enclosure-iii- pre-feasibility...
TRANSCRIPT
Shri Radha Ropeway at Radha Rani Temple
19
M/s Perfact Enviro Solutions Pvt. Ltd.
ENCLOSURE-III- PRE-FEASIBILITY REPORT
Shri Radha Ropeway at Radha Rani Temple
20
M/s Perfact Enviro Solutions Pvt. Ltd.
PROJECT DESCRIPTION
With a view to increase its religious tourism, the Department of Tourism, Government of Uttar
Pradesh has identified three sites for development of ropeway facilities as a pilot project. One
of those chosen sites is the Radha Rani temple at Barsana, Mathura.
The ropeway will be built in one phase with its Upper Terminal Point at the west corner of the
Radha Rani temple and the Lower Terminal Point at the forest land on the northern part of
the foothills.
The proposed Development of Ropeway shall be developed at Radha Rani temple, Banaras,
Mathura by Shri Radha Rani Ropeways Pvt. Ltd. The proposed system to be installed will be
Mono-Cable Pulsed Gondola System. The alignment will be 216.241 metres in length with an
elevation difference of 33 metres, covering an area of 14082.61 sqm (including Terminal
Stations, ropeway corridor & Parking Area). The elevation of LTP is 193.0 m & UTP is 226.0 m
above MSL.
Type of Project
The project being an Aerial Ropeway falls under the item 7 (g) of the EIA notification, 2006
and is a designated Project as per Schedule and falls under category A, as Inter-State Boundary
of Rajasthan falls within 5 km and thus, General Conditions Apply.
Project Proponent
Department of Tourism, GoUP is the organization responsible for the development of tourism
destinations, circuits and tourist infrastructure in the state. For the development and
implementation of this project, a Special Purpose Vehicle (SPV) will be incorporated under
the Companies Act, 1956. This SPV will be formed between the Department of Tourism, GoUP
and the Successful Bidder selected through the competitive bidding process. The selected
bidder will be required to design, build, finance, construct and operate & maintain the project
for a specific concession period. UP Tourism has nominated MVDA as the Nodal Agency.
Description of Project Site:
Mathura is widely known as the birth place of Lord Krishna. Located on the western bank on
the River Yamuna, it is regarded as a holy city and religious tourism is its main offering.
According to the oldest Indian epic, the Ramayan in which this city is mentioned, the Ishwaku
prince Shatrughna had slain a demon called Lavanasura and claimed the land. He then named
the lands ‘Madhuvan’ as it was thickly wooded. Later this city was named Madhupura and
eventually came to be known as Mathura.
People from all walks of life visit Mathura to pay homage to the most important deity of the
region in the many temples spread across the city and to be able to have an experience of an
Shri Radha Ropeway at Radha Rani Temple
21
M/s Perfact Enviro Solutions Pvt. Ltd.
ancient, holy city. Several people from far off are reflected in the monuments, museums and
galleries in the city
The official figures for tourism footfalls in Barsana, which mainly occurs due to the Radha Rani
Temple, have been provided by the Department of Tourism of Uttar Pradesh as shown below.
These figures were verified through a primary market research carried out at site.
The Radha Rani temple at Barsana is located on top of a hill. Currently, the mode of travel
from the settlement at the foot of the hill to the temple at the top includes either walking up
the 190-200 steps or on a palanquin, which can be costly and time consuming still. Hence,
through the introduction of a competition in terms of transportation facility, 8% of the total
footfalls at Barsana have been assumed to avail the ropeway facility instead of the available
modes.
The base year for footfalls at Barsana have been kept as 2012 after which it has been
increased by the factor of 0.75% and capped at 35 lakhs. At the start of the project, the
utilisation of ropeway has been assumed at 8.50% of the total footfalls at Barsana. This
utilisation will be increased by 1% per annum and will be capped at 16% of the total footfalls
in the following years.
Hence, the following factors were recorded for aid in the process of selection of a ropeway
technology:
• Seasons of visitation and festivals
• Traffic recorded and counted
• Profile of visitors
• Likely ropeway riders
• Proposed ropeway capacity
• Forecast of ropeway riders in years to come
Need/Justification of the Project:
Uttar Pradesh abounds in places of tourist interest. Places of religious, historical,
archaeological and of natural beauty are worth-seeing. It is estimated that nearly 170 million
tourists, both domestic and foreign, visited different places of the State in 2012.
Aimed at promoting religious tourism and providing better transit facilities to pilgrims,
Government of Uttar Pradesh (GoUP) has decided to develop first group of ropeways in the
state. As an added attraction to the tourists, these Passenger Ropeways would be developed
at the following three places through Public Private Partnership mode:
• Radha Rani Temple (Ladlee ji Temple) in Barsana, Mathura in Braj Region.
• Ashtabhuja Temple and Kalikhoh Temple in Mirzapur in Vindhyachal Region.
• Lakshman Pahari in Chitrakoot in Bundelkhand Region.
Shri Radha Ropeway at Radha Rani Temple
22
M/s Perfact Enviro Solutions Pvt. Ltd.
In view of the above, Department of Tourism, GoUP appointed the consortium of UDeC Ltd,
IDFC Ltd and Innovest Advisory Services Pvt Ltd as consultant for carrying out necessary
studies, prepare both a feasibility report and a master plan for these three projects involving
establishment of Passenger Ropeways.
Location of the Project Alignment
The ropeway will be built in one phase with its Upper Terminal Point at the west corner of the
Radha Rani temple and the Lower Terminal Point at the forest land on the northern part of
the foothills. The alignment will be 216.241 metres in length with an elevation difference of
33 m.
Figure 1: Location of Barsana
Shri Radha Ropeway at Radha Rani Temple
23
M/s Perfact Enviro Solutions Pvt. Ltd.
