Reconstructionof the Old Fortress barracks
into a recreational–tourist complex with tourist infrastructure
KAMYANETS-PODILSKY
Distans from
Kamyanets-Podilsky, km
Berlin
1112
Bratislava
972
Budapest
783
Bucharest
564
Warsaw
522
Prague
1070
Sofia
1139
Minsk
730
Moscow
1223
Kamyanets-Podilsky
Kamyanets-Podilsky
P R O J E C T O B J E C T I V E S establishing of a recreational – tourist complex with a number of
infrastructure objects on the basis of the state historical architectural monument of Ukraine “Barracks of the Old Fortress”
to carry out health improvement of the people from all over Ukraine
to provide the visitors and tourists of the town with accommodation.
BACKGROUND INFORMATION
Information
about the town
area 27,84 кm2
population103 100 people
Dynamics of the quantity of the town
visitors
2008 alltogether 226 400 peopleincluding
foreigners17 900 people
2009 alltogether 202 900 peopleincluding
foreigners.21 000 people
2010alltogether 220 500 peopleincluding
foreigners.12 000 people
Measures indended for popularization
of Kamyanets-Podilsky
opening of the tourist season International festival “Festival of the stone
period” May days of the town (day of the town, cup
laser show on the walls of the Old Fortress International festival “Retrofest” All – Ukrainian festival of aquatic sportsInternational historical festival “The last
capital” International military – historical festival
“Terra-Heroica”;Kamyanets–Podilsky is one of most interesting towns of
Easrern Europe in the historical architectural and cultural plan. The town was also twice nominated in the “Seven wonders of Ukraine”. Therefore, taking into consideration the considerable historical – architectural inheritance of the town, the development of its tourist potential becomes expedient.
Deposit of bromine water of high mineralization
BACKGROUND INFORMATION In the canyon of the Smotricg river between the barracks of the Old Fortress and the main bridge “Strimka Lan’ ” there was
found the deposit of bromine waters of high mineralization in 1999- 2000 years. The usage of the aforementioned water resource for recreation purposes draws additional attention to the project of reconstruction of the barracks of the Old Fortress into a recreational – tourist complex with tourist infrastructure.
Amount of the
mining boreholes
Exploring operational 2
For external treatment applied to
illnesses
of locomorium;
observational 3 central and peripheral of the nervous system;
Power of the deposit
107 m3/per 24 hourscardiovascular system;
organs of the female reproductive system;
allergodermias.
Water according to chemical
composition
Chloride sodium 11,4-14,0 g/dm3
For internal application diluting to 8 g/dm3 used for
treatment
gastrointestinal tract;
Hepatobiliary system and pancreas;With the content of bromine
22-28 mg/dm3 genito- urinary ways;
Metabolism and endocrine gland.
Complex of buildings of the Old Fortress
barracks 2 190 m.
945 m.
The distance on the town highways from the deposit to the complex of buildings of the
barracks of the Old Fortress constitutes 3750 m.
PECULIARITIES OF THE PROJECT
the project of reconstruction of the barracks of the Old Fortress into a recreational – tourist complex with tourist infrastructure includes the maintainance of the authentic facades ;
the project is at the same time of recreational and tourist orientation and this fact draws investors attention and increases its profitability;
the investor will be exempt from rental payment for the occupiend territory during the reconstruction of the object in order to spend the mentioned money for the arrangement of access roads to the complex .
Infrastructure of the recreational – tourist complex Number of units Area,
m2 .
