emergency action plan for votehole dam - karwaterresources.kar.nic.in/eap report-votehole.pdfgorur,...
TRANSCRIPT
Project ID Code KA06HH00154 Page A-2
Emergency Action Plan for
Votehole Dam KA06HH0154
Water Resources Department
State of Karnataka.
Emergency Action Plan For Votehole Dam May-2019
Project ID Code KA06HH00154 Page A-3
Emergency Action Plan
VOTEHOLE Dam
[KA06HH0154]
Prepared for
Karnataka Water Resource Department
(CAUVERY NEERAVARI NIGAM LIMITED)
Prepared by
Chief Engineer,
Hemavathy Project Zone,
Gorur.
06/05/2019
Emergency Action Plan For Votehole Dam May-2019
Project ID Code KA06HH00154 Page A-4
Votehole Dam
Project ID Code KA06HH0154
Emergency Action Plan for Votehole Dam is publishing For the First Time during April-2018
Disclaimer
Every effort has been taken to estimate the severity of flooding and inundation areas likely to be af-
fected by Votehole dam in an emergency condition. These estimates are based on available primary
and secondary data. Every effort has been made to foresee varied emergency possibilities and develop
appropriate notification procedures for timely rescue and relief operations.However, implementation
of the Emergency Action Plan (EAP) involves many agencies, who are required to work in a coordi-
nated manner to reduce the consequences of the emergency triggered by the dam site condition. Effec-
tiveness of the rescue and relief operations depend on many factors including the adequacy and accu-
racy of the estimation of the severity of flooding, coordinated efforts of all the agencies involved in
rescue and relief efforts and availability of facilities like power, telephones, road communications, etc.
EAP Developer may therefore, not be held responsible for the efficacy of the EAP.
For any information, please contact:
C.Manjappa
Chief Engineer,
Hemavathy Project Zone,
Gorur, Karnataka
Mobile Number: 9448088467
Office Number:08172-225437
Emergency Action Plan For Votehole Dam May-2019
Project ID Code KA06HH00154 Page A-5
Emergency Action Plan
Votehole Dam
Karnataka Water Resource Department (CAUVERY NEERAVARI NIGAM LIMITED)
Contents
Notification Flowchart (Watch Condition) .............................................................................................. [A5]
Notification Flowchart (Failure Condition) ............................................................................................. [A6]
EAP Distribution List .............................................................................................................................. [A7]
Log Sheet of Changes .............................................................................................................................. [A9]
Approval and Implementation ............................................................................................................... [A10]
Emergency Action Plan…………………………………………………………………… [A 11 To A12]
1. Purpose
2. Dam Description
2.1. General
2.2. Reservoir Operations
3. Responsibilities…………………………………………………………….... [A 12 To A14]
3.1. Dam Owner’s Responsibilities
3.2. Responsibilities for Notification
3.3. Emergency Operations Center
3.4. Responsibilities for Evacuation
3.5. Responsibilities for Duration, Security, Termination, and Follow-up
3.6. Communications
4. Emergency Detection, Evaluation, and Classification ………………………….. [A14 to A19]
4.1. Emergency Detection]
4.2. Emergency Evaluation and Classification
4.3. Previously Known Problems
5. Preparedness ……………………………………………………………………. .. [ A20]
6. Supplies and Resources…………………………………………………………... [A20 to 21]
6.1. Contracts
6.2. Equipment and Supplies
6.3. Reports
7. Inundation Area……………………………………………………………………….... [A22]
7.1. Local Evacuation Plan]
8. Implementation…………………………………………………………………..[A22]
8.1. Development
8.2. Updating
8.3. Testing
8.4. Training]
Tab 1 – Vicinity Map ........................................................................................................................... [A24]
Tab 2 – Inundation Map ...................................................................................................................... [A25]
Tab 3 – Dam Description ..................................................................................................................... [A58]
Tab 4 – Sample Public Announcements ............................................................................................. [A60]
Tab 5 – Evidence of Distress ............................................................................................................... [A61]
Tab 6 – Supplies and Resources .......................................................................................................... [B 1]
Tab 7 – Annual EAP Evaluation Checklist ........................................................................................ [B 3]
Tab 8 – Plan Review and Update ......................................................................................................... [B 4]
Tab 9 – Training Record ....................................................................................................................... [B5]
Emergency Action Plan For Votehole Dam May-2019
Project ID Code KA06HH00154 Page A-6
VOTEHOLE DAM –WATCH CONDITION NOTIFICATION FLOW CHART
Chief Engineer Hemavathy project Zone Office
Cauvery Neeravari Nigam Limited
Name: Manjappa.C
Title: Chief Engineer Incharge
Mobile Number: 9483510818
Name: N.C Prasad
Title: Deputy Chief Engineer
Mobile Number9449993254
Office Number: 08172-225437
Email: [email protected]
Superintending Engineer
Hemavathy project Circle
Office
Cauvery Neeravari Nigam Limited
NameC.Manjappa
Title: Superintending Engineer
Mobile Number9483510818
Office Number:08172-225298
Email: secnnlhpc-
Name C.S Vishwanath
Title: Technical Assistant to S.E.
