energy storage and distribution

16
Energy Storage and Distribution

Upload: others

Post on 22-Jan-2022

16 views

Category:

Documents


1 download

TRANSCRIPT

Page 1: Energy Storage and Distribution

Energy Storage and Distribution

Page 2: Energy Storage and Distribution

Energy Technologies Institute www.eti.co.uk0302

The UK’s energy networks will require substantial investment in new capacity, technology development and innovation to accommodate low carbon generation sources to ensure that they are fit for purpose to meet predicted future demand.

Therefore, networks must have the capacity to not only meet peak flow demand, but also build in extra capacity. There is every chance that there will be greater interdependence between networks in the future.

There is scope for significant innovation in the way that energy is delivered to end customers. In the future, there will be an important role for storage technologies to cater for more intermittent supplies. Heat networks may also emerge as a critical new infrastructure requirement and there will be implications for the role of gas in the future energy mix together with investment in gas storage.

Why?

Energy networks enable the transfer of energy. They are capital intensive, long life assets. They have to be robust to the requirements of the wider energy system. They operate within the backdrop of a highly regulated market.

Page 3: Energy Storage and Distribution

The core themes to the ETI’s Energy Storage & Distribution Programme are

●● Adapt and develop networks to enable the delivery of a cost effective and secure future low carbon energy system in the UK.

●● Develop and demonstrate new infrastructure approaches to support the energy transition out to 2050.

Page 4: Energy Storage and Distribution

Energy Technologies Institute www.eti.co.uk04 05

Offshore Connection

●● Research project into the connection of offshore energy to the UK grid system

●● Consideration of the impact of large-scale offshore development

●● Analysis of designs and strategies to collect, manage and transmit energy back to shore

This project examined the specific challenges and opportunities arising from the connection of offshore energy to the UK grid system and considered the impact of large-scale offshore development.

It also looked into the novel electrical system designs and control strategies that could be developed to collect, manage and transmit energy back to shore and identified and assessed innovative technology solutions to these issues and quantified their benefits.

The research was delivered by Sinclair Knight Merz, a leading projects firm with global capability in strategic consulting, engineering and project delivery. This £250,000 project was completed in 2010.

What have we done to date?

Page 5: Energy Storage and Distribution

Network Capacity

●● Research project into new technology solutions that can enhance transmission and distribution capacity in the UK

●● Assessing the feasibility of technologies to provide improved management of power flows and increased capacity

●● Seeking to enable the increased deployment of low carbon energy sources in the UK

The Network Capacity research project identified and assessed new technology solutions that could enhance transmission and distribution capacity in the UK.

It assessed the feasibility and quantified the benefits of using innovative approaches and novel technologies to provide improved management of power flows and increased capacity, enabling the deployment of low carbon energy sources in the UK.

The £600,000 project was undertaken by the management, engineering and development consultancy Mott MacDonald and completed in 2010.

£600kThe £600,000 Network Capacity project was undertaken by the management, engineering and development consultancy Mott MacDonald and completed in 2010.

Page 6: Energy Storage and Distribution

Heat Storage

●● Examination of the feasibility of capturing large quantities of waste heat from power stations and industrial processes then storing it underground

●● Investigation into the cost effectiveness of storing large quantities of heat for long periods of time

●● Evaluating the practicality and technology needs of such storage schemes

Heat is the biggest end use of energy in the UK – most of it is used for heating homes and providing hot water.

This research project examined the feasibility of capturing large quantities of waste heat from power stations and industrial processes and then storing it underground for later use in homes and offices.

It investigated the cost effectiveness and practicalities of storing large quantities of heat for long periods of time to meet a significant proportion of the UK’s winter heat demand. It evaluated the practical limits for this type of storage, the technology development needs and where in the country large-scale heat storage could be most effectively exploited.

International consulting engineers Buro Happold completed the £140,000 research project in 2011.

Continued

Energy Technologies Institute www.eti.co.uk06 07

What have we done to date?

