entering the danger zone: the art of risk management cindy margules, pmp pmo director, convio ...
TRANSCRIPT
Entering the
Danger Zone:
The Art of Risk
Management
Cindy Margules, PMP
PMO Director, Convio
www.allposters.com
International Project Management Day
November, 2010
Cindy Margules, PMP Entering the Danger Zone November 2010
What is a risk? Risks are things / situations that MAY happenIssues are things / situations that are in progress
What is risk management?The processes involved with identifying, analyzing, and responding to project risk
Little known fact:Risk management is a time waster!
Risk management is proactive – effort not urgently neededIssue management is reactive – firefighting
Every noble acquisition is attended with its risks; he who fears to encounter the one must not expect to obtain the other. - Metastasio -
Risk Terminology
Cindy Margules, PMP Entering the Danger Zone November 2010
Quietly write on the paper given all the risks you can think of to the following situation. Additionally:
• In the upper left corner estimate the probability of the risk happening (1=low, 2=med, 3=high)
• In the upper right corner estimate the impact if the risk occurred (1=low, 2=med, 3=high)
Your project is to build a zoo. Success is defined as doors open March 1, with 35 different types of animals to view and the infrastructure to support 400 guests / hour average. What are risks that might keep you from being successful?
First Activity
Cindy Margules, PMP Entering the Danger Zone November 2010
Risk Management Knowledge Area
The objective is to increase the probability and impact of positive events and decrease that of negative events.
Risk Management Planning – deciding how to approach, plan, and execute the risk management activities for a project.
Risk Identification – determining which risks might affect the project and documenting their characteristics.
Quantitative Risk Analysis – numerically analyzing the effect on overall project objectives of identified risks.
Cindy Margules, PMP Entering the Danger Zone November 2010
Qualitative Risk Analysis – prioritizing risks for subsequent further analysis or action by assessing and combining their probability of occurrence and impact.
Risk Response Planning – developing options and actions to enhance opportunities, and to reduce threats to project objectives.
Risk Monitoring and Control – tracking identified risks, monitoring residual risks, identifying new risks, executing risk response plans, and evaluating their effectiveness throughout the project life cycle.
Risk Management Knowledge Area
Cindy Margules, PMP Entering the Danger Zone November 2010
SpecificQuantitative
Cause and effect
Typical Risk Example: “The tool recommended may not be approved.”
Good Risk Example: “If the tool recommended is not approved due to
cost, then the schedule will slip by 3 months to reevaluate a different tool.”
Writing a Risk
Cindy Margules, PMP Entering the Danger Zone November 2010
Typical:PM or other lead evaluates risks based on
experience
Benefits:QuickCovers “most” high risks (assumed)
Disadvantages:
Incomplete - does not utilize vast experience of team
Biased - dependant on one person, his / her take on history
which feeds type / amount / variety of inputs
and impacts, probabilities, mitigations
Skewed actions – less creative mitigations, reactionary and
may not be well thought out
Greater chance of risks becoming issues!!
Greater chance of risks becoming issues!!
Risk Assessments
Cindy Margules, PMP Entering the Danger Zone November 2010
Entire group in one room
Establish directive parameters charter, schedule, communication, etc may have leading question
Focused response sticky notes group writes as many as possible within 5 minute period
Categorize in silence, first person puts notes on board second person “groups” like notes and adds his continues through group – becomes “categories” one more time through to regroup exception – if same sticky note keeps going back and forth
(3 times) then is reproduced and located in both categories
Clarify, Capture
Formal Risk Assessments
Cindy Margules, PMP Entering the Danger Zone November 2010
Detailed analysis:
Evaluate probability (L, M, H or 1,3, 9, or 1, 2, 3)o virtual certainty vs. more likely than not
Evaluate impact quantitatively (same) and qualitatively Determine risk total (P x I) - unacceptable, high, medium, low
Determine trigger Determine response plan
o avoid, accept, mitigate, transfero ownero timeframe
Contingency plan
COMMUNICATE – team, stakeholders, etc. … OFTEN!
