emf radiation - update europacable for trim mtg 10 feb 2014 1
DESCRIPTION
TRANSCRIPT
What underground cables can and can not do: Introducing the Concept of Partial Undergrounding
Meeting organised by Marian Harkin, MEP North East Pylon Pressure Dr. Volker Wendt, Director Public Affairs, Europacable
Trim, 10 February 2014
Europacable, Boulevard A. Reyers, 80 1030 Brussels
www.europacable.com
1
Introducing Europacable Objectives of today‘s presentation
Introducing Europacable: What we do and what we don´t do
Introducing the Europacable Concept of Partial Undergrounding
Overview of partial undergrounding deployment in Europe
What are the challenges ahead?
Discussion: Clarification of any technical questions you may have
2
Europacable represents approx. 85% of the European wire and cable manufacturers in Brussels
Globally leading, multinational cable makers and specialized SMEs Data-, Telecommunication- & Energy-cable technology Environmental topics EU & international standardisation
Objective Provide clear, consistent technical information to all interested parties in a fully transparent manner Raise visibility of European technology leadership
Introduction
3
Europacable does NOT take any view whether or not a line is needed does NOT take any position on the technology to be used to construct a line
Europacable
does provide the exact same technical information on extra high voltage XLPE power transmission cables (AC and DC) to all interested parties seeks to contribute to an informed discussion based on today´s state of the art technology available in Europe
Introduction
4
2012 ENTSO-E TYNDP
51.500 km EHV power lines to be built/refurbished by 2020
70% of new investments forecast in North Sea Region
But: Risk of delays
30% of current grid projects across Europe are delayed
75% of projects in North Sea Region are classified as medium or high risk of not meeting the planned commissioning date
How do we minimise delays?
mainly due to “social resistance & lengthy permitting procedures”
we need innovative solutions!
5
The Challenge: Europe needs more grids
Europacable Concept of Partial Undergrounding Essentials for 380 / 400 kV AC Networks
Most of Europe‘s new grids will be overhead lines
It‘s not „overhead lines against underground cables“
but
„Partial undergrounding complementing overhead lines in sensitive areas“
6
Europacable Concept of Partial Undergrounding Essentials of 380/400kV Partial Undergrounding
Sections upto around 20km possible without compensation
Allows for alternative, possibly shorter routing
Limited, manageable environmental and visual impact
Ability to be integrated into existing meshed AC networks
Higher investment costs may be neutralised due to quicker realisation
Core technology: Extra High Voltage Cross Linked Polyethylene Underground Cables – in short: EHV XLPE Underground Cables
7
Joint Paper on feasibility of partial undergrounding, 2011
EU Transmission System Operators (ENTSO-E) & Europacable
Co-ordinated by European Commission DG Energy
Approves EHV XLPE cable technology
“Extra high voltage cross linked polyethylene cable XLPE are mature and reliable technology”
“Partial undergrounding is a means to upgrade & expand Europe’s EHV electricity grid”
“Solutions are to be considered on a case-by-case basis”
Key reference for EHV XLPE underground cables
Available at www.europacable.com
8
EHV XLPE Cables – Key facts
EHV XLPE Cables – Key facts
Laying of EHV XLPE Cables
Usually directly buried into the ground, surrounded by sand blending, can also be installed in tunnels, ducts or pipes
Average laying depth: 1,60 m
Average cable length: 700 – 1000 meters
Cables are linked by joint bays Directly buried in the ground, surrounded only by sand blending; or
Placed in underground structure, typically 10m by 2.5m by 2.1m depth
Considerable work required during installation
9
EHV XLPE Cables – Key facts
Environmental impact
Installation works represent considerable impact on the environment
Vegetation will be re-installed after 1 – 2 seasons
Limited impact during operation No drying of soil
No limitation to cultivation apart from deeply rooted trees
No limitation on agriculture – need to introduce compensation schemes
Cable section will be visible if cutting through forest – but will blend into open landscape
10
EHV XLPE Cables – Key facts Electromagnetic Exposure
EMF over cable at full load may be higher than for overhead line but drops quicker on the sides, taking less space
Shielding technologies available – at higher cost
As for overhead lines, exposure to EMF stays well within limit of EU Recommendation 199/519/EC
11
EHV XLPE Cables – Key facts Reliability
Complete cable systems undergo thorough test procedures (IEC Standards) after production, after installation and before being placed in operation
Once in ground, cables are well protected against external impacts
XLPE underground cables are reliable technology
Repairs
Single faults on cable may take longer to repair than on overhead line - repair times on larger systems are comparable
CIGRE Brochure 379: Over 1/3 of cable faults were repaired and system re-energised within less than 1 week
More than 75% of cable faults within 1 months
Keeping spare parts is critical
N-1 Criterion ensures security of supply at all times
12
EHV XLPE Cables – Key facts
Costs of partial undergrounding
Investment cost factor for 400 kV XLPE cables is 3 – 10 dependent on project details and soil conditions (up to 60%)
3 – 10 cost multiple applies to undergrounded section only
Cost factor for investment for entire line project will be 1.2 – 2
Speedier realisation will reduce or may even neutralise investment cost
Life cycle costs of project are to be considered
13
EHV XLPE Cables – State of the Art
AC XLPE cables in use
More than 25 years commercial experience at HV levels (110-150 kV)
More than 20 years commercial experience at EHV level (220 – 275 kV)
More than 15 years experience at EHV level (380 – 400 kV)
AC XLPE cables installation globally since 2000
High Voltage: > 200.000 km
Extra High Voltage: > 10,000 km
EHV XLPE Availability
40% capacity increase from 2008 to 2011
Annual capacity for Europe alone is about 3.500 KM
Global technology leadership of European manufacturers
It works!
14
15
TenneT: Randstadt Project, The Netherlands
Total length: 85 km linking Rotterdam, Amsterdam & The Hague
Double circuit 380kV, transmission capacity 2x2635 MVA
Twofold innovation
New pylon design for overhead line „Windtrack“
Partial undergrounding on total of 20km: Southern section: 10,8 km undergrounding operational since Sept 2013
Northern section: 9,5 km undergrounding to be built 2015 - 2017
Partial undergrounding – Deployment in Europe
Projects currently in construction / in planning:
TenneT: EnLAG projects, Germany ca. 6 km Dörpen / West Meppen, in planning
ca. 7 km Fedderwahren – Conneforde, permitting phase
ca. 12 km Gannderkeese – St. Hülfe, permitting phase
ca. 8 – 10 km Wahle-Mecklar, permitting phase
Amprion: 7 km, Rasfeld, Germany
Swissgrid: 1 km, Riniken, Switzerland
RTE: over 1000 km cables 225 kV, France
National Grid: £500 Million Fund to undergrounding existing 400kV overhead lines in National Parks, UK
16
Partial undergrounding – Deployment in Europe
Conclusions
Partial undergrounding is available
Each project needs to be carefully evaluated on a case by case basis
Requires new thinking, creates new possibilities for reliable, acceptable and affordable grid extension in Europe
Need to create reliable framework for local communities & TSOs
When to deploy partial undergrounding – and when not?
How to consider partial undergrounding from the outset of permitting procedures?
How to avoid a limitation of cost considerations to installation cost only but to consider full life cycle cost – including possible effects of acceleration?
Different member states are currently pursuing different approaches
We should aim for a harmonised approach across Europe
17
18
Thank you for your attention!
Dr. Volker Wendt, Director Public Affairs
Europacable, Boulevard A. Reyers, 80 - 1030 Brussels
www.europacable.com