en-gb method statement bracket platform m · pdf filein the relevant technical documentation...
TRANSCRIPT
The Formwork Experts
10/2011
en-GB999723002
User informationMethod statement
Bracket platform M
9723-208-01
2 999723002 - 10/2011
Introduction User information Bracket platform M
The Formwork Experts
Introduction
© by Doka Industrie GmbH, A-3300 Amstetten
User information Bracket platform M Introduction
3999723002 - 10/2011
The Formwork Experts
Contents4 Introduction4 Elementary safety warnings6 Eurocodes at Doka8 Doka services
10 Formwork planning with Tipos-Doka
11 System description11 Product description12 The Doka bracket platform M in detail13 Areas of use16 Easy utilisation planning17 Layout of Bracket platforms M
18 Assembly instructions18 Set-up procedure19 Separate single brackets20 Corner solutions24 Bridging storey-high openings26 Handrail lengthening piece for extending the
range of use of the Bracket platform M as a rooftop fall barrier
28 Moving the platform
29 Anchoring on the structure29 Overview of suspension methods30 Suspension point in concrete33 Retrofitted suspension point in masonry34 Suspension points subsequently fixed onto
the concrete floor-slab36 Suspension points in pre-cast construction
38 General remarks38 Sideguards on exposed platform-ends39 Fall-arrest systems on the structure40 Transporting, stacking and storing
47 Component overview
4 999723002 - 10/2011
Introduction User information Bracket platform M
The Formwork Experts
IntroductionElementary safety warnings
User target groups● This User Information booklet (Method Statement) is
aimed at everyone who will be working with the Doka product or system it describes. It contains informa-tion on the standard design for setting up this sys-tem, and on correct, compliant utilisation of the sys-tem.
● All persons working with the product described herein must be familiar with the contents of this man-ual and with all the safety instructions it contains.
● Persons who are incapable of reading and under-standing this booklet, or who can do so only with dif-ficulty, must be instructed and trained by the cus-tomer.
● The customer is to ensure that the information mate-rials provided by Doka (e.g. User Information book-lets, Instructions for Assembly and Use, Operating Instruction manuals, plans etc.) are available to all users, and that they have been made aware of them and have easy access to them at the usage location.
● In the relevant technical documentation and form-work utilisation plans, Doka shows the workplace safety precautions that are necessary in order to use the Doka products safely in the usage situations shown. In all cases, users are obliged to ensure compliance with national OH&S (occupational health and safety) rules throughout the entire project and to take appro-priate additional or alternative workplace safety pre-cautions where necessary.
Hazard assessment● The customer is responsible for drawing up, docu-
menting, implementing and continually updating a hazard assessment at every job-site. This document serves as the basis for the site-spe-cific hazard assessment, and for the instructions given to users on how to prepare and utilise the sys-tem. It does not substitute for these, however.
Remarks on this document● This User Information booklet can also be used as a
generic method statement or incorporated with a site-specific method statement.
● Many of the illustrations in this booklet show the situation during formwork assembly and are therefore not always complete from the safety point of view.Any safety accessories not shown in these illustra-tions must still be used by the customer, in accord-ance with the applicable rules and regulations.
● Further safety instructions, especially warnings, will be found in the individual sections of this document!
Planning● Provide safe workplaces for those using the form-
work (e.g. for when it is being erected/dismantled, modified or repositioned etc). It must be possible to get to and from these workplaces via safe access routes!
● If you are considering any deviation from the details and instructions given in this booklet, or any application which goes beyond those described in the booklet, then revised static cal-culations must be produced for checking, as well as supplementary assembly instructions.
Rules applying during all phases of the assignment:● The customer must ensure that this product is
erected and dismantled, reset and generally used for its intended purpose under the direction and super-vision of suitably skilled persons with the authority to issue instructions. These persons' mental and physical capacity must not in any way be impaired by alcohol, medicines or drugs.
● Doka products are technical working appliances which are intended for industrial/commercial use only, always in accordance with the respective Doka User Information booklets or other technical docu-mentation authored by Doka.
● The stability of all components and units must be ensured during all phases of the construction work!
● The functional/technical instructions, safety warn-ings and loading data must all be strictly observed and complied with. Failure to do so can cause acci-dents and severe (even life-threatening) damage to health, as well as very great material damage.
● Fire-sources are not permitted anywhere near the formwork. Heating appliances are only allowed if properly and expertly used, and set up a safe dis-tance away from the formwork.
● The work must take account of the weather condi-tions (e.g. risk of slippage). In extreme weather, steps must be taken in good time to safeguard the equipment, and the immediate vicinity of the equip-ment, and to protect employees.
● All connections must be checked regularly to ensure that they still fit properly and are functioning cor-rectly. It is very important to check all screw-type connec-tions and wedge-clamped joins whenever the con-struction operations require (particularly after excep-tional events such as storms), and to tighten them if necessary.
User information Bracket platform M Introduction
5999723002 - 10/2011
The Formwork Experts
Assembly● The equipment/system must be inspected by the
customer before use, to ensure that it is in suitable condition. Steps must be taken to rule out the use of any components that are damaged, deformed, or weakened due to wear, corrosion or rot.
● Combining our formwork systems with those of other manufacturers could be dangerous, risking damage to both health and property. If you intend to combine different systems, please contact Doka for advice first.
● The assembly work must be carried out by suitably qualified employees of the client's.
● It is not permitted to modify Doka products; any such modifications constitute a safety risk.
Erecting the formwork● Doka products and systems must be set up in such
a way that all loads acting upon them are safely transferred!
Pouring● Do not exceed the permitted fresh-concrete pres-
sures. Excessively high pouring rates lead to form-work overload, cause greater deflection and risk causing breakage.
Striking the formwork● Do not strike the formwork until the concrete has
reached sufficient strength and the person in charge has given the order for the formwork to be struck!
● When striking the formwork, never use the crane to break concrete cohesion. Use suitable tools such as timber wedges, special pry-bars or system features such as Framax stripping corners.
● When striking the formwork, do not endanger the stability of any part of the structure, or of any scaf-folding, platforms or formwork that is still in place!
Transporting, stacking and storing● Observe all regulations applying to the handling of
formwork and scaffolding. In addition, the Doka slinging means must be used - this is a mandatory requirement.
● Remove any loose parts or fix them in place so that they cannot be dislodged or fall free!
● All components must be stored safely, following all the special Doka instructions given in the relevant sections of this User Information booklet!
Regulations; industrial safety● Always observe all industrial safety regulations and
other safety rules applying to the application and uti-lisation of our products in the country and/or region in which you are operating.
Instruction as required by EN 13374:● If a person or object falls against, or into, the edge
protection system and/or any of its accessories, the edge protection component affected may only con-tinue in use after it has been inspected and passed by an expert.
Maintenance● Only original Doka components may be used as
spare parts. Repairs may only be carried out by the manufacturer or authorised facilities.
Symbols usedThe following symbols are used in this booklet:
MiscellaneousWe reserve the right to make alterations in the interests of technical progress.
Important noteFailure to observe this may lead to malfunc-tion or damage.
CAUTION / WARNING / DANGERFailure to observe this may lead to material damage, and to injury to health which may range up to the severe or even life-threaten-ing.
InstructionThis symbol indicates that actions need to be taken by the user.
Sight-checkIndicates that you need to do a sight-check to make sure that necessary actions have been carried out.
TipPoints out useful practical tips.
ReferenceRefers to other documents and materials.
☞
6 999723002 - 10/2011
Introduction User information Bracket platform M
The Formwork Experts
Eurocodes at DokaIn Europe, a uniform series of Standards known as Eurocodes (EC) was developed for the construction field by the end of 2007. These are intended to provide a uniform basis, valid throughout Europe, for product specifications, tenders and mathematical verification.The EC are the world's most highly developed Stand-ards in the construction field.In the Doka Group, the EC are to be used as standard from the end of 2008. They will thus supersede the DIN norms as the "Doka standard" for product design.
The widely used "Permissible stress design" (compar-ing the actual stresses with the permissible stresses) has been superseded by a new safety concept in the EC.The EC contrast the actions (loads) with the resistance (capacity). The previous safety factor in the permissible stresses is now divided into several partial factors. The safety level remains the same!
Comparison of the safety concepts (example)
Ed Design value of effect of actions (E ... effect; d ... design) Internal forces from action Fd (VEd, NEd, MEd)
Rd Design value of the resistance (R ... resistance; d ... design) Design capacity of cross-section (VRd, NRd, MRd)
Fd Design value of an actionSteel: Rd =
Rk Timber: Rd = kmod ·Rk
Fd = γF · Fk γM γM
(F ... force)Fk Characteristic value of an action
"actual load", service load (k ... characteristic) e.g. dead weight, live load, concrete pressure, wind
Rk Characteristic value of the resistance e.g. moment resistance to yield stress
γF Partial factor for actions (in terms of load; F ... force) e.g. for dead weight, live load, concrete pres-sure, wind Values from EN 12812
γM Partial factor for a material property (in terms of material; M...material) e.g. for steel or timber Values from EN 12812
kmod Modification factor (only for timber – to take account of the moisture and the duration of load action) e.g. for Doka beam H20 Values as given in EN 1995-1-1 and EN 13377
Ed
Rd
Permissible stress design EC/DIN concept
Factual≤ Fpermissible Ed≤ Rd
A Utilisation factor
60 [kN]
60<70 [kN]
115.5 [kN]
� ~ 1.65
Fyield
Fpermissible
Factual
9801
3-10
0
A
90 [kN]
115.5 [kN]
90<105 [kN]
Rk
Rd
Ed
�M
= 1.1
�F
= 1.5
9801
3-10
2
A
The "permissible values" communicated in Doka documents (e.g.: Qpermissible = 70 kN) do not correspond to the design values (e.g.: VRd = 105 kN)!➤ Avoid any confusion between the two!➤ Our documents will continue to state the per-
missible values. Allowance has been made for the following par-tial factors: γF = 1.5 γM, timber = 1.3 γM, steel = 1.1 kmod = 0.9In this way, all the design values needed in an EC design calculation can be ascertained from the permissible values.
