Engineering Procurement Construction (EPC)
Operation & Maintenance
Provision of Technical Manpower
Asset Integrity Services
Vessel Support Services
We are committed to delivering technically challenging mega-projects
safely, on time, on budget
to the highest standard of quality.
“ “
01
VISION STATEMENT
We aim to provide reliable and qualitative services to the Nigerian
energy industry.
10%
30%
60%
MISSIONSTATEMENT
To be Nigeria's best Engineering, Procurement and Construction Company in the energy sector. We will achieve this by:
¤ Leading the industry in HSE, performance and environmental stewardship
¤ Developing a sustainable and diverse business
¤ Attracting and retaining smart, flexible, and adaptable people
¤ Adapting to changing markets and consistently delivering as sold to our customers
02
C O R E V A LU E S
We are committed to delivering technically challenging mega-projects safety, on time, on budget, to the highest standard of quality.
Performance Excellence:
We provide the highest quality product for the best cost and deliver on what we promise.
Mutual respect, integrity, honesty and open communication at all levelsare the driving force for how we build relationships with our staff, clients, contractors and suppliers.
We are driven by an unwavering promise to keep our people and sites “100% Safe.”
Environmental protection and social responsibility - the foundations of sustainable development - are integral to our continued
Safety:
Sustainability:
Ethics:
Fair Return:
03
Operational
Philosophy
01We are committed to providing a safe and healthy work place for our employees and partners, ensuring operations are carried out in the manner that protect personnel, the environment and the host communities.
SAFETY
02We carefully design every process to yield the highest organizational excellences and greatest client satisfaction. Quality is carefully contained in our culture and it's in the fabric of our organization.
QUALITY
03We carefully design every process to yield the highest organizational excellences and greatest client satisfaction. Quality is carefully contained in our culture and it's in the fabric of our organization.
COST EFFECTIVENESS
04Our collective corporate strategies is to systematically accelerate the transfer of technology, engineering experience, and specialized know-how from our expatriates and foreign technical partners to indigenous nationals.
LOCAL CONTENT DEVELOPMENT
04
ndexPro International Services Limited is registered in Nigeria and located
Iour representative offices in Lagos, Port-Harcourt, Rivers State, and Eket,
Akwa Ibom State of Nigeria to support Oil and Gas Business in Nigeria and
the West African Sub-region, providing maximum local resources deployment
and also to ensure accessibility and quick response to EPC needs of most Oil
and Gas operators in Nigeria with the most efficient cost and timely delivery.
We also have our International office in Houston TX, USA.
We are a company of choice to many major operators and assets owners in
Nigeria, with a track record consistently delivering successful projects.
IndexPro delivers engineering solutions ranging from conceptual studies to
FEED, detailed engineering design and follow-on.
IndexPro Construction and Engineering Teams have robust diversified
experience in fabrication and installations on topside and floating vessels.
We deliver sea fastening operations on vessels and fabrication and
installation aids for deep water wellhead installation programs.
IndexPro delivers a complete range of procurement solutions, We cover both
fixed platforms, floating and sub-sea production systems. We have executed
successful materials delivery project for our clients on major projects.
IndexPro has extensive offshore operation and maintenance experience,
deploying some of the industry's most experience personnel with over 20 years
in running the operation of fertilities including FPSOs, FSOs, Flow Stations and
Offshore Platforms.
ABOUT INDEXPRO
05
We aim to provide reliable and qualitative services
to Nigerian energy industry.“ “
06
ENGINEERING
IndexPro provides broad range of professional services for Fixed Platforms, Marine and
Offshore Projects, including:
¤ Conceptual /FEED / Detail / Production Engineering Design & Analysis
¤ Construction Management
¤ Modification Design & Analysis of Marine Structure
¤ Project Feasibility Studies (New-Build/Conversion/Modification)
¤ On-Site Supervision / Technical Support / Survey
¤ Analysis for Naval Architecture & Anchor Mooring
¤ Engineering Drawings/Analysis Reports for Client Approvals and
Classification Society Verifications.
07
CONSTRUCTION
08
¤ Health, Safety and Environment Management
¤ Field Engineering
¤ Quality Assurance
¤ Contracts Management
¤ Field Procurement
¤ Materials Management
¤ Field IT Support
¤ Field Project Controls
¤ Constructability Analysis
¤ Construction Planning.