Formal Risk Assessments - continued
Probability
HIGH 3 6 9
MEDIUM 2 4 6
LOW1 2 3
LOW MEDIUM HIGH
Impact
Add: mitigation
probability of working (L, M, H)
Cindy Margules, PMP Entering the Danger Zone November 2010
www.cartoonstock.com
avoid, accept, mitigate, or transfer?
Cindy Margules, PMP Entering the Danger Zone November 2010
Establish directive parameters charter, schedule, communication, etc create web survey with focused leading questions
Establish the time frame (one week to complete)
Focused response: no communication between team members additional inputs requested
Categorize: Review in core team each risk – clarify Group into categories – regroup / re-categorize Evaluate probability; impact; status (uhml) – group buy-in Determine trigger Determine response plan
o Avoid, accept, mitigate, transfero Owner, timeframe
Non Co-located Formal Risk Assessments
Cindy Margules, PMP Entering the Danger Zone November 2010
ID Risk
Probability Rating(1-3)
Impact Rating (1 - 3)
RiskRating (1 - 9)
Impact Description
Contingency Plan
Mitigation Action
Probability Mitigation Will Work
Action
OwnerDate Last Reviewed
CurrentStatus
1 Rain 2 2 4 slow traffic
leave 30 minutes
early
check weather
night before H me 23Jun09 ok
Excel Formal Risk Logs
Cindy Margules, PMP Entering the Danger Zone November 2010
Revisit risk analysis often and with different objectives
Assumptions / Requirements
Cindy Margules, PMP Entering the Danger Zone November 2010
who, what, where, when, why, how
For understanding Risk Management (the process) …
5Ws and the H
and to utilize in the detailed evaluations of individual risks
Cindy Margules, PMP Entering the Danger Zone November 2010
What are the risksWhat are the best ways to comprehend themWhat are your stakeholders / customers / team
members concerned about
How to find risksHow to run a risk analysisHow to mitigate risksHow to prioritize risksHow to store risk assessments, changes, status
Risk Management Process
Cindy Margules, PMP Entering the Danger Zone November 2010
When should you look for risksWhen should you mitigate the risksWhen should people be informed of, and changes to, the risks
Where should you conduct analysisWhere should you share and store the information
Who should have the informationWho is the owner of the riskWho should you utilize to ensure your risks are thoroughWho should you inform of changes
Why is it a risk - probability and impact
Risk Management Process
Cindy Margules, PMP Entering the Danger Zone November 2010
cost, schedule, quality
critical resource personnel availability
non-human resources not functioning
different motivations
objectives / business goals
requirements
gossip
mitigation not working / coverage of mitigation
assumptions
unplanned work
process maturity
communication paths
Leading Question Categories
Cindy Margules, PMP Entering the Danger Zone November 2010
lost information, ignored or misunderstood email
poor documentation
utilize non team members, SMEs, customer
SWOT – strengths, weaknesses, opportunities, threats
positive risks
improvements
organizational barriers
risk of senior management not buying into proposed
solution
non-participation
multitasking
other projects impacting
5ws and the h
Leading Question Categories - continued
Cindy Margules, PMP Entering the Danger Zone November 2010
Communication!
Risks changewording, probability, impact, status, closure, triggers,
responses, ownership, timeframe, etc.
Less risks become issues
More time for quality work / reasonable workweek
Project efficiency – significant cycle time reduction
Most important business reasons …
Increased Profitability and Customer Satisfaction
Best Reasons for Formal Risk Analysis
Cindy Margules, PMP Entering the Danger Zone November 2010
Review top risks daily
Escalation
Change management
Resources
It takes a strategic mindset to focus on risks over issues
or other items that take up your time
Control / Governance
NOT the problem!
