Page 1: ENGINEERING & CONSTRUCTION FY21 OPPORTUNITIES

US Army Corps of Engineers ®

ENGINEERING & CONSTRUCTION FY21 OPPORTUNITIES

Mark W. Sutton, P.E. Lead Civil Engineer Huntington/Great Lakes & Ohio River Division/Engineering & Construction Division 8 October 2020

Page 2: ENGINEERING & CONSTRUCTION FY21 OPPORTUNITIES

I

2

ENGINEERING & CONSTRUCTION DIVISION — Responsible for providing leadership, management, strategic planning, regionalization,

resource balancing and development, staff supervision, integration, unification and implementation of policies regarding engineering and construction work throughout the Huntington District.

— Responsible for all construction program requirements, including contract and construction management, quality assurance, and technical services.

— Responsible for performing supervision of EPA superfund work assignments in Ohio and West Virginia; grant assistance for HUD in West Virginia and part of Ohio; and military DERP projects in West Virginia and part of Ohio.

Page 3: ENGINEERING & CONSTRUCTION FY21 OPPORTUNITIES

3

ENGINEERING & CONSTRUCTION DIVISION

August W. Martin, PE, PMP Chief, Engineering and Construction Division

Shane D. Hall, PE William A. Miller, PE Deputy Chief, Engineering and Construction Division Chief, Design Branch

Chief, Construction Management and Field Support Branch

Page 4: ENGINEERING & CONSTRUCTION FY21 OPPORTUNITIES

4 4

LRH A/E OPPORTUNITIES FY21 Opportunity Location Release Date

(Qtr) NAICS Est Value SBSA / Unrestricted

Solicitation Type

Engineering and Construction Management

Corps-Wide 1Q FY21 541330 $90M Unrestricted IDIQ

Hazardous, Toxic, Radioactive Waste Division-Wide 2Q FY21 541620 $3M TBD IDIQ

Planning Services for PCXIN & PPM Division-Wide 1Q FY21 541330 $15M SBSA IDIQ

Geotechnical Services Division-Wide 2Q FY21 541330 $15M SBSA IDIQ

Value Engineering Services Division-Wide 2Q FY21 541330 $50M SBSA IDIQ

Cost Engineering Services Division-Wide 3Q FY21 541330 $10M SBSA MATOC IDIQ

Engineering Design Services Division-Wide 1Q FY21 541330 $25M SBSA IDIQ

Geospatial Services Division-Wide 2Q FY21 541330 $3M SBSA IDIQ

Page 5: ENGINEERING & CONSTRUCTION FY21 OPPORTUNITIES

5 5

LRH CONSTRUCTION OPPORTUNITIES FY21 Opportunity Location Release Date

(Qtr) NAICS Est Value SBSA / Unrestricted

Solicitation Type

Various Small Construction Projects IDIQ

Division-Wide 1Q FY21 237990 $100M SBSA RFP MATOC

Clendening Tunnel Repair

Clendening, OH 3Q FY21 237990 $1M - $5M TBD TBD

Delaware Dam Filter Blanket Delaware, OH 1Q FY21 237990 $1M - $5M TBD TBD

Streambank Erosion (Section 14, P.L. 79-526)

Newark, OH TBD 237990 $1M - $5M TBD TBD

DSM - Box Culvert and I Wall at Mohicanville Lake/Dam

Mohicanville, OH 3Q FY21 237990 $5M - $10M SBSA IFB

Hydraulic Power Unit Replacement

Reedsville, OH 2Q FY21 237990 $5M - $10M SBSA IFB

Page 6: ENGINEERING & CONSTRUCTION FY21 OPPORTUNITIES

6 6

LRH CONSTRUCTION OPPORTUNITIES FY21

Opportunity Location Release Date (Qtr) NAICS Est Value SBSA /

Unrestricted Solicitation

Type Iaeger Town Hall Demo and Construction

Iaeger, WV 2Q FY21 237990 $1M - $5M SBSA TBD

Tainter Gate Cleaning/Painting

Paint Creek, OH 3Q FY21 237990 <$1M SBSA RFQ

Magnolia Levee Repair/Culvert Installation

Magnolia, OH 3Q FY21 237990 $1M - $5M TBD TBD

Portsmouth Levee Repair, Cut-Off Wall

Portsmouth, OH 1Q FY21 237990 $25M - $100M Unrestricted RFP

Lower Mud River FRM Project Milton, WV 2Q FY21 237990 $25M - $100M Unrestricted TBD

