environment protection (water quality) policy 2015...
TRANSCRIPT
South Australia’s Environment Protection Authority
Environment Protection (Water
Quality) Policy 2015, stormwater
pollution prevention & dewatering
guidance
Clive Jenkins, Ruth Ward and Lara Settimio
Outline
1. Key water quality policy change: Clive Jenkins
2. Stormwater management: Ruth Ward
3. Draft dewatering guideline: Lara Settimio
Key WQEPP change
• Remove clause 13. Requirement to not cause pollutant concentrations
to exceed specific criteria
- Mandatory with an offence provision but no link to environmental
harm (not based on risk)
• Add clause 9. General environmental duty
- Non-mandatory (no offence provision) and an clear links to
environmental harm and risk management.
The previous WQEPP clause 13…
13—Obligation not to contravene water quality criteria
(Schedule 2)
(1) A person must not, by discharging or depositing a pollutant into any waters,
cause any of the water quality criteria applicable (see Schedule 2) to those
waters—
(a) to be exceeded or, if already exceeded (whether through natural
causes, the discharge or deposit of a pollutant or a combination of both),
further exceeded; or
(b) in the case of a minimum level specified in Schedule 2 in relation to a
characteristic of water—to be decreased or, if already decreased
(whether through natural causes, the discharge or deposit of a pollutant
or a combination of both), further decreased.
Mandatory provision: Category B offence.
• Apply the Waste Management Hierarchy
• Follow EPA Guidelines and Codes
• Protect “environmental values” by reference to National Water Quality Guidelines
• Promote and encourage changes which achieve improved environmental outcomes.
• Risk-based regulatory decision making to investigate environmental harm and/or seek compliance
by issuing Environment Protection Orders or by application of other regulation options and tools.
• Failure to comply with the duty indicates that environmental harm may be occurring.
• Failure to comply with the duty does not constitute an offence…however the EPA may apply a
regulatory response consistent with the level of environmental risk
Requirements that demonstrate application of the GED
EPA responsibilities
Implications if a person fails to comply
Clause 9: General Environmental Duty
Stormwater - Clause 10 and 11
- replace Clause 17 and 19
• Clause 11 requires that class 2
pollutants (Schedule 3) of the policy
are not discharged to waters, includes
soil, clay, gravel or sand
• The definition of waters includes the
stormwater system
• Mandatory offence provisions
• Clause 10 requires Class 1 pollutants (Schedule 2) of the policy are not
discharged into waters or onto land where they are likely to enter waters,
includes many pollutants relevant to civil construction
Stormwater - Clause 10 and 11
• Still guided by the waste
management Hierarchy
• Avoid and minimise pollutants
entering the stormwater system
and other waters
• Reuse and recycle, can water be
collected and used as an alternative
water supply e.g. dust suppression
• Treatment and disposal is the least
preferable and may be costly, better
to stop the pollutants entering the
system
Stormwater Pollution Prevention
Code of Practice
• Stormwater pollution prevention code of practice for
the building and construction industry prescribed
code linked to Clause 9
• Mandatory measures must be complied with
• A Soil Erosion Drainage Management Plan
(SEDMP) must be prepared
• SEDMP a tool to outline how pollutants from the
activity will be minimised and managed
• Follow the waste management hierarchy
• Avoid and minimise the generation of soil and
other pollutants by minimising erosion
• Capturing and treating to remove the sediment is
less effective and more costly
Stormwater Pollution Prevention
Code of Practice - changes ahead
• Codes of Practice to be replaced with a Stormwater Standard.
• This will have MUSTS supported by guideline material
• If undertaking construction activities there will be a requirement to develop,
implement and maintain a soil erosion drainage management plan
• This a tool to demonstrate how to prevent pollutants discharging to waters
and
• demonstrates how you intend to fulfil your obligations under Clause 9 –
general environmental duty and Clause 10 & 11
• Guideline material will be web based with a tool that will allow you to create
your own PDF document and be kept informed of any updates.