At IndexPro, Construction Management (CM) is our core strength. IndexPro's CM Team is
composed of seasoned experts and line leadership who have experience steering some
of the most complex construction jobs in the energy sector.
IndexPro offers complete construction management services by outsourcing some of the
best hands in the construction industry for project execution. Our CM services include:
OFFSHORE AND ONSHORE | FLOATING & FIXED PLATFORMS
09
TOTAL CORROSION MANAGEMENT
¤ Corrosion Audits / Inspections
¤ Provision of Skilled Personnel
¤ Surface Preparation and Painting
¤ Scaffolding Services
¤ Rope Access Services
¤ Supply of Equipment such as UHP Units, Air Compressors, Airless Spray Pumps, Etc.
IndexPro International Services offers comprehensive corrosion management solutions,
in-situ, for FPSOs, platforms and rigs both onshore and offshore, including customized
and comprehensive auditing, inspection, planning, execution and project management
services. The company's total corrosion management solutions for the marine and
offshore industry include:
10
11
One important component ofCorrosion Management, and one that is comonly usedby IndexPro in the upstream Oil and Gas industry, is the use of Corrosion Inhibitors.
PROCUREMENT SERVICES
SUPPLIES OF HIGH PRESSURE VALEVES & PIPING SYSTEMS
IndexPro with wide range of partnerships with OEMs offers high quality, quick and efficient
service when it comes to wide variety high pressure valves, fittings and piping solutions.
12
¤ PIPES
¤ MANIFOLD FITTINGS
¤ ANSIB 16.9 FITTINGS
¤ DRILLING VALVES
¤ TOPSIDE VALVES
¤ SUB-SEA VALVES
¤ FLANGES AND CONNECTORS
¤ MANIFOLDS
¤ HOSES
¤ SUB-SEA FITTINGS AND FLANGES
¤ COMMISSION, SERVICE
AND MAINTENANCE
13
14
Clientele/Partners
w w w. i n d e x p ro l td . co m
15
Above Ground and Under Ground Piping
Fabrication and Erection of Structural Pipe
Support and Piping for Tie-in and Mechanical
Installation on site at Kwale in Delta State.
SCOPE OF WORK8NAME OF CL IENT8
Amazon Energy Ltd. / NAOCTYPE OF CONTRACT8
Kwale Gas Flare Down ProjectD U R AT I O N8 On-going
DAT E :8 July 2018
16
17
18
VESSEL SUPPORT AND OFFSHORE WELDINGAND FABRICATION SERVICES
E X P E R I E N C E S
19
20
IndexPro executed the Front End Engineering, detailed
Engineering and Construction Engineering to cover
the entire Deck Structure, Process Piping and 6” X
15km Pipeline to tie-in the production at Crude
Processing Facility (CPF) to be installed within
NAOC Beneboye Flow Station Perimeter.
IndexPro execute detailed Engineering for
Modification of the existing Metering Package.
The Scope of Service involved Re-engineering
of Mystras Metering Skid and Project
Management for and Commissioning.
Design and Construction of Land-field
location Helipad for Elcrest E&P
SCOPE OF WORK8
TYPE OF CONTRACT8
AKEPO 1 WELLHEAD And 15km Pipeline Design
D U R AT I O N8 6 Months
DAT E :8 July 2013
NAME OF CL IENT8
Oando Exploration/Vandrezzar Energy Services Limited
¤
¤
¤
Material Procurement, Fabrication of the
Bladder Tank Frame. Inspection, Blasting,
Painting and Delivery of 2 Sub-sea Bladder
Containment Tank (PO issued already). Minor
Refurbishment of existing Bladder Containment
Tanks: Inspection, Shot Blasting, Painting and
Delivery of 2 Sub-sea Bladder Containment Tank.
(PO issued already) Minor
Engineering, Procurement of Materials, Fabrication
and Delivery of 1 Sub-sea Bladder Containment Tank
Framework (Mudmat and i-Beam Stands).
Rigging Specifications and Procurement for the Support
Frame and Bladder Containment Tank
Storage, Operation/Deployment and Maintenance
Manuals/ Procedure.