Figure 2: Proposed Ropeway Alignment at Barsana
The latitude longitude of the site is given below:
Station Latitude Longitude
Terminal T1 (LTP) 27°39'6.13"N 77°22'20.39"E
Terminal T2 (UTP) 27°38'59.60"N 77° 22'21.36"E
Figure 2: Proposed Ropeway Alignment at Barsana
Shri Radha Ropeway at Radha Rani Temple
24
M/s Perfact Enviro Solutions Pvt. Ltd.
Figure 2: Topographical Map
Connectivity:
Nearest Railway Station: Chhata Railway Station- 14.49 Km NE
Nearest Airport : Indira Gandhi International Airport – 104.45 km NNW
Nearest Highway: NH44– 5.70 Km NW
Shri Radha Ropeway at Radha Rani Temple
25
M/s Perfact Enviro Solutions Pvt. Ltd.
Area Requirement:
The area required for the construction of the terminal stations and line towers would be
about 14082.61 sqm.
The detailed area summary is given below:
LOWER STATION As per the Plans Received
Station Area 300.0. sqm
Passenger waiting area 500.0 sqm
Ropeway Technical Facilities 200.0 sqm
Minimum Passenger Amenities 70.0 sqm
Parking 7419.0 sqm
Total LTP Area-A 8489.0 sqm
UPPER STATION
Station Area 330.0 sqm
Passenger waiting area 1850.0 sqm
Ropeway Technical Facilities 100.0
Minimum Passenger Amenities 70.0 sqm
Total UTP Area-B 2350.0 sqm
ROPEWAY CORRIDOR
Inclined Distance 216.241 m
Width 15 m
Total Ropeway Corridor-C 3243.61 sqm
Total Area (A+B+C) 14082.61 sqm
PROJECT DETAILS
Total
Technology of ropeway Mono-cable Pulsed Gondola system
Length 216.241 m
Elevation difference 33 m
Haulage rope dia 36 mm
Passenger capacity of ropeway 400 PPH during peak hours 50 PPH during normal hours
Trip time 120 secs
Line speed 0.0-5.0 m/sec
No of cabins in line 4 no.
Total no. Of cabins 8
Cabin group Spacing 102.202
Number of towers 2 no.
Power load requirement 415 V
DG sets (back-up power) 1 X 125 KVA at LTP main power 1 x 50 KVA at LTP as rescue motor backup UTP: Nil
Shri Radha Ropeway at Radha Rani Temple
26
M/s Perfact Enviro Solutions Pvt. Ltd.
Population Details:
POPULATION
Visitors 400PPH*2 hrs= 800 passengers (peak hour) Normal hours 50 x 8 hrs= 400 Total 1200 passengers per day
Staff for Ropeway & Shops 25
Residents for accommodation 25
Restaurant population 100
TOTAL POPULATION 1350
Alignment Options for Ropeway System at Shri Radha Rani Ropeway
Barsana is a small but densely developed town spread across east to south of the shallow hill.
Now, ropeways are a complicated technology which requires open space to be developed.
Keeping these factors in mind, several alignment options were worked out of which the best
option was selected.
Figure 1: Alignment Options for Ropeway System at Barsana
Alignment 1
This alignment starts with its LTP at an open field belonging to the Forest Department next to
a Hindu Crematorium at the foothills and goes up to the top with the location of UTP on the
western edge of the Radha Rani Temple.
Shri Radha Ropeway at Radha Rani Temple
27
M/s Perfact Enviro Solutions Pvt. Ltd.
This alignment traverses over thin forest vegetation and provides for a large parking area at
the bottom near the LTP. It also has an independent access road in which the vehicles can
turn before entering the township of Barsana, and hence avoid further congestion.
Alignment 2
This alignment also traverses over thin forest vegetation while disturbing minimal residential
area of the township. However, its LTP is located on the other side of the hill which is not
widely used by people to arrive at Barsana. The generation of parking space for sufficient
number of vehicles may not be possible at the designated LTP. Execution of a Ropeway project
at this location may not be a financially attractive proposal for prospective investors.
Alignment 3
This is the most natural alignment to the stairway to the Radha Rani Temple. However, it
traverses over a thickly populated area which will pose constraints of land acquisition for
generation of LTP as well as locating the towers for the ropeway. Rescue operations would
also be difficult in this alignment.
Selected Alignment:
Considering the pros and cons the three given alignments and the immediate requirement
in the region as per the visiting tourists, Alignment No. 1 is considered as most suitable for
the following reasons:
• The alignment is clear of any urban habitat in its corridor
• The lower terminal provides adequately large space for parking of the vehicles of
visitors to the temple
• The approach to the site offers an alternate access system which will not burden the
existing congested areas of Barsana.
• It is the closest location to the existing stairway to the Radha Rani Temple, thereby
maintaining its attractiveness as an alternate mode of travel and ensuring better
financial viability of the ropeway project.
It is logical to place the LTP in the open parcel of land towards the north-west of the hillock.
This will avoid any need restructuring of the constructed buildings and help in preserving the
local charm of the city.
Shri Radha Ropeway at Radha Rani Temple
28
M/s Perfact Enviro Solutions Pvt. Ltd.
Alignment 1
Figure 4: Selected Alignment for Ropeway
Figure 5: Elevation Profile for the Proposed Ropeway
Shri Radha Ropeway at Radha Rani Temple
29
M/s Perfact Enviro Solutions Pvt. Ltd.