• Construction guidelines International Erosion Control Association (IECA)
including the field guides which are free to download
Guidelines available on the EPA
website, environmental information,
stormwater management
South Australia’s Environment Protection Authority
DRAFT Guideline Environmental Management of
Dewatering During Construction Activities
Purpose
• To provide guidance for the environmental management of dewatering
during and after construction activities in accordance with the Environment
Protection Act 1993 (i.e. the Act)
• For the purpose of this guideline dewatering is defined as…
…the process of removal of any water that accumulates in earthwork
excavations or below ground structures at or below the existing
watertable as a result of intersecting aquifers, seepage of soil
water / groundwater or storm events.
• Consider guidance provided for Construction Environmental Management
Plans (CEMPs)
This does not provide guidance to long term/on-going dewatering, acid sulfate soils or
mine dewatering
What we think is happening…
…. maybe
we should
have
planned for
this….
I’m calling the
EPA, I need to
turn on the pump
to discharge this
to stormwater
….NOW!
What we want to happen….
I’d like to include
a two-storey
below ground
basement in the
design…
…we need to
consider
groundwater in the
area and either plan
to dewater or
contact the EPA
before we start
digging…
Let’s
collect some
preliminary
data…
Legislative requirements
• The EP Act (2003)
– General Environment Duty
• Environment Protection (Water Quality) Policy (2015)
– Trigger Values, Environmental Value
– The Waste Management Hierarchy
• Earthworks Drainage
– the Act, declares this to be a prescribed activity of environmental
significance if more than 100 kiloliters of waste water containing
suspended solids in concentration exceeding 25 milligrams per litre is
discharged directly or indirectly to marine waters or inland waters.
Where that is the case, an environmental authorization (i.e. license) is
required.
Waste Management Hierarchy (clause 4)
AVOID
MINIMISE
REUSE
RECYCLE
RECOVER
TREAT
DISPOSE
Most preferable
Least preferable
...a person must minimise waste that has been avoided to an extent that is reasonably practicable….
…then they must reuse the waste that has been minimised to an extent that is reasonably practicable
…then they must recycle the waste that has been reused to an extent that is reasonably practicable
…then they must recover energy from the waste that has been recycled to an extent that is reasonably practicable
…then they must treat waste that has had energy recovered to an extent that is reasonably practicable
…then they must dispose waste that has been treated to an extent that is reasonably practicable. Disposal must be done in a manner that causes least environmental harm.
Planning considerations
• Development Applications
– Ideally dewatering concerns should be raised here
– Site Contamination framework for the SA planning system will be
considered
– CEMPs can be required at this point and can address dewatering
management
• Desktop risk assessment
– Identify potential risks, potential for contaminated groundwater to be
encountered on site e.g. if petrol stations are nearby
• Geotechnical assessment
– Depth and quality of groundwater to be discharged
– Dewatering volumes, rate, duration etc
Refer to EPA for consideration
• Groundwater prohibited areas
(GPA)
• Known or suspected site
contamination
• Potential for disturbance of acid
sulfate soils (ASS)
• Earthworks drainage
• Activation of trigger values
• Foreseen long-term and ongoing
dewatering
Dewatering Management Plan
Issues to be addressed:
1. Purpose of dewatering (an explanation of why dewatering is necessary).
2. Description of dewatering technique to be employed.
3. Anticipated dewatering flow rate, duration and total volume.
4. Water collection and storage options (if applicable).
5. Assessment of water quality.
6. Water re-use options.
7. Water treatment options.
8. Proposed discharge disposal options.
Other considerations (if applicable)
– Noise and odor considerations.
– People, property, water bodies that could be affected by the dewatering activity.
– Contingency plans.
– Maintenance Plans for equipment, & mitigation plans if equipment fails.
Questions and further information
• Call 8204 2004 and ask
for Clive Jenkins, Ruth
Ward or Lara Settimio
• Email [email protected]