As-Built Drawings for the Sub-sea Bladder Containment
Frame Work.
SCOPE OF WORK8
D U R AT I O N8 24 DAYSDAT E :8 JULY 2014
NAME OF CL IENT8
Snepco/Marine PlatformsTYPE OF CONTRACT8
Sub-Sea Bladder Tank Support
¤
¤
¤
¤
¤
¤
1. Engineering (IFC Drawing Review, Prepared Show
Drawings, Weld Maping and As-Built.)
2. Material Procurement
3. Onshore Fabrication of the Sub-Sea VCM Parking
Stand, Lifting Yoke and 4 No. Hang-off Collars. NDT
Inspection, Padeye Pull Test,blasting, painting
and delivery at Eko Support Base - Lagos
SCOPE OF WORK8
NAME OF CL IENT8
CEONA / Marine Platforms
TYPE OF CONTRACT8
VCM Sub-Sea Parking Stand, Lifting Yoke and Hang-off Collars
D U R AT I O N8 34 Days DAT E :8 Aug 2014
Total Refurbishment:
(I) Load out from MPL base-Onne.
(ii) Refurbishment of A-Frame & WINCH Seafastening Grillage
(iii) Fabrication of 10No. Cruciform Plate
(iv) Blasting and Painting
(v) As-Built (vi) Close out Documentation
(vii) Delivery at MPL Yard - Onne
SCOPE OF WORK8
NAME OF CL IENT8
Marine Platforms
TYPE OF CONTRACT8
A Frame & Winch Sea- Fastening Grillage Refurbishment
D U R AT I O N8 15 Days DAT E :8 Sept 2014|
1) Engineering: (IFC Drawing Review, Raise Technical
Query if any, Prepared Show Drawings, Weld Map
Drawings, and As-Built Drawing.)
2) Procurement and Fabrication and load out to Brawal
Jetty of Stanchion for Rover Nelson, and Jason 51, Concrete
Mattress Deployment Frame and Spreader Bars,
3) Sea-fastening of 128 Nos. Stanchions on River Nelson and
Jascon 55.
SCOPE OF WORK8
NAME OF CL IENT8
Saidel / Marine Platforms
TYPE OF CONTRACT8
Stanchions, Spreader Bars and Conrete Mattress
D U R AT I O N8 15 Days DAT E :8 March 2018|
21
1. Engineering: (IFC Drawing Review, Raise Technical Query if any, Prepared Show Drawings, Weld Map Drawings, and
As-Built Drawing).
2. Procurement: (Material Procurement, Inspection and Verification.
3. Onshore Fabrication: (Fabrication of IUTA Lifting Frame (ii) NDT Inspection, blasting and painting
(iii) Delivery at Quay Side FOT - Onne, (iv) Close Documentation.
SCOPE OF WORK8
NAME OF CL IENT8
CHEVRON / Marine Platforms
TYPE OF CONTRACT8
Fabrication Of IUTA Lifting Frame
D U R AT I O N8 7 Days
DAT E :8 November 2014
1. Engineering: (IFC Drawing Review, Raise Technical
Query if any, Prepared Show Drawings, Weld Map
Drawings, and As-Built Drawing.)
2. Procurement: (Material Procurement, Inspection and
Verification.
3. Onshore Fabrication: (I) Fabrication of
CraneFoundation (ii) Crane Boom Rest Cross Over
Platform and (iv) Crane Pedestral Reinforcement (v) NDT
Inspection (vi) blasting and painting (vii) Delivery at Kidney
Island Port Harcourt (ix) Close Documentation.
SCOPE OF WORK8
NAME OF CL IENT8
Bumi Armada/Rostrum Oil & Gas
TYPE OF CONTRACT8
Fabrication Of Boomrest, Crane Foundation & Crossover Platform
D U R AT I O N8 29 Days DAT E :8 Dec. 2014
22
SOW include the following: key task; labour; materials; tools; facilities; personnel and consumables required to undertake
the preparation; welding and finishing work for the list task below. (I) Deck Strengthening work (ii) On-deck
Strengthening (iii) Under-deck Stiffening (iv) On deck Stiffening (v) Works management - Documentation,
As-built Dossier, Supervision of welding personnel during works onboard, HSE management, Interface
with the Normand Pacific Personnel and Logistics.