A sat of rooms which can be arranged into a sanatorium or hotel complex, among them there ere the following: 120 4 000
De-luxe rooms (VIP) 40 2 200
First-rank rooms 60 1 440
Second- class rooms 20 360
Conference halls and rooms for the conducting of business negotiations and meetings 4 260
Conference hall №1 1 100
Conference hall №2 1 100
A hall for the conducting of businesses and meetings №1 1 30
A hall for the conducting of businesses and meetings №2 1 30
A restaurant room sits 150 people 475
wine sampling room 1 100
A banquet – room is in style of the late Middle ages (sits 50 people) 1 250
A pub (sits 32 people) 1 125
Sports and fitness complex 1591
swimming – pools including: 3 200
An outdoor swimming pool with a ground for beach – beds and tables for 80 visitors 1 80
An indoor swimming – pool with heating 1 120
Hydromassage swimming – pool 1 30
pump room 1 61
gym 1 150
Finnish sauna( Russian bath-house) 1 150
Tennis courts 2 200
Sports grounds (basket – ball, volley – ball) 2 600
Parking 1 600
THE STRUCTURE OF THE PROJECT RECONSTRUCTION OF THE OLD FORTRESS BARRACKS INTO A RECREATIONAL–TOURIST COMPLEX WITH TOURIST INFRASTRUCTURE
General building plan
A sketch layout of the interblock view of the
recreational – tourist complex
Model of recreational- tourist complex
IMPLEMENTATION OF PROJECT PHASES
FIRST PHASEExclusion of the object from the Ukrainian state monuments registration book;Conducting of an auction connected with the transfer of the complex of buildings of barracks of the Old Fortress into the private property;Drawing of the project estimate of expenditures;
SECOND PHASESupply of engineering networks;Implementation of reconstruction of the complex of buildings of barracks of the Old Fortress into a recreational – tourist complex;
THIRD PHASEBeginning of functioning of the recreational – tourist complex;Installation of pump rooms and also recreational infrastructure (manipulation rooms, specialized baths, etc. ).
CALCULATION OF ECONOMIC EFFECT
Type to the roomAmount of the
numbers .Cost of the
numbers, UAH
De- luxe 40 600,00
First rank 60 400,00
Second rank 20 250,00
Average cost to a room 441,60
Gross receipt from the functioning of the recreational-touristcomplex in case its work load is 35% will constitute 6770750UAH(for year ). Calculation[40 х 600 UAH + 60 х 400 UAH + 20 х 250 UAH] х 365daysх0,35==6 770 750 UAH
Gross receipt from the infrastructure of recreational – tourist complex in case the worl load of the restaurant is 30% , the work load of the conference hall is 10%, and the work load of the rest of the objects - 30%, will constitute about – 2 036 150 UAH (for year).
Calculation[150 х 100UAH х 365days х 0,3]+[2500UAH х 365days х 0,1]+[120 people х700UAH х 12month х 0,3]=2 036 150 UAH
ON THE COMPLEX OF RECREATIONAL – TOURIST COMPLEX
ON INFRASTRUCTURE OF THE RECREATIONAL – TOURIST COMPLEX
Name of object of infrastructure
Number of seats
Approximate average cost of an
order,UAH
Restaurant 150 100,00
Conference hall 2500,00
Sports- recreational complex 700,00/in month
From 1 person
ON MAINTENANCE OF PERSONNEL AND RECREATIONAL – TOURIST COMPLEX
Item of expensesApproximate sum, UAH.
Fund remuneration 1 320 000,00
An extra charge salary 487 080,00
Municipal payments 549 000,00
The principal items of expenses related to maintenance of personnel (100 people with an average salary – 1100 UAH) and maintenance of recreational – tourist complex (water – 61000 UAH; heating, hot water – 150000 UAH, electric power – 290000 UAH; communication – 48000 UAH) constitute – 2 356 080 UAH
Calculation1320000+487080+549000=2 356 080 UAH
Location of the object32300, Hospitalna street 14, Kamianets -Podilsky, Khmelnytsky region, Ukraine
Historical referenceA national architectural monument XVII century (safeguard №751)
The owner of the object Kamianets–Podilsky city council
Information about the complex of buildings
Three - storeyed building of the Barracks and two- storeyed building of the headman. General area of apartments are
5 246 m2
Size of the ground area 1,4360 ha
Building project Sketch layout
Sources of financing Money of investors
Approximate amount of investments 50 000 000 UAH.
Approximate term of recoupment 7 years (not taking into consideration price index)
Address of the developer of the project
32300, Vidrodzhennya square 1, Kamianets-Podilsky, Khmelnytsky region, Ukraine
Contacts
City chairman Mykhailo Simashkevych
tel.: +380 3849 5•16•50; 3•60•00;
fax: +380 3849 5•06•00;
e-mail: [email protected]
Information concerning the project of reconstructions of the barracks of the Old Fortress into recreational–tourist complex is with tourist infrastructure