Regional Dredging Support Division-Wide 4Q FY21 237990 $45M Unrestricted RFP

Haysi Municipal Building Haysi, VA 3Q FY21 237990 $1M - $5M SBSA TBD

Page 7: ENGINEERING & CONSTRUCTION FY21 OPPORTUNITIES

7 7

LRH SERVICES OPPORTUNITIES FY21 Opportunity Location Release Date

(Qtr) NAICS Est Value SBSA / Unrestricted

Solicitation Type

Demolition and Remediation Services

Division-Wide 3Q FY21 562910 $5M SBSA RFP

Drydock Repairs to Barge 792 (R3F Fleet)

TBD TBD 336611 N/A TBD RFQ

Drydock Repairs to M.V. Evanick TBD 1Q FY21 336611 N/A TBD RFQ

Drydock Repairs to Derrick Boat 65 TBD 1Q FY21 336611 N/A TBD RFQ

Pump Overhauls (R3F Fleet) TBD TBD 333914 N/A SBSA RFP

Fire Suppression System Update for Pittsburgh Repair Station

Pittsburgh, PA 3Q FY21 238220 N/A SBSA RFP

Page 8: ENGINEERING & CONSTRUCTION FY21 OPPORTUNITIES

8 8

LRH SERVICES OPPORTUNITIES FY21 Opportunity Location Release Date

(Qtr) NAICS Est Value SBSA / Unrestricted

Solicitation Type

Tow Haulage Units at Winfield Dam Winfield, WV 1Q FY21 333613 N/A TBD RFP

Elevator Inspection and Repair Services

District-Wide 1Q FY21 333921 $1M - $5M Unrestricted IDIQ

Metal Fabrication Services District-Wide 1Q FY21 332312 <$25M SBSA IDIQ MATOC

Mowing and Maintenance Services

Alum Creek, OH 1Q FY21 561730 <$1M SBSA IDIQ

Mowing and Maintenance Services

Delaware, OH 1Q FY21 561730 <$1M SBSA IDIQ

Mowing and Maintenance Services

Paint Creek, OH 1Q FY21 561730 <$1M SBSA IDIQ

Mowing and Maintenance Services

Paintsville, KY 1Q FY21 561730 <$1M SBSA IDIQ

Page 9: ENGINEERING & CONSTRUCTION FY21 OPPORTUNITIES

9 9

LRH SERVICES OPPORTUNITIES FY21 Opportunity Location Release Date

(Qtr) NAICS Est Value SBSA / Unrestricted

Solicitation Type

Mowing and Maintenance Services

Lower Tuscarawas,

OH 1Q FY21 561730 $1M - $5M SBSA IDIQ

Cleaning and Janitorial Services Sutton, WV 1Q FY21 561720 <$1M SBSA IDIQ

Cleaning and Janitorial Services

Summersville, WV 1Q FY21 561720 <$1M SBSA IDIQ

Real Estate Title Evidence Services

Southwestern VA 1Q FY21 541110 <$1M SBSA IDIQ

Real Estate Appraisal Services

Southwestern VA 1Q FY21 531320 <$1M SBSA IDIQ

Real Estate Title Evidence Services Eastern KY 1Q FY21 541110 <$1M SBSA IDIQ

Water Quality Testing Services District-Wide 1Q FY21 541380 $1.5M (Not-to-

Exceed) Unrestricted IDIQ

Park Attendant Burnsville, WV 2Q FY21 561720 <$500K SBSA IDIQ

Park Attendant Summersville, WV 2Q FY21 561720 <$500K SBSA IDIQ

Page 10: ENGINEERING & CONSTRUCTION FY21 OPPORTUNITIES

l ·, I

I

J .

L ! ~ .,

W"l','/E

:., -l

MIiton I

lOO.Q/i

10

LOWER MUD RIVER FLOOD RISK MANAGEMENT

Lower Mud River Basin ► Extends from its confluence with

Middle Fork in Hamlin to the mouth of Mud River in Barboursville

► Milton is the major flood damage center in basin

• Over 450 residential and 160 commercial structures located within the 500-year floodplain

Milton, West Virginia ► Located 19 miles above the mouth

of Mud River ► Growing population currently

estimated at 2,600

Milton, West Virginia

Page 11: ENGINEERING & CONSTRUCTION FY21 OPPORTUNITIES

11

LOWER MUD RIVER FLOOD RISK MANAGEMENT

Flood of record occurred in March 1997 ► Estimated 3.7% annual chance of

exceedance (27-year flood event) ► Caused over $23M dollars in damage

(1997 price levels) $42M in FY18 price level

► Damaged approximately 360 residential structures, 80 businesses, and 20 public and institutional buildings including two schools