SCOPE OF WORK8
NAME OF CL IENT8
CEONA / Marine Platforms Limited
TYPE OF CONTRACT8
Deck Strengthening Onboard the Normand Pacific Project
D U R AT I O N8 14 Days
DAT E :8 October2014
1) Remove section of 6” FO cargo pipeline and carry fabrication to fit new flow
meter which will be supplied by the equipment maker
(2) Remove section of ½ inch fuel supply and return pipeline for port and
starboard main engine, carry out fabrication of the pipeline and
install new flow meters (1 on each fuel supply/ return line)
(3) Remove section 3/8 inch fuel supply and return pipeline for
auxiliary engine No 1 & 2, carry out fabrication of the pipeline
and install new flow meters
4) Install electrical cabinet and cable and keep ready for
termination which shall be carried out by the equipment
supplier
SCOPE OF WORK8
NAME OF CL IENT8
THOME
TYPE OF CONTRACT8
Installation Remote FO Monitoring
D U R AT I O N8 14 Days DAT E :8 Oct 2014
1) Engineering: (IFC Drawing Review, Raise Technical
Query if any, Prepared Show Drawings, Weld Map
Drawings.
2) Procurement:( Material Procurement, Inspection and
Verification.
(3) Key Task; labour; materials; tools; facilities; personnel and
consumables required to undertake the preparation; welding
and finishing work on the Suffer landing.
4) Works management -Documentation, As-built Dossier,
Supervision of welding personnel during works onboard, HSE
management, Interface with the Normand Pacific Personnel and
Logistics.
SCOPE OF WORK8
NAME OF CL IENT8
SNEPCO / Marine Platforms / AGIP
TYPE OF CONTRACT8
Modification of Surfer Landing/ Demob of Normard Pacific
D U R AT I O N8 8 Days DAT E :8 Oct 2014|
1) Seafastening of Equipment, Containers and Structural Frame
work.
2) Works management - Documentation, Material Control,
tool, Consumables, Supervision of welding personnel
during works onboard, HSE management, Interface
with the Normand Pacific Personnel and Logistics.
SCOPE OF WORK8
NAME OF CL IENT8
SNEPCO/LADOL/Marine Platforms
TYPE OF CONTRACT8
Mobilization Support at Sea Eagle
D U R AT I O N8 3 Days
DAT E :8 October 2014
23
24
1. Engineering: (IFC Drawing Review, Prepared Show Drawings, Weld Maping and As-Built.)
2. Material Procurement: Review of Engineering Drawings and Preparation of Sop Drawings.
- Material Procurement. - Fabrication - NDT / Load Test Inspection - Blasting and
Painting. - Loading out and deliver to Onne. E59
SCOPE OF WORK8
NAME OF CL IENT8
CEONA / Marine Platforms
TYPE OF CONTRACT8
PP00011-ABO-12 Well Completion (Installation And Fabrication)
D U R AT I O N8 27 Days
DAT E :8 January 2015
1) Engineering: (IFC Drawing Review, Raise
Technical Query if any, Prepared Show Drawings,
Weld Map Drawings, and As-Built Drawing.)
2) Procurement: (Material Procurement, Inspection
and Verification.
3) Onshore Fabrication: (i) Fabrication of A-Frame and
WINCH Grillage. (ii) Access Platforms (iii) Access Ladder
(iv) Stair Access Platform (v) A-Frame & WINCH Frame
Brackets (vi) NDT Inspection, blasting and painting (iii)
Delivery at Quay Side FOT - Onne, (iv) Close Documentation.
SCOPE OF WORK8
NAME OF CL IENT8
Total / Marine Platforms
TYPE OF CONTRACT8
West Jupiter ROV Project
D U R AT I O N8 16 Days DAT E :8 Jan. 2015
1. Engineering: (IFC Drawing Review, Prepared Show
Drawings, Weld Maping and As-Built.)
2. Material Procurement: Engineering Drawings Reviewed - Preparation of Shop Drawings.
- Material Procurement. - Fabrication of the 4 Nos
Hose Reel and 4 Nos Spreader bar. - NDT Inspection
& Load Test - Blasting & Painting.
