ENGINEERING STANDARD SPECIFICATION Ontario TITLE ENGINEERING AND STUDIES MATERIALS ENGINEERING NDE – SELF-PROPELLED BOOM-SUPPORTED ELEVATING WORK PLATFORMS VALE # SPEC-83052 PAGE 1/17 Last Revision 2020/09/29 REV. 7 1.0 PURPOSE This specification describes the minimum required technical information to conduct the Nondestructive Evaluation in accordance with established Vale practices and industry standards. This standard covers the inspection of in-service self-propelled boom-supported elevating work platforms that have a platform capable of being positioned completely beyond the base and that are used to position personnel, along with their necessary tools and materials, at work locations. This standard does not cover the general maintenance inspections (pre-shift, monthly, etc.) which is covered in the maintenance specifications. 2.0 INSPECTION REQUIREMENTS General inspections performed by operator or HDET is covered in MSPEC-81002. VALE ESTABLISHED NDE PRACTICES Vale established practice for NDE examination is as follows: 2.1.1 NDE Type 1 (MAJOR - STRUCTURAL) All items evaluated while partially or completely disassembled. 2.1.2 NDE Type 2 (Pins only) All items evaluated in place without disassembly GENERAL REQUIREMENTS As per B354.4-02 the following inspections must be carried out on all self-propelled boom-supported elevating work platforms regardless of manufacturer. A complete and concise record of any information concerning regular inspections (daily inspection exempted), tests, maintenance and structural inspections, and electronic and machine repair that have a direct bearing on the safety of the aerial platform shall be kept permanently by the owner. (B354.4-02) 2.1.3 Structural Inspection (NDE – Type 1 Major) Structural inspection shall be performed: - As per frequencies listed in MSPEC-81002. - After any actual, suspected, or potential damage is sustained during an incident that could potentially affect the structural integrity or stability of the aerial platform. Such incidents may include electrical contact, shock loads, fall arrest, collision, or cases of overstressing or stability failure

Upload: others

Post on 25-Mar-2021

3 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: ENGINEERING STANDARD SPECIFICATION Ontarioextportal.vale.com/eng/Sud/standards/pdf/SPEC-83052.pdfMagnetic particle inspection is to be carried out in accordance with ASTM E709 using

ENGINEERING STANDARD SPECIFICATION Ontario

TITLEENGINEERING AND STUDIESMATERIALS ENGINEERINGNDE – SELF-PROPELLED BOOM-SUPPORTED ELEVATINGWORK PLATFORMS

VALE #SPEC-83052

PAGE

1/17Last Revision

2020/09/29

REV.

7

1.0 PURPOSE

This specification describes the minimum required technical information to conduct theNondestructive Evaluation in accordance with established Vale practices and industry standards.

This standard covers the inspection of in-service self-propelled boom-supported elevating workplatforms that have a platform capable of being positioned completely beyond the base and that areused to position personnel, along with their necessary tools and materials, at work locations.

This standard does not cover the general maintenance inspections (pre-shift, monthly, etc.) which iscovered in the maintenance specifications.

2.0 INSPECTION REQUIREMENTS

General inspections performed by operator or HDET is covered in MSPEC-81002.

VALE ESTABLISHED NDE PRACTICESVale established practice for NDE examination is as follows:

2.1.1 NDE Type 1 (MAJOR - STRUCTURAL)

All items evaluated while partially or completely disassembled.

2.1.2 NDE Type 2 (Pins only)

All items evaluated in place without disassembly

GENERAL REQUIREMENTSAs per B354.4-02 the following inspections must be carried out on all self-propelled boom-supportedelevating work platforms regardless of manufacturer.

