engineering economics lecture 18 project management 6 january 2010
DESCRIPTION
A project is a sequence of unique, complex, and connected activities having one goal or purpose and that must be completed by a specific time, within budget, and according to specifications. A project is a sequence of unique, complex, and connected activities having one goal or purpose and that must be completed by a specific time, within budget, and according to specifications. What is a Project?TRANSCRIPT
Engineering EconomicsEngineering Economics
Lecture 18Lecture 18Project ManagementProject Management6 January 20106 January 2010
What is a project? A Project is a temporary endeavor
undertaken to create a unique product or service.– Temporary– Unique
A project is a A project is a sequence of uniquesequence of unique, , complexcomplex, ,
and and connected activitiesconnected activities having having one goalone goal or or
purpose and that must be completed by a purpose and that must be completed by a
specific timespecific time, , within budgetwithin budget, and , and according according
to specificationsto specifications..
What is a Project?
Project characteristics Endeavors of any size may be a project
– Large and small projects demand different handling
Temporary– Distinguishes projects from operations
Unique– Not the same old thing
What is Project Management?
• a method for organizing tasks• a structured framework to help a group
work productively• tools to aid in task sequencing,
dependency analysis, resource allocation, scheduling, etc.
• tools to track progress relative to plan
• Project management is a set of Project management is a set of principles and tools forprinciples and tools for– DefiningDefining– PlanningPlanning– ExecutingExecuting– Controlling . . . and Controlling . . . and – Completing Completing aa PROJECT PROJECT
What is Project Management?
• Projects are Projects are orientedoriented towards a goal. towards a goal.• There is something There is something uniqueunique about every project. about every project.• Projects have a Projects have a finitefinite duration. duration.• Projects require coordination of Projects require coordination of interrelatedinterrelated
activities.activities.
Project Management Criteria
Why Need Project Management?
1.1. Multiple peopleMultiple people2.2. Multiple resources (labs, equipment, Multiple resources (labs, equipment,
etc.)etc.)3.3. Multiple tasks – some must precede Multiple tasks – some must precede
othersothers4.4. Multiple decision points – approvalsMultiple decision points – approvals5.5. Phased expenditure of fundsPhased expenditure of funds6.6. Matching of people/resources to tasksMatching of people/resources to tasks
Why Projects FailWhy Projects Fail
1.1. Failure to align project with organizational Failure to align project with organizational objectives objectives
2.2. Poor scopePoor scope3.3. Unrealistic expectationsUnrealistic expectations4.4. Lack of executive sponsorshipLack of executive sponsorship5.5. Lack of project managementLack of project management6.6. Inability to move beyond individual and Inability to move beyond individual and
personality conflictspersonality conflicts7.7. PoliticsPolitics
Why Projects Succeed!Why Projects Succeed!
1. Project Sponsorship at executive level2. Good project charter3. Strong project management4. The right mix of team players5. Good decision making structure6. Good communication7. Team members are working toward common goals
Laws of Project ManagementLaws of Project Management
No major project is ever on time, within No major project is ever on time, within budget, budget, Yours will not be the firstYours will not be the first. .
Projects progress quickly until they become Projects progress quickly until they become 90% complete, then they remain at 90% 90% complete, then they remain at 90% complete forever. complete forever.
When things are going well, something will When things are going well, something will go wrong. go wrong.
When things just cannot get any worse, When things just cannot get any worse, they will. they will.
Laws of Project Management
When things appear to be going better, you have When things appear to be going better, you have overlooked something. overlooked something.
No system is ever completely debugged. Attempts to No system is ever completely debugged. Attempts to debug a system inevitably introduce new bugs that are debug a system inevitably introduce new bugs that are even harder to find. even harder to find.
A carelessly planned project will take three times longer A carelessly planned project will take three times longer to complete than expectedto complete than expected
A carefully planned project will take only twice as long. A carefully planned project will take only twice as long. Project teams refuse progress reporting because it Project teams refuse progress reporting because it
manifests their lack of progress. manifests their lack of progress.
Core Project Management Tools
Project CharterProject Charter Work Breakdown Structure (WBS)Work Breakdown Structure (WBS) Project ScheduleProject Schedule Project BudgetProject Budget
Project Charter
What must be done?What must be done?– What are the required resources?What are the required resources?– What are the constraints?What are the constraints?– What are the short and long term implications?What are the short and long term implications?
Why do it?Why do it? When must it be done?When must it be done? Where must it be done?Where must it be done? Who does what?Who does what?
– Who is behind the project?Who is behind the project?– Who is funding the project?Who is funding the project?– Who is performing the work of the project?Who is performing the work of the project?
Project Charter
Who What Where Why When
Project Charter
Project Goal & ObjectiveSponsorStakeholdersTimelineResources requiredDeliverables
• Organize your approach• Generate a credible schedule• Track progress and control your project• Identify where to focus your efforts • Identify problems early – before they are crises• Saves you TIME….MONEY
Why is Project Management Important?
Five Phases of Project Management
Scoping the Project
Developing the Plan
Scoping the Project
Launching thePlan
Monitoring &ControllingClosing Out the
Project
Suggested Steps in Project Management
1.1. Generate a definition of project, goals, constraintsGenerate a definition of project, goals, constraints2.2. Identify project start/end dates, mandatory Identify project start/end dates, mandatory
milestones.milestones.3.3. List constraints – money, equipment, holidays, etc.List constraints – money, equipment, holidays, etc.4.4. Identify tasks to be accomplishedIdentify tasks to be accomplished5.5. Refine detailed task list, dropping/ combining, Refine detailed task list, dropping/ combining, 6.6. Estimate time (person hours, calendar period)Estimate time (person hours, calendar period)7.7. Identify resources (people, money, parts, etc.)Identify resources (people, money, parts, etc.)8.8. Monitor, record progress at least weekly Monitor, record progress at least weekly 9.9. Revise plan as needed to take into account changesRevise plan as needed to take into account changes
Proposal writing. Project planning and scheduling. Project costing. Project monitoring and reviews. Personnel selection and
evaluation. Report writing and presentations.
Management activities
Project Planning: Project Planning: ResourcesResources
• People - skills and value• Facilities• Equipment• Money• Materials• Time
The project plan
The project plan sets out:– The resources available to the project;– The work breakdown;– A schedule for the work.
PROJECT PLAN STRUCTURE
1.1. Introduction.Introduction.2.2. Project organisation.Project organisation.3.3. Risk analysis.Risk analysis.4.4. Hardware and software resource Hardware and software resource
requirements.requirements.5.5. Work breakdown.Work breakdown.6.6. Project schedule.Project schedule.7.7. Monitoring and reporting mechanisms.Monitoring and reporting mechanisms.
Planning the Project:Planning the Project:Work Breakdown Structure Work Breakdown Structure
(WBS)(WBS)
• A WBS is the functional decomposition A WBS is the functional decomposition of a systemof a system
• Breaks the project into chunks of work Breaks the project into chunks of work at a level of detail that meets planning at a level of detail that meets planning and scheduling needsand scheduling needs
Project scheduling
1.1. Split project into tasks and estimate time and Split project into tasks and estimate time and resources required to complete each task.resources required to complete each task.
2.2. Organize tasks concurrently to make optimal Organize tasks concurrently to make optimal use of workforce.use of workforce.
3.3. Minimize task dependencies to avoid delays Minimize task dependencies to avoid delays caused by one task waiting for another to caused by one task waiting for another to complete.complete.
4.4. Dependent on project managers intuition and Dependent on project managers intuition and experience.experience.
End