- Loading Out and Deliver to FOT Onne.
SCOPE OF WORK8
NAME OF CL IENT8
CHEVRON / Marine Platforms
TYPE OF CONTRACT8
Fabrication of 4 Nos. GE Hose Reel & 4 Nos Spreader Bar
D U R AT I O N8 10 Days
DAT E :8 October 2015
1. Material Procurement, Fabrication of the ROV Blacket Frame
and the ROV Tooling Basket. Inspection, blasting, painting
and delivered at FOT, Onne.
2. Rigging Specification and Load Test for the ROV Tooling
Basket Frame.
3. As-Built Drawings for the ROV Tooling Basket
Frame.
SCOPE OF WORK8
NAME OF CL IENT8
CHEVRON / MPL
TYPE OF CONTRACT8
ROV Tooling Basket
D U R AT I O N8 9 Days
DAT E :8 January 2016
1. Engineering (IFC Drawing Review, Prepared Show Drawings,
Weld Mapping and As-Built.)
2. Material Procurement
3. Onshore Fabrication of the Sub-Sea H-Link.
4. NDT Inspection,Padeye Pull Test,blasting, painting
and delivery at Ladol - Lagos
SCOPE OF WORK8
NAME OF CL IENT8
ARIOSH / OCEAN INSTALLER LTD
TYPE OF CONTRACT8
H-LINK
D U R AT I O N8 10 Days DAT E :8 Feb 2016|
1. Engineering: (IFC Drawing Review, Raise Technical
Query if any, Prepared Show Drawings, Weld Map
Drawings, and As-Built Drawing.)
2. Procurement: (Material Procurement, Inspection and
Verification.
3. Onshore Fabrication: (i) Fabrication of Cargo Skip and
Waste Skip. (ii)NDT Inspection, blasting and painting
(iii) Delivery at Quay Side FOT - Onne, (iv)Close Documentation.
SCOPE OF WORK8
NAME OF CL IENT8
CHEVRON / Marine Platforms
TYPE OF CONTRACT8
Fabrication of Cargo Skip Man Riding Basket, Waste Skip & Gas Rack
D U R AT I O N8 15 Days DAT E :8 July 2015|
25
26
1. Engineering: (IFC Drawing Review, Raise Technical Query if any, Prepared Show Drawings, Weld Map Drawings, and
As-Built Drawing).
2. Procurement: (Material Procurement, Inspection and Verification.
3. Onshore Fabrication: (Fabrication of 4 No. Spreader Beam (ii) NDT Inspection, blasting and
painting (iii) Delivery at Ladol Yard - Lagos, (iv) Close Out Documentation.
SCOPE OF WORK8
NAME OF CL IENT8
ARIOSH / Ocean Installer Ltd.
TYPE OF CONTRACT8
Spreader Bar
D U R AT I O N8 15 Days
DAT E :8 February 2016
1) Engineering: (IFC Drawing Review, Raise Technical
Query if any, Prepared Show Drawings, Weld Map
Drawings, and As-Built Drawing).
2) Procurement: (Material Procurement, Inspection and
Verification.
3) Onshore Fabrication: (Fabrication of 4No. Chutes (ii) NDT
Inspection, blasting and painting (iii) Delivery at Ladol Yard -
Lagos, (iv) Close Out Documentation.
SCOPE OF WORK8
NAME OF CL IENT8
ARIOSH / Ocean Installer Ltd.
TYPE OF CONTRACT8
CHUTE
D U R AT I O N8 16 Days DAT E :8 March 2016
1. Engineering: (IFC Drawing Review, Raise Technical Query if any, Prepared Show Drawings, Weld Map Drawings,
and As-Built Drawing).
2. Procurement: (Material Procurement, Inspection and Verification.
3. Onshore Fabrication: (Fabrication of Manifold Grillage (ii) NDT Inspection, blasting and
painting (iii) Delivery at Ladol Yard - Lagos,
(iv) Close Out Documentation.
SCOPE OF WORK8
NAME OF CL IENT8
ARIOSH / Ocean Installer Ltd.