Proposed Ropeway Layout Section
Alignment of the proposed Ropeway System at Barsana
CLIENTTITLE:
0
NOTES-:
SURVEY CONSULTANTS-:
SAKSHI PROJET CONSULTANCYPLOT NO-56,2nd FLOOR (FRONT SIDE)SHAKTI KHAND -III INDIRAPURAM GHAZIABAD(201014)
DO NOT MODIFY OR
ALTER/ASK IN CASE
OF DOUBTSCALE - DATE -25 MAY 2014
BASE
PARAMETERS
L-SECTION
LOWER
TERMINAL
UPPER
TERMINAL
CHAINAGE
LS:RL
LS:GRADIENT
T1/4.88
-8/-8
T2/15
-6/-6
T4/6.47
+10/+10
Horinontal Distance 253.989 Mtr.
Elevetion Difference 65.0000 Mtr.
Inclined Distance 263.724 Mtr.
Lower Terminal Area 300.000 Sq.Mtr.
Upper Terminal Area 330.000 Sq.Mtr.
Ropeway corridor 3955.86 Sq.Mtr.Width 15.000 Mtr.
T3/15
-8/-8
Shri Radha Ropeway at Radha Rani Temple
30
M/s Perfact Enviro Solutions Pvt. Ltd.
The proposed project components can be divided into those located at Lower Station and Upper Station. The details are given as under.
Lower Terminal
• Lower Terminal Station (LTP): The lower terminal station shall be a structural shed,
which will house all ropeway drive machinery. Under-part of the shed will provide the
foundation for ropeway structure. The shed height shall be as per industries norms
and the same shall be open from all sides for better visibility.
• Control Room: It will house the control panel for operation of the ropeway. This shall
be located inside the terminal station building. The control room has glass on all sides
to provide uninterrupted view to the operator; of the cabins movement and
passengers boarding and de-boarding.
• Workshop: A small workshop will be provided at the lower station to facilitate the
ropeway crew to undertake repairs and other associated work of the ropeway parts.
The workshop is normally provided next to spare parts room and can be located inside
or outside the terminal station.
• Spares Stock Room: Ropeways use special parts and some parts are specific to the
plant. The plant therefore houses sufficient quantity of such spares and other off-the-
shelf spares as inventory to undertake any repair. These spares are stored in a fully
closed room. The spare parts room is normally located next to Work shop.
• Guard Room: The plant has to be protected against any theft or mischief during the
silent hour and patrolling guards shall be deployed for the same. Guards are also
needed for crowd control during operational time. A guard room is therefore provided
in the station area.
• Ticket Booth: Ticketing booth is located adjacent to station perimeter near the
entrance gate. As the name suggest, it is used to dispense manual/computerised ticket
of the ropeway to visitors. It is normally built solid with small window for transaction
and inside lockable door, as the space has fair amount of cash money.
• Drinking Water Fountains: Drinking water fountains shall be scattered all over the
station area. The water is fed from overhead tank or pressurised feed line, which is
processed by either individual or central Reverse Osmosis (RO) plant. The water is
cooled in the electrically operated coolers during summer time for passenger comfort.
If the municipality water supply is not available in the area, the ropeway company
should be allowed to make a bore well in the station premises.
• Toilet Block: Clean toilets are a national requirement and ropeway station is capable
of proving the same. The proposed toilet block for male and female passengers should
be established in the station block. The male block should have 3 urinals and two
Shri Radha Ropeway at Radha Rani Temple
31
M/s Perfact Enviro Solutions Pvt. Ltd.
latrines; whereas the female block should have 4 Indian latrines with auto flush facility.
The common area should have a combined wash space with three wash basins in each
block. The entire toilet and wash block for men and women should be provided clad
with ceramic tiles to maintain spotless cleanliness. The block should also have good
ventilation system to keep bad odour away. The discharge of these blocks can go to
an underground bacterial septic tank and its processed outlet water may be used for
watering the garden plants.
• Landscaping: The ropeway company should undertake minor landscaping of area
surrounding the station building to add to the greenery as well beauty of the place.
• Parking Space: The ropeway company should undertake development of full or part
construction of parking space with concrete-tiled finish, which should be sufficient for
over 500 standard cars. It should be paid parking and the area should be properly
marked for systematic movement of the vehicles.
• Staff Welfare, Dining and Rest Room: The ropeway company should provide a small
but well-appointed room as staff entertainment, welfare and dining facility. It is quite
possible that during the tourist season, the ropeway may need to operate for 18 hours
daily. This will lead to requirement of a place for staff to relax while on duty or take
breaks between their shifts, so as to be able to maintain their utmost performance.
• Transformer Room: Since the lower station will house all the power machinery, the
ropeway company can install combination of GODO pole with transformer or can
house the transformer with gang switches in designated transformer room.
• First Aid Room: The lower station shall have one small but equipped first aid room for
passengers and the staff, in case of any eventuality.
• Diesel Generator Room/Shed: A room housing for the diesel generator would be
provided with a tall stack to conform to the Pollution Control Board norms. Or else,
the generator may be an outdoor type with an acoustic housing.
Upper Terminal
• Upper Terminal Station (UTP): Upper Terminal Station will be minimal structural shed
and shall house the necessary tension device and just enough place to accommodate
the boarding and de-boarding platform. The entire station will be enclosed in chain
link fencing for safety, security and passenger management. The equipment
foundation shall be the floor area of the station. No miscellaneous facilities are
envisaged due to the proximity of the temple.
• Ticket Booth: A small ticket booth shall be provided, which will serve the dual purpose
of return ticket check as well fresh issue of one-way return ticket to those passenger,
who wish to avail ropeway ride only for their return trip.
Shri Radha Ropeway at Radha Rani Temple
32
M/s Perfact Enviro Solutions Pvt. Ltd.
• Guard Room: A Guard room shall be provided for security of the plant during non-
working hours and silent hours.
• Drinking Water Fountains: As part of essential passenger amenities, drinking water
fountains and water coolers will be provided at Upper Station for passengers. Toilet
block shall not be provided as the temple is located in proximity.