User information Bracket platform M Introduction
7999723002 - 10/2011
The Formwork Experts
8 999723002 - 10/2011
Introduction User information Bracket platform M
The Formwork Experts
Doka services
Support in every phase of the projectDoka offers a broad spectrum of services, all with a sin-gle aim: to help you succeed on the site.Every project is unique. Nevertheless, there is one thing that all construction projects have in common – and that is a basic structure with five phases. We at Doka know our clients' varying requirements. With our consulting, planning and other services, we help you achieve effective implementation of your formwork assignment using our formwork products – in every one of these phases.
Project development phase Tendering phase Operations scheduling phase
Taking well-founded decisions thanks to professional advice and consulting
Optimising the preliminary work with Doka as an experienced part-ner
Controlled, regular forming oper-ations, for greater efficiency resulting from realistically calculated formwork concepts
Find precisely the right formwork solutions, with the aid of● help with the bid invitation● in-depth analysis of the initial sit-
uation● objective evaluation of the plan-
ning, execution, and time-risks
Draw up potentially winning bids, by● basing them on realistically calcu-
lated guideline prices● making the right formwork
choices● having an optimum time-calcula-
tion basis
Plan cost-effectively right from the outset, thanks to● detailed offers● determination of the commission-
ing quantities● co-ordination of lead-times and
handover deadlines
1 2 3
User information Bracket platform M Introduction
9999723002 - 10/2011
The Formwork Experts
The advantages for you thanks to professional advice and consulting
● Cost savings and time gains When we advise and support you right from the word "go", we can make sure that the right formwork systems are chosen and then used as planned. This lets you achieve optimum utilisation of the formwork equipment, and effec-tive forming operations because your workflows will be correct.
● Maximised workplace safety The advice and support we can give you in how to use the equip-ment correctly, and as planned, leads to greater safety on the job.
● Transparency Because our services and costs are completely transparent, there is no need for improvisation dur-ing the project – and no unpleas-ant surprises at the end of it.
● Reduced close-out costs Our professional advice on the selection, quality and correct use of the equipment helps you avoid damage, and minimise wear-and-tear.
(Shell) construction phase (Shell) completion phase
Optimum resource utilisation with assistance from the Doka Formwork Experts
Seeing things through to a posi-tive conclusion with professional support
Workflow optimisation, thanks to● thorough utilisation planning● internationally experienced
project technicians● appropriate transport logistics● on-site support
Doka Services are a byword for transparency and efficiency here, offering● jointly handled return of rented
formwork● professional dismantling● efficient cleaning and recondition-
ing using special equipment
4 5
10 999723002 - 10/2011
Introduction User information Bracket platform M
The Formwork Experts
Formwork planning with Tipos-Doka
Tipos-Doka helps you to form even more efficientlyTipos-Doka has been developed to assist you in planning the use of your Doka formwork. For wall formwork, floor formwork and platforms, it puts the same tools into your hands that we at Doka use ourselves for formwork planning.
Easy to use, fast and accurate resultsThe easy-to-use interface makes for very fast working. From when you input your layout (with the "Schal-Igel"® on-screen assistant), all the way through to when you manually put the finishing touches to the formwork solution the program gives you. All this saves time - yours.The program contains a large number of templates and wizards, so you can be sure of always getting the opti-mum technical and economical solution to your form-work task. This makes for greater operational reliability, and cuts costs.You can get to work right away with the piece-lists, plans, views, sections and perspective drawings that the program gives you. Operational reliability is also enhanced by the high level of detail of the plans.Among other things, Tipos-Doka plans the following with Bracket platforms M:● distribution of the bracket platforms● closures● corner solutions● safety railings● height-adjusted applications (raised/lowered)
Drawings of formwork and platforms really can be this detailed! Both for the layout and for spatial representations, Tipos-Doka sets an impressive new standard of visual presentation.
Always the right quantities of form-work and accessories
You can import the automatically generated piece-lists into many other programs for further processing.Formwork components and accessories that have to be organised at short notice, or replaced by improvisation, are the ones that cost the most. This is why Tipos-Doka offers complete piece-lists that leave no room for improvisation. Planning with Tipos-Doka eliminates costs before they have a chance to even arise. And your depot can make the best possible use of its stocks.
User information Bracket platform M System description
11999723002 - 10/2011
The Formwork Experts
System descriptionProduct description
For greater safety in masonry and pre-cast constructionThe Doka bracket platform M is a site-ready, light-weight working and protection platform that gives a big boost to safety in the field of masonry and pre-cast con-struction.The winner of an EU award, the Bracket platforms M fulfil the criteria for use as:● EN 12811-1 compliant working platforms● DIN 4420-1 and ÖNORM B4007 compliant protec-
tion platformsThe Doka bracket platform M puts an end to the time-consuming and risky business of improvising protection platforms from separate brackets and planks.The system also provides a solution for corner configu-rations.Standardised system solutions are available for bridg-ing storey-high openings and lengthening the railings etc.
Among the many advantages of the Doka bracket platform M:● is readied for operation in only a few simple steps:
- tilt up the railings- fix the brackets- hang the platform into place.- That's it!
● The 1.55 m working width and 3.00 m platform length provide a safe working environment
● Safe, close-meshed lattice railings● The wide (2.50 m) centre-distance of the brackets
means fewer suspension points
● Long brackets for bridging window gaps down as far as parapet height
● Good bridging of wall and window openings● A second drop-in rod on each bracket allows the
platform height to be adjusted by 1.00 m● No projecting parts: The retractable crane hoisting
points leave an even, safe work-deck.
Further advantages:● Takes up very little storage and transport space● Pallet for platform brackets M, for holding up to 18
brackets● Low bracket-weight of only 32 kg● Captive, unloseable parts● Long service life thanks to its sturdy design, var-
nished floor planking and galvanised steel construc-tion
Permitted service load: 3.0 kN/m2 (300 kg/m2)Load Class 4 to EN 12811-1:2003(depends on the type of suspension point)
12 999723002 - 10/2011
System description User information Bracket platform M
The Formwork Experts
The Doka bracket platform M in detail
The Platform decking M 3.00m (A) can also be used for bridging openings and for closures, without having to be modified first.
System dimensions:
Crane slinging pointsNo projecting parts: The retractable crane hoisting points leave an even, safe work-deck.
Drop-in rodThanks to the long drop-in rods, no extra safeguards are needed to protect against accidental lift-out of the platform (according to DIN 4420)
A Platform decking M 3.00mB Platform bracket M
9723-201-01
A
B
9723-290-01
148
124
100
220
10
104
9723-200-01
9723-216-01
User information Bracket platform M System description
13999723002 - 10/2011
The Formwork Experts
Areas of use
Working platform
a ... 155.0 cmb ... 130.0 cmc ... 229.0 cmd ... 104.0 cm
Protection platforms: Fall barriers
a ... 100 cmb ... 130.0 cm
Max. compressive load which may occur: Fk = 6.6 kN (Rd = 9.9 kN)
9723
-246
-01
b
a
dc
F
Max. compressive load which may occur: Fk = 6.6 kN (Rd = 9.9 kN)
Drop h Dimension cAs per DIN 4420-1 max. 3.0 m min. 1.30 mAs per ÖNORM B 4007 and "BauV" Construc-tion Worker Protection Ordinance
max. 4.0 m min. 1.50 m
9723
-247
-01
a
b
c
h
F
14 999723002 - 10/2011
System description User information Bracket platform M
The Formwork Experts
Protection platforms: Sloping-rooftop fall barriers
Sloping-rooftop fall barrier as defined by DIN 4420
a ... Eaves depthc ... 1.90 mh ... max. 1.50 m
Diagram for determining the max. height level (h) of the platform decking for different eaves depths (a) (to DIN 4420)
Areas of use
Sloping-rooftop fall barrier as defined by Önorm B 4007
a ... min. 60 cmc ... 1.90 mh ... max. 1.50 m
A Universal handrail lengthening piece M
☞ ● When using the Universal handrail lengthen-ing piece M – max. influence width: 3.00 m
● Allow for the min. lift-out distance (b) of 35 cm!
Dimension "a" [m]
h [m
] (fr
om d
ecki
ng to
edg
e of
eav
es)
Y Bracket platform M (standard configuration)Z Bracket platform M with Handrail lengthening piece
b
a
c
h
9723
-250
-01
9723-100
0.85
1.05
1.15
1.35
0.65
0.95
0.75
0.55
1.25
1.45
0.45
0.10.35
0.2 0.3 0.4 0.5 0.6
1.50
0
Y
Z
☞ ● When using the Universal handrail lengthen-ing piece M – max. influence width: 3.00 m
● Allow for the min. lift-out distance (b) of 35 cm!
b
c
a
h
9723
-250
-01
User information Bracket platform M System description
15999723002 - 10/2011
The Formwork Experts
Extending the range of use by adjusting the height
Platform raisedRaising the height of the Bracket platform M provides optimum working conditions, in which work can move ahead swiftly and safely.
a ... 100 cm (A) The ∅ 13 mm holes drilled in the profile of the Platform bracket M make it possible to attach site-provided guard-rail boards, as a fall-arrest barrier (B) Doka beam H20 as a horizontal bridging beam. Alter-natively, two nailed 5x20 cm planks can be used. Fix these so that they cannot fall off.
Platform loweredThe Suspension beam M makes it possible to lower the Bracket platform M by 50 cm or 100 cm.
a ... 50 cm or 100 cm
Suspension shoe in the outside corner zone (plan view)
Centre-to-centre distance "a" of the suspension loops from the edge of the structure: 4.0 cm (instead of the standard 15.0 cm).Applies to corner solutions with:● Corner platform decking M as the outside corner● Bracket platform M with Corner transition M 1.80 m
Permitted clear gaps of openingsNormal position 5 m
Raised 3 m
B
A
9723
-248
-01
a
9723
-210
-01
A Universal handrail lengthening piece MB Suspension beam M
Permitted service load: 1.5 kN/m2 (150 kg/m2)Load Class 2 to EN 12811-1:2003
☞ ● The Suspension beam M can be connected to the Platform brackets M – in this way, only one crane cycle is needed when the platform is lifted and repositioned
● When using the Universal handrail lengthen-ing piece M – max. influence width: 3.00 m
● Allow for the min. lift-out distance (b) of 15 cm!