► Inundated portions of US Route 60 – cutting off access for emergency response

March 1997 Flood – Flood of Record Similar flood events occurred in 1913, 1939, 3.7% annual chance of exceedance (27-year flood event) and 1978

More recent events have occurred in 2015 and 2018

History of Flooding Major Floods in 1913, 1939, 1978, 1997, 2003, 2015, & 2018

Page 12: ENGINEERING & CONSTRUCTION FY21 OPPORTUNITIES

12

LOWER MUD RIVER FLOOD RISK MANAGEMENT City of Milton

Simulated 1% Annual Chance of Exceedance (100-year Flood Event)

Majority of the City of Milton lies within the 100-yearfloodplain – limiting future economic growth and development

Flood of Record within Milton is estimated at a 3.7% annual chance of exceedance (27-year flood event)

Estimated damage to residential and commercialstructures during the 1% annual chance ofexceedance (100-year flood event) is over $68M ► Damage would occur to approximately 550

structures including 145 commercial structures

Additional consequences associated with flooding ► Life safety risk ► Damage to infrastructure including utilities,

roadways, and bridges ► Vehicle damage ► Cost of emergency response and recovery ► Loss of economic productivity

Page 13: ENGINEERING & CONSTRUCTION FY21 OPPORTUNITIES

13

LOWER MUD RIVER FLOOD RISK MANAGEMENT Overall Site Plan

0.4% Annual Chance of Exceedance (250-year) Levee with Channel Modification Major Project Features:

1. Levee a. ~8300 ft. in length b. ~19 ft. tall on average

2. Pump Stations a. Newman’s Branch b. John’s Branch

3. Gate Closure a. Height: 6.4 ft. b. Width: 33 ft. - 3 in. c. Type: Stop Log

4. Channel Relocation a. ~4200 ft. in length

5. Environmental Mitigation a. Wetland/ Development b. Natural Channel Development

6. Parking Mitigation a. Field Parking Development

250-year Levee Alignment and Channel Modification within Milton, WV

Page 14: ENGINEERING & CONSTRUCTION FY21 OPPORTUNITIES

AC SRaAC \SEE 'TYPICAL SECflON

n;; i:T t

r EXIS I GRO D

~~~~~~~~~~~~-~L. __ _

1' TO TOP OF ROCI<

. s A, 31+60) @ ~ TY=P;;-;;IC-;;c. :=c..cc.=...c= ....:::..;:c:...=....:.:....::c:...::.__ ________ _

FILTER

14

LOWER MUD RIVER FLOOD RISK MANAGEMENT Levee

0.4% Annual Chance of Exceedance (250-year) Levee with Channel Modification

Levee Features: 1. ~8300 ft. in Length 2. 19 ft. in Height (Average) 3. Impervious Earth Fill Composition 4. Cutoff Wall/Seepage Barrier

a. ~7600 ft. in Length b. Variable Depth to Bedrock

5. Aggregate Crest Access Road 6. Aggregate Interior Toe Access Road 7. Filter Drainage 8. Stone Slope Protection

a. Select Sections of River Side

Page 15: ENGINEERING & CONSTRUCTION FY21 OPPORTUNITIES

,, .. , , ••\a,'

"' ,, 1,..,,.----I - " I

,.

[

Iii $ ~

!

r l I )l'tl.&.

n-w· -••••· --•- Ii -.-- I --- -·- -·- --- - -,... ~~ rt--·- I . •~:-.•.:e1--u:11•

1-- -. ~ ~ !Ll'"";lil: !:!!,&ir.

H:::-."'-!!.~·~•#1 .... , ·- I

"

ti 9:\>-'I.., , ....... ._ _l_ E!:i:Nitfl::tm:'!& El k"'"rt!.,,..- ..... , ,1

--• . -=----~~ - ~ ~ - ,==,

I I --,..- ,)

I I .. ~ j . ~ Tl1 ~ rtT Th rtr

'" "

15

LOWER MUD RIVER FLOOD RISK MANAGEMENT Pump Stations

0.4% Annual Chance of Exceedance (250-year) Levee with Channel Modification

1. Newmans’ Branch Pump Station a. Capacity: 63,000 GPM b. 3 Vertical Line Shaft, Mixed

Flow Pumps c. 2 - 6 ft. x 6 ft. Gravity Outfall

Culverts

2. Johns’ Branch a. Capacity: 87,750 GPM b. 3 - Vertical Line Shaft, Mixed

Flow Pumps c. 2 - 8 ft. X 6 ft. Gravity Outfall

Culverts

Page 16: ENGINEERING & CONSTRUCTION FY21 OPPORTUNITIES

.. .... ri ■r mt\ ,-----,. _...,..-

' 1 ; ,, ; ii ~

~ ~

~ ~

_,.v ~ Q .

' ' I I I I I I

~ •-w I I I I

I I I I

,J L -- - ----- ,-jt-, I I I I I I I

Ci ...... 1, I 11 ,

I I

I i I I I

I I I j \

\

............ . ..... "' ' --.. ~ "-~ ~111~" 1n~

11!-''"''1:<FL-.,;;;,;

~r.1/!

...

1 ,

I I I I I I

111 I I

1 I I I I I -· I I I I ,-.. -,-,,- --10 .L-

V I I

/ \ j

_y

I

V

-ELE'.YA, p ',J 1C!al1;;JJ • - 1· •D"

~ ' " (. " S- 1~ r IIIC"I T

lll ■ r , ... I .,...--. ~-· I r 1

' j I

I I I ,r.,s I

! r I .....

[

I I r ....... !

I r , 11 1 I I .I I I

I I I I I ~! I I I I I I I I

-----1-- I I 1- , ,-11-, _ 1 , -:, n I-I I I I I) I

I I I I

I I I I I I I

' ..... \ I

\ \ ., _J

16

LOWER MUD RIVER FLOOD RISK MANAGEMENT Gate Closure

0.4% Annual Chance of Exceedance (250-year) Levee with Channel Modification Stop Log Gate Closure Features:

1. Closure Width: 33’-3” 2. Closure Height: 6-5” 3. Two (2) Support Posts 4. Three (3) Stop Log Bays 5. Storage Building

Typical Storage Building Typical Gate Installation

Page 17: ENGINEERING & CONSTRUCTION FY21 OPPORTUNITIES

17

LOWER MUD RIVER FLOOD RISK MANAGEMENT Channel Relocation

0.4% Annual Chance of Exceedance (250-year) Levee with Channel Modification

Includes: 1. ~4200 LF of New

Channel 2. Two Channel Plugs US

and DS ends of remnant channel

3. Raw Water Intake Structure and Weir

4. Stone Slope Protection on Bends

5. Environmental mitigation/natural channel features

Page 18: ENGINEERING & CONSTRUCTION FY21 OPPORTUNITIES

18

LOWER MUD RIVER FLOOD RISK MANAGEMENT Environmental Mitigation

0.4% Annual Chance of Exceedance (250-year) Levee with Channel Modification

Includes: 1. Natural Channel Features within the

4200 LF of Channel Relocation 2. Wetland Development Along

Relocated Channel and within Select Borrow Sites

Page 19: ENGINEERING & CONSTRUCTION FY21 OPPORTUNITIES

19

LOWER MUD RIVER FLOOD RISK MANAGEMENT Parking Mitigation – WV Pumpkin Festival

0.4% Annual Chance of Exceedance (250-year) Levee with Channel Modification

Mitigation for Cultural Resource 1. Applies to parking for

Pumpkin Festival Only, not for Pumpkin Park Parking.

2. Current Plan Calls for filling Sewage Lagoons and grading them into a parking area.

Page 20: ENGINEERING & CONSTRUCTION FY21 OPPORTUNITIES

I

20

LOWER MUD RIVER FLOOD RISK MANAGEMENT Subcontracting Opportunities

Demolitions Required to remove and dispose of residential and commercial structures acquired

by the Non-Federal Project Sponsor prior to proposed construction activities Seepage Barrier/Cutoff Wall

Component of the levee cross section Pump Stations

Structural Concrete Architectural Infrastructure Mechanical/Electrical

Gate Closure Structural Concrete Structural Steel Mechanical/Electrical Roadway

Environmental Mitigation/Monitoring Wetland development at borrow sites Stream bank development

Page 21: ENGINEERING & CONSTRUCTION FY21 OPPORTUNITIES

I

21

LOWER MUD RIVER FLOOD RISK MANAGEMENT

Construction Contract Structure Phased

Non-Federal Sponsor funding availability Non-Federal Sponsor real estate acquisition

Forecast

Anticipated Construction Contract Advertisement: 2nd Quarter FY21

Start Construction: 4th Quarter FY21