• Rescue Gear Storage Lockers: Upper station traditionally houses the rescue gear for
rescuing the passengers from the stranded cabins in event of any eventuality. The
rescuers move with the gravity from top to bottom and therefore the rescue gear,
including the rescue chair is stored at upper station in two large lockers. These lockers
are part of upper station shed and no extra space is needed.
Proposed Ropeway System Technology
From the analysis of the terrain on rising hill contour between stations and also the design system capacities being recommended, i.e. 400 Persons Per Hour (PPH), the following considerations have been made:
A. Fixed Grip Gondola system is ruled out because of the following reasons:
i. Boarding/de-boarding needs to be carried out when the system is on. This would
lead to serious problems, particularly in the case of elderly persons and children.
ii. Being fixed grip system, the ropeway will run at low speeds. Hence, considering
the length of the ropeway and the recommended capacity, large number of
cabins would need to be installed.
B. Detachable Grip Gondola system is not recommended as the ropeway alignment
and the capacity does not ideally warrant for such a system.
C. Jig Back system is ruled out because of the following reasons:
i. Capacity of the cabin will be high (about 25 passengers) for such a system
considering the length of the ropeway.
ii. Even with the high speed and high cabin capacity the ropeway capacity could be
met, but it might require a bi-cable ropeway and would be expensive.
D. Mono-cable Pulsated System is felt in order because of the following reasons:
i. It will be a fixed grip mono cable system.
ii. Cost will be low as compared to mono cable detachable system.
iii. Boarding/de-boarding from the system can be done at dead stop condition.
iv. Length & capacity is ideal for Pulsed Gondola system.
v. Cabin / Gondola capacity of 4/6 passengers would serve the purpose.
vi. Introduction of Independent rescue system would allow a Mono-cable ropeway
system to be introduced in this alignment. It would be a less expensive system.
Shri Radha Ropeway at Radha Rani Temple
33
M/s Perfact Enviro Solutions Pvt. Ltd.
Based on the above, it is therefore recommended the use of the following ropeway system:
Name of the Alignment Ropeway System
Passenger Ropeway System between Horticulture Bagh to Radha Rani Temple at Barsana, Uttar Pradesh, India
Mono-cable Pulsed Gondola system
vii. The flexibility will however be allowed for the promoter of the ropeway to used fixed
grip slow speed circulating system as well.
System Description: Monocable Fixed Grip Pulsated Gondola System
In a Mono-cable system, only one rope termed as hauling rope is responsible for supporting
the weight of cabins along with passengers as well hauling the cabins. In this system, one
cabin or a group of cabins on either side of the line are attached to the hauling rope and the
cabins do not get detached from the rope at terminal stations. Functioning of the system is
as follows:
While one group of cabins starts moving from one terminal station to other terminal station,
the other group of cabins simultaneously starts from opposite terminal station. Once they
reach the opposite terminal stations, cabins stop and boarding & de-boarding of passengers
take place.
The System proposed has 4 groups of cabins. In each group there are 2 numbers cabin and
Boarding & de-boarding will be at the Drive Station only no boarding & de-boarding at the
end point, cabins will be go around the return sheave and return back to Drive Station. In the
‘Starting Mode’ first group is stationed in the Drive station and another in the end point
(Return Station). Once the ropeway starts operation, the cabins of both stations moving at a
constant speed in opposite direction and cabins will reach to the opposite terminal. The
boarding & de-boarding of cabins takes place and the process is repeated again and again.
TECHNICAL DATA
Technical Specifications
S. No. Item Parameters
1. System Mono-cable Pulsed Gondola system
2. Direction of operation Clockwise
3. Design Capacity, Persons Per Hour (PPH)
400 PPH during peak hours
50 PPH during normal hours
4. Line speed, m/sec 0.0 -5.0
5. Horizontal distance (m) 204.405
6. Vertical rise (m) 33
Shri Radha Ropeway at Radha Rani Temple
34
M/s Perfact Enviro Solutions Pvt. Ltd.
Technical Specifications
S. No. Item Parameters
7. Inclined length, m 216.241
8. Cabin capacity, seater 4
9. Alignment Straight
10. Line gauge, m 4.4 or more
11. Cabin Group spacing, m 102.202
12. No of cabins in line 4
13. No of cabins in stations 4
14. Total no. of cabins 8
15. Type of cabin Fully enclosed cabin with lockable door, fabricated from Aluminium and Magnesium
Alloy Section and sheeting duly painted
16. Travel time one way, sec 120
17. Rope 36mm, 6x19 Langs Lay, PP Core, 1770 Grade
18. Location of Tension system Lower station
19. Type of Tension System Hydraulic
20. Value of Tension 19.0 tons
21. Location of Drive gears Lower station
22. Main drive motor, HP 60
23. Engine drive for emergency, HP 20, Automotive engine with integral clutch
24. Line Rescue System Vertical by ladder, safety belt and Independent arrangement
25. Stand by D.G. set @ Lower station, KVA
1 X 125 KVA at LTP main power 1 x 50 KVA at LTP as rescue motor backup
26. Stand by D.G. set @ Upper station for station lighting, KVA
Nil
27. Power supply at Lower and Upper Station
415V, 50 Cycles, 3 Phase by SEB
28. Ambient temp 0° C min and 47 ° C max
29. Relevant standard IS 5228
ROPEWAY EQUIPMENT
1. System : Mono-cable Fixed grip
Shri Radha Ropeway at Radha Rani Temple
35
M/s Perfact Enviro Solutions Pvt. Ltd.
2. Haulage Rope : 36 mm Dia, 6x19 Langs
Lay, PP Core, 1770
Grade
3. Intermediate trestle complete cathead and ladder of
steel construction including station front Hold down/
Pressure frame towers
: Approx. 2 Nos. (as
required after final
design shall be
provided)
4. Rope supporting trestle mounts comprising of sheaves,
their support beams and pedestals
: 2 sets per trestle.