A Corner platform decking M
b
A
B
a
9723
-249
-01
A
9723
-251
-01 a
a
16 999723002 - 10/2011
System description User information Bracket platform M
The Formwork Experts
Easy utilisation planning
A Bracket platform MB Platform decking M 3.00mC Platform decking M 3.00m with one Platform bracket MD Corner platform decking as outside cornerE Corner platform decking as inside cornerF Corner transition M 1.80m
9723-268-01
9723
-215
-01
A
A
A
A
A
A
AA
B
B
B
D
D
D
E
E
E
F
F
C
C
C
C
C
User information Bracket platform M System description
17999723002 - 10/2011
The Formwork Experts
Layout of Bracket platforms MVariable combinations of platform decking and brack-ets make for optimum adaptation to the structure.
Standard layout
Adapting with overlapping platformMinimum overlap 25 cm
Adapting with Platform decking M 3.00 m for gap-bridgingMinimum overlap 25 cm
a ... 250.0 cmb ... Variable up to 250.0 cmc ... 50.0 cm
Permitted service load: 3.0 kN/m2 (300 kg/m2)Load Class 4 to EN 12811-1:2003(depends on the type of suspension point)
A Bracket platform MB Platform decking M 3.00mC Platform decking M 3.00m with one Platform bracket M
9723
-205
-01
A A
a ac
9723
-207
-01
C A
ab
9723
-206
-01
A AB
a ab
18 999723002 - 10/2011
Assembly instructions User information Bracket platform M
The Formwork Experts
Assembly instructionsSet-up procedure
Putting up the railings➤ Tilt up the railings (A) . These automatically slot in
when they reach the stop.
Attaching the crane➤ Pull out the lifting bows from the recesses, attach a
four-part lifting chain (e.g. Doka 4-part chain 3.20m) (B) and lift the Platform decking M.
Suspending and fixing the Platform bracket M➤ Hook both brackets into the front claws of the plat-
form.
➤ Raise the Bracket platform.
The Platform bracket M (C) now automatically pivots upwards.
➤ Push through a scaffolding bolt (D) and lock it.➤ Tighten the Star grip nut G (E) .
The fixing components are captively connected to the bracket.
Hanging the Bracket platform M into place
Thanks to the long drop-in rods, no extra safeguards are needed to protect against accidental lift-out of the platform (according to DIN 4420)
A
580548000-3b
9723-285-01
B
9723-281-02
The handle (F) must be pointing in the same direction as the bracket plane!
C
9723-281-01
9723
-281
-03
D
E
F
a
9723
-269
-01
User information Bracket platform M Assembly instructions
19999723002 - 10/2011
The Formwork Experts
Separate single brackets
using the Bracket railing postHighly irregular façades require a great deal of flexibility from the platform system. Often, sites attempt to make the necessary adaptations by means of inherently risky improvisations. For these cases, too, Doka also offers a standardised system solution.Adding a Bracket railing post M to the Doka bracket platform M creates a single bracket that can be used to make a safe railing.
Platform boards as specified by German "ZH" employee safety rule n° 1/534 and/or ÖNORM B 4007
Distance between a single bracket and the suspension point of the next platform: max. 1.50 mOnce the floor-planks have been laid in place and the guard-rail boards have been fixed in the Bracket railing post M, the result is a safe and economical platform with exactly the right length for the usage situation in question.
Assembly instructions➤ Slot the Bracket railing post M onto the Platform
bracket M.
➤ Fixing the captive pin in place prevents accidental lift-out of the Bracket railing post M.
A Bracket railing post MB Platform bracket M
9723
-224
-01
A
B
A Bracket platform MB Platform bracket M with Bracket railing post
Make sure that the claws of the Bracket railing post M fit over the welded-on bolt of the plat-form bracket.
A Fixing pin
9723
-278
-01
A B
A97
23-2
77-0
1
20 999723002 - 10/2011
Assembly instructions User information Bracket platform M
The Formwork Experts
Corner solutionsThe system offers several different ways of dealing with corner zones.The result is safe corner transitions that meet all possi-ble requirements.All corner configurations are designed not to need any extra connections to the adjacent platforms.
Corner platform decking M as the outside corner
Platform decking can be placed onto the Corner plat-form decking M from both sides. This makes it easy to create closures in the corner zones.The whole unit can be lifted and repositioned in a single crane cycle. This makes it possible to arrange platform layouts very quickly, even in corner zones.Another advantage of this type of corner is that the full working width of 1.55 m is still available.For drops of up to 3.00 m.
a ... 155.0 cm b ... Closure width max. 200 cm c ... 250.0 cm d ... 15.0 cm e ... 10.0 cm f ... 35.0 cm g ... 22.5 cmA Corner platform railing M
B Corner platform decking MC Platform bracket MD Corner platform strut M
9723
-213
-01
A
B
C
D
A Bracket platform MB Corner platform decking M as the outside cornerC Platform decking M 3.00m
9723-264-01
c
e d
a
ab
fg
d
A
C B
User information Bracket platform M Assembly instructions
21999723002 - 10/2011
The Formwork Experts
Assembly instructions
Mounting the rear railings➤ Insert the Corner platform railing M into the Corner
platform decking M.➤ Pull out the lifting bows from their recesses and
attach the 4-part chain. Lift the platform.
Attaching and fastening the Platform brackets M➤ Hook the first bracket into the front claws of the plat-
form.➤ Lift the Corner platform decking M.
The Platform bracket M (C) now automatically pivots upwards.
➤ Push through a scaffolding bolt and lock it.➤ Tighten the Star grip nut G
➤ Hook in and fasten the second Platform bracket M.
The fixing components are captively connected to the bracket.
Mounting the Corner platform M➤ Place the Corner platform strut M in the horizontal in
such a way that the hooks engage in the shaped tubes of the bracket pressure plate.
Fastening the Corner platform strut M at the bottom
➤ Tilt up the Corner platform strut M and fasten it with a scaffolding bolt and a Star grip nut G.
A Corner platform railing MB Corner platform decking M
A Platform bracket M
9723-221-01
A
B
9723
-222
-01
A
The handle (F) must be pointing in the direc-tion of the bracket plane!
The hooks of the Corner platform strut M must engage in the shaped tubes of the bracket pressure points.
9723
-281
-03
D
E
F
9723-212-01
9723-211-01
22 999723002 - 10/2011
Assembly instructions User information Bracket platform M
The Formwork Experts
Corner platform decking M as the inside cornerThe Corner platform decking M is designed so that it can also be used for inside corners. To do this, the two platform brackets are mounted in parallel with one another. The direction of the brackets relative to the Corner platform decking is not important and can be chosen as best suits the usage situation.It is also possible to place platform decking on one side, to bridge gaps.
a ... 155.0 cm b ... 120.0 cm c ... 195.0 cm d ... 25.0 cm
Assembly instructionsLifting the Corner platform decking M by crane➤ Pull out the lifting bows from their recesses and
attach the 4-part chain. Lift the platform.Suspending and fixing the Platform bracket M➤ Hook both brackets into the front claws of the Corner
platform decking M.➤ Lift the Corner platform decking M. The Platform
bracket M now automatically pivots upwards➤ Push through a scaffolding bolt and lock it.➤ Tighten the Star grip nut G
A Corner platform decking MB Platform bracket M
A Bracket platform MB Corner platform decking M as the inside cornerC Platform decking M 3.00m
9723
-215
-01
A
C
B
ab
a
c
d
9723-266-01
☞ Important note:Closures are not allowed on the cantilevering side (A) of the Corner platform M!
The handle (F) must be pointing in the direc-tion of the bracket plane!
A
9723-266-01
User information Bracket platform M Assembly instructions
23999723002 - 10/2011
The Formwork Experts
Corner transition M 1.80mThis ready-to-use, fold-down platform is a fast, safe way of providing outside corner transitionsWhen folded closed, it is easy to transport and does not take up much storage space.
Necessary preconditionThe first suspension points for the two bracket plat-forms (one on either side of the corner) must be located at a distance 'a' of 15.0 cm from the edge of the struc-ture.
● Clear access passage 0.90 m● For drops of up to 3.00 m.
Assembly instructions➤ Tilt up the railings of the Corner transition M 1.80m:
These automatically slot in when they reach the stop.➤ Pull out both lifting bows from their recesses, and
attach the lifting chain.➤ Place the decking of the Corner transition M 1.80m
down onto the two bracket platforms on either side of the corner, so that it covers an equal length of each platform.Apart from this, no other fixing is needed.
Field-built corner solutions using planksIf there are no ready-made corner solutions available on the site, corners may be safeguarded using field-built solutions.
Necessary preconditionThe first suspension points for the two bracket plat-forms (one on either side of the corner) must be located at a distance 'a' of 15.0 cm from the edge of the struc-ture.● Clear access passage 0.90 mDrop height:● up to 2.50 m without Universal handrail lengthening
piece M● up to 3.00 m with Universal handrail lengthening
piece M
Assembly instructions➤ Cover the corner zone with planks. (Min. overlap
25 cm).➤ Insert the guard-rail boards through the gaps in the
lattice railings, at chest, medium and footguard height.
➤ Push a Universal handrail lengthening piece M all the way into the handrail post of each of the adjoining platform decking units
➤ Insert a top guard-rail board into the holders on the Universal handrail lengthening piece M.
The guard-rail boards must be at least 4x20 cm, and the planks at least 5x20 cm.
A Corner transition M 1.80m
9723-245-01
a
a
9723-233-01
A
A Universal handrail lengthening piece MB PlanksC Guard-rail boards
9723-226-01
A
C
B
24 999723002 - 10/2011
Assembly instructions User information Bracket platform M
The Formwork Experts
Bridging storey-high openings
With Lengthening piece MThe Lengthening piece M is required in situations where the pressure point of the Bracket platform is not resting against part of the structure (as in e.g. skeleton-type construction, wall openings etc).
a ... min. 2.40 m – max. 4.00 m
Adjustable support shoeMarkings on the vertical tube of the Lengthening piece make it easier to position the support shoe.
