energy science building general construction pre-proposal meeting argonne, illinois april 6, 2011
TRANSCRIPT
Energy Science BuildingGeneral Construction Pre-Proposal MeetingArgonne, IllinoisApril 6, 2011
http://www.anl.gov/esb/
UChicago Argonne, LLC | ESB Pre-Proposal Meeting, April 6, 2011
2
Outline Introduction Instructions to Offerors Scope of Work Project Schedule Payment Process Safety/Insurance Project Approach Questions & Answers Closing Site Visit
UChicago Argonne, LLC | ESB Pre-Proposal Meeting, April 6, 2011
3
Introduction
Prequalified Contractors
Barton Malow Company
Clark Construction Group, LLC
Gilbane Building Company
Power Construction Company, LLC
Ragnar Benson Construction
Walsh Construction
UChicago Argonne, LLC | ESB Pre-Proposal Meeting, April 6, 2011
4
Introduction Team Members
George Paliulionis – DOE Federal Project DirectorAngela Harvey – DOE Deputy Federal Project Director
Karen Hellman – Argonne Project DirectorJeff Sims – Argonne Project ManagerJohn Szott – Argonne Deputy Project ManagerPat Hogan – Argonne Construction ManagerAnne Frankowski - Argonne Supervisor Contracts
UChicago Argonne, LLC | ESB Pre-Proposal Meeting, April 6, 2011
5
Introduction
Roles & Responsibilities
Architect – HDR Architecture, Inc. Civil Engineer – Mackie Consultants LLC
Commissioning Agent – KJWW Engineering Consultants Building Envelope Commissioning – Wiss, Janney, Elstner Associates, Inc.
Construction Manager – Jacobs
Materials Testing - TBD
UChicago Argonne, LLC | ESB Pre-Proposal Meeting, April 6, 2011
6
RFP Mandatory Requirements Evidence required with response to RFP
Proposed Project Manager- At least 15 Years Experience- At least 3 Completed Projects of Similar Type- Completed Projects with Storm Water Pollution Prevention Plan (SWPPP)- Governmental Project Experience- OSHA 30-Hour Training Course
Proposed Superintendent- At least 20 Years Experience- At least 5 Completed Projects of Similar Type- Completed Projects with Storm Water Pollution Prevention Plan (SWPPP)- Governmental Project Experience- OSHA 30-Hour Training Course
UChicago Argonne, LLC | ESB Pre-Proposal Meeting, April 6, 2011
7
RFP Mandatory Requirements Proposed Safety Manager
- At least 15 Years Construction Industry Experience- Certified Safety Professional or comparable professional registration- At least 5 Completed Projects with Safety incentive Programs- Completed Projects with Storm Water Pollution Prevention Plan (SWPPP)
Proposed MEP Subcontractor - At least 10 Years Experience within the past 12 years with construction of laboratories (with a project value of $15MM or greater).
Proposed Scheduler- At least 3 Years Experience with CPM Scheduling Applications- At least 2 Completed Projects as Scheduler of Similar Type
• Attendance at Pre-Proposal Meeting
UChicago Argonne, LLC | ESB Pre-Proposal Meeting, April 6, 2011
8
RFP Evaluation of Additive Alternates Lowest Responsive Responsible Offeror based on Funds
Available
Example (Funding Available of $1,500,000)
Contractor 1 Contractor 2 Contractor 3
Base Proposal $1,000,000 $850,000 $1,5000,000
Alternate 1 $500,000 $300,000 No Evaluation
Alternate 2 No Evaluation $350,000 No Evaluation
Total $1,500,000 $1,500,000 $1,5000,00
Based on funding available at time of proposal opening, Contractor 2 is identified as the apparent low offeror and awarded the project.
Proposals maybe rejected if deemed materially unbalanced
UChicago Argonne, LLC | ESB Pre-Proposal Meeting, April 6, 2011
9
RFP Time & Material Rates / Unit Prices All-Inclusive (i.e. shall include costs for labor, supervision,
material, equipment, bond, overhead, profit, etc.).
Not Utilized for determining “Low-Offeror”
Offeror shall provide rates for the following labor types:
Carpenter Electrician Iron WorkerLaborer Operator PlumberPipefitter Glazier Insulator MasonPainter Roofer Cement FinisherSheet Metal Worker Low Voltage Electrician
Refer to Technical Specifications for details regarding Unit Price work.
UChicago Argonne, LLC | ESB Pre-Proposal Meeting, April 6, 2011
10
Explanation or Interpretation of RFP Documents
All requests shall be submitted in writing by close of business, Wednesday, April 20, 2011.
UChicago Argonne, LLC | ESB Pre-Proposal Meeting, April 6, 2011
11
RFP Davis-Bacon Compliance
The minimum wages paid laborers and mechanics engaged in construction work within the scope of this request shall be in accordance with the Department of Labor minimum wage determination.
Refer to Paragraph VII – D-B Compliance of the RFP document for additional information.
UChicago Argonne, LLC | ESB Pre-Proposal Meeting, April 6, 2011
12
RFP Safety Performance Requirements Offerors must complete and submit with its proposal the
Contractor Safety Questionnaire, PFS-525 (March 8, 2011)
UChicago Argonne, LLC |ESB Pre-Proposal Meeting, April 6, 2011
13
RFP Subcontracting Plan Required to be submitted by Successful Offeror
Intent to include Small, Disadvantaged and Women-Owned Businesses on the ESB Project
The Statutory ESB Project Goals are:
- 23% Small Businesses
- 5% Small Disadvantaged Businesses
- 5% Women-Owned Small Businesses
- 3% Hub-Zone Businesses
- 3% Service-Disabled Veteran-Owned Small Businesses
Reference the Small Business Model Subcontracting Plan included with the RFP for details.
