energy storage system for der integration in the...
TRANSCRIPT
Laura Pimpinella Enel Distribuzione
Energy Storage System for DER integration in the GRID4EU Italian Demo
EUW - November 6, 2014
Agenda
� The Italian Demostration
� Electrical Energy Storage System – Capability
– A bit of history
– Functionalities
– Integration with the Grid4EU Architecture
– Connection to the MV Network
– 61850 Information Model
– Network Topology
– Commissioning Process, List of Tests and Roles
� Numerical Simulations
� Conclusions
� Lessons Learnt
www.grid4eu.eu 2
The Italian Demostration
Project Targets, Architecture and Solutions Adopted
3 www.grid4eu.eu
The Italian demonstration
4
Increase the Medium Voltage (MV) network's hosting capacity for Distributed Energy Resources (DER, in particular solar), introducing Active Control and Demand Response of
MV generators, controllable loads and storage
www.grid4eu.eu
Key Figures and Highlights Context
The main driver of the Italian demonstration is the development of RES (Renewable Energy Sources) registered over the past few years in Italy.
HV/MV Substation "Cesena Ovest"
HV/MV Substation “Quarto"
MV/LV Substation “Smistamento"
The project involves: • 2 HV/MV Subs
• +100 MV Subs
• +20 MV Feeders
• +5 MV Generators
• About 35.000 LV
customers impacted
Back feeding phenomenon due to:
• High penetration of RES mostly PV (about 105 MWp)
• Low consumption area in comparison
(peak load ≈80 MW)
Around 60% connected to the MV network
Realization of an advanced control system communicating with the renewable generators, HV/MV & MV/LV substations and storage facility.
Realization of an “always on”, IP standard-based communication solution connecting all the relevant nodes in the network (wireless, wired and PLC)
Installation of a storage facility (1 MVA / 1 MWh) connected to a MV power line
The new solution
5
ControlSystem
HV/MVSubstations
PhotovoltaicFacilities
MV/LVSubstations
Storage
www.grid4eu.eu
Simplified Architecture
Basic Concepts
Increase the MV network hosting capacity
Implement an anti-
islanding system
Test and assess the use
of a storage device for optimized network
management
Implement voltage
control (at all nodes) and power flow
control
Enable the dispatching
of RES
Electrical Energy Storage System • Capability
• A bit of history
• Functionalities
• Integration with the Grid4EU Architecture
• Connection to the MV Network
• 61850 Information Model
• Network Topology
• Commissioning Process, List of Tests and Roles
6 www.grid4eu.eu
Electric Energy Storage System (EESS) – 1 MVA, 1 MWh
www.grid4eu.eu www.grid4eu.eu 7
Lithium-Ion Batteries Apparent Power: 1MVA Capacity: 1MWh
A bit of history …
www.grid4eu.eu 8
Aerial inspection
Foundations
Container Placement
Ready for test! (July 2014)
Enel has installed, closed to the MV substation “Smistamento”, a storage system (1 MVA – 1 MWh), that can be connected to several feeders. A variety of applications provided by electricity storage systems can be identified along the electricity value chain, from generation support over transmission and distribution support to end-consumer uses. DEMO 4 is focusing on a subset of such applications:
Eurelectric view of the EESS functions*
Electric Energy Storage System (EESS) - Functionalities
www.grid4eu.eu www.grid4eu.eu 9
* Source Eurelectric
§ Voltage Control § Capacity Grid Support § Losses Management
Integration with the GRID4EU system architecture: USE CASES
www.grid4eu.eu www.grid4eu.eu 10
Algorithms output P, Q
Detailed description: CIGRE2014
Each sampling time the Control System inside the HV/MV Substation “Quarto” sends commands towards EESS local controllers. Also the switches status (Open/Close) inside the MV/LV Substation can be changed
Connection to the MV network
www.grid4eu.eu 11
Batteries + BMSs Shelter
MV/LV Substation
MV point of connection LV auxiliary
services supply
MV/LV Trasfo + Inverters + main controller Shelter
HMI
61850 Information Model � A model has been developed (state machine diagram) � Logical nodes has been mapped on that model � A file.icd has been implemented
www.grid4eu.eu www.grid4eu.eu 12
Network Topology
www.grid4eu.eu 13
About 10 Km
PS “Quarto”
PS “Cesena Ovest”
EESS
DER
The network topology allows the EESS to be
connected to 5 different MV feeders (belonging to 2 Primary Substations)
EESS Commissioning: Process
� Guidelines for EESS commissioning have been issued by ENEL DISTRIBUZIONE in which Rules and Roles have been defined.
www.grid4eu.eu www.grid4eu.eu 14
Guidelines Commissioning Report
Commissioning Result: q Successful Commissioning q Positive Commissioning with minor notes q Negative Commissioning with major notes q Unsucessful Commissioning
� The commissioning lasts at least 2 weeks, during which the EESS has been tested in order to verify that it is compliant with the tender specifications.