Extra horizontal bridgingFor usage situations where the support shoe does not rest up against any part of the building, a Multipurpose or steel waling WS10 Top50 can be used to bridge the gap. ➤ The Multi-purpose waling must be secured so that it
cannot fall off.
A Lengthening piece M
9723
-216
-01
A
9723-263-01
a
A MarkingB Support shoe
Safety railings on raised Bracket platform M
(A) The ∅ 13 mm holes drilled in the profile of the Platform bracket M make it possible to attach site-provided guard-rail boards, as a fall-arrest barrier
A Multi-purpose waling WS10 Top50B Hexagon screw M16x100 + Hexagon nut M16
9723
-217
-01
A
B
3.5
9723-261-01
A
9723-267-01
AB
User information Bracket platform M Assembly instructions
25999723002 - 10/2011
The Formwork Experts
Assembly instructions➤ Lift the Bracket platform M by crane.➤ Bolt the Lengthening piece M in the hole (A) on the
bracket, using a connection bolt, and secure this with a spring cotter.
➤ The Lengthening piece automatically swivels down-wards the further the Bracket platform is lifted.
➤ Detach the front strut of the Lengthening piece from the transport lock and bolt it onto the bottom pres-sure point (B) of the bracket, using a connection bolt secured with a spring cotter.
The Bracket platform M plus Lengthening piece is now ready for use.
9723-259-01
A
9723-262-01
9723-260-01
B
26 999723002 - 10/2011
Assembly instructions User information Bracket platform M
The Formwork Experts
Handrail lengthening piece for extending the range of use of the Bracket platform M as a rooftop fall barrierThe Universal handrail lengthening piece M signifi-cantly extends the range of use of the Bracket platform M as a sloping-rooftop fall barrier (see the section headed "Areas of use")
With Corner platform decking M
Overall height of railings 1.90 m
Assembly instructions➤ Push a Universal handrail lengthening piece M all
the way into the handrail post of each of the adjoining platform decking units.
➤ Insert scaffolding tubes into the quick-acting cou-plings of the Universal handrail lengthening piece M. Wedge in place firmly.
➤ Connect the scaffolding tubes at the corner with a Swivel coupler 48.3 mm.
➤ Fix the safety nets in place.
With Corner transition M 1.80m
Overall height of railings 1.90 m
Assembly instructions➤ Tilt up the railings of the Corner transition M 1.80m:
These automatically slot in when they reach the stop.➤ Pull out both lifting bows from their recesses, and
attach the lifting chain.➤ Place the decking of the Corner transition M 1.80m
down onto the two bracket platforms on either side of the corner, so that it covers an equal length of each platform. (Apart from this, no other fixing is needed).
➤ Push a Universal handrail lengthening piece M all the way into the handrail post of each of the adjoining platform decking units.
➤ Insert scaffolding tubes into the quick-acting cou-plings of the Universal handrail lengthening piece M. Wedge in place firmly.
➤ Link the scaffolding tubes at the corners with Swivel couplers 48.3mm.
➤ Fix the safety nets in place.
A Corner platform decking M (as the outside corner)B Universal handrail lengthening piece MC Scaffolding tube 48.3mmD Swivel coupler 48mmE Safety net
9723-228-01
A
C
EBD
A Corner transition M 1.80mB Universal handrail lengthening piece MC Scaffolding tube 48.3mmD Swivel coupler 48mmE Safety net
9723-232-01
A
C
EB D
User information Bracket platform M Assembly instructions
27999723002 - 10/2011
The Formwork Experts
With in-situ bridging using planks
Overall height of railings 1.90 m
Assembly instructions➤ Cover the corner zone with planks. (Min. overlap
25 cm).➤ Insert the guard-rail boards through the gaps in the
lattice railings, at chest and footguard height, and for fixing the net to.
➤ Push a Universal handrail lengthening piece M all the way into the handrail post of each of the adjoining platform decking units.
➤ Insert scaffolding tubes into the quick-acting cou-plings of the Universal handrail lengthening piece M. Wedge in place firmly.
➤ Link the scaffolding tubes at the corners with Swivel couplers 48.3mm.
➤ Fix the safety nets in place.
using the Bracket railing post
Assembly instructions➤ Take off the fixing-plate from the top of the Bracket
railing post M.This makes it possible to push the Universal handrail extension M all the way in.
➤ Push a Universal handrail extension M all the way into each of the Bracket railing posts M.
➤ Attach guard-rail boards at foot and chest height, and for fixing the net to.
➤ Insert scaffolding tubes into the quick-acting cou-plings of the Universal handrail lengthening piece M. Wedge in place firmly.
➤ Fix the safety nets in place.
A PlanksB Universal handrail lengthening piece MC Scaffolding tube 48.3mmD Swivel coupler 48mmE Safety net
9723-225-01
A
C
EB
D
A Bracket railing post MB Guard-rail board min. 15x3 cm (site-provided)C Universal handrail extension MD Scaffold tube 48.3mmE Safety net
D
E
A
B
C
9723-295-01
28 999723002 - 10/2011
Assembly instructions User information Bracket platform M
The Formwork Experts
Moving the platformThe Bracket platforms M are normally lifted using suit-able four-part lifting chains such as the Doka 4-part chain 3.20m.In special usage situations, the Platform transport fork K/M may be used.
Lifting with Platform transport fork K/MAlways use the Platform transport fork K/M for lifting the platforms:● when it is not possible to walk onto the platform to
attach the four-part lifting chain;● when the platform is being used as a sloping-rooftop
fall barrier and cannot be lifted out by four-part lifting chain because of the projecting eaves.
a ... min. 35 cm
Follow the directions in the "Platform transport fork K/M" Operating Instructions!
☞ Before using with Bracket platforms M, check the following:The telescopic beam must be completely pushed in, and fixed in place.
Close-up showing telescopic beam pushed in
9723-283-01
a
User information Bracket platform M Anchoring on the structure
29999723002 - 10/2011
The Formwork Experts
Anchoring on the structureOverview of suspension methodsReaction forces when subjected to a load correspond-ing to Load Class 4 EN 12811-1 and DIN 4420-1 (300 kg/m2)
Suspension point in concreteWithout insulation (standard suspension point)
Suspension point for reduced loading require-ments
Suspension point fixed in a hole subsequently drilled in the concrete
Suspension points subsequently fixed onto the concrete floor-slabWithout insulation, or with insulation up to 10 cm thick
With insulation and/or facing-brickwork between 10 and 30 cm thick
Retrofitted suspension point in masonry
Permitted horizontal force: 8.6 kNPermitted vertical force: 10.7 kN
Expendable partSuspension loop ES
2 per bracket
Expendable parts Re-useable partsBridge edge beam anchor
30kN/15.0
Nailing cone 15.0
Suspension shoe M
Screw-in cone 30kN/15.0
1 of each, for each bracket
Re-useable partSuspension shoe M Dowel
1 of each, for each bracket
Re-useable partSuspension plate ES
1 per bracket
Re-useable partSuspension profile ES
1 per bracket
Re-useable partsSuspension shoe M, Wall anchor M and Anchor bracket M
1 of each, for each bracket97
23-2
31-0
1
30 999723002 - 10/2011
Anchoring on the structure User information Bracket platform M
The Formwork Experts
Suspension point in concrete
Without insulation (standard sus-pension point)
with Suspension loop ES
The Suspension loop ES from Doka conforms to the DIN, EN and ÖNORM rules. For other makes of loop, a statical check must be performed.
a ... min. 50 cmb ... min. 13.0 cmc ... 9.0 cmd ... 9.0 to 10.0 cme ... 8.0 cmf ... 4.0 cm
Corner solution
g ... 15 cm
Installation➤ Embed the Suspension loops ES in the concrete
floor-slab.➤ After the concrete has cured, hang the bracket plat-
forms into place.
Permitted live load: 3.0 kN/m2 (300 kg/m2)Load Class 4 to EN 12811-1:2003
Characteristic cube compressive strength of the con-crete (fck,cube):min. 10 N/mm2 or 100 kg/cm2
A Suspension loop ES
☞ Do not deform (bend, buckle etc.) Suspension loops!
Restriction applicable when used in Austria:● Permitted service load: 2.0 kN/m2 (200 kg/m2)
when suspended from ∅ 8 mm loops (see "Con-struction Worker Protection Ordinance (BauV) § 63, Sect. 4")
a
c
b
A9723-269-01
9725-417-01
d
e
ff
9723-291-01
g
g
User information Bracket platform M Anchoring on the structure
31999723002 - 10/2011
The Formwork Experts
Suspension point for reduced load-ing requirementsThe Bridge edge beam anchor 30kN 15.0 is type-tested.
Fitting the Bridge edge beam anchor➤ Nail a Nailing cone to the form-ply (position as shown
in shop drawing / assembly plan).
➤ Push the Bridge edge beam anchor onto the nailing cone.
➤ Tie the Bridge edge beam anchor tightly to the rein-forcements with binding wire.This prevents it becoming detached during pouring and vibrating.
After formwork has been struck➤ Remove the Nailing cone from the anchoring point.
a ... Depth of concrete cover 4.0 cmb ... Installation depth 11.5 cm
Mounting the Suspension shoe MTools needed: ● Reversible ratchet 1/2"● Extension 11cm 1/2"➤ Fix the Suspension shoe M in the Bridge edge beam
anchor 30kN 15.0 with a Screw-in cone 30kN 15.0.
To make the suspension point reusable and achieve lasting protection against corrosion*Where an ungalvanised "standard" Bridge edge beam anchor 30 kN 15.0 has been used, you can give the suspension point lasting (electrochemical) protection against corrosion by screwing a Zinc plug 15.0 into the anchor after the formwork has been removed.* European Patent EP 1 045 087Field of use: Especially in bridge-building:● piers● superstructuresFor suspension points which are intended to be re-usa-ble in many years' time, when the time comes to reha-bilitate the structure.