UChicago Argonne, LLC |ESB Pre-Proposal Meeting, April 6, 2011
14
RFP Performance & Payment Bonds Required to be submitted by Successful Offeror within 10
calendar days of the effective date of the Contract
Payment Bond on Argonne Form (Enclosure 1.H)
Performance Bond on Argonne Form (Enclosure 1.I)
Include all costs for Performance & Payment Bonds in the Proposal Amount.
UChicago Argonne, LLC |ESB Pre-Proposal Meeting, April 6, 2011
15
RFP Proposal Submittals Evidence for Mandatory Requirements (Resumes, etc.) Proposal Form, dated March 8, 2011 (Enclosure 1.N) List of Subcontractors, dated December 7, 2010 (Enclosure 1.O) Time & Materials Rates, dated January 13, 2011 (Enclosure 1.L) Unit Prices, dated March 8, 2011 (Enclosure 1.M) Workplace Substance Abuse Programs at DOE Sites Certification of
Compliance (Enclosure 1.S) Pre Award Information Booklet, including Booklet of
Representations & Certifications (Enclosure 2) Contractor Safety Questionnaire, PFS-525 (Enclosure 3)
UChicago Argonne, LLC |ESB Pre-Proposal Meeting, April 6, 2011
16
RFP Proposal Date / Time / Location Date – Wednesday, May 4, 2011
Time – On or before 3:00 P.M., Local Prevailing Time
Location - Argonne National Laboratory
Building 201, OCF-PRO
9700 South Cass Avenue
Lemont, IL 60439
Attn: Anne Frankowski
Reference - RFP No. 1-AF61-P-00092-00
UChicago Argonne, LLC | ESB Pre-Proposal Meeting, April 6, 2011
17
Project Scope
General Construction
- Telecommunications
- Laboratory Equipment
- Laboratory Furnished/Laboratory Installed Items
BIM- Provided for Proposal
- Updated and Provided to Successful Contractor
- Contract Closeout Expectations
UChicago Argonne, LLC | ESB Pre-Proposal Meeting, April 6, 2011
18
Project Schedule
Contract Award on or about June 10, 2011
Construction Start ~ August 2011
Construction Substantial Completion (Beneficial Occupancy) by June 30, 2013
Final Completion three (3) months after BO
Construction Duration - 23 Months
UChicago Argonne, LLC | ESB Pre-Proposal Meeting, April 6, 2011
19
Payment Process Availability of Funds Clause
- Funds Available FY11 - $11,000,000
- Funds Available FY12 - $32,000,000
Tax Exempt Project
Progress Payment Retainage – 10%
Cost Loaded P6 Schedule
Earned Value Reporting
UChicago Argonne, LLC | ESB Pre-Proposal Meeting, April 6, 2011
20
Safety / Insurance
Safety Guide
Safety Incentive Plan
Safety Questionnaire
Conventional Insurance
UChicago Argonne, LLC | ESB Pre-Proposal Meeting, April 6, 2011
21
Project Approach – Project Constraints Buildings 222 & 223 must have at least one fully functional loading
dock at all times (either 222’s or 223’s).
Building 223 fire department connection and fire alarm panel must be relocated prior to demo/excavation at 233 loading dock.
Work in Building 223 must be coordinated with grade/high school education activities.
School Bus drop-off and turn-around capabilities at southwest corner of Building 223 must be maintained during school year.
Pedestrian access from the north parking lot to Building 222 (East Entrance) must be maintained at all times.
Other Argonne constraints will be identified during review and approval of GC’s proposed schedule.
UChicago Argonne, LLC | ESB Pre-Proposal Meeting, April 6, 2011
22
Project ApproachOverall Site Boundaries
UChicago Argonne, LLC | ESB Pre-Proposal Meeting, April 6, 2011
23
Project Approach
Site Logistics Overall site boundaries Temporary work outside “permanent” boundary Telecommunication logistics Temporary power Outside Food Vendors “Roach Coach”
Laboratory Facilities Sanitary Facilities Cafeteria
UChicago Argonne, LLC | ESB Pre-Proposal Meeting, April 6, 2011
24
Project Approach
• Project Management System - Prolog RFI Process Submittal Process Other processes
• Field Change Authority GC will be authorized to proceed with schedule-critical
additional work via the Argonne FCA process
• Material Testing Firm• Commissioning Agent
UChicago Argonne, LLC | ESB Pre-Proposal Meeting, April 6, 2011
26
Closing & Summary Addendum 1 to include:
– Penthouse panel and louver profile revisions.
– Architectural and Structural revisions at terrace above north entrance.
– Furniture package.
– Lab flooring finish and pattern revisions.
– Flash steam recovery system.
– Sizing of condensate system pressure powered pumps.
– Mechanical related demo & new work for Bldg. 222 & 223.
– Control pressure sensors for air and water systems.
– Metering of utilities for building energy use calculations and display in lobby kiosk.
– Lighting controls and circuiting.
– Sub-metering of electrical circuits for building energy use calculations and reporting.
– BMS monitoring of additional sub-meters on the Lab and Domestic Water, Process Cooling and Clean Steam Make-Up Water Systems.