environmental consultant - kspcb.gov.inkiadb)4ph_21082018.pdf · environmental consultant ....

12
EnvironmEntal impact assEssmEnt for Amendment in the Environmental Clearance to allow red category industries in the Dobaspet 4th Phase Industrial Area in the villages Yedehalli, Chandana Hosahalli, Honnenahalli, Kengal Kempohalli, K.G.Srinivasapura, Billanakote, Nelamangala Taluk, Bangalore Rural District, Karnataka EXEcUtivE sUmmarY PROJECT PROPONENT Karnataka Industrial Areas Development Board # 49, 4th & 5th Floor, East Wing Khanija Bhavan, Race Course Road, Bangalore-560 001 ENVIRONMENTAL CONSULTANT

Upload: others

Post on 09-Aug-2020

12 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: ENVIRONMENTAL CONSULTANT - kspcb.gov.inKIADB)4Ph_21082018.pdf · ENVIRONMENTAL CONSULTANT . Executive Summary 1 INTRODUCTION Karnataka Industrial Area Development Board (KIADB) is

EnvironmEntal impact assEssmEnt for

Amendment in the Environmental Clearance to allow red category industries in the Dobaspet 4th Phase Industrial Area

in the villages Yedehalli, Chandana Hosahalli, Honnenahalli, Kengal Kempohalli, K.G.Srinivasapura, Billanakote,

Nelamangala Taluk, Bangalore Rural District, Karnataka

EXEcUtivE sUmmarY

PROJECT PROPONENT

Karnataka Industrial Areas Development Board # 49, 4th & 5th Floor, East Wing

Khanija Bhavan, Race Course Road, Bangalore-560 001

ENVIRONMENTAL CONSULTANT

Page 2: ENVIRONMENTAL CONSULTANT - kspcb.gov.inKIADB)4Ph_21082018.pdf · ENVIRONMENTAL CONSULTANT . Executive Summary 1 INTRODUCTION Karnataka Industrial Area Development Board (KIADB) is

Executive Summary 1 INTRODUCTION

Karnataka Industrial Area Development Board (KIADB) is a wholly owned

infrastructure agency of Government of Karnataka, set up under Karnataka Industrial

Areas Development Act of 1966. KIADB has developed 160 industrial areas spread all over

the state. KIADB has proposed Amendment in the Environmental Clearance to allow

red category industries in the Dobaspet 4th Phase Industrial Area in the villages of

Yedehalli, Chandana Hosahalli, Honnenahalli, Kengal Kempohalli, Avverahalli,

K.G.Srinivaspura, Billanakote, Nelamangala Taluk, and Bangalore Rural District.

2 PROJECT DETAILS

Table - 1 : Salient details of the project

Sl. No Particular Details

1. Project Proponent Karnataka Industrial Areas Development Board (KIADB)

2. Project Name Amendment in the Environmental Clearance to allow red

category industries in the Dobaspet 4th Phase Industrial

Area.

3. Project Location In the villages Yedehalli, Chandana Hosahalli,

Honnenahalli, Kengal Kempohalli,

K.G.Srinivasapura, Billanakote, Nelamangala Taluk,

Bangalore Rural District, Karnataka.

4. Land Requirement 360.68Hectares (891.26 Acres)

5. Schedule & Category 7 (c) & B category

6. Total Cost of the project The existing cost of the project is Rs. 677.33 Crores. There

will not be any additional cost for this amendment.

2.1 PROJECT LOCATION

The proposed project site is located at Dobaspet 4th Phase in the villages Yedehalli,

Chandana Hosahalli, Honnenahalli, Kengal Kempohalli, Avverahalli, K.G.Srinivasapura,

Billanakote, Nelamangala Taluk, Bangalore Rural District, and Karnataka.

2.2 LAND REQUIREMENT

The land requirement for the proposed project is 360.68 Hectares (891.26 Acres). The

land use break up for proposed activity is given in the Table - 2.