5. Drive Station complete with required mechanical
equipment and support structures of steelwork
construction
: 1 Set
6. Return Station complete with required mechanical
equipment and support structures of steel work
construction
: 1 Set
7. Ropeway Drive Equipment comprising of Drive Sheave,
Speed Reduction Units, Electric Motor, diesel engine
drive for emergency, Braking Device etc
: 1 Set
8. Hauling rope Tensioning equipment comprising of
Return Sheave, Tension Gear, Trolley, Counter Weight
and Tension Rope etc
: 1 Set
9. Ropeway cabin complete with Grip and Hanger : 6 nos.
10. Wind speed monitor : 1 No.
11. Communication System : 2 sets
12. Passenger Rescue System : 2 set
13. Fire Extinguishers Dry Powder at Stations : 8 Nos.
Shri Radha Ropeway at Radha Rani Temple
36
M/s Perfact Enviro Solutions Pvt. Ltd.
ENVIRONMENT MANAGEMENT PLAN
Land Environment:
Construction phase:
The proposed ropeway shall be developed from LTP at the forest land on the northern part
of the foothills to UTP at the west corner of the Radha Rani Temple. There will be continuous
ropeway line from LTP to UTP.
About 9000 sq. m (0.90 ha) of area of forest land will be required. This activity will be carried
out as per the guidelines of the Forest (Conservation) Act, 1980. The permission for the same
has already been applied and it is awaited. The diversion of forest land will be required for
construction of terminal stations, and line towers along the corridor. Felling of trees is
required only for construction of pillars and for the same 25 number of trees shall be felled.
However, compensatory afforestation shall be done in the ratio of 1:10. Permission for the
same has been obtained.
Operation Phase:
Although no major impact on land is envisaged during the operation phase, proper collection
shall be taken care for no disposal of solid or hazardous waste & wastewater on land.
Air Environment
Construction phase:
During the construction activities for the proposed terminal stations there will be fugitive
emission such as particulate emission etc. on small scale. Water sprinkling shall be done to
mitigate the impacts of dust generation.
The particulate emissions will be minimal and short term in nature. For the construction of
line towers, the generation of the dust will be low as compared to the construction of terminal
stations. Moreover, the dust generated during the construction phase will be considerably
reduced due to localized meteorological conditions.
Operation Phase:
The operation of the proposed ropeway will not involve major air emissions. Ropeway
operation is an environment friendly non-polluting transport system.
Shri Radha Ropeway at Radha Rani Temple
37
M/s Perfact Enviro Solutions Pvt. Ltd.
DG set of 1 x 125 KVA for main power and 1x50 KVA for rescue motor backup are proposed
located at LTP. No DG sets are proposed at UTP. These D.G. Sets will be provided with proper
stack height as per the CPCB norms.
As per the specifications from D.G. Set manufacturer, the emissions rates that shall be
maintained are given in Table below:
D. G. Set. Capacity
No. PM gm/kw-hr
NOx gm/kw-hr
SO2
gm/kw-hr CO gm/kw-hr
50 KVA 1 0.3 9.2 1.3 3.5
125 KVA 1 0.3 9.2 1.3 3.5
The impact of pollutants such as SO2, NOx and CO mainly released from D.G sets and their
concentration & impact will be very negligible and of short term duration.
The system will be operated mainly on electricity provided by Grid. DG sets will be used as a
stand-by only at the time of power failure.
Noise Environment
Construction Phase:
The noise emission sources during construction phase will include construction machineries/
equipment to be employed at site.
The management measures for noise & vibration control are as follows:
▪ Standard methods and machinery shall be used.
▪ Job rotation and provision of earmuffs to the workers in high noise areas.
▪ Vehicles used in transportation of construction material will be kept fully covered & will
be PUC certified.
▪ DG set shall be installed with adequate stack height to avoid concentration of emissions
on ground and shall be bought acoustically enclosed.
Operation Phase:
DG set of 1 x 125 KVA for main power and 1x50 KVA for rescue motor backup are proposed
located at LTP. No DG sets are proposed at UTP. Acoustically enclosed DG Sets will be bought
and installed at LTP.
The noise & vibration management measures are discussed below:
• Noise free and less air pollution emitting, acoustically enclosed DG Sets, approved by the
CPCB will be bought and installed.
• The system will be operated mainly on electricity provided by Grid. DG sets will be used
as a stand-by only at the time of power failure. DG sets shall be installed on proper
vibration pads to avoid vibration impacts.
Shri Radha Ropeway at Radha Rani Temple
38
M/s Perfact Enviro Solutions Pvt. Ltd.
• The noise pollution due to operation of DG set can be controlled by installation of silent
cowling to a value of 65 dB (A).
The normal ropeway operations are always lower than 50 dB (A) of noise level. Proper
maintenance of the ropeway during the operational phase will be done to ensure low or no
noise and environmental impacts.
Water Environment
Construction Phase:
Approx. 50 Local labors will be preferably employed. During construction Phase, water will
mainly be required for ropeway development, dust suppression & human consumption. It is
estimated that around 5 KLD of water shall be required. The waste water generated shall be
disposed off in septic tank via soak pit.
Operation Phase:
The total water requirement has been estimated as 28 KLD as per detailed below and the
source will be municipal supply. Water shall be used mainly for accommodation purposes for
residents, flushing, drinking, hand washing & horticulture purposes. Total quantity of waste
water generation has been estimated to be 16 KLD. The generation of total waste water shall
be disposed in 2 number of soak pits via septic tank.
