energy networks association flow weighted average calorific value options biomethane campaign...
TRANSCRIPT
EnergyNetworksAssociationFlow Weighted Average Calorific Value Options
Biomethane Campaign Working Group 7th August 2014
The Voice of the Networks
2 The Voice of the Networks
Current Arrangements
BEU RTU DNCC GNCC
ΣFWAC“Energy management
team” (manage the FWACV process)
GCoTEGSMR
Only volume volume
CV + vol separate due to the limitations on historical protocol (modbus)
CVDD
Meter
Controller 2551
FC
PC DANINT HPMIS
EOD File
Approved device - LoA
Meter not under LoA but interpretation of TER is requisite (% accuracy)
DANINT interfaces with CVDD and meter to collect dataApproved software under LoA
DATA
XOSERVE
CV
volume
CalibrationGases
3 The Voice of the Networks
• Propose that sites less than a specified threshold input (10,000 scmh) are not directed sites
• NEA specifies CV device accuracy and calibration – managed in the same manner as GS(M)R Removes the requirement for Approved devices and software
• Agree accuracy class of CV measurement device and calibration regime – could ENA lead on defining this?
• Customer still propanates to meet FWACV value supplied by DN (and if CV is too low, no flow allowed)
Low Flow Sites Not Directed
RTU DNCCCustomerPLC
CVDD
Meter
• This option reduces costs, complexity and is simple to implement
• Will also facilitate new entrants and innovation in the Grid Entry Unit market
• Customers are protected as FWACV is targeted by the Operator – governed by NEA with Ofgem oversight
GNCC
CV and volume follows identical route managed by Customers ‘Flow Computer
4 The Voice of the Networks
• GCoTE would require that an approved software is still used
• GCoTE also stipulate that the calculations must be carried out on site
• Subject to agreement to amend GCoTE would still require reconciliation at DNCC
• CVDD is still approved device so would need daily and 35-day test – this is a Gas Act requirement so harder to change
Modified Direction
RTU DNCCCustomerPLC
CVDD
Meter
• Significant effort and complexity developing alternative process and infrastructure for minimal benefit
• Requirements for 35 day test and calibration remain along with Network Capping implications
• Exactly same local consumer impact as the “Not Directed” option but would incur higher costs
DANINT or EquivalentCalibration Gases
Approved device - LoA
GNCC
Approved software - LoA