Table – 2 : Land Use Breakup of the project

1 July 2018

Page 3: ENVIRONMENTAL CONSULTANT - kspcb.gov.inKIADB)4Ph_21082018.pdf · ENVIRONMENTAL CONSULTANT . Executive Summary 1 INTRODUCTION Karnataka Industrial Area Development Board (KIADB) is

Executive Summary

Sl No. Description Acres %Land Use

1 Industrial 431.58 48.42

2 Commercial 24.93 2.79

3 Amenity 23.70 2.65

4 Utility 23.89 2.68

5 Residential 43.24 4.85

6 Park 81.61 9.15

7 Buffer 87.70 9.80

8 Truck Parking 44.58 5.00

9 Road 113.57 12.74

10 BMRDA Road 16.46 1.80

Total Area 891.26 100

2.3 WATER REQUIREMENT & WASTEWATER GENERATION

There will not be any construction activity proposed as existing infrastructure is enough

for the proposed amendment. Water demand is 8.37 MLD and 5.19 MLD fresh water for

the operation phase is drawn from Hemavathi River for project needs and Industries are

not going to draw water from Tippagondanhalli reservoir.

During operation phase sewage generated will be treated in the Sewage Treatment Plant

(SBR) planned in 4.7 Ac on modular basis. The estimated Sewage generations from

domestic purpose during operation phase, 1.984 MLD. The treated water shall be reused

for toilet flushing, gardening etc. and the wastewater generated from the industries will

be treated in their respective Effluent Treatment Plants (ETP) on the basis of zero discharge

concept. The treated effluent will be reuse for industries like cooling, heat exchangers,

boilers, cleaning equipment’s etc.

2.4 POWER REQUIREMENT

The power requirement for the proposed development is 66.845 MVA and 10.2 Ac provided

for Sub Station. Power supply source from KARNATAKA POWER TRANSMISSION

CORPORATION LIMITED/BESCOM.

2.5 Solid Waste Generation

The quantities of waste likely to be generated from the industrial and non-industrial

phases have been estimated on the basis of population and land use characteristics. Table

- 3 presents the estimated solid waste quantities from the proposed project.

2 July 2018

Page 4: ENVIRONMENTAL CONSULTANT - kspcb.gov.inKIADB)4Ph_21082018.pdf · ENVIRONMENTAL CONSULTANT . Executive Summary 1 INTRODUCTION Karnataka Industrial Area Development Board (KIADB) is

Executive Summary

Table - 3 : Solid waste Generation

2.6 Project Location

Dobaspet 4th Phase Industrial Area for Establishment of Orange & Green Category

Industries on a Plot area of 891.26 Acres ( 360.68 Ha) in the Villages of Yedehalli,

Chandana Hosahalli, Honnenahalli, Kengal Kempohalli, Avverahalli, K. G. Srinivasapura,

Billanakote of Nelamangala Taluk, Bangalore Rural District has obtained Environmental

Clearance vide SEIAA 1 IND 2013 dated 27.08.2015. Site is well connected by road, rail

and airport. Study area of 10-km radius around the project site is shown in Figure – 1 &

Environmental Setting in the Table 4

2.7 ENVIRONMENTAL SETTING OF THE PROJECT SITE

Table 4 Environmental Setting of the Project

Selection Criteria Details

Elevation above Mean Sea Level 900m

Climatic Conditions Max temp: 35oC

Min temp:17oC

Average Rainfall : 829mm

Land availability 891.26 Acres

Nearest Highway • NH 4 Adjacent to Eastern side

• SH 3 Adjacent to Western side

S. No Solid Waste Bio- Degradable, in Kg/day

Non- biodegradable, in Kg/day

Recyclable, in Kg/day

Total waste from different phases, in Kg/day

1. Industrial Waste 1,888 2,428 1,079 5,395

2. Residential Waste 1,038 519 173 1,730

3. Other (commercial, CA, GBD, Roads etc.)

638 668 178 1,485

4. STP Sludge 210 210 Total Solid Waste, in Kg/day 3,774 3,615 1,430 8,819

3 July 2018

Page 5: ENVIRONMENTAL CONSULTANT - kspcb.gov.inKIADB)4Ph_21082018.pdf · ENVIRONMENTAL CONSULTANT . Executive Summary 1 INTRODUCTION Karnataka Industrial Area Development Board (KIADB) is

Executive Summary

Nearest Railway station Dobaspet -1 Km (N)

Nearest airport Bangalore Airport- 44.0 Km (E)

Nearest Town / City • Nelamangala – 15.0 Km (E)