Water Management
S. No.
Population Factor
(lpcd) Water Requirement (in KLD)
Waste water (in KLD)
Total water requirement
Domestic Flushing
1. Visitors 1200 6 7 2 (1KLD for
hand washing and
1 KLD for drinking
purposes)
5
2. Staff 25 45 1 0.3 0.7
3. Residents in Accommodation facility
25 135 3 2 1
4. Restaurant & café population
100 70 7 2 5
Shri Radha Ropeway at Radha Rani Temple
39
M/s Perfact Enviro Solutions Pvt. Ltd.
Sub Total
18 KLD (Domestic: 6.3 KLD, Flushing: 11.7 KLD)
Domestic: 4 Flushing: 11.7 KLD Total waste water generated= 16 KLD
3. Gardening
10 KLD NIL
Total 1350 28 KLD 16 KLD
WATER BALANCE
Shri Radha Ropeway at Radha Rani Temple
40
M/s Perfact Enviro Solutions Pvt. Ltd.
Storm Water Management
Maximum collection of rain water shall be done and the stored water shall be reused
wherever possible. Proper channelization for the collection of the same shall be done.
Garland drains are proposed around the pillars/towers to ensure the proper drainage of the
storm water and to prevent disturbance to the drainage pattern of the area.
Solid Waste Management
During Construction Phase: Wastes which are likely to be generated during the construction
of towers and terminals include the following:
Construction and Demolition Waste: Construction and demolition material may contain a
mixture of inert and non-inert material. Construction and demolition materials arising from
the construction may include waste timber formwork, spent concrete and cement screening,
and material and equipment wrappings.
Excavated materials: Since the sites for terminal stations and line towers comprise over
overburden material extending up to 5 - 8 m in depth, the foundations will have to be taken
up to the bedrock to impart stability and will involve excavation works. However, the
excavated overburden will be used for filling and will be compacted.
Chemical Wastes: Plant and vehicle servicing will likely be the primary source of chemical
wastes during the construction period. The majority of chemical waste produced is therefore
expected to consist of waste oils and solvents. However, volumes are expected to be less than
approximately 20 litres a month.
Municipal Waste: Workers engaged during construction phase will generate municipal
wastes such as food wastes, packaging and wastepaper. The waste from labour tents would
be mainly household domestic waste.
Operation Phase: During operation phase, solid waste will be generated by ropeway users,
employee, etc. The estimates of the solid waste generated from the proposed project have
been shown in table below:
Shri Radha Ropeway at Radha Rani Temple
41
M/s Perfact Enviro Solutions Pvt. Ltd.
Type of Waste Colour of Bin
Category Disposal Method Total Waste (kg/day)
Organic Waste Green Bio-degradable
The waste will be treated in Organic Waste Convertor
and converted into compost
147
Recyclable Waste Blue Recyclable Collected and given to approved recycler
63
Total Waste
210 kg/ day
The above table indicates that the total 210 Kg/day of waste will be generated due to the
proposed development. The waste oil generated from D.G sets will be sent to authorize
hazardous waste disposal authority.
Technology of Organic Waste Convertor Salient Features
• Quick waste disposal solution
• Easy to operate, fast, takes very less space and makes waste odour free.
• APT for Household, Industrial canteen, Restaurants, Temples, Markets, Large housing
complex
• Organic Waste Converter uses bio-culture to decompose waste into black manure
• It helps maintain hygiene and create cleaner, greener and healthier environment.
Process Description for Organic Waste Converter Machine System
• The segregated organic waste is bio-mechanically treated in the Organic Waste
Converter Machine.
• Waste is homogenizing with bio-culture and organic media. The coarse wastes are
shredded prior to feeding into OWC machine. Leachate is also controlled during
homogenization process.
• The output from Machine is raw compost which is uniform in colour and soil
structured coarse powder, and also free of bad odour.
• The Organic Waste Converter operates in batch cycle of about 15-20 minutes. The
waste treated in Converter machine accelerates the composting cycle.
Shri Radha Ropeway at Radha Rani Temple
42
M/s Perfact Enviro Solutions Pvt. Ltd.
• The raw compost is placed into compost curing system & moisture is controlled by
using fogging system.
• The raw compost is bio-converted matured compost, in about 10-15 days of curing
period.
• The matured compost can be utilized for gardening etc.
Process flow chart
Ecological Environment
The alignment partially falls within a Forest land for development of terminal stations & line
towers. About 9000 sq m (0.90 ha) of area of forest land will be required. This activity will be
carried out as per the guidelines of the Forest (Conservation) Act, 1980. The permission for
the same has already been applied and it is awaited.
Felling of trees is required only for construction of pillars and for the same 25 number of
trees shall be felled. However, compensatory afforestation shall be done in the ratio of 1:10.
Permission for the same has been obtained.
Socio Economic Scenario
There will be no displacement or immigration of the human population due to the proposed
project. Elderly, children and disabled people, who have to climb the arduous steps, will be
able to take safe and convenient travel to the holy place. Provide direct and indirect
ORGANIC WASTE
WASTE TREATMENT
15 MIN
RAW COMPOST
COMPOST CURING SYSTEM
COMPOST (IN 2 WEEKS)
KITCHEN GARDEN/LANDSCAPING
APPLICATION OF COMPOST
Shri Radha Ropeway at Radha Rani Temple
43
M/s Perfact Enviro Solutions Pvt. Ltd.
employment opportunities to the local people. Enhance visitor experience and boost tourism
in the region.
The impacts expected due to the proposed project during construction and operation phase
are detailed out below:
Positive Impacts
Job opportunity: Construction phase will generate jobs that relate to unskilled, semi skilled
as well as skilled labour category. Employment may be provided to suitable locals considering
their skill set. The ropeway construction requires high skill set and labour from outside may
be required. However, for construction of buildings, accommodation facilities, local labour
will be given preference.