Permitted live load: 2.0 kN/m2 (200 kg/m2)Load Class 3 to EN 12811-1:2003
A Nailing cone 15.0B Sealing ring
Make sure that the sealing ring is fitted cor-rectly!
C Bridge edge beam anchor 30kN 15.0Z Extra reinforcement steel
☞ If statically required – place extra reinforcement steel.
9418
-203
-01AB
9418
-204
-01
ZC
A Nailing cone 15.0
C Bridge edge beam anchor 30kN 15.0E Suspension shoe MF Screw-in cone 30kN 15.0
9418-205-01
a
b
A
9723-292-01
FC
E
32 999723002 - 10/2011
Anchoring on the structure User information Bracket platform M
The Formwork Experts
Suspension point fixed in a hole subsequently drilled in the concrete
a ... 6 cmThe dowel is fitted in the small (diam. 21 mm) hole in the Suspension shoe.
e.g.: Hilti stud anchor HST M20/30 or equivalent dow-els from another manufacturer.
Other possible areas of use for the Suspension shoe M
In walls
with a Stop-anchor 15.0 16cm
a ... 2.0 cm
In floor-slabs
with a Pigtail anchor 15.0
a ... 2.0 cm
Permitted live load: 3.0 kN/m2 (300 kg/m2)Load Class 4 to EN 12811-1:2003
C Suspension shoe M
Minimum load-bearing capacity for dowel-type connections (these forces occur simultaneously): Tensile force: Rd≥ 24.9 kN (Fperm≥ 16.6 kN) Shear force: Rd≥ 16.1 kN (Fperm≥ 10.7 kN)Follow the manufacturer's applicable fitting instruc-tions.
9723-271-01
a
C
Permitted live load: 3.0 kN/m2 (300 kg/m2)Load Class 4 to EN 12811-1:2003
A Stop-anchor 15.0 16cmB Suspension cone 15.0 5cmC Suspension shoe M
A Pigtail anchor 15.0B Suspension cone 15.0 5cmC Suspension shoe M
9723-274-01
a
A
CB
9723-275-01
a
A
CB
User information Bracket platform M Anchoring on the structure
33999723002 - 10/2011
The Formwork Experts
Retrofitted suspension point in masonry
With Suspension shoe M, Wall anchor M and Anchor bracket M
a ... 2.0 cmα ... max. 45°
Installation
Tools needed: ● Spanner for tie-rod 15.0/20.0➤ Drill a ∅28 hole through the masonry at the point
required.➤ Insert the Wall anchor M.➤ Push the Multi-purpose waling WS10 Top50 (min.
1.00 m long) onto the Wall anchor M and fix it with the Anchor bracket M.
➤ Bolt the plumbing strut onto the Anchor bracket M and anchor it to the floor-slab so that it is resistant to tensile and compressive forces.
Drilled holes in the footplates
a ... diam. 26 mm b ... diam. 18 mm
Anchoring the footplateThe Doka Express anchor can be re-used many times over - the only tool needed for screwing it in is a ham-mer.
Dismantling➤ Remove the Bracket platforms M.
➤ Unscrew the Express anchor or dowel, and remove the suspension point.
Permitted live load: 3.0 kN/m2 (300 kg/m2)Load Class 4 to EN 12811-1:2003
A Anchor bracket MB Multi-purpose waling or Steel waling WS10 Top50C Wall anchor MD Suspension shoe ME Plumbing strut for pre-cast membersF Doka Express anchor 16x125mm
➤ Only anchor in masonry that has sufficient load-bearing capacity.
Bulk density ≥ 0.8 kg/dm3 Characteristic compressive strength: ≥ 10 N/mm2 (100 kg/cm2) Wall thickness at least 24 cm
☞ Important note:Special care is needed when preparing suspen-sion points in masonry. Every suspension point must be inspected by a skilled person before being loaded.
9723-272-01
a
A
B
C
D
E
F
Plumbing strut 340, 540 Plumbing strut 260
Characteristic cube compressive strength of the con-crete (fck,cube): min. 25 N/mm2 or 250 kg/cm2 (C20/25 grade concrete)
Follow the Fitting Instructions!
Required safe working load of alternative anchors for foot-plates: Rd≥ 20.3 kN (Fpermissible≥ 13.5 kN)Follow the manufacturer's applicable fitting instruc-tions.
Before proceeding with any further worksteps, make absolutely sure that the platforms have been removed from the suspension points.
a
9727-343-01
b
9723-288-01
b
34 999723002 - 10/2011
Anchoring on the structure User information Bracket platform M
The Formwork Experts
Suspension points subsequently fixed onto the concrete floor-slabFor creating suspension points on concrete floor-slabs when building in brick or refurbishing old buildings.
Without insulation, or with insula-tion up to 10 cm thick
With Suspension plate ES
a ... 60.0 cmb ... min. 16.0 cm
Corner solution with Corner suspension plate M
The Corner suspension plate M provides an improved method for suspending Bracket platforms M in corner zones. This component prevents Suspension plates ES "colliding" in the corners.
Dismantling➤ Remove the Bracket platforms M.
➤ Unscrew the Express anchor or dowel, and remove the suspension point.
Permitted live load: 3.0 kN/m2 (300 kg/m2)Load Class 4 to EN 12811-1:2003
A Suspension plate ESB Doka Express anchor 16x125mmC Insulation, max. 10 cm thick
Minimum load-bearing capacity for dowel-type con-nections (these forces occur simultaneously):Tensile force: Rd≥ 7.5 kN (Fperm≥ 5.0 kN)Shear force: Rd≥ 12.9 kN (Fperm≥ 8.6 kN)e.g.: Doka Express anchor 16x125mmMinimum value of the characteristic cube compressive strength (fck,cube): 25 N/mm2 or 250 kg/cm2 (C20/25 grade concrete)
Follow the directions in the "Doka Express anchor 16x125mm" Installation Instructions!
Installation hint:Leave out a brick where the suspension plate is to be mounted. The suspension plate can then be dismounted from inside the structure.
9723
-273
-01
AB
a
b
C
9725-420-01
A Corner suspension plate MB Doka Express anchor 16x125mmC Insulation, max. 5 cm thick
Minimum load-bearing capacity for dowel-type con-nections (these forces occur simultaneously):Tensile force: Rd≥ 7.5 kN (Fperm≥ 5.0 kN)Shear force: Rd≥ 18.3 kN (Fperm≥ 12.2 kN)e.g.: Doka Express anchor 16x125mmMinimum value of the characteristic cube compressive strength (fck,cube): 25 N/mm2 or 250 kg/cm2 (C20/25 grade concrete)
Follow the directions in the "Doka Express anchor 16x125mm" Installation Instructions!
Before proceeding with any further worksteps, make absolutely sure that the platforms have been removed from the suspension points.
TR593-200-01
C
B
A
User information Bracket platform M Anchoring on the structure
35999723002 - 10/2011
The Formwork Experts
With insulation and/or facing brick-work between 10 and 30 cm thick
With Suspension profile ES
a ... 113.0 cmb ... min. 16.0 cmc ... max. 30.0 cm
Dismantling➤ Remove the Bracket platforms M.
➤ Unscrew the Express anchor or dowel, and remove the suspension point.
A Suspension profile ESB Express anchor 16x125mmC InsulationD Facing brickwork
Minimum load-bearing capacity for dowel-type con-nections (these forces occur simultaneously):Tensile force: Rd≥ 7.5 kN (Fperm≥ 5.0 kN)Shear force: Rd≥ 12.9 kN (Fperm≥ 8.6 kN)e.g.: Doka Express anchor 16x125mmMinimum value of the characteristic cube compressive strength (fck,cube): 25 N/mm2 or 250 kg/cm2 (C20/25 grade concrete)
Follow the directions in the "Doka Express anchor 16x125mm" Installation Instructions!
Installation hint:Leave out a brick where the suspension plate is to be mounted. The suspension plate can then be dismounted from inside the structure.
9723-286-01
AB
D
a
c
bC
9725-421-01
Before proceeding with any further worksteps, make absolutely sure that the platforms have been removed from the suspension points.
36 999723002 - 10/2011
Anchoring on the structure User information Bracket platform M
The Formwork Experts
Suspension points in pre-cast construction
On hollow-wall elements
For using the Bracket platform M on prefabricated hol-low-wall elements.
a ... 2490 mm
Shoring the panel
Hollow-wall anchor
➤ Anchor the plumbing strut to the ground so that it is resistant to tensile and compressive forces!
Assembly instructions➤ Fit the Precast member head M into the Platform
bracket M➤ Swivel it forwards
➤ Bolt it in place with a Tube wedge 16mm and secure with a 3mm spring cotter (the play of up to 5 mm compensates for any tolerances).
Once the Pre-cast member head M has been mounted to the Bracket platform M, the unit is ready to be used on hollow-wall elements.The Pre-cast member head M can also be premounted in the same way on the Platform bracket M.
Permitted service load: 1.5 kN/m2 (150 kg/m2)Load Class 2 to EN 12811-1:2003
A Precast member head MB Platform decking M 3.00mC Platform bracket MD Plumbing strut for pre-cast membersE Doka express anchor 16x125mmF Hollow-wall anchor
Max. compressive load which may occur: Fk = 6.6 kN (Rd = 9.9 kN)
CAUTION➤ Make sure that the pre-cast members have
adequate shoring!➤ Do not suspend bracket platforms from dam-
aged hollow-wall elements (do a sight-check first). Before using the Precast member head M, check with the pre-cast part manufacturer to establish whether the loads imposed by the platform can be sustained (if necessary, pro-vide extra reinforcement steel as statically required).
➤ Mount the Precast member head M in the top drop-in position only – as shown in the practical example.
9723-289-01
a
A
F
B
E
C
DF
A Plumbing strut for pre-cast membersB Hollow-wall anchor
TR566-216-04
A
B
TR56
6-20
0-01
1
2
TR56
6-20
1-01
User information Bracket platform M Anchoring on the structure
37999723002 - 10/2011
The Formwork Experts
To prevent the drop-in rod being encased in concrete when the hollow-wall element is filled, a Mounting sleeve M (expendable part) must be fitted over it.➤ Push on the Mounting sleeve M as far as it will go
This means that all the system components (corner transitions, closures etc.) are also available for use on construction sites where pre-cast hollow-wall elements are being used.