A complete and concise record of any information concerning regular inspections (daily inspectionexempted), tests, maintenance and structural inspections, and electronic and machine repair thathave a direct bearing on the safety of the aerial platform shall be kept permanently by the owner.(B354.4-02)

2.1.3 Structural Inspection (NDE – Type 1 Major)

Structural inspection shall be performed:- As per frequencies listed in MSPEC-81002.- After any actual, suspected, or potential damage is sustained during an incident that could

potentially affect the structural integrity or stability of the aerial platform. Such incidents mayinclude electrical contact, shock loads, fall arrest, collision, or cases of overstressing orstability failure

Page 2: ENGINEERING STANDARD SPECIFICATION Ontarioextportal.vale.com/eng/Sud/standards/pdf/SPEC-83052.pdfMagnetic particle inspection is to be carried out in accordance with ASTM E709 using

ENGINEERING STANDARD SPECIFICATION Ontario

TITLEENGINEERING AND STUDIESMATERIALS ENGINEERINGNDE – SELF-PROPELLED BOOM-SUPPORTED ELEVATINGWORK PLATFORMS

VALE #SPEC-83052

PAGE

2/17Last Revision

2020/09/29

REV.

7

- After a change of ownership, unless a complete services history is provided, includingmaintenance and inspection records.

2.1.4 PINS (NDE – Type 2 Major)

Certification will include- Nondestructive testing of pins as listed in table- Visual inspection & photo of pressure vessel(s) relief valve to verify, at minimum:

§ Valve number§ Vale make / model§ Date of test or repair§ CRN§ Set Pressure

Note: the relief valves are not installed directly on tank but on a manifold station on the truck.The required information is either on a tag that is held to the relief valve with write (see Figure1 for typical valve layout, Figure 2A for typical tag).

- Visual inspection & photo of pressure vessel(s) nameplate to verify condition. Note:Nameplate is typically on vessel head and covered by metal shield (See Figure 3 for typicalnameplate.)

Figure 1: Typical relief valve on ANFO truck pressure vessel

Circular tag for databasenumbering only

nameplate

Typical tag

Page 3: ENGINEERING STANDARD SPECIFICATION Ontarioextportal.vale.com/eng/Sud/standards/pdf/SPEC-83052.pdfMagnetic particle inspection is to be carried out in accordance with ASTM E709 using

ENGINEERING STANDARD SPECIFICATION Ontario

TITLEENGINEERING AND STUDIESMATERIALS ENGINEERINGNDE – SELF-PROPELLED BOOM-SUPPORTED ELEVATINGWORK PLATFORMS

VALE #SPEC-83052

PAGE

3/17Last Revision

2020/09/29

REV.

7

Figure 2A: Typical pressure relief valve tag

Figure 3: Typical ANFO truck pressure vessel nameplate

Page 4: ENGINEERING STANDARD SPECIFICATION Ontarioextportal.vale.com/eng/Sud/standards/pdf/SPEC-83052.pdfMagnetic particle inspection is to be carried out in accordance with ASTM E709 using

ENGINEERING STANDARD SPECIFICATION Ontario

TITLEENGINEERING AND STUDIESMATERIALS ENGINEERINGNDE – SELF-PROPELLED BOOM-SUPPORTED ELEVATINGWORK PLATFORMS

VALE #SPEC-83052

PAGE

4/17Last Revision

2020/09/29

REV.

7

3.0 PRE-NDE REQUIREMENTS (CLEANING AND PREPARATION)

MAGNETIC PARTICLE & VISUAL INSPECTIONSAll items to be free of grease, rust scale and loose paint.

Method of cleaning – sandblasting, steam cleaning, wire brushing and chemical cleaner canbe used.

Note: Any method or combination can be used. If paint is properly adhered, then it does nothave to be removed, as it does not interfere with magnetic particle evaluation.

ULTRASONIC INSPECTION –Clean all pins removed during disassembly. Ensure ends of pins are flat & true. If required,grind ends.

Areas of cleaning and inspection. See sketches for typical vehicle mounted aerial deviceassembly and identification of areas to be cleaned and inspected.

4.0 RESPONSIBILITY

All performing evaluations are to ensure compliance to this specification.

Any deviation from this specification must be noted and is subject to VALE approval.

Preliminary inspection by mechanical or structural engineer should be carried out, whenrequired, to determine the feasibility of a repair.