� All the test have been done under the supervision of the supplier technicians.
� The supplier proposes a detailed test cases approved by ENEL technical management office: – Capability – Charging efficiency – Discharging efficiency
– Measurement accuracy – Power quality – System modularity – Signaling, monitoring, communication – LV auxiliary system consumption – Self-dis/charge tests
– Modes of operation
EESS Commissioning: List of Tests and Roles
15
Enel Technical management
Office (ED TMO)
Supplier Technical management Office
(STMO)
Numerical Simulations
Network Topology and Results
16 www.grid4eu.eu
Recalling the Network Topology
www.grid4eu.eu 17
PS “Quarto”
PS “Cesena Ovest”
EESS
DER
Network topology for Simulations
§ 24h horizon, 1h step, voltage range: [0.96 – 1.05 p.u.] [14.40 – 15.75 kV]
§ OLTC, modulaLon of reacLve power from 4 PV plants (G1-‐G4)
§ The baTery is used for reducing voltage drop (3) and for network losses reducLon (1,2)
§ Calculated acLve power modulaLon for the baTery (recharge constraint: 50% Emax at the end of the horizon)
EESS active power exchange
2 1
3
15,6
16,11
15,36
15,74
15.50
15,2
15,3
15,4
15,5
15,6
15,7
15,8
15,9
16
16,1
16,2
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
Vol
tage
kV
Node
Baseline EESS connected to another feeder EESS connected to the feeder
Time: 1 p.m. EESS reactive power exchange
Bus-‐bar
Storage
-1000
-900
-800
-700
-600
-500
-400
-300
-200
-100
0
100
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24
Rea
ctiv
e P
ower
[kV
Ar]
Time [h]
Numerical simulation - some results Voltage Regulation – Feeder A “Active”
Generator
15,6
14,43
15,36
14,2
14,4
14,6
14,8
15
15,2
15,4
15,6
1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21
Vol
tage
[kV
]
Node
baseline EESS connected to the feeder EESS connected to another feeder
§ 24h horizon, 1h step, voltage range: [0.96 – 1.05 p.u.] [14.40 – 15.75 kV]
§ The baTery is used for reducing voltage drop (3) and for network losses reducLon (1,2); the baTery is recharged when favorable (4,5) to be available in the required periods
§ Calculated acLve power modulaLon for the baTery (recharge constraint: 50% Emax at the end of the horizon)
Numerical simulation - some results Voltage Regulation – Feeder B “Passive”
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25-300
-200
-100
0
100
200
300
Time [h]
Pow
er [
kW]
2 1 3
4 5
EESS active power exchange
Time: 1 p.m.
Bus-‐bar
Storage EESS reactive power exchange: About (+) 1MVAr flat, according to
the EESS capabilities
§ 24h horizon, 1h step, voltage range: [0.96 – 1.05
p.u.] [14.40 – 15.75 kV]
§ Summer Sunday: generation > load (partly cloudy
day)
§ The goal of the optimization is to reduce the reverse
power flow, when possible (technical constraints
must be respected)
§ The battery is discharged (2) to be available in the
critical time to absorb the excess of energy (1)
§ Calculated active power modulation for the battery
(recharge constraint: 50% Emax at the end of the
horizon)
0 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 21 22 23 24 25-0.4
-0.3
-0.2
-0.1
0
0.1
0.2
0.3
B Ptot
Time [h]
Pow
er [
MW
]2 2
1
Numerical simulation - some results Reduction of reverse power flow (MV -> HV)
MV bus-bar active power flow
EESS active power exchange
§ EESS is able to contribute effectively to the voltage regulation; it can help HV-MV power flow control too (according to EESS capacity)
§ The optimization horizon can cover from minutes to several
days (reliability of forecast), with a reasonable computation time
§ The EESS cycle efficiency should be taken into account in
comparison to the network losses reduction obtained by the Voltage Regulator (VR)
Conclusions
EESS Commissioning: First lessons learnt
� Software is the risky side of the project 1. Integration with other systems (SCADA ) 2. Cyber Security for maintenance accesses 3. Heterogeneous degree of knowledge among actors
22
� Electromechanical side of the project has a lower degree of criticality due to the ENEL’s high level of expertise
� Personnel Training and new tools are needed for network optimal operations
TLC infrastructure
capable to support
information delivery !
Thanks!
Energy Storage System for DER Integration in the GRID4EU Italian Demo Laura Pimpinella Enel Distribuzione [email protected]
23 www.grid4eu.eu