• Bengaluru – 35.0 Km

Topography Plain

Archaeologically important places Nil within 15km radius

National parks/ Wildlife Sanctuaries Nil within 15km radius

Water Bodies/Rivers • Lekkanahalli Kere ≃ 3.44 Km (E)

• Kuluvanahalli Kere ≃ 4.95 Km (SE)

• Devara Kere ≃ 3.3 Km (W)

• Muddalinganahalli kere ≃5.0 Km (NE)

• Thyamagondluamami kere ≃ 4.5 Km (E)

• Tavare kere ≃ 5.6 Km (E)

• Hale Nijagana Lake ≃ 4.50km (NW)

Lakes adjacent to the Project Site (75m Buffer

Zone Provided)

Avvarehalli Kere

Kengal Kemponahallli Kere

Honnenahalli Kere

Yedehalli Kere

Reserved Forests • Mavinakompanahalli RF ≃ 8.30KM-NE

• Kengal RF ≃ 1.95 KM-W

• Nijagal RF ≃2.10 KM-W

• Adarangi North RF ≃ 3.85 KM-SW

Seismicity The study area falls under seismic zone-II

Defence Installations Nil in 10 km radius

4 July 2018

Page 6: ENVIRONMENTAL CONSULTANT - kspcb.gov.inKIADB)4Ph_21082018.pdf · ENVIRONMENTAL CONSULTANT . Executive Summary 1 INTRODUCTION Karnataka Industrial Area Development Board (KIADB) is

Executive Summary

Fig. 1 Topo map of the 10 km radius

5 July 2018

Page 7: ENVIRONMENTAL CONSULTANT - kspcb.gov.inKIADB)4Ph_21082018.pdf · ENVIRONMENTAL CONSULTANT . Executive Summary 1 INTRODUCTION Karnataka Industrial Area Development Board (KIADB) is

Executive Summary

3.0 DESCRIPTION OF ENVIRONMENT Monitoring has been carried out at various sampling locations within the study area during

the period of 16th March 2018 to 15th June 2018. The findings of the baseline environmental

status of the land, Meteorology, Air, Noise level, Ecological Environment, Socio-economic

conditions are given below and interpreted with reference to environmental standards.

Study area of 10-km radius around the project site is shown in Figure - 1.

3.1 Meteorology

The minimum and maximum temperature for study period is 20.6°C & 34.9°C. The

predominant wind direction during study period was west followed by the westerly south

west.

3.1.1 Air Environment

The prime objective of baseline air monitoring is to evaluate the existing air quality of the

area. This will also be useful for assessing the conformity to standards of the ambient air

quality during the construction and operation of the proposed project. This section

describes the selection of sampling locations, methodology adopted for sampling,

analytical techniques and frequency of sampling. The results of ambient air monitoring

carried out in the 8 locations of the study area. The results of ambient air monitoring

carried out during the study during the month of 16th March 2018 to 15th June 2018.

a) PM2.5 – The maximum value of 34.1 µg/m3 was observed at Project Site (AAQ1). A

minimum of 17.9 µg/m3 was observed at Jolumaranhalli (AAQ7).The 24 hours applicable

limit is 60µg/m3 for industrial/residential/rural areas, the sampled locations are within the

prescribed limit

b) PM10 – A maximum value of 69.1 µg/m3 was observed at Project Site (AAQ1). A

minimum of 40.8 µg/m3 was observed at Sripathihalli (AAQ6).The 24 hours applicable

limit for industrial/residential/rural areas is 100µg/m3, the sampled locations are within

the prescribed limit.

c) SO2 - The maximum value of 19.3 µg/m3 was observed at Project Site (AAQ1). A

minimum of 5.12 µg/m3 was observed at Sripathihalli (AAQ6). The 24 hours applicable

limit is 80µg/m3 for industrial/residential/rural areas, the sampled locations are within the

prescribed limit.

d) NOX - The maximum value of 19.6 µg/m3 was observed at Lekkanhalli (AAQ4). A

minimum of 8.52 µg/m3 was observed at Sripathihalli (AAQ6). The 24 hours applicable

limit is 80µg/m3 for industrial/residential/rural areas, the sampled locations are within

the prescribed limit. Other parameters like ammonia, ozone, CO, VOCs, Arsenic & Nickel

6 July 2018

Page 8: ENVIRONMENTAL CONSULTANT - kspcb.gov.inKIADB)4Ph_21082018.pdf · ENVIRONMENTAL CONSULTANT . Executive Summary 1 INTRODUCTION Karnataka Industrial Area Development Board (KIADB) is

Executive Summary are below detectable limit. The air quality data in the monitored area within the project

site is within the prescribed limit.