Additional Services: There will be an additional demand for the related services that will
provide alternative income generation avenues to the locals.
Negative Impacts
Population Influx: Although the Radha Rani temple is already a known tourism destination,
its development would create an additional influx of tourists in to the region. This will force
an additional pressure on the local infrastructure and space but are hoped to be taken care
of by augmenting such infrastructure with the development of the project.
Negligible Impacts
Demography: During construction phase, limited number of work force from outside the
surrounding areas may come. However, that will be temporary in nature and therefore it will
cause only a temporary change in the local demography.
Culture and Heritage: The ropeway project is conceived keeping in mind the convenience of
pilgrims visiting Radha Rani temple. The proposed project aims at boosting the religious
tourism in the area and thus, no significant impact is expected on the culture and heritage
of the area.
Displacement: The proposed project does not involve any resettlement/rehabilitation
issues.
Shri Radha Ropeway at Radha Rani Temple
44
M/s Perfact Enviro Solutions Pvt. Ltd.
SAFETY AND RESCUE PLAN
Maintenance Schedule:
Detailed operation and maintenance instruction manuals covering all aspects of maintenance
of the Ropeway System would form an integral part of system documentation.
The essential aspects of maintenance are, however, briefly listed below:
• cabins, hangers and grips etc shall be done.
• Periodic lubrication at the Stations shall be done.
• Routine lubrication at the Stations.
• Regular cleaning at stations to ensure a clean and dust-free atmosphere.
• Periodic Inspection, checking and replacement of hauling rope especially the spliced
zones.
• Inspection, checking, lubrication and replacement if and when required of line
components such as line sheaves.
• Tightening of all station tower bolts periodically.
• Checking of prime mover such as motors, gearbox, couplings etc.
• Regular checking of service and emergency brakes.
• Regular checking of DG set and Diesel Engine.
• Mock trial of rescue system at periodic intervals.
• Adequate maintenance spares will be stocked for smooth operation.
• Special tools & tackles will have kept in the workshop.
Safety Plan
The proposed ropeway is short and maximum degree of elevation is less than 30 degrees. Safe profiling of the system will result in cabins at less than 20 meters from the ground profile.
The ropeway technology is fixed grip and hence the issue of grip slipping does not arise. The
grips of the ropeway shall be shifted once in three months to a new location to allow the rope
to breathe and revert into its original condition. The health and condition monitoring of the
rope and Ultra Testing of all load bearing components will be carried out annually. The drive
and return terminal rotating components will undergo vibration testing and recording for
generation of failure trend.
The ropeway, therefore, is unlikely to meet with any incident or accident, if maintained
properly as per the manufacturer recommendation.
Some of short term failure and their mitigation are as enumerated below:
Power Failure: In the event of main electrical power failure and cabins with passenger on
rope line, the ropeway will restore motion by starting and taking on load the full capacity
Diesel Generator. The ropeway can and will continue commercial operation on Diesel
Generator.
Shri Radha Ropeway at Radha Rani Temple
45
M/s Perfact Enviro Solutions Pvt. Ltd.
Main Gear Box Failure: In the event of main gear box failure or allied power transmission
system, the emergency drive (Diesel engine or Hydraulic Motor or Electrical Motor) can be
coupled with main girth gear which is hard coupled to main drive sheave. These prime movers
are aimed at operating the ropeway at speeds less than 1m/s and bring back the stranded
passengers in the cabin back to nearest terminal station. These auxiliary drives are not
intended for continuation of commercial operation.
Before making it for public use the ropeway project shall be thoroughly inspected to ensure
the ropeway project is safe for public use. After getting clearance certificate, the commercial
operation of the ropeway would be able to commence.
Safety Measures
• Strict adherence of ropeway manufacturers’ maintenance routine shall be complied
with. The routine undertaken shall be recorded in maintenance register with
description of routine and the person undertaking routine shall be indicated clearly.
• The ropeway shall logically undertake two shut down routines during lean season. One
shut down for about 3-5 days will be taken as Half Yearly Shut Down. 7-10 days of shut
down will be taken once in year as Annual Maintenance Shut Down. The shutdown
schedule shall be intimated to district administration as well displayed at prominent
location of ropeway premises for the visitors.
• The ropeway operator will undertake rope testing through magnetograph to ascertain
thickness of the rope and broken wires. IS standard being to be followed in
determining residual life of rope and decision to replace the rope. The rope shall be
immediately changed and no commercial operation shall be permitted, if the strands
have collapsed and touching each other; also known as “dead rope”.
• All load bearing pins and shaft and critical components as grips and hangers shall be
tested using Ultra Testing and record of such testing should be retained. All rotary
components and bearing housing shall be tested for vibration analysis. On the basis of
signature forecast, preventive replacement and maintenance shall be undertaken.
• The Gondolas shall be provided with door lock, which cannot be opened by the
passengers
• All elements of the ropeway shall be mounted onto a steel structure which is anchored
on concrete foundations.
• Emergency push buttons should be provided at all stations to stop the ropeway, if
required.
Rescue Arrangement:
The Ropeway system would be provided with a rescue arrangement to enable the passengers
being evacuated in case of an extreme emergency where cabins are stranded on line.
Shri Radha Ropeway at Radha Rani Temple
46
M/s Perfact Enviro Solutions Pvt. Ltd.
1. Ladder Rescue shall be adopted for cabins which are stranded close to the ground. An
attendant stabilizes the ladder from below while another attendant goes up to open the
door and help the passengers to come down.
2. Vertical Rescue System shall be provided involving small winch and the carrier unit which
will enable a rescuer to reach the stranded cabins and lower the passengers to the ground.
3. The Emergency Drive with diesel engine enables the passengers to be evacuated in the
event of the power failure.