Page 7: Energy Storage and Distribution

Resistive Superconducting Fault Current Limiter

●● Development and demonstration of a resistive superconducting fault current limiter

●● Aim to reduce the impact of faults on electricity distribution networks through improved flexibility and reliability

●● Installation and demonstration on the network at a Western Power Distribution substation

Fault current levels are a barrier to the installation of low-carbon and other distributed generation. Successful management of these fault levels is a key enabler for the growth of smart distribution systems.

Fault current limiters can benefit the networks in a number of ways. They mitigate against network reinforcement and maintain operational flexibility when connecting new generation or large loads to the network, thereby reducing both connection costs and time to connection.

Once developed the limiter will be installed and demonstrated on the network at a Western Power Distribution substation in Loughborough. The project is being led by Applied Superconductor Ltd, and includes E.ON and Rolls Royce.

.

This project is currently on hold due to the administration of Applied Superconductor

Coolant

Cryogenic Cooling

Current Leads

Super Current Limiting Modules

Page 8: Energy Storage and Distribution

Pre-saturated Core Fault Current Limiter

●● Development and demonstration of a pre-saturated core fault current limiter

●● Product design offers advantages of a non-superconducting pre-saturated core fault current limiter with instant response and recovery, a small footprint based on established transformer design and build process

●● Commissioned into service in May 2013 at a UK Power Networks main substation in Newhaven

Designed by GridON, this pre-saturated core fault current limiter uses a direct current coil to magnetically saturate the iron core, providing a very low impedance during normal operation. This is based on combining industry standard proven transformer technology alongside GridON’s concept of magnetic flux alteration to saturate the iron core.

The limiter is fully scalable for use at voltage levels on both distribution and transmission systems. Its design removes the need for superconducting components or associated cryogenic systems.

It was commissioned into service in May 2013 at a UK Power Networks main substation in Newhaven. Here it will be demonstrated in “real life” operation for two years.

E.ON are providing technical assurance expertise and network modelling support for the demonstration. The £4million project is due to complete in the summer of 2015.

Energy Technologies Institute www.eti.co.uk08 09

ContinuedWhat have we done to date?

Page 9: Energy Storage and Distribution

2050 Energy Infrastructure Outlook

●● Research project to provide data on costs and performance of key types of fixed energy infrastructure

●● Helps to understand the infrastructure that will carry energy from where it is generated to where it is consumed

●● Assesses the relevant merits of different infrastructure options given different energy generation and demand scenarios

In order to assess the opportunities for meeting long term emissions reductions targets, it is necessary to understand amongst other things – the costs and performance of the energy infrastructure that will carry energy from where it is generated to where it is consumed.

This £400,000 research project led by international consulting engineers Buro Happold will provide data on the costs and performance associated with key types of fixed energy infrastructure. The scope also includes the identification of possible “grey areas” where it is feasible that technology innovation could significantly influence cost and performance.

It will provide data for the energy vectors of electricity, gas, hydrogen and heat over the period of 2010-2050.

The intention is that the data produced will be used to assess the relative merits of different infrastructure options against different energy generation and demand scenarios.

The research will be complete by the end of 2013.

Page 10: Energy Storage and Distribution

Energy Technologies Institute www.eti.co.uk10 11

●● Demonstration of grid scale energy storage technology on a Western Power Distribution network site

●● Technology developed by Hampshire SME Isentropic - using a combined heat pump/heat engine to generate electricity to create temperature difference for storage efficiency

●● ETI equity investment to support development of the company and its technology to a level of scale

This project is demonstrating the feasibility of a revolutionary new approach to storing electricity at grid scale.

Hampshire SME, Isentropic have developed their own Pumped Heat Electricity Storage (PHES) technology for large-scale energy storage. It uses

an innovative heat pump/engine which converts electrical energy to heat, stored in low cost gravel storage vessels. The process is reversible, with hot gas expanded in the engine to drive a generator with an achievable round trip efficiency of approximately 75%.