Resetting by crane➤ Use the right slinging points! (Always attach the
slings to the suspension rings on the inside of the Precast member head M)
On solid pre-cast membersThis is the standard mode of utilisation in normal con-crete and masonry construction.To cut costs when pre-cast members are to be used, the anchoring components for mounting the Suspen-sion shoes should be incorporated in the pre-cast members as part of their production process.This type of suspension point is especially appropriate for solid pre-cast members.The necessary load-bearing capacities of the embed-ded components must be discussed and agreed with the pre-cast part plant, in line with the intended pur-pose.
a ... 115 mm
For instructions on installing the Bridge edge beam anchor, see the section headed "Suspension point in concrete".
Shoring the panel
For instructions on installing the Bridge edge beam anchor, see the section headed "Suspension point in concrete".➤ Anchor the plumbing strut to the ground so that it is
resistant to tensile and compressive forces!A Precast member head MB Doka 4-part chain 3.20mC Platform bracket MD Platform decking M 3.00m
TR56
6-21
3-01
9723-287-01
AB
9723-287-01
C
A
B
D
A Bridge edge beam anchor 30kN 15.0B Screw-in cone 30kN 15.0C Suspension shoe MD Pre-cast concrete member
A Bridge edge beam anchor 30kN 15.0B Tie-rod 15.0C Hexagon nut 15.0D Plumbing strut for pre-cast members
9723-292-01
a
BA
C
D
TR566-216-03
A
B
C
D
38 999723002 - 10/2011
General remarks User information Bracket platform M
The Formwork Experts
General remarksSideguards on exposed platform-endsOn pouring platforms that do not completely encircle the structure, suitable sideguards must be placed across exposed end-of-platform zones.
Side handrail clamping unit T
The sideguard consists of:● 1 side handrail clamping unit T● 1 railing plank min. 15/3 cm (in situ)How to mount:➤ Fasten the clamping part to the decking of the
Bracket platform using the wedge (clamping range 4 to 6 cm).
➤ Slot in the railing.➤ Extend the telescopic railing to the desired length
and secure it.➤ Insert footguard (railing plank).
Handrail clamp S
The sideguard consists of:● 2 Handrail clamps S● 3 guardrail boards, min. 15 x 3 cm (in-situ)How to mount:➤ Fasten the handrail clamps to the decking of the fold-
ing platform using the wedge (clamping range 2 to 43 cm).
➤ Secure the guardrail boards to the loops on the Handrail clamp S with one 28 x 65 nail per loop.
A Integrated telescopic handrailB Guard-rail board min. 15x3 cm (in-situ)C Bracket platform M
9723
-220
-01
A
CB
A Guard-rail board min. 15x3 cm (in-situ)B Handrail clamp SC Bracket platform M
Follow the directions in the “Handrail clamp S” User information!
9723
-219
-01
A
B
C
User information Bracket platform M General remarks
39999723002 - 10/2011
The Formwork Experts
Fall-arrest systems on the structure
Handrail post XP 1.20m● Attached with Screw-on shoe XP, railing clamp,
Handrail-post shoe or Step bracket XP● Protective grating XP, guard-rail boards or scaffold
tubes can be used as the safety barrier
a ... > 1.00 m
Handrail clamp S● Attached with integral clamp● Guard-rail boards or scaffold tubes can be used as
the safety barrier
a ... > 1.00 m
Handrail clamp T● Fixed in embedded anchoring components or
reinforcement hoops● Guard-rail boards or scaffold tubes can be used as
the safety barrier
a ... > 1.00 m
Handrail post 1.10m● Fixed in a Screw sleeve 20.0 or Attachable sleeve
24mm● Guard-rail boards or scaffold tubes can be used as
the safety barrier
a ... > 1.00 m
Follow the directions in the "Edge protection system XP" User Information booklet!
Follow the directions in the “Handrail clamp S” User information!
9803
1-20
0-01
a
geprüfte
Sicherheit
9756
-206
-01
a
geprüfte
Sicherheit
Follow the directions in the "Handrail clamp T" User Information!
Follow the directions in the "Handrail post 1.10m" User Information!
9755
-205
-01
a
geprüfte
Sicherheit
9771
-200
-01
a
geprüfte
Sicherheit
40 999723002 - 10/2011
General remarks User information Bracket platform M
The Formwork Experts
Transporting, stacking and storing
Pallet for platform brackets MStorage and transport device for Platform brackets M (max. 18 per pallet):● durable● stackable – both when filled and when folded closed● collapsible – do not take up much spaceSuitable transport appliances:● crane● pallet stacking truck● forklift truck
a ... 280 cmb ... 115 cmc ... 156 cm
The pallets can be collapsed to save space when trans-ported empty.
b ... 115 cmd ... 146 cme ... 41 cmStacking height of 6 pallets on top of one another: 236 cm.➤ After unfolding the pallet, fix all four corner-posts
firmly by hammering in the wedge.
Loading the transport device➤ Place the brackets into the pallet alternately from
right and left, as shown in the illustration.
Max. carrying capacity: 600 kgPermitted imposed load: 2000 kg
☞ ● Multi-trip packaging items that each contain very different loads must be stacked with the heaviest ones at the bottom and the lightest ones at the top!
● Rating plate must be in place and clearly leg-ible
9723-202-01
c
b
a
The top hooks of the Platform brackets M must be hooked into the cross-profiles of the pallet.
9723-297-01
e
b d
9723-297-02
9221-208-01
9723
-298
-01
User information Bracket platform M General remarks
41999723002 - 10/2011
The Formwork Experts
Using 'Pallets for platform brackets M' as stor-age units
Max. n° of units on top of one another
Using 'Pallets for platform brackets M' as transport devices
Lifting by crane
Repositioning by forklift truck or pallet stacking truck
When stacked horizontally
Alternately nesting the Platform brackets M in one another protects them against slippage.When transporting them by truck, secure them with ten-sion straps as well.
Platform decking M 3.00mSpace-saving, and safe against overturningStack of 18 Platform decking units M 3.00 m (2 stacks of 9 each).
Note:Only ever lift bundles of 9 platform decking units at a time.
Alternately nesting the Platform brackets M in one another protects them against slippage.When transporting them by truck, secure them with ten-sion straps as well.When folded closed, the platform decking units are easy to transport and store.
Outdoors (on the site) IndoorsFloor gradient up to 3% Floor gradient up to 1%
2 full pallets 4 full pallets4 collapsed pallets 15 collapsed pallets
It is not allowed to stack empty, unfolded pallets on top of one another! 3 empty unfolded pallets
☞ ● Multi-trip packaging items may only be lifted one at a time.
● Secure the load in part-loaded pallets!● Use a suitable lifting chain. (Do not exceed
the permitted load capacity). e.g: Doka 4-part chain 3.20m.
● Spread-angle β max. 30°!
☞ ● The forks of the stacker truck may only be placed beneath the marked points (red marking)!
● Multi-trip packaging items may only be lifted one at a time.
9221-206-01
9221-207-01
9723-209-01
☞ Always place squared-timber sleepers (A) at the edges of the stack.
9723-255-01
10.6
107.
0
212.
0
12.9
9723-203-01
9723-254-01
A
42 999723002 - 10/2011
General remarks User information Bracket platform M
The Formwork Experts
This optimum packing density translates into low ship-ping volume and excellent utilisation of the loading area of the truck.
a ... 240 cm
9723-256-01
a
User information Bracket platform M General remarks
43999723002 - 10/2011
The Formwork Experts
Doka skeleton transport box 1.70x0.80m
Storage and transport devices for small items:● durable● stackableSuitable transport appliances:● crane● pallet stacking truck● forklift truckTo make the "Doka skeleton transport box" easier to load and unload, one of its sidewalls can be opened.
Using Doka skeleton transport boxes 1.70x0.80m as storage units
Max. n° of boxes on top of one another
Using Doka skeleton transport boxes 1.70x0.80m as transport devices
Lifting by crane
Repositioning by forklift truck or pallet stacking truckThe forks can be inserted under either the broadside or the narrowside of the containers.
Utilise the benefits of Doka multi-trip packaging on your site.Multi-trip packaging such as containers, stacking pal-lets and skeleton transport boxes keep everything in place on the site, minimise time wasted searching for parts, and streamline the storage and transport of sys-tem components, small items and accessories.
Max. load: 700 kgPermitted imposed load: 3150 kg
☞ ● Multi-trip packaging items that each contain very different loads must be stacked with the heaviest ones at the bottom and the lightest ones at the top!
● Rating plate must be in place and clearly leg-ible
Outdoors (on the site) IndoorsFloor gradient up to 3% Floor gradient up to 1%
2 5It is not allowed to stack empty pallets on top of one another!
➤ Only lift the boxes when their sidewalls are closed!
☞ ● Multi-trip packaging items may only be lifted one at a time.
● Use a suitable lifting chain. (Do not exceed the permitted load capacity). e.g: Doka 4-part chain 3.20m.
● Spread-angle β max. 30°!
9234-203-01
44 999723002 - 10/2011
General remarks User information Bracket platform M
The Formwork Experts
Doka multi-trip transport box 1.20x0.80m galv.
Storage and transport devices for small items:● durable● stackableSuitable transport appliances:● crane● pallet stacking truck● forklift truck
Multi-trip transport box partitionDifferent items in the Multi-trip transport box can be kept separate with the Multi-trip transport box partitions 1.20m or 0.80m.
Possible ways of dividing the box
Using Doka multi-trip transport boxes as stor-age units
Max. n° of boxes on top of one another
Using Doka multi-trip transport boxes as transport devices
Lifting by crane
Repositioning by forklift truck or pallet stacking truckThe forks can be inserted under either the broadside or the narrowside of the containers.
Max. load: 1500 kgPermitted imposed load: 7900 kg
☞ ● Multi-trip packaging items that each contain very different loads must be stacked with the heaviest ones at the bottom and the lightest ones at the top!