PROJECT SCHEDULE & COST ESTIMATES
The estimated project cost is of Rs. 15.5 crores
The scheduled completion date shall occur after 2 years from the appointed date. On or
before the scheduled Completion date, the concessionaire shall have completed the
construction of the entire project.
COST ON EMP
CAPITAL EXPENDITURE
Sl No
Description Capital Cost
(Rs. In Lacs)
Recurring Cost (Rs. in Lacs/
Year)
1 Landscaping 2.5 0.4
2 Septic Tank 10.0 2.0
3 D.G. set Stack & Enclosure 0.5 0.1
4 Solid Waste Management/ OWC 25.0 3.0
5 Environmental Monitoring - 0.5
Total Rs. 38.0 Lacs Rs. 6.0 Lacs/yr
PROJECT BENEFITS
I. Aerial Ropeway is fast emerging technology of providing not only tourist experience
but an urban transportation means especially for hilly and tough terrains. It is totally
environment friendly with least generation of any type of pollutants. The land
requirement is minimal as the transportation happens aerially.
Shri Radha Ropeway at Radha Rani Temple
47
M/s Perfact Enviro Solutions Pvt. Ltd.
II. Safety & Comfort: Ropeways provide more safe and comfortable journey. Elderly,
children and disabled persons which may not be able to take-up the arduous trek, would
be able to take up the journey to Shri Radha Rani Temple.
III. Traffic Regulation: The ropeway would help in regulating traffic to Shri Radha Rani
Temple as only a specified number of tourists can board and de-board the system at a
pre-defined interval of time. This would help in restricting and regulating carrying
capacity of the place.
IV. Socio-Economic benefits: The increase in tourism of the area would subsequently
increase the ancillary businesses, thereby increasing the local economy of the area and
of the Mathura District.
V. Local Employment: The project would require local people, who are accustomed of
living under the existing conditions, for skilled / unskilled activities in course of
construction and operations of the project. The project will provide direct and indirect
employment opportunities to the local people & hence improving their status of living.
VI. Infrastructure development or facilities like toilets, drinking water, sewage treatment,
solid waste management, medical facilities, etc. will be helpful in maintaining the
beauty as well as ecology of such alluring place. And, the medical facilities will help
the casualties caused to be addressed on time & in proper way.
Shri Radha Ropeway at Radha Rani Temple
48
M/s Perfact Enviro Solutions Pvt. Ltd.
Enclosure 1: Certification of Incorporation
Shri Radha Ropeway at Radha Rani Temple
49
M/s Perfact Enviro Solutions Pvt. Ltd.
Enclosure 2: Permission of Felling of Trees
Shri Radha Ropeway at Radha Rani Temple
50
M/s Perfact Enviro Solutions Pvt. Ltd.
Enclosure 3: L Section Model
LOWERTERMINAL
UPPERTERMINAL
CHAINAGE
LS:RL
LS:GRADIENT
T1/3.69 -6/-6
T3/4.93 +6/+6
T2/11.00 +4/+4
Horinontal Distance 204.405 Mtr.
Elevetion Difference 60.0000 Mtr.
Inclined Distance 216.241 Mtr.
Lower Terminal Area 300.000 Sq.Mtr.
Upper Terminal Area 330.000 Sq.Mtr.
Ropeway corridor 3243.61 Sq.Mtr.Width 15.000 Mtr.
Shri Radha Ropeway at Radha Rani Temple
51
M/s Perfact Enviro Solutions Pvt. Ltd.
Enclosure 4: Layout
RADHA RANI T E M P L E
B O
U N
D A
R Y
W
A L
L
B O U N D A R Y W A L L
B O U
N D
A R
Y W
A L
L
B U I L D I N G
SMADI
F O O
T
T R A
C K
F O O
T
T R
A C
K
GRAVEYARD
6.00
0
14.0
00
15.000
5.000
204.
405
8.00
0
14.0
00
Horinontal Distance 204.405 Mtr.
Elevetion Difference 60.0000 Mtr.
Inclined Distance 216.241 Mtr.
Lower Terminal Area 300.000 Sq.Mtr.
Upper Terminal Area 330.000 Sq.Mtr.
Ropeway corridor 1764.00 Sq.Mtr.Width 10.000 Mtr.
5.000
10.000
4.31
1
44.262
51.863
61.113
17.9
08
21.873
17.5197.
794
5.17
3
53.0
76
11.3
41
3.150
14.0
63
123.
5 80
8.258
10.872
130.704
3.207
15.000
20.0
00
64°
90°
93°
4.52
2
BM2
BM1
15.000
82.170
48.000
72.0
00
10.000
82.170
13.000
84.000
LOWER STATION
STATION AREA
PASSANGER WAITING AREA
ROPEWAY TECHNICAL FACILITIES
MINIMUM PASSANGER AMENITIES
PARKING
8489.0 Sq.mt.
300.0 Sq.mt.
500.0 Sq.mt
200.0 Sq.mt.
70.0 Sq.mt.
7419.0 Sq.mt.
UPPER STATION
STATION AREA
PASSANGER WAITING AREA
ROPEWAY RESCUE FACILITIES
MINIMUM PASSANGER AMENITIES
2350.0 Sq.mt.
330.0 Sq.mt.
1850.0 Sq.mt
100.0 Sq.mt.
70.0 Sq.mt.
36.991
60.00
0
45.2
51
40.195
13.523
KHASARA NO.- 133
KHASARA NO.- 126
98.0
00
79.830
79.830
2350.00 Sq.mt.
Shri Radha Ropeway at Radha Rani Temple
52
M/s Perfact Enviro Solutions Pvt. Ltd.
Enclosure 5: Bidding Agreement
Shri Radha Ropeway at Radha Rani Temple
53
M/s Perfact Enviro Solutions Pvt. Ltd.
Enclosure 6: Letter of Award