3.1.2 NOISE ENVIRONMENT

a) Day Time Noise Level:-Noise levels during day time were found to be in the range

48.6 – 70.2 dB (A). The maximum noise level was observed to be 70.2 dB (A) at Project

site (N1) and a minimum of 48.6 dB (A) was observed at Birogondan Halli (N4). The

monitored locations during the Day time are under the prescribed limit.

b) Night Time Noise Levels: -Noise levels observed to fall in the range 40.3- 59.0 dB

(A) during the night time. Maximum noise level of 59.0 dB (A) was observed at Project

Site (N1) and a minimum of 40.3 dB (A) observed at Birogondan Halli (N4). The monitored

locations during the Night time are under the prescribed limit.

The Noise Level data in the monitored area near project site is below the prescribed limit

3.1.3 WATER ENVIRONMENT The water pH of groundwater samples is in the range is in between 6.72-7.84 and surface

water pH is between 7.34 and 7.91. Total dissolved solids (TDS) of groundwater samples

are 232-616 kg/ha. The total dissolved solids (TDS) of surface water samples are 121-279

kg/ ha. Correspondingly the hardness, alkalinity, chlorides & sulphates were also in

average. The groundwater and Surface water at project site is comparatively good and

with some treatment, can be used for domestic and Industrial purpose.

3.1.4 SOIL ENVIRONMENT

It has been found red sandy soil observed that the pH of the soil ranges from 6.82 - 7.54

indicating that the soil is ideal for plant growth. The nitrogen values are in the range of

284-426 kg/ha and the potassium values range between 194-346 kg/ha, which indicate

that the soils have moderate quantities of potassium. The soil from the study area shows

moderately fertility.

3.2 ECOLOGY

The flora and fauna in the study area are explored by the expert crew. The land type,

forest area and other ecological aspects are detailed in this section. The impact of the

proposed project to the biodiversity, terrestrial and aquatic ecology has been studied.

7 July 2018

Page 9: ENVIRONMENTAL CONSULTANT - kspcb.gov.inKIADB)4Ph_21082018.pdf · ENVIRONMENTAL CONSULTANT . Executive Summary 1 INTRODUCTION Karnataka Industrial Area Development Board (KIADB) is

Executive Summary 3.3 DEMOGRAPHY AND SOCIO- ECONOMICS

The baseline data includes the socio economic status of the area. The data about the

human settlements in and around the project site, health status of the community, existing

infrastructure facilities for social welfare, job opportunities, safety and security of the

workers and the surrounding population. The positive impact of the proposed project and

the socio economic status in the buffer zone is reported.

4. ENVIRONMENTAL IMPACTS & MITIGATION MEASURES 4.1 Air Environment

The impact on air environment depends on the raw materials of member industries. SO2

& NOX are anticipated during the usage of DG sets and boilers. The vehicles used for

transportation of raw materials will cause air pollution.

Mitigation Measures

Use of low Sulphur diesel will minimize the emission from diesel generators.

Development of green belt will reduce the level of particulate matter.

The emission standards fixed by government authorities will be followed.

Vehicles will be maintained properly.

Green belt development

Pollution abatement via green belt development is one of the vital components for any

Industrial activity. The main objectives of green belt development plan in any area are

1. Aesthetic Enhancement.

2. Reduction of impacts of air pollution and dust.

3. Arrest soil erosion

4. Climatic amelioration

4.2 Noise Environment

During operation phase, noise pollution will be aroused due to DG sets, vehicular

movements and machineries in industries. There will not be much noise during Operation

phase.

Mitigation Measures

Proper acoustic measures will be provided to reduce the noise generated by DG sets

and isolation of DG will reduce the noise at receiver’s end.

Green belt development will also reduce noise level.

8 July 2018

Page 10: ENVIRONMENTAL CONSULTANT - kspcb.gov.inKIADB)4Ph_21082018.pdf · ENVIRONMENTAL CONSULTANT . Executive Summary 1 INTRODUCTION Karnataka Industrial Area Development Board (KIADB) is

Executive Summary 4.3 Water Environment

During the operation phase water will be sourced from Hemavathi River. The effluent which

is supposed to be generated may cause severe problems to the environment when

compared with the wastewater generated by domestic activities. The members industries

are responsible for treating effluent from industries.