● Rating plate must be in place and clearly leg-ible
A Slide-bolt for fixing the partition
Multi-trip transport box partition Lengthways Crossways
1.20m max. 3 partitions —0.80m — max. 3 partitions
Tr75
5-20
0-02
A
Tr755-200-04 Tr755-200-05
Outdoors (on the site) IndoorsFloor gradient up to 3% Floor gradient up to 1%
3 6It is not allowed to stack empty pallets on top of one another!
☞ ● Multi-trip packaging items may only be lifted one at a time.
● Use a suitable lifting chain. (Do not exceed the permitted load capacity). e.g: Doka 4-part chain 3.20m.
● Spread-angle β max. 30°!
9206-202-01
User information Bracket platform M General remarks
45999723002 - 10/2011
The Formwork Experts
Doka stacking pallet 1.55x0.85m and 1.20x0.80mStorage and transport devices for long items:● durable● stackableSuitable transport appliances:● crane● pallet stacking truck● forklift truckThe Bolt-on caster set B turns the stacking pallet into a fast and manoeuvrable transport trolley.
Using Doka stacking pallets as storage units
Max. n° of units on top of one another
Using Doka stacking pallets as transport devices
Lifting by crane
Repositioning by forklift truck or pallet stacking truck
Follow the directions in the "Bolt-on castor set B" Operating Instructions!
Max. load: 1100 kgPermitted imposed load: 5900 kg
☞ ● Multi-trip packaging items that each contain very different loads must be stacked with the heaviest ones at the bottom and the lightest ones at the top!
● Rating plate must be in place and clearly leg-ible
Outdoors (on the site) IndoorsFloor gradient up to 3% Floor gradient up to 1%
2 6It is not allowed to stack empty pallets on top of one another!
☞ ● How to use with bolt-on castor set: Always apply the fixing brake when the con-tainer is "parked".When Doka stacking pallets are stacked, the bottom pallet must NOT be one with a bolt-on caster set mounted to it.
☞ ● Multi-trip packaging items may only be lifted one at a time.
● Use a suitable lifting chain. (Do not exceed the permitted load capacity). e.g: Doka 4-part chain 3.20m.
● Load the items centrically.● Fasten the load to the stacking pallet so that
it cannot slide or tip out.● When lifting stacking pallets to which Bolt-on
castor sets B have been attached, you must also follow the directions in these Operating Instructions!
● Spread-angle β max. 30°!
aDoka stacking pallet 1.55x0.85m max. 4.0 mDoka stacking pallet 1.20x0.80m max. 3.0 m
☞ ● Load the items centrically.● Fasten the load to the stacking pallet so that
it cannot slide or tip out.
92815-224-01
a
= =
46 999723002 - 10/2011
General remarks User information Bracket platform M
The Formwork Experts
Doka accessory boxStorage and transport devices for small items:● durable● stackableSuitable transport appliances:● crane● pallet stacking truck● forklift truckThe Doka accessory box is the tidy, easy-to-find way of storing and stacking all interconnection and form-tie components.The Bolt-on caster set B turns the stacking pallet into a fast and manoeuvrable transport trolley.
Doka accessory box as storage units
Max. n° of boxes on top of one another
Doka accessory box as transport devices
Lifting by crane
Repositioning by forklift truck or pallet stacking truckThe forks can be inserted under either the broadside or the narrowside of the containers.
Bolt-on castor set BThe Bolt-on caster set B turns the stacking pallet into a fast and manoeuvrable transport trolley.Suitable for drive-through access openings > 90 cm.
The Bolt-on caster set B can be mounted to the follow-ing multi-trip packaging items:● Doka accessory box● Doka stacking pallets
Follow the directions in the "Bolt-on castor set B" Operating Instructions!
Max. load: 1000 kgPermitted imposed load: 5530 kg
☞ ● Multi-trip packaging items that each contain very different loads must be stacked with the heaviest ones at the bottom and the lightest ones at the top!
● Rating plate must be in place and clearly leg-ible
Outdoors (on the site) IndoorsFloor gradient up to 3% Floor gradient up to 1%
3 6It is not allowed to stack empty pallets on top of one another!
☞ ● How to use with bolt-on castor set: Always apply the fixing brake when the con-tainer is "parked".When Doka accessory boxes are stacked, the bottom box must NOT be one with a bolt-on castor set mounted to it.
☞ ● Multi-trip packaging items may only be lifted one at a time.
● Use a suitable lifting chain. (Do not exceed the permitted load capacity). e.g: Doka 4-part chain 3.20m.
● When lifting stacking pallets to which Bolt-on castor sets B have been attached, you must also follow the directions in these Operating Instructions!
● Spread-angle β max. 30°!
Follow the directions in the Operating Instruc-tions!
92816-206-01
Article n°[kg] Article n°[kg]
47999723002 - 10/2011
User information Bracket platform M Component overview
The Formwork Experts
Component overviewDoka Safety SystemsBracket platform M
Platform bracket M 33.6 580547000Bühnenkonsole M
Platform decking M 3.00m 121.7 580548000Bühnenbelag M 3,00m
Corner transition M 1.80m 77.9 580556000Eckübergang M 1,80m
Corner platform decking M 64.7 580550000Eckbühnenbelag M
Corner platform railing M 25.4 580551000Eckbühnengeländer M
Corner platform strut M 13.3 580552000Eckbühnenstrebe M
Support lengthening piece M 33.7 580553000Abstützverlängerung M
Suspension beam M 17.6 580572000Einhängeträger M
Universal handrail extension M 6.7 580560000Universal-Geländerverlängerung M
Bracket railing post M 11.0 580554000Konsolgeländerholm M
Handrail clamp S 11.5 580470000Schutzgeländerzwinge S
Handrail clamp T 12.3 584381000Schutzgeländerzwinge T
GalvanisedLength: 136 cmHeight: 230 cm
Timber parts varnished yellowSteel parts galvanisedDelivery condition: folded closed
Timber parts varnished yellowSteel parts galvanisedDelivery condition: folded closed
Timber parts varnished yellowSteel parts galvanisedLength: 160 cmWidth: 160 cm
GalvanisedLength: 177 cmHeight: 123 cm
GalvanisedHeight: 232 cm
GalvanisedHeight: 338 cmDelivery condition: folded closed
GalvanisedHeight: 221 cm
GalvanisedHeight: 113 cm
GalvanisedHeight: 232 cm
GalvanisedHeight: 123 - 171 cm
GalvanisedHeight: 122 - 155 cm
Article n°[kg] Article n°[kg]
48 999723002 - 10/2011
Component overview User information Bracket platform M
The Formwork Experts
Handrail post 1.10m 5.6 584384000Schutzgeländer 1,10m
Screw sleeve 20.0 0.03 584386000Schraubhülse 20,0
Attachable sleeve 24mm 0.03 584385000Steckhülse 24mm
Side handrail clamping unit T 29.1 580488000Seitenschutzgeländer T
Suspension loop ES 1.0 580458000Einhängeschlaufe ES
Suspension plate ES 9.2 580493000Aufhängeblech ES
Corner suspension plate M 19.0 580591000Eckeinhängeblech M
Suspension profile ES 15.3 580596000Aufhängeprofil ES
Suspension shoe M 4.3 580557000Aufhängeschuh M
Anchor bracket M 1.2 580558000Ankerbügel M
Wall anchor M 1.5 580559000Wandanker M
Tie rod wrench 15.0/20.0 1.9 580594000Ankerstabschlüssel 15,0/20,0
Screw-in cone 30kN 15.0 0.74 581895000Einschraubkonus 30kN 15,0
Bridge edge beam anchor 30kN 15.0 0.45 581896000Bridge edge beam anchor 30kN 15.0 galv. 0.44 581890000Gesimsanker 30kN 15,0
Nailing cone 15.0 0.02 581897000Nagelkonus 15,0
Precast member head M 7.0 580573000Fertigteilkopf M
Mounting sleeve M 0.09 580574000Einbauhülse M
GalvanisedHeight: 134 cm
YellowLength: 20 cmDiameter: 3.1 cm
GreyLength: 16.5 cmDiameter: 2.7 cm
GalvanisedLength: 115 - 175 cmHeight: 112 cm
Non-treatedLength: 72 cm
GalvanisedLength: 68 cm
GalvanisedLength: 73 cm
GalvanisedLength: 109 cm
GalvanisedWidth: 15 cmHeight: 18 cm
GalvanisedWidth: 8 cmHeight: 16 cm
GalvanisedLength: 80 cm
GalvanisedLength: 37 cmDiameter: 8 cm
GalvanisedLength: 15 cm
Length: 7 cmFollow fitting instructions!
BlackLength: 7 cm
GalvanisedHeight: 55 cm
GreyLength: 29 cm
Article n°[kg] Article n°[kg]
49999723002 - 10/2011
User information Bracket platform M Component overview
The Formwork Experts
Plumbing strut 260 for precast members 13.9 588480000Justierstütze 260 für Fertigteile
Plumbing strut 340 for precast members 18.2 588296000Justierstütze 340 für Fertigteile
Plumbing strut 540 for precast members 33.3 588297000Justierstütze 540 für Fertigteile
Doka express anchor 16x125mm 0.31 588631000Doka-Expressanker 16x125mm
Doka coil 16mm 0.009 588633000Doka-Coil 16mm
Scaffold tube 48.3mm 1.00m 3.6 682014000Scaffold tube 48.3mm 1.50m 5.4 682015000Scaffold tube 48.3mm 2.00m 7.2 682016000Scaffold tube 48.3mm 2.50m 9.0 682017000Scaffold tube 48.3mm 3.00m 10.8 682018000Scaffold tube 48.3mm 3.50m 12.6 682019000Scaffold tube 48.3mm 4.00m 14.4 682021000Scaffold tube 48.3mm 4.50m 16.2 682022000Scaffold tube 48.3mm 5.00m 18.0 682023000Scaffold tube 48.3mm 5.50m 19.8 682024000Scaffold tube 48.3mm 6.00m 21.6 682025000Scaffold tube 48.3mm .....m 3.6 682001000Gerüstrohr 48,3mm
Swivel coupler 48mm 1.5 582560000Drehkupplung 48mm
Doka 4-part chain 3.20m 15.0 588620000Doka-Vierstrangkette 3,20m
Fix-De-Fix remote uncoupling system 3150kg 27.0 586014000Abhängeautomat Fix-De-Fix 3150kg
Platform transport fork K/M 194.0 580492000Bühnen-Umsetzgabel K/M
GalvanisedLength: 145 - 268 cm
GalvanisedLength: 190 - 341 cm
GalvanisedLength: 309 - 550 cm
GalvanisedLength: 18 cmFollow fitting instructions!