Using this technology, the project will develop and demonstrate a cost-effective 1.5MW/6MWh energy storage device that will operate on a Western Power Distribution network site.

The £15.7million project sees ETI become a minority equity shareholder in Isentropic to allow them to develop the business to meet the demands of the project specification. It is scheduled to complete in the summer of 2018.

ContinuedWhat have we done to date?

Distribution Scale Energy Storage Project

Page 11: Energy Storage and Distribution

The programme intends to look at the following aspects:

●● Heat infrastructure development - to understand what options are available for lowering the cost of heat networks, asking how much of an impact they can make

●● Total life cycle cost reduction - developing a methodology for assessing the life cycle costs and benefits of different ways of using, upgrading or replacing network assets

●● Engineering analysis of gas vector transitions - determining what the practical engineering implications are for the UK to undertake major changes in its use of different gases for carrying energy

●● The evolution of future networks - investigating how to progress the transition to future networks

Future activity

Page 12: Energy Storage and Distribution

Energy Technologies Institute www.eti.co.uk12 13

£4-19bn

Innovation in Electricity Networks & Storage technologies could save the UK £4-19billion in deployment costs to 2050

Low carbon technologiesInnovation has the potential to unlock benefits by enabling the deployment of other low carbon technologies

5-36mEstimated potential UK deployment of electric vehicle charging controllers by 2050

£5bnInnovation in energy storage technologies has the potential to yield estimated total system cost savings of £5billion to 2050

Key facts and figuresThese figures are taken from the Low Carbon Innovation Coordination Group Technology Innovation Needs Assessment on Energy Storage

Page 13: Energy Storage and Distribution

£0.2bnInnovation in smart distribution advanced control systems and fault current limiters makes up most of the potential estimated total system cost savings of £0.2billion to 2050

£0.3-1.6tn

The UK could capture a 4% share of a global market with potential cumulative gross value-added of between £0.3-1.6 trillion up to 2050

£6-34bn

Innovation can also help create UK-based business opportunities that could contribute an estimated £6-34billion of GDP to 2050

Page 14: Energy Storage and Distribution

Energy Technologies Institute www.eti.co.uk14 15

About ETI

Energy Storage & DistributionBuildings

Offshore Wind Marine

Carbon Capture & Storage Transport

Distributed Energy

Smart Systems & Heat

Bioenergy

Through its work, the ETI is:

●● Providing new technology and business concepts

●● Generating UK economic development

●● Building a better understanding of the UK’s energy challenges

●● A force for collaboration

●● An informer of policy

It’s industry and government partnership shares risk and creates affordability for the development and demonstration of new low carbon technologies.

The ETI’s projects are delivered by consortiums of project partners. These partners include academia, SME’s, major corporates and global companies. The ETI is forecast to spend £400m over its project portfolio by 2017.

The nine technology programme areas are:

The Energy Technologies Institute (ETI) is a public-private partnership between global energy and engineering companies – BP, Caterpillar, EDF, E.ON, Shell & Rolls-Royce – and the UK Government.

Established in 2007, the ETI’s role is to act as an important link between, academia, industry and government to accelerate the development of low carbon technologies. It brings together engineering projects that develop affordable, secure and sustainable technologies to help the UK address its long term emissions reductions targets as well as delivering nearer term benefits.

The ETI makes targeted commercial investments in nine technology programmes across heat, power, transport and the infrastructure that links them. The ETI also undertakes strategic modelling of the UK energy system to determine its investment spend and maps pathways to an affordable low carbon energy system that meets the UK’s legally binding emissions reductions targets at least cost through technology innovation.

Page 15: Energy Storage and Distribution

ETI Members

ETI Programme Associate

ETI Project Partners

Page 16: Energy Storage and Distribution

For more information about the ETI visit www.eti.co.uk

The ETI can be followed on Twitter @the_ETI

Energy Technologies InstituteHolywell BuildingHolywell WayLoughborough LE11 3UZ

For general enquiries please telephone 01509 202020

Sign up to receive News alerts by emailing [email protected]