database by

providing your contact details to the EIA consultants. Registration will

ensure that you receive on-going communication about the EIA process,

meeting invitations, project updates and invitations to review the draft

reports.

94

STAMPRIED FARM PIGGERY PROJECT

REGISTRATION AND COMMENTS FORM

Please register me as an Interested and Affected Party (I&AP) to

receive ongoing communication about the EIA process and the

proposed project.

Table 12: IAP REGISTRATION AND COMMENTS FORM

Full name Contact Number Comment (s)

95

96

Annex 3: List of registered Interested and Affected Parties and

Neighbours’ questionnaires.

97

98

99

100

101

102

103

104

105

106

107

108

109

Annex 4: Advertisements and posters

110

Annex 5: EIA Practitioner’s details CONSULTANT’S PARTICULARS

CURRICULUM VITAE Mukutiri, Josiah Tonderai

Name of Firm

: Outrun Consultants CC (Formerly

Outrun Investments CC)

Full Name (s) : Josiah Tonderai Mukutiri

Position : Director

Date of Birth : 28 March 1976

Years with Firm/Entity : 12Years

Nationality : Zimbabwean

Permanent residence : Zimbabwe

Position in Company : Director

Detailed Tasks

assigned

: Compilation of Project Proposals,

BIDs, Carrying out Environmental

Impact Studies and compiling

Environmental Management Plans,

Managing Client Relationship, and

Carrying out feasibility studies, Project

Appraisal, Project Management and

Monitoring & Evaluation. Training and

facilitation, Project Management and

Coordination, Resource Mobilization

and Information Dissemination.

111

Education:

Years Institution Degree/Diploma

1 Year

3 Years

2 Years

City & Guilds of London Institute

University of Zimbabwe

Aldersgate College

Certificate in Quality

Assurance & Materials

Processing Solids

BSC Honours in Applied

Environmental Science

Master in Business

Administration

Employment Record:

2006 to date Outrun Investments CC, Windhoek, Namibia.

Position: Director – Conducting Impact studies and feasibility studies, data

collection, data analysis report writing, training, impact identification and analysis,

developing management plans, business plans, feasibility studies, Agronomy,

Developing training materials, facilitation, training needs assessment and

managing client relationship, Project Management and Coordination, Information

Dissemination.

2003 – 2006 University of Zimbabwe, Harare, Zimbabwe

Position: Research and Teaching Assistant focusing environmental monitoring & management, impact studies and waste management & pollution control.

1997 – 1999 Broken Hill Proprietary (BHP) (Pty) Ltd, Selous, Zimbabwe

Position: Senior Process Controller responsible for production, quality control, safety, health and environmental management.

1995 - 1997 Zimbabwe Alloy Refinery Division (Pty) Ltd, Gweru, Zimbabwe

Position: Process Plant Controller responsible for production, quality control, safety, health and environmental management.

PREVIOUS ACCOMPLISHMENTS IN THE TARGET ENVIRONMENT

PROJECT TITLE: Training of 150 Rural Water Extension Officers for the MAWF – WASH

capacity building programme. Client: Ministry of Agriculture, Water & Forestry

Contact Person: CAVIN MWINGA Cell No.: +264 811 486 360

PROJECT TITLE: Feasibility Study and Environmental Impact Assessment for the

Establishment of Omaenene Business Park. Client: OFFSHORE DEVELOPMENT COMPANY

(ODC). ODC is the infrastructure development arm for the Ministry of Trade and Industry

112

with a focus on Export Processing Zones (EPZ). CONTACT PERSON: PHILLIP NAMUNDJEBO

AND / OR REUBEN AMAAMBO

OTHER PROJECTS:

PROJECT TITLE: Feasibility Study and Business Plan, Environmental Impact Assessment and

Environmental Management Plan for the Establishment of a Dimension stone / Granite

Mine at Otjohorongo in Erongo Region - Namibia, (Four Mining Claims within an EPL).

Client: Ekungungu Trading CC

Contact Person: Lukas Sasamba Cell No.: +264 811 275 423

PROJECT TITLE: Environmental Impact Assessment and Management Plan for the

Installation of New Incinerators at Intermediate Hospital Katutura in Khomas Region.

Client: Ministry of Health & Social Services

Contact Person: Benjamin Ongeri Cell No.: +264 813 462 013

PROJECT TITLE: Environmental Impact Assessment and Environmental Management Plan for

the Establishment of a Lithium Mine and Processing Plant at Karibib in Erongo Region, (Eight

mining Claims within an EPL).

Client: LiCore Mining (Pty) Ltd

Contact Person: Gert Nell Cell No.: +264 812 945 895

LANGUAGE Speaking Reading Writing

English Very Good Very Good Very Good

Afrikaans Bad Not at all Not at all

German Not at all Not at all Not at all