Mitigation Measures

The waste water generated by domestic activities will be treated in STP of capacity 2.0

MLD. Industrial effluents having different properties will be treated in ETP of respective

industry. KIADB will mandate member industries to adopt Zero Liquid Discharge System

as well as Rain Water Harvesting structures.

Storm water drains will be provided to collect water during rains. It would be sized

adequately to prevent flooding of the site. It is proposed to have rain water harvesting

structures for recharge of roof top rain water and rainwater of paved surface at respective

buildings. The storm water drains will be acting as recharge trench and intermittent check

dams will be provided in the storm water drains to infiltrate maximum amount of water

into the ground.

4.4 Soil Environment

Dumping of municipal and industrial waste on the land will affect the soil quality. Poor

Garbage management will lead to unsanitary conditions including vermin, odor and fly

infestation. The spillage of waste oil from DG sets will also affect the land.

Mitigation Measures

• The waste generated will be treated and disposed properly.

• Toxic waste from industries will not be disposed on land without treating it in a

proper manner.

• Generation of waste will be minimized at the source.

5. ENVIRONMENTAL MONITORING PROGRAMME

Environmental Monitoring programme given in the Table - 5.

Table - 5 : Environmental Monitoring Programme

S. No Particulars Monitoring

Frequency Duration of Sampling

Monitoring Parameters

1 Ambient Air Quality Monitoring

9 July 2018

Page 11: ENVIRONMENTAL CONSULTANT - kspcb.gov.inKIADB)4Ph_21082018.pdf · ENVIRONMENTAL CONSULTANT . Executive Summary 1 INTRODUCTION Karnataka Industrial Area Development Board (KIADB) is

Executive Summary

a Project site Once in 3 months 24 hour PM10, PM2.5, SO2, NOx and CO

2 Stack Monitoring

a DG set Once in 3 months 30 min SO2, NOx, SPM, CO, CO2

3 Ambient Noise Level a Near DG set Once in 3 months 8 hr continuously

with 1hr interval Noise level (dB)

4 Ground / Drinking water Quality

a Ground water at project site

Once in 3 months Grab Sampling Parameters specified under ISO: 10500, 1993

5 Sewage Quality Monitoring a STP Inlet Once in a month Grab Sampling Physical, Chemical

and Biological parameters specified under IS: 2490:1982

b STP Outlet

6 Soil Quality

a At the green belt area

Once in a year Samples collected from three different depths viz., 30cm, 60cm and 100cm below the surface.

pH, texture, EC, organic matter, nitrogen, phosphate, calcium, potassium and magnesium.

6. ADDITIONAL STUDIES

KIADB will gives directions to member industries during plot allotment to carry out

preliminary risk assessment study, disaster management plan & occupational health &

safety if applicable.

7. PPROJECT BENEFITS

1. The major benefit due to proposed project will be in the sphere of generating

employment for substantial number of personnel. Hence local people in the

surrounding area will be benefitted.

2. The State Government will benefit through revenue recovery from excise duty.

3. Due to proposed Industrial Area infrastructure facilities such as laying of roads,

drainage network, green belt development, power, business establishments etc. will

be developed.

4. Industries will take up Corporate Social Responsibility (CSR) activities which in turn

help in enhancement of the educational, medical & social realm.

1 0 July 2018

Page 12: ENVIRONMENTAL CONSULTANT - kspcb.gov.inKIADB)4Ph_21082018.pdf · ENVIRONMENTAL CONSULTANT . Executive Summary 1 INTRODUCTION Karnataka Industrial Area Development Board (KIADB) is

Executive Summary 5. Overall proposed project will help in improving the socioeconomic conditions of the

surrounding area.

8. ENVIRONMENTAL MANAGEMENT PLAN

An organizational structure for managing the environment has been recommended for the

development of proposed Dobaspet Industrial Area. The General Manager (Environment)

is directly responsible for environment management of the proposed project. The

organizational set up of the Environmental Management Cell is shown in Figure below.

Figure 2 – Environment Management Cell

1 1 July 2018