environment impact assessment study
DESCRIPTION
PRESENTATION ON ENVIRONMENT IMPACT ASSESSMENT STUDY by ENVIRONMENT DEPARTMENT ENGINEERS INDIA LIMITEDTRANSCRIPT
120/09/14
PRESENTATION ON ENVIRONMENT IMPACT ASSESSMENT STUDY
ENVIRONMENT DEPARTMENT
ENGINEERS INDIA LIMITED
20/09/14 2
Environment – Indian Scenario
India is the first country to make provision for protection and improvement of
Environment in its constitution vide 42nd Amendment to constitution in 1976
Directive principle of state policy in Chapter-IV of constitution, Article – 48 –A
was inserted which empowers state to make provision for environment
protection and improvement
Fundamental duties was inserted vide Article – 51 – A(g) for all citizen to protect
and improve environment
After Stockholm conference on Human Environment in 1972, in order to have
uniform law, Water Act (Prevention and Control), 1974 was passed under
Article 252 of constitution
This led to formation of Central Pollution Control Board and State PCBs
Then came Water (Cess) act in 1977 to conserve water and Air Act in 1981.
Then came unified act under EPA, 1986
20/09/14 3
INSTITUTIONAL FRAMEWORK FOR POLLUTION PREVENTION
Govt. of India
Min. Of Env andForests
Central PollutionControl Board
State Govt
Dept. Of Env
State Pollution Control Board
Zonal Office Regional Office
20/09/14 4
Indian Policies Requiring EIA
1976-77 by planning commission for river-valley projects. Later extended to those required to get PIB approval
On January 27, 1994 under Environment (Protection) Rules, 1986, Government of India advised that all expansion or modernisation of any activity (if pollution load is to exceed the existing one) or a new project listed in Schedule I is required to undergo EIA process
The schedule I include 30 different types of projects Site clearance is need for site specific projects like mining, pit-head thermal
power stations, hydro-power, major irrigation projects and/or their combination including flood control, ports and harbours (excluding minor ports) and prospecting and exploration of major minerals in areas above 500 ha.
However, this notification is not applied to any project of Schedule-I if the investment is less that Rs. 100 crores or for any item reserved for Small Scale
Industrial sector with investments less than Rs.1 crore.
20/09/14 5
The EIA Cycle and Procedures
THE EIA PROCESS IN INDIA IS MADE UP OF FOLLOWING PHASES
SCREENING
SCOPING AND CONSIDERATION OF ALTERNATIVES
BASELINE DATA COLLECTION
IMPACT PREDICTION
ASSESSMENT OF ALTERNATIVES, DELINEATION OF MITIGATION
MEASURES AND ENVIRONMENTAL IMPACT STATEMENT
PUBLIC HEARING
ENVIRONMENT MANAGEMENT PLAN
DECISION MAKING
MONITORING THE CLEARANCE CONDITIONS
20/09/14 6
Roles in the EIA Process
EIA INVOLVES MANY PARTIES, GROUPED BY THEIR ROLE DEFINITION WITHIN THE PROCESS. THEY ARE :
THE PROJECT PROPONENT THE ENVIRONMENTAL CONSULTANTS THE STATE POLLUTION CONTROL BOARD / POLLUTION CONTROL
COMMITTEES (PCCS) THE PUBLIC THE IMPACT ASSESSMENT AGENCY
20/09/14 7
Roles in the EIA Process
• THE PROJECT PROPONENT
• Project proponent needs to prepare the DFR and submits the executive
summary, to be made available to concerned public.
• The proponent has to approach the concerned SPCB for NOC and holding
the public hearing. After the public hearing the proponent submits
application to IAA for environmental clearance.•THE ENVIRONMENTAL CONSULTANTS
The consultant should guide the proponent through initial screening of the
project and establish whether EIA studies are required to be conducted and
if so finalise the scope of such study.
The environmental consultant is responsible for supplying all the
environment-related information required by the SPCB and IAA through the
proponent.
The consultant is also required to justify the findings in the EIA and EMP
during the meeting with the expert groups at IAA.
20/09/14 8
Roles in the EIA Process
STATE POLLUTION CONTROL BOARD (PCB) /POLLUTION CONTROL COMMITTEE (PCC)
The state PCBs/ PCCs are responsible for assessing the compatibility of a
proposed development with current operational and prescribed standards.
If the development is in compliance, the PCB will then issue its NOC.
They shall also hold the public hearing as per the provisions of EIA
notification. The details of public hearing shall be forwarded to IAA.
PUBLIC
The public also has an important role to play in EIA. The concerned
persons will be invited through press advertisement to review information
and provide their views on the proposed development requiring
environmental clearance.
20/09/14 9
Roles in the EIA Process
IMPACT ASSESSMENT AGENCY (IAA)
Where a proponent is required to obtain environmental clearance, the iaa
will evaluate and assess the EIA report. In this process the project
proponent will be given a chance to present his proposal.
If a project is accepted the IAA will also prepare a set of recommendations
and conditions for its implementation based on this assessment.
Environmental clearance conditions and recommendations of IAA are
made available to the public on request through SPCB.
During the implementation and operation of the project, the IAA will also be
responsible for the environmental monitoring process.
20/09/14 10
Roles in the EIA Process
TWO TYPES OF EIARAPID COMPREHENSIVE
Rapid EIA is for speedier appraisal process.
While both types of EIA require inclusion/ coverage of all significant
environmental impacts and their mitigation,
Rapid EIA achieves this through the collection of ‘one season’ (other than
monsoon) data only to reduce the time required.
The review of rapid EIA submissions will show whether a comprehensive EIA is
warranted or not.