5.0 PERSONNEL QUALIFICATION

Visual weld inspection shall be performed and documented by a person qualified to therequirements of CSA standard W178.2

Nondestructive Evaluation (NDE) personnel performing the evaluation shall be certified bythe Canadian General Standards Board to standard CAN CGSB-48.9712, Level II, or III orEquivalent to International Certification to ISO 9712 Level II or III in the appropriatemethod(s).

CGSB Level I personnel performing the inspection are to have been certified by the ValeNDE supervisor to be able to perform these inspection or are to work in strict accordance

Page 5: ENGINEERING STANDARD SPECIFICATION Ontarioextportal.vale.com/eng/Sud/standards/pdf/SPEC-83052.pdfMagnetic particle inspection is to be carried out in accordance with ASTM E709 using

ENGINEERING STANDARD SPECIFICATION Ontario

TITLEENGINEERING AND STUDIESMATERIALS ENGINEERINGNDE – SELF-PROPELLED BOOM-SUPPORTED ELEVATINGWORK PLATFORMS

VALE #SPEC-83052

PAGE

5/17Last Revision

2020/09/29

REV.

7

with a written instruction prepared by a CGSB Level II or III. Any suspect indications are tobe reported to a CGSB Level II or III.

6.0 MAGNETIC PARTICLES INSPECTION (MT)

Magnetic particle inspection is to be carried out in accordance with ASTM E709 using the following:

.1 AC yoke with lifting force of 10 lbs.

.2 Dry or wet magnetic particles.

.3 Continuous magnetization.

Area of inspection

.1 In place inspection: All accessible welds, edges and change of sections as per figuresin section 12

Magnetization

.1 Each part must be magnetized in at least two directions approximately at right anglesto each other.

7.0 ULTRASONIC INSPECTION (UT)

Longitudinal ultrasonic inspection is to be carried out in accordance with ASTM E114 using 5.0 or2.25 Mhz transducers with a maximum 15mm diameter.

Inspection to be performed in the axial direction from both ends covering 100% of cross-section andfull length.

Sweep calibration shall be established externally from the part utilizing a suitable calibration standardfor the entire range at a minimum of five points through the range.

Sensitivity shall be established at 6db over 100% of back echo or 100% second back echo whicheveris the lesser.

Each area with grease grooves shall be inspected using a maximum of 5" sweep. This shall beachieved by using the zoom function. Sensitivity shall be established at 80% screen height from thegrease hole in the area inspected.

8.0 VISUAL INSPECTION (VT)

Direct visual inspection is to be carried out using white light.

Page 6: ENGINEERING STANDARD SPECIFICATION Ontarioextportal.vale.com/eng/Sud/standards/pdf/SPEC-83052.pdfMagnetic particle inspection is to be carried out in accordance with ASTM E709 using

ENGINEERING STANDARD SPECIFICATION Ontario

TITLEENGINEERING AND STUDIESMATERIALS ENGINEERINGNDE – SELF-PROPELLED BOOM-SUPPORTED ELEVATINGWORK PLATFORMS

VALE #SPEC-83052

PAGE

6/17Last Revision

2020/09/29

REV.

7

9.0 NDE ACCEPTANCE CRITERIA

All methods: No linear discontinuities are acceptable. Inherent discontinuities may be acceptable ifapproved by design engineer.

Ultrasonic inspections

All indications greater than 20 % reference shall be fully investigated. Discontinuity rejection is basedon an indication of greater than 20 % reference screen height.

Inspection of welds as per CSA W59 dynamically loaded structures.

10.0 REPAIR PROCEDURE

Repair is to be approved by a Professional Engineer or OEM. Methodology shall include the followingdetails, at minimum:

· Welding in accordance with CSA W47.1 and W59.

· Cleaning / degreasing method

· Defects are to be removed by grinding or gouging.

