engineering economics lec5

Upload: mafuzal-hoque

Post on 05-Feb-2018

237 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/21/2019 Engineering Economics Lec5

    1/19

    2/26/20

    $

    ,

    $

  • 7/21/2019 Engineering Economics Lec5

    2/19

    2/26/20

    ,

    Principle:

    How fast can I recover my initial investment?

    Method:

    Based on the cumulative cash flow (or

    accounting profit)

    Screening Guideline:

    If the payback period is less than or equal to

    some specified payback period, the projectwould be considered for further analysis.

    Weakness:

    Does not consider the time value of money

  • 7/21/2019 Engineering Economics Lec5

    3/19

    2/26/20

    Pizza-in-a-Hurry operates a pizza delivery, they use,two eight year-old vehicles for delivery, both of whichare large, consume a great deal of gas and are startingto cost a lot to repair. The owner, Ray, is thinking ofreplacing one of the cars with a smaller, three-year-oldcar that his sister-in-law is selling for $8000. Rayfigures he cansave $3000, $2000, and $1500 per year for the nextthree years and $1000 per year for the following twoyears by purchasing the smaller car. What is the paybackperiod for this decision?

    Example 1

    yearyearyearyear AAAA BBBB

    0 -$1000 -$2783

    1 +200 +1200

    2 +200 +1200

    3 +1200 +1200

    4 +1200 +1200

    5 +1200 +1200

    6 +1200 +1200

    The cash flows for two alternatives are as follows:

    Find the Pay Back Period

  • 7/21/2019 Engineering Economics Lec5

    4/19

    2/26/20

    $1000

    $200

    $1200

    0

    1 2 3 4 5 6

    YearsAnnual

    cashflow

    $200

    $1200 $1200 $1200

    -1000-500

    0

    500

    1000

    1500

    0 1 2 3 4 5 6Years (n)

    2.5 years

    Payback period

    Cumulativecashflow($)

    How long does it take to recover the initialinvestment for Project B in Example 2?

  • 7/21/2019 Engineering Economics Lec5

    5/19

    2/26/20

    A firm is trying to decide which of two weighingscales it should install to check a package-fillingoperation in the plant. If both scales have a 6-yearlife, which one should be selected? Assume an8% interest rate.

    AlternativeAlternativeAlternativeAlternative Cost ($)Cost ($)Cost ($)Cost ($) Uniform AnnualUniform AnnualUniform AnnualUniform AnnualBenefitBenefitBenefitBenefit

    ($)($)($)($)

    EndEndEndEnd ofofofof useful Lifeuseful Lifeuseful Lifeuseful Life(salvage Value) ($)(salvage Value) ($)(salvage Value) ($)(salvage Value) ($)

    Atlas Scale 2000 450 100

    Tom Thumb 3000 600 700

  • 7/21/2019 Engineering Economics Lec5

    6/19

    2/26/20

    Discounted Payback Period

    Principle:How fast can I recover my initial investment

    plus interest?

    Method:

    Based on the cumulative discounted cash flow

    Screening Guideline:

    If the discounted payback period (DPP) is less

    than or equal to some specified payback period,

    the project would be considered for further

    analysis.

    Weakness:

    Cash flows occurring after DPP are ignored

    Autonumerics company has just bought a new

    spindle machine at a cost of $105,000 to

    replace one that had a salvage value of 20,000.

    the projected annual after-tax savings via

    improved efficiency, which will exceed the

    investment cost, are as follows:

    What is the Discounted Pay back Period ?

  • 7/21/2019 Engineering Economics Lec5

    7/19

    2/26/20

    $85,000

    $15,000

    $25,000$35,000

    $45,000 $45,000

    $35,000

    0

    1 2 3 4 5 6

    Years

    Annualcashflow

    Discounted Payback Period Calculation

    Period Cash Flow Cost of Funds

    (15%)*

    Cumulative

    Cash Flow

    0 -$85,000 0 -$85,000

    1 15,000 -$85,000(0.15) = -$12,750 -82,750

    2 25,000 -$82,750(0.15) = -12,413 -70,163

    3 35,000 -$70,163(0.15) = -10,524 -45,687

    4 45,000 -$45,687(0.15) =-6,853 -7,540

    5 45,000 -$7,540(0.15) = -1,131 36,329

    6 35,000 $36,329(0.15) = 5,449 76,778

    **** Cost of funds = (Unrecovered beginning balance) X (interest rate)Cost of funds = (Unrecovered beginning balance) X (interest rate)Cost of funds = (Unrecovered beginning balance) X (interest rate)Cost of funds = (Unrecovered beginning balance) X (interest rate)

  • 7/21/2019 Engineering Economics Lec5

    8/19

    2/26/20

    Two equivalent pieces of quality inspectionequipment are being considered for purchase bySquare D Electric. Machine 2 expected to beversatile and technologically advanced enoughto provide net income longer than machine 1.Assume i= 15%.

    Machine 1 Machine 2

    First cost($) 12,000 8,000

    Annual NCF($) 3,000 1,000(years 1-5)3,000(years 6-14)

    Maximum life (years) 7 14

  • 7/21/2019 Engineering Economics Lec5

    9/19

    2/26/20

    Principle: Compute the equivalent net surplus at n = 0 for a given

    interest rate of i.