It is, therefore, clear that the submission of a professionally prepared
comprehensive EIA in the first instance would generally be the more efficient
approach.
20/09/14 11
Screening
Screening is done to see whether a project requires environmental
clearances as per the statutory notifications based on
scales of investment
Type of development
Location of development
A project requires statutory environmental clearance only if the provisions of
EIA notification and/or other statutory notification.
20/09/14 12
Scoping
Scoping is a process of detailing the terms of reference of EIA. It has to be
done by the consultant in consultation with the project proponent and
guidance, if need be, from impact assessment agency.
The ministry of environment and forests has published guidelines for
different sectors, which outline the significant issues to be addressed in the
EIA studies.
Quantifiable impacts are to be assessed on the basis of magnitude,
prevalence, frequency and duration and non-quantifiable impacts (such as
aesthetic or recreational value), significance is commonly determined
through the socio-economic criteria.
After the areas, where the project could have significant impact, are
identified, the baseline status of these should be monitored and then the
likely changes in these on account of the construction and operation of the
project should be predicted.
20/09/14 13
Analysis of alternatives
• ALTERNATIVES ANALYSIS COVER Project location Process technologies. ‘No project’ option also.
Alternatives should then be ranked for selection of the best environmental option
for optimum economic benefits to the community at large.
Once alternatives have been reviewed, a mitigation plan should be drawn up for
the selected option and is supplemented with an Environmental Management
Plan (EMP) to guide the proponent towards environmental improvements.
An EIA report should provide clear information to the decision-maker on the
different environmental scenarios without the project, with the project and with
project alternatives. Uncertainties should be clearly reflected in the EIA report.
20/09/14 14
Baseline Data
Baseline data describes the existing environmental status of the identified study area. The site-specific primary data should be monitored for the identified parameters and supplemented by secondary data if available.
Rapid EIA : One SeasonComprehensive EIA : Three Seasons
Third party Data Collection General data : Data Collection Agencies Specialized data : Specialized Agencies
•Land use/land Cover : NRSA•Marine : NIO• Geophysical/ground water : NGRI•Socioeconomic : IGIDR/NIRD•Biological : SACON/WII
20/09/14 15
Impact Assessment
Impact prediction is a way of ‘mapping’ the environmental consequences of the significant aspects of the project and its alternatives.
The following issues of impacts of the project should be assessed: Air changes in ambient levels and ground level concentrations due to
total emissions from point, line and area sources effects on soils, materials, vegetation, and human health
Noise changes in ambient levels due to noise generated from equipment
and movement of vehicles effect on fauna and human health.
20/09/14 16
Impact Assessment
Water availability to competing users changes in quality due to discharge sediment transport due to project activity ingress of saline water
Land
changes in land use and drainage pattern changes in land quality including effects of waste disposal changes in shoreline/riverbank and their stability
Biological
deforestation/tree-cutting and shrinkage of animal habitat. impact on fauna and flora (including aquatic species if any) due to
contaminants/pollutants impact on rare and endangered species, endemic species, and
migratory path/route of animals. Impact on breeding and nesting grounds
20/09/14 17
Impact Assessment
Socio-Economic
Land acquisition and Rehabilitation and Resettlement (R&R) issue impact on the local community including demographic changes. Impact on economic status impact on human health. impact of increased traffic
Solid Waste
Can be Hazardous or Non-Hazardous Classification under Hazardous Waste Management and handling
Rules requires certain obligation in terms of disposal. Comprehensive inventorisation if area has has no land for disposal or
existing capacity is near full or prone to flooding or high ground water table
20/09/14 18
Impact Evaluation
THE IMPACT IS SIGNIFICANT OR UNACCEPTABLE IF EMISSION/DISCHARGE LOAD AND CHARACTERISTICS OR THE RESULTANT ENVIRONMENTAL QUALITY ARE IN VIOLATION OR EXCEED:
Ambient Environmental Quality standard (IS10500, NAAQS) Policies of government or statutory bodies Compliance with international obligations (World Bank, TNO, OSHA) Assimilative capacity of the region
20/09/14 19
Environmental Management Plan
EMP should include
Delineation of mitigation and compensation measures
Delineation of unmitigated impacts
Physical planning including work program, time schedule and locations for
mitigation and compensation
Delineation of financial plan
20/09/14 20
Environmental Management Plan
Technological Measures
Pollution Prevention
Waste minimization
End-of-the-pipe treatment
Attenuation in the source receptor pathway
Protection of sensitive receptor
Mitigation measures
Physical Planning
Listing devices of pollution control, prevention and protection
Schedule of implementation
The proposed layout plan of the facilities
20/09/14 21
Environmental Management Plan
Human Resources (Staffing/training/awareness) Identification of Skills required for implementations of EMP
Organization chart for implementation of EMP
Provision of financial supporting human resources
Financial Planning
Cost of mitigation measures
Cost of maintenance and operation Documentation of evidence
Monitoring Plan
- Stipulated Conditions
- Implementation of EMP
- Priority of specific conditions
- Issued raised in the public hearing
20/09/14 22
PUBLIC HEARING AND DECISION MAKING
PUBLIC HEARING
Law requires that public must be informed and consulted on a proposed
development after the completion of EIA report
Any one likely to get affected by the project is entitled to have access to the
executive summary of the EIA.
DECISION MAKING
Decision making is a process involve consultation between the project proponent (assisted by a consultant) and the impact assessment authority (assisted by a group of expert).
The decision on environmental clearance is arrived through a number of steps including evaluation of EIA and EMP
20/09/14 23
www.engineersindia.com
Thank You