· Defect removal shall be verified using magnetic particle method (MT) prior to welding

· All repair welding shall be verified using MT

11.0 NDE REPORT

The report shall include following, at minimum:

1. Background information.

2. Detailed description of evaluated items.

3. Name & signature of the inspector.

4. Method used for evaluation of each item.

5. Date of inspection.

6. Reference drawing when applicable.

7. Qualification of the inspector to the method used.

Page 7: ENGINEERING STANDARD SPECIFICATION Ontarioextportal.vale.com/eng/Sud/standards/pdf/SPEC-83052.pdfMagnetic particle inspection is to be carried out in accordance with ASTM E709 using

ENGINEERING STANDARD SPECIFICATION Ontario

TITLEENGINEERING AND STUDIESMATERIALS ENGINEERINGNDE – SELF-PROPELLED BOOM-SUPPORTED ELEVATINGWORK PLATFORMS

VALE #SPEC-83052

PAGE

7/17Last Revision

2020/09/29

REV.

7

8. All recordable discontinuities or indications on a sketch showing size and location.

9. A clear statement of acceptance with reference to specification acceptance criteria.

10. Extent of inspected area.

11. Description of test method.

12. Equipment used.

Page 8: ENGINEERING STANDARD SPECIFICATION Ontarioextportal.vale.com/eng/Sud/standards/pdf/SPEC-83052.pdfMagnetic particle inspection is to be carried out in accordance with ASTM E709 using

ENGINEERING STANDARD SPECIFICATION Ontario

TITLEENGINEERING AND STUDIESMATERIALS ENGINEERINGNDE – SELF-PROPELLED BOOM-SUPPORTED ELEVATINGWORK PLATFORMS

VALE #SPEC-83052

PAGE

8/17Last Revision

2020/09/29

REV.

7

12.0 TYPES OF SELF-PROPELLED BOOM-SUPPORTED ELEVATING WORK PLATFORMS

ANFO LOADER – MARCOTTE

Page 9: ENGINEERING STANDARD SPECIFICATION Ontarioextportal.vale.com/eng/Sud/standards/pdf/SPEC-83052.pdfMagnetic particle inspection is to be carried out in accordance with ASTM E709 using

ENGINEERING STANDARD SPECIFICATION Ontario

TITLEENGINEERING AND STUDIESMATERIALS ENGINEERINGNDE – SELF-PROPELLED BOOM-SUPPORTED ELEVATINGWORK PLATFORMS

VALE #SPEC-83052

PAGE

9/17Last Revision

2020/09/29

REV.

7

Page 10: ENGINEERING STANDARD SPECIFICATION Ontarioextportal.vale.com/eng/Sud/standards/pdf/SPEC-83052.pdfMagnetic particle inspection is to be carried out in accordance with ASTM E709 using

ENGINEERING STANDARD SPECIFICATION Ontario

TITLEENGINEERING AND STUDIESMATERIALS ENGINEERINGNDE – SELF-PROPELLED BOOM-SUPPORTED ELEVATINGWORK PLATFORMS

VALE #SPEC-83052

PAGE

10/17Last Revision

2020/09/29

REV.

7

Page 11: ENGINEERING STANDARD SPECIFICATION Ontarioextportal.vale.com/eng/Sud/standards/pdf/SPEC-83052.pdfMagnetic particle inspection is to be carried out in accordance with ASTM E709 using

ENGINEERING STANDARD SPECIFICATION Ontario

TITLEENGINEERING AND STUDIESMATERIALS ENGINEERINGNDE – SELF-PROPELLED BOOM-SUPPORTED ELEVATINGWORK PLATFORMS

VALE #SPEC-83052

PAGE

11/17Last Revision

2020/09/29

REV.

7

Page 12: ENGINEERING STANDARD SPECIFICATION Ontarioextportal.vale.com/eng/Sud/standards/pdf/SPEC-83052.pdfMagnetic particle inspection is to be carried out in accordance with ASTM E709 using

ENGINEERING STANDARD SPECIFICATION Ontario

TITLEENGINEERING AND STUDIESMATERIALS ENGINEERINGNDE – SELF-PROPELLED BOOM-SUPPORTED ELEVATINGWORK PLATFORMS

VALE #SPEC-83052

PAGE

12/17Last Revision

2020/09/29

REV.