GalvanisedDiameter: 1.6 cm
Galvanised
GalvanisedWidth-across: 22 mm
Follow the directions in the "Operat-ing Instructions"!
Follow the directions in the "Operat-ing Instructions"!
Painted blueLength: 205 - 262 cmWidth: 210 cmDelivery condition: folded closedFollow the directions in the "Operat-ing Instructions"!
Article n°[kg] Article n°[kg]
50 999723002 - 10/2011
Component overview User information Bracket platform M
The Formwork Experts
Access system XS
Connector XS Wall formwork 20.8 588662000Anschluss XS Wandschalung
Connector XS DM/SL-1 11.7 588672000Anschluss XS DM/SL-1
System ladder XS 4.40m 33.2 588640000System-Leiter XS 4,40m
Ladder extension XS 2.30m 19.1 588641000Leiternverlängerung XS 2,30m
Securing barrier XS 4.9 588669000Sicherungsschranke XS
Ladder cage XS 1.00m 16.5 588643000Ladder cage XS 0.25m 10.5 588670000Rückenschutz XS
Ladder cage exit XS 17.0 588666000Rückenschutz-Ausstieg XS
Multi-trip packaging
Pallet for platform brackets M 74.9 580549000Palette für Bühnenkonsolen M
Doka skeleton transport box 1.70x0.80m 87.0 583012000Doka-Gitterbox 1,70x0,80m
Doka multi-trip transport box 1.20x0.80m 75.0 583011000Doka-Mehrwegcontainer 1,20x0,80m
Multi-trip transport box partition 0.80m 3.7 583018000Multi-trip transport box partition 1.20m 5.5 583017000Mehrwegcontainer Unterteilung
GalvanisedWidth: 89 cmHeight: 63 cm
GalvanisedLength: 100 cm
Galvanised
Galvanised
GalvanisedLength: 80 cm
Galvanised
GalvanisedHeight: 132 cm
GalvanisedLength: 146 cmWidth: 115 cmHeight: 156 cmFollow the directions in the "Operat-ing Instructions"!
GalvanisedHeight: 113 cmFollow the directions in the "Operat-ing Instructions"!
GalvanisedHeight: 78 cmFollow the directions in the "Operat-ing Instructions"!
Timber parts varnished yellowSteel parts galvanised
Article n°[kg] Article n°[kg]
51999723002 - 10/2011
User information Bracket platform M Component overview
The Formwork Experts
Doka stacking pallet 1.55x0.85m 42.0 586151000Doka-Stapelpalette 1,55x0,85m
Doka stacking pallet 1.20x0.80m 39.5 583016000Doka-Stapelpalette 1,20x0,80m
Doka accessory box 106.4 583010000Doka-Kleinteilebox
Bolt-on castor set B 33.6 586168000Anklemm-Radsatz B
GalvanisedHeight: 77 cmFollow the directions in the "Operat-ing Instructions"!
GalvanisedHeight: 77 cmFollow the directions in the "Operat-ing Instructions"!
Timber parts varnished yellowSteel parts galvanisedLength: 154 cmWidth: 83 cmHeight: 77 cmFollow the directions in the "Operat-ing Instructions"!
Painted blue
999723002 - 10/2011The Formwork Experts
The Doka bracket platform Mlets you work quickly and safely.
The Bracket platform M is a site-ready, lightweight working and protection platformthat gives a big boost to safety in the field of
masonry and pre-cast construction. The winner of an EU award, the Bracket platform M complies with both EN 12811-1 (for use as a
working platform), and DIN 4420 (for use as a protection platform).Doka bracket platforms M are available for rental, leasing or purchase.
At any of the Doka branches in your region.Why not give us a call?
The Doka Group's central plant at Amstetten, Austria
USADoka USA, Ltd.214 Gates RoadLittle Ferry, NJ 07643Telephone: +1 201 329-7839Telefax: +1 201 641-6254E-Mail: [email protected]: www.dokausa.com
Doka internationalDoka GmbH
Josef Umdasch Platz 1, A 3300 Amstetten, AustriaTel.: +43 (0)7472 605-0, Fax: +43 (0)7472 64430
E-Mail: [email protected]: www.doka.com
IndiaDoka India Pvt. Ltd.Plot No. 26 A, Sector-7, Khargar Mahavir Landmark Bldg.601 to 606, 6th Floor, 410210 Navi MumbaiTelephone: +91 22 2774 6452Telefax: +91 22 2774 6451E-Mail: [email protected]
IrelandDoka Ireland Formwork Techn. Ltd.Monasterboice, DroghedaTinure Industrial ComplexCounty LouthTelephone: +353 41 686 1620Telefax: +353 41 686 1525E-Mail: [email protected]
JapanDoka Japan K.K.Miwanoyama 744-6 Nagareyama-shi270-175 Chiba-KenTelephone: +81 471 78 8808Telefax: +81 471 78 8812E-Mail: [email protected]
KoreaDoka Korea Ltd.444-1, Yongdoo-ri, Gongdo-eup456-821 Anseong-Si, Gyeonggi-DoTelephone: +82 31 8053 0700Telefax: +82 31 8053 0701E-Mail: [email protected]
AlgeriaSARL Doka Algérie24 A Route de la RassautaBordj-El-Kifane, BP 170, 16120 AlgerTelephone: +213 21 21 27 42Telefax: +213 21 21 28 98E-Mail: [email protected]
AustraliaDoka Formwork Australia Pty. Ltd.52, Airds Road2566 Minto NSWTelephone: +61 2 9603 3300Telefax: +61 2 9603 3311E-Mail: [email protected]
CanadaDoka Canada Ltd.5404 - 36th Street S.E.Calgary AB T2C 1P1Telephone: +1 403 243-6629Telefax: +1 403 243-6787E-Mail: [email protected]
ChinaDoka Formwork (Shanghai) Co., Ltd.No. 3883 Yuanjiang RoadMinhang District, Building 2Shanghai 201109Telephone: +86 21 6090 0899Telefax: +86 21 6090 1099E-Mail: [email protected]
Other subsidiaries and representatives:AngolaAzerbaijanBahrainBelgiumBelarus
Bosnia andHerzegovinaBrazilBulgariaChile
CroatiaCzech RepublicDenmark EgyptEstonia
FinlandFranceGermanyGreece Hungary
Iceland IranItalyJordanKazakhstan
LatviaLithuaniaLuxembourgMaroccoMexico
NetherlandsNew ZealandOmanPanamaPoland
PortugalRomaniaRussiaSenegalSerbia
SlovakiaSloveniaSpainSwitzerlandTaiwan
ThailandUkraineVietnam
ISO 9001Certified to
KuwaitDoka KuwaitDiv. of Riham Gen. Trad. & Cont. Co.Street No. 1, Plot 157-173,Shuwaikh Port Authority Area P.O. Box 221722023 SalmiyahTelephone: + 965 2 4822 462Telefax: +965 2 4822 472E-Mail: [email protected]
LebanonDoka GmbH - Branch LebanonDamascus Street, Sodeco Square,Block C / 9th floor - AshrafiehBeirutTelephone: +961 1 612 569Telefax: +961 1 612 570E-Mail: [email protected]
NorwayDoka Norge ASHeggstadmoen 47080 HeimdalTelephone: +47 72 89 38 10Telefax: +47 72 89 38 11E-Mail: [email protected]
QatarDoka Qatar WLL2nd Gate, Light Industrial Area, Mesaieed-QatarP.O. Box 23439, Doha-QatarTelephone: +974 4 4500 628Telefax: +974 4 4500 608E-Mail: [email protected]
Saudi ArabiaDoka Formwork TechnologyMahmoud Othman & Sons LLCThalia Street, Al-Jol Building, 4th Floor, Flat 303/403/404 P.O. Box 7620Jeddah 21472Telephone: +966 0)2 669 10 08Telefax: +966 (0)2 664 86 25E-Mail: [email protected]
SingaporeDoka Formwork Pte. Ltd.9 Gul CircleSingapore 629565Telephone: +65 6897 7737Telefax: +65 6897 8606E-Mail: [email protected]
South AfricaDoka South Africa (Pty) Ltd.Johannesburg Branch2 Sebasa Road, Chloorkop Ext.10Kempton Park 1619, P.O.Box 8337, Halfway House, 1685 JohannesburgTelephone: +27 11 310 9709Telefax: +27 11 310 9711E-Mail: [email protected]
SwedenDoka Sverige ABKurödsvägen 2045155 UddevallaTelephone: +46 10 45 16 300Telefax: +46 10 45 16 309E-Mail: [email protected]
TunisiaDoka Tunisia Ltd.Rue de l‘usine, Le Kram, Zone Industrielle 2015 TunisTelephone: +216 71 977 350Telefax: +216 71 977 856E-Mail: [email protected]
TurkeyDoka Kalip-IskeleSanayi ve Ticaret A.S.Güzeller Org. San. BölgesiInönü Mah. Nazarbayev Sok. No:1941400 Gebze, KocaeliTelephone: +90 262 751 50 66Telefax: +90 262 751 50 05E-Mail: [email protected]
United Arab EmiratesDoka Gulf FZEP.O. Box 61407Jebel Ali Free Zone, DubaiTelephone: +971 4 870 8700Telefax: +971 4 870 8702E-Mail: [email protected]
United KingdomDoka UK Formwork Technologies LtdMonchelsea Farm, Heath RoadBoughton MonchelseaMaidstone, Kent, ME17 4JDTelephone: +44 1622 74 90 50Telefax: +44 1622 74 90 33E-Mail [email protected]