    Decision Rule for Single Project Evaluation: Accept the project if the

    net surplus is positive.

    Decision Rule for Comparing Multiple Alternatives: Select the

    alternative with the largest net present worth.

    2 3 4 5

    0 1Inflow

    Outflow

    0

    PW(i)inflow

    PW(i)outflow

    Net surplus

    PW(i) > 0

  • 7/21/2019 Engineering Economics Lec5

    10/19

    2/26/20

    $75,000

    $24,400 $27,340$55,760

    01 2 3

    outflow

    inflow

    An electrical motor rated at 15HP needs to bepurchased for $1,000.

    The service life of the motor is known to be 10years with negligible salvage value.

    Its full load efficiency is 85%.

    The cost of energy is $0.08 per kwh.

    The intended use of the motor is 4,000 hoursper year.

    Find the total cost of owning and operating themotor at 10% interest.

  • 7/21/2019 Engineering Economics Lec5

    11/19

    2/26/20

    0 1 2 3 4 5 6 7 8 9 10

    $4,211

    $1,000

  • 7/21/2019 Engineering Economics Lec5

    12/19

    2/26/20

    Given: Cash flows and MARR (i)

    Find: The net equivalent worth at aspecified period other thanpresent, commonly the end ofproject life

    Decision Rule: Accept the project ifthe equivalent worth is positive.

    $75,000

    $24,400 $27,340$55,760

    01 2 3

    Project life

    NFW is based on the equivalent worth of all cash inflows and outflows at theend of the study period at an interest rate that is generally the MARR.

    A $45,000 investment in a new conveyor

    system is projected to improve throughput and

    increasing revenue by $14,000 per year for five

    years. The conveyor will have an estimated

    market value of $4,000 at the end of five years.

    Using FW and a MARR of 12%, is this a good

    investment?

  • 7/21/2019 Engineering Economics Lec5

    13/19

    2/26/20

    NFW = -$45,000(F/P, 12%, 5)+$14,000(F/A, 12%, 5)+$4,000

    NFW = $13,635.70 >0.0

    NFW = -$45,000(1.7623)+$14,000(6.3528)+$4,000

    Higgins Corporation (HC) has developed a robot called Helpmate The firm would need a new plant for manufacturing. Plant could be built and would be ready for production in 2 years 12 hectares site is needed (could be purchased with a cost of 1.5

    million in year 0 ) Building construction would begin early in year 1 and continue

    throughout year 2 Building cost 10 million (4 million at the end of year 1 and 6 million

    at the end of year 2) Manufacturing equipment 13 million at the end of year 2 After termination land after tax worth 2 million , building 3 million

    and equipment 3 million The plant would begin operation at the beginning of year 3, first cash

    flow at the end of year 3 and economic life is 6 years i = 15%

  • 7/21/2019 Engineering Economics Lec5

    14/19

    2/26/20

    Barcewell, built a hydroelectric plant using his personal savings

    of $800,000

    Power generating capacity of 6 million kwhs

    Estimated annual power sales after taxes - $120,000

    Expected service life of 50 years

    Was Bracewell's $800,000 investment a wise one?

    How long does he have to wait to recover his initial investment,

    and will he ever make a profit?

  • 7/21/2019 Engineering Economics Lec5

    15/19

    2/26/20

  • 7/21/2019 Engineering Economics Lec5

    16/19

    2/26/20

    Principle: PW for a project with an annual receipt ofA over

    infinite service life

    Equation:

    CE(i) =A(P/A, i, ) =A/i

    A

    0

    P = CE(i)

    Capitalized worth is a special case of the present worth, it is the

    present worth of all revenues or expenses over an infiniteproject life time.

    Capitalized costExpenses only

    10

    $1,000

    $2,000

    P = CE (10%) = ?

    0

    Given: i= 10%, N=

    Find: Por CE (10%)

  • 7/21/2019 Engineering Economics Lec5

    17/19

    2/26/20

    10

    $1,000

    $2,000

    P = CE (10%) = ?

    0

    Construction cost = $2,000,000

    Annual Maintenance cost = $50,000

    Renovation cost = $500,000 every 15 years

    Planning horizon = infinite period

    Interest rate = 5%

  • 7/21/2019 Engineering Economics Lec5

    18/19

    2/26/20

    $500,000 $500,000 $500,000 $500,000

    $2,000,000

    $50,000

    0 15 30 45 60

    Years

    Solution:

    Construction CostP1 = $2,000,000

    Maintenance Costs

    P2 = $50,000/0.05 = $1,000,000

    Renovation Costs

    P3 = $500,000(P/F, 5%, 15)

    + $500,000(P/F, 5%, 30)

    + $500,000(P/F, 5%, 45)

    + $500,000(P/F, 5%, 60)

    .

    = {$500,000(A/F, 5%, 15)}/0.05= $463,423

    Total Present Worth

    P = P1 + P2 + P3 = $3,463,423

  • 7/21/2019 Engineering Economics Lec5

    19/19

    2/26/20

    Concept: Find the effective interest rate per payment period

    Effective interest rate for a 15-year cycle

    i = (1 + 0.05)15 - 1 = 107.893%

    Capitalized equivalent worth

    P3 = $500,000/1.07893= $463,423

    15 30 45 600

    $500,000 $500,000 $500,000 $500,000