7

This Drawing is included for referenceOnly. The item numbers on thisdrawing do not refer to the Table in 12.1

Page 13: ENGINEERING STANDARD SPECIFICATION Ontarioextportal.vale.com/eng/Sud/standards/pdf/SPEC-83052.pdfMagnetic particle inspection is to be carried out in accordance with ASTM E709 using

ENGINEERING STANDARD SPECIFICATION Ontario

TITLEENGINEERING AND STUDIESMATERIALS ENGINEERINGNDE – SELF-PROPELLED BOOM-SUPPORTED ELEVATINGWORK PLATFORMS

VALE #SPEC-83052

PAGE

13/17Last Revision

2020/09/29

REV.

7

ANFO LOADER –MACLEAN GEN 3Item Pins – Detail & Location Proc.

1 Left hand swing cylinder outboard pin UT2 Left hand swing cylinder inboard pin UT3 Right hand swing cylinder outboard pin UT4 Right hand swing cylinder inboard pin UT5 Upper turret pin UT6 Lower turret pin UT7 Lower main lift cylinder pin UT8 Upper Main lift cylinder pin UT9 Lower aux lift cylinder pin UT

10 Upper aux lift cylinder pin UT11 Main boom hinge pin UT12 Main extension cylinder pin (turret end) UT13 Main extension cylinder pin (basket end) UT14 Basket tilt cylinder pin (boom end) UT15 Basket tilt cylinder pin (basket end) UT16 Basket mount joint pin UT17 Inner extension cylinder pin turret end (accessible when boom is fully retracted) UT

18 Inner extension cylinder pin basket end (NOT accessible when boom is assembled,It requires disassembly)

UT

19 Pressure relief valve & nameplate VT + photo20 Pressure vessel tank nameplate VT + photo21 Main pedestal MT22 Main pedestal mounting plate on truck MT23 Pedestal boom mount assembly MT24 Main boom MT & VT25 Intermediate boom MT & VT26 Extension boom MT & VT27 Inner extension boom cylinder and bracket MT & VT28 Outer extension boom cylinder MT & VT29 Slave cylinder MT & VT30 Main boom lift cylinder MT & VT31 Left swing cylinder MT & VT32 Right swing cylinder MT & VT33 Basket mounting location MT & VT34 Basket mount / Cylinder mount basket end MT & VT35 Basket mount basket end MT & VT36 Basket tilt cylinder MT & VT37 Basket MT & VT38 Basket Cylinder Mount Boom End MT & VT

Page 14: ENGINEERING STANDARD SPECIFICATION Ontarioextportal.vale.com/eng/Sud/standards/pdf/SPEC-83052.pdfMagnetic particle inspection is to be carried out in accordance with ASTM E709 using

ENGINEERING STANDARD SPECIFICATION Ontario

TITLEENGINEERING AND STUDIESMATERIALS ENGINEERINGNDE – SELF-PROPELLED BOOM-SUPPORTED ELEVATINGWORK PLATFORMS

VALE #SPEC-83052

PAGE

14/17Last Revision

2020/09/29

REV.

7

ANFO NEW STYLE (MACLEAN GEN 3) PINS LOCATIONS

NDE 1,2

7

3,4

6

5

9

1112

10

13

14

15

8

Item 18 is located on a cylinder inside the extension boom. Requires 1hrdisassembly for inspection

17

16

35

34

38

Page 15: ENGINEERING STANDARD SPECIFICATION Ontarioextportal.vale.com/eng/Sud/standards/pdf/SPEC-83052.pdfMagnetic particle inspection is to be carried out in accordance with ASTM E709 using

ENGINEERING STANDARD SPECIFICATION Ontario

TITLEENGINEERING AND STUDIESMATERIALS ENGINEERINGNDE – SELF-PROPELLED BOOM-SUPPORTED ELEVATINGWORK PLATFORMS

VALE #SPEC-83052

PAGE

15/17Last Revision

2020/09/29

REV.