TYPE OF CONTRACT8
Manifold Grillage
D U R AT I O N8 5 Days
DAT E :8 March 2016
1) Engineering: (IFC Drawing Review, Prepared Show
Drawings, Weld Mapping and As-Built).
2) Material Procurement
3) Onshore Fabrication of the 2Nos 8" & 4" Clamp
4) NDT Inspection, Padeye Pull Test,blasting, painting
and delivery at Ladol - Lagos
SCOPE OF WORK8
NAME OF CL IENT8
ARIOSH / Ocean Installer Ltd.
TYPE OF CONTRACT8
8" AND 4" CLAMP
D U R AT I O N8 8 Days
DAT E :8 March 2016
1) Engineering: (IFC Drawing Review, Prepared Show Drawings,
Weld Mapping and As-Built.)
2) Material Procurement
3) Onshore Fabrication of the 1 No. Production Manifold
Grillage, 2 Nos. Suction Pile Grillage.
4) NDT Inspection, Padeye Pull Test, Blasting, painting
and delivery at FOT Onne
5) Sea-fastening of the fabricated items onboard
African Inspiration
SCOPE OF WORK8
NAME OF CL IENT8
CHEVRON / Marine Platforms Ltd.
TYPE OF CONTRACT8
AGBAMI Phase Three Project
D U R AT I O N8 25 Days DAT E :8 Sept 2017|
1. Material Procurement, Fabrication of the ROV
Grillage (A-Frame and WINCH Frame). Inspection,
blasting, painting and delivered at FOT, Onne.
2. Rigging Specification and Load Test for the ROV A-
Frame and WINCH Frame.
3. As-Built Drawings for the ROV Grillage.
SCOPE OF WORK8
NAME OF CL IENT8
MPN / MPL
TYPE OF CONTRACT8
ROV Grillage (Jascon 55)
D U R AT I O N8 9 Days
DAT E :8 April 2016
27
28
1. Engineering: (IFC Drawing Review, Prepared Show Drawings, Weld Maping and As-Built).
2. Material Procurement
3. Onshore Fabrication of the 1No. Coil Tubing, 1 No.CROSS IWOCS 33 Grillage, 1 No. Moonpool Gillage, 1 No. LARS
Lunching & Recovery system Grillage, 1 No. CROSS WRP Grillage , 1 No. Dive Spread Structural Grillage.
4. NDT Inspection, Padeye Pull Test,blasting, painting and delivery at FOT Onne.
5. Sea-fastening of the fabricated coil tubing onboard BOA Deep C.
SCOPE OF WORK8
NAME OF CL IENT8
SNEPCO / Marine Platforms Ltd.
TYPE OF CONTRACT8
BONGA SIL / LWI Project
D U R AT I O N8 37 Days
DAT E :8 January 2017
1) Material Procurement, Fabrication of the 1 No. Riser
Recovery Frame(Chute), 2 No of Holdback padeyes, 2
No. Drip tray and 2No. Coral Stantion, 1 No. Diving
LARS Grillage, 1 No. Snatch block padeye, 1No Hang Off
Frame
2) Inspection, blasting, painting and delivered at FOT.
3) Sea-fastening of the above mentioned fabricated item
onboard African Vision.
4. As-Built Drawings for the above mentioned fabricated items.
SCOPE OF WORK8
NAME OF CL IENT8
SNEPCO / Marine Platforms Ltd.
TYPE OF CONTRACT8
BOOR Engineering Support Project
D U R AT I O N8 28 Days DAT E :8 May 2017
1) Material Procurement, Fabrication of the 1 No. Suffer
Ladder
2) Inspection, blasting, painting and delivered at FOT.
3) Sea-fastening / Installation of the Suffer Ladder on
board MV PRIMUS.
4) As-Built Drawings for the above mentioned
fabricated items.
SCOPE OF WORK8
NAME OF CL IENT8
SNEPCO / Marine Platforms Ltd.
TYPE OF CONTRACT8
BOOR Engineering Support Project
D U R AT I O N8 13 Days
DAT E :8 September 2017
We are privately owned,
led by active, experienced management
and driven by values that underpin everything we do.
“ “
indexproltd
Km 22, Port Harcourt-Aba Expressway,Port Harcourt, Rivers State.
+234 (0) 818 132 [email protected]