Cindy Margules, PMP Entering the Danger Zone November 2010
Skeptical team members
PM did this for client in-depth planning:• Took about 1 – 1.5 hours the first day • Additional time added the second day since the client
found it so valuable• Client talked about how important this activity was
(although they weren’t sure about it at first)• Client requested PM lead this same type of activity
for the Partners• PM actively managing her risk log for this
engagement
Next slides can be cut / paste into presentation for a Risk Analysis
Successes
Cindy Margules, PMP Entering the Danger Zone November 2010
What is a Risk?
Anything that could potentially happen on a project that would impact its timing, budget, quality or overall success
Risks/Opportunities can either positively or negatively impact your project
Example: Your tire may have a blowout on your upcoming trip.
What is a Mitigation Plan?
A plan to avoid or reduce the impact or probability (or both) of a specific risk or exploit an opportunity
Example: You buy new tires.
(Decreased probability – NOT impact)
Risk Management Overview
Cindy Margules, PMP Entering the Danger Zone November 2010
What is an Issue?
An issue is a risk or event that has already occurred.
What is a Contingency Plan?
A pre-prepared action plan created if an identified risk turns into an issue anyway (usually for high risks)
Example: You buy a medical emergency kit and put it in your trunk.
Risk Management Overview
Cindy Margules, PMP Entering the Danger Zone November 2010
Why is Risk Management Important?• Empowers us to think proactively over the lifecycle of the
project
• Allows us to plan for the future success of the project
• Identifies those risks that are the most likely to occur and present the greatest impact to the project
• Gives us an opportunity to develop a mitigation plan to avoid a risk turning into issue
• Gives us an opportunity to develop a contingency plan to act when a risk becomes an issue
Risk Management Overview
Cindy Margules, PMP Entering the Danger Zone November 2010
SpecificQuantitative
Cause and effect
Typical Risk Example: “The tool recommended may not be approved.”
Good Risk Example: “If the tool recommended is not approved due to
cost, then the schedule will slip by 3 months to reevaluate a different tool.”
Writing a Risk
Cindy Margules, PMP Entering the Danger Zone November 2010
Description of Risk
Risk Probability Ranking
Risk Impact Ranking
Risk Probability - chance that risk will occur
• 1 – Small (0 – 25%)• 2 – Medium (26 – 74%)• 3 – Large (75 – 100%)
Risk Impact • 1 – Minor Impact • 2 – Significant Impact• 3 – Huge Impact /
Deal Breaker
No talking and write legibly PLEASE!
Possible Owner
Your Name
(you may want to first use an example to discuss with group to determine individual’s different perceptions)
Risk Management – Group Activity
Cindy Margules, PMP Entering the Danger Zone November 2010
In silence:• First person puts sticky notes on white board
(flip chart paper) their guess as to categories
• Second person adjusts categories, adds their risks (combining if required)
• Third person … until last.
• Re-review and categorize with marker (no miscellaneous / 1 – 2 re-categorize).
Risk Management - Group Activity
Cindy Margules, PMP Entering the Danger Zone November 2010
Probability
HIGH 3 6 9
MEDIUM 2 4 6
LOW1 2 3
LOW MEDIUM HIGH
Impact
After notes are agreed upon by team in categories, mark the categories on the back of the sticky notes.
Then, take the notes and re-decide as a group their probability and impact and place them in the appropriate boxes.
Risk Management – Group Activity
Cindy Margules, PMP Entering the Danger Zone November 2010
Next Steps
• The Project Manager enters the risks identified into a risk log and develops plans (with the team) for how to manage those risks
• Risks are reviewed individually and with the team OFTEN: To ensure new ones are captured Identify risks changing wording, impact, probability,
mitigation plans, contingency plans, dates, etc.
Risk Management - Group Activity
Cindy Margules, PMP Entering the Danger Zone November 2010
Thank you!Cindy Margules, PMP
Project Management Office Director, Convio
www.linkedin.com/in/cindymargules