7

ANFO NEW STYLE (MACLEAN GEN 3) MAJOR COMPONENTS INSPECTION

22

21

23

2425

2628

Item 27 is located inside the extension boom. Requires disassembly forinspection

29

30

31, 32 33

34, 35

36

37

38

27

Page 16: ENGINEERING STANDARD SPECIFICATION Ontarioextportal.vale.com/eng/Sud/standards/pdf/SPEC-83052.pdfMagnetic particle inspection is to be carried out in accordance with ASTM E709 using

ENGINEERING STANDARD SPECIFICATION Ontario

TITLEENGINEERING AND STUDIESMATERIALS ENGINEERINGNDE – SELF-PROPELLED BOOM-SUPPORTED ELEVATINGWORK PLATFORMS

VALE #SPEC-83052

PAGE

16/17Last Revision

2020/09/29

REV.

7

13.0 REFERENCE DOCUMENTATION

The following documents are related to this specification and shall be used to their latest revision:

ASTM E269 Magnetic particle examination – DefinitionsASTM E709 Magnetic particle examinationASTM E114 Ultrasonic examinations - GeneralASTM E317 Ultrasonic examinations – Evaluating performance characteristicsASTM E500 Ultrasonic examinations - DefinitionsB354.4-02 Self-propelled boom-supported elevating work platformsCSA W59 Welded steel constructionSPEC-83039 QA - New Surface and Underground Elevating Work Platform Quality

Assurance RequirementSPEC-83040 QA - Reconditioned Surface and Underground Elevating Work Platform

Quality Assurance RequirementSPEC-83021 NDE - Ultrasonic and Magnetic Particle examinations of Round Bar StockMSPEC-81002 Lifting and Elevating Device Mobile Equipment Inspection Requirements.

Page 17: ENGINEERING STANDARD SPECIFICATION Ontarioextportal.vale.com/eng/Sud/standards/pdf/SPEC-83052.pdfMagnetic particle inspection is to be carried out in accordance with ASTM E709 using

ENGINEERING STANDARD SPECIFICATION Ontario

TITLEENGINEERING AND STUDIESMATERIALS ENGINEERINGNDE – SELF-PROPELLED BOOM-SUPPORTED ELEVATINGWORK PLATFORMS

VALE #SPEC-83052

PAGE

17/17Last Revision

2020/09/29

REV.

7

14.0 REVISION AND TRANSITION NOTES

Revision notes describe: what was changed, and if applicable, why it was changed, and the plan toimplement the change, including whether changes are retroactive.Note: The revision notes are a summary of the changes and may not necessarily be a complete list.

A risk code is entered for each revision and if applicable, the revision notes will describe how riskwas addressed for the revision.RiskCode Risk Category

A This revision is a minor change and/or introduces no risk.

B Risk has been addressed for this revision by the reviewer and approver. Low risk or no new hazards identified.

C For this revision, a PHR or other risk management tool has been used to address risk and minimize hazards. Thisrisk assessment has been documented and is available through Central Engineering.

Rev Revision Notes RiskCode

Approvedby

Reviewedby

Issue DateYYYY/MM/DD

1 New standard for Self-propelled boom supportedelevating work platforms

PB2013/12/12

AA2013/12/12

2014/01/22

2 Corrections to pages 14,15,16, 17 PB2014/03/26

AN2014/03/26

2014/04/24

3 Added inspection of basket in section 14.0 PB2014/08/28

PB2014/08/28 2014/10/24

4 Clarified diagrams, added ANFO inspection, and removedgen maintenance

KLR2015/06/29

KLR2015/06/29

2015/06/29

5 Updated Section 3.0,6.0, 13.0 PB2016/03/11

PB2016/03/11

2016/03/11

6 Document Format Updated - Removed Inspectionfrequencies already defined in MSPEC-81002 P. Belzile P. Belzile 2016/06/07

7 5 Yr. Review P. Belzile A. Nadeau 2020/09/29