Mobile Number:9448731989
Office Number:08172-225298 Email: [email protected]
Office of the Dam
Executive Engineer
Hemavathy Dam Division Office Gorur
Cauvery Neeravari Nigam Limited
Name: Gangadhar.
Title: Executive Engineer incharge
Mobile Number: 8618946407
Office Number:08172-256749 Email: [email protected]
Name: Puttaswamy
Title: Assistant Engineer (PA to EE)
Mobile Number:9448734343
Office Number: 08172-256749
Email: [email protected]
AvailableResources
Heavy Equipment Service
Name:Manjunatha earth
movers
Mobile Number:
9844120205
Name :- Best earth movers
Mob;_ 09845924691
sakleshpur
Sand and Gravel Supply
Name: Senior Geologist office,
K.R puram, Hassan.
Mobile Number: 9483949610
Ready Mix Concrete Supply
Name:S.L.V Ready Mix Concrete
Mobile Number:8747844121.
Name :- Shivashanker
Mobile :-9448471189,09900717383
State Dam safety Office
(SDSO)
Name: Chikkarayappa
Title: Director
Office Number: 08236-257223
Email: [email protected]
Site Office of DamOwner/Operator
Owner/Operator: Karnataka
Water Resources Department
Name: G. Hanumanthaiah
Title: Assistant Executive Engineer
Mobile Number: 9964118054
Office Number:08170-218123
email: [email protected]
Name: Sandeep K
Title: Assistant Engineer
Mobile Number: 9844243475
Office Number:08170-218123
email:[email protected]
1
3
2
Order of notification 1
Design Wing, Mysore
Name: shankaregowda
Office ;-08212477719, Mob :- 9632393263
Title: Superintending Engineer
Office Number: [email protected]
Email:
Project ID Code KA06HH00154 Page A-8
VOTEHOLE DAM –FAILURE CONDITION NOTIFICATIONFLOW CHART
Site Office of Dam Owner/ Operator
Owner/ Operator: Karnataka, WRD
Name: G. Hanumanthaiah Title: Assistant Executive Engineer
Mobile Number: 9964118054, Office Number:08170-218123
email: [email protected]
Name: Sandeep K Title: Assistant Engineer Mobile Number: 9844243475
Office Number:08170-218123, email:[email protected]
Central Water Commission
Name: N K mathur
Title: Chief Engineer(CDSO)
Mobile Number: 971733380
Office Number:011-26106848
Name: Pramod Narayan
Title: Director DRIP,CWC
Mobile Number:9958975928
Office Number: 011-26192633
Office of the District Collector
(Hassan)
Name ;- Shri. Akram Pasha,(IAS)
Title: District Collector
Mob: 948326111
Off No:08172-267345
Fax No: 08172-265418
Mail I.D: [email protected]
Heavy Equipment Service Name:Manjunatha earth mov-
ers
Mobile Number: 9844120205
Name :- Best earth movers
Mob;_ 09845924691
sakleshpur
Sand and Gravel Supply
Name: Senior Geologist of-
fice, K.R puram, Hassan.
Mobile Number: 9483949610
Ready Mix Concrete Supply
Name:S.L.V Ready Mix Concrete
Mobile Number:8747844121
Name :- Shivashanker
Mobile :-9448471189,
National Disaster Management
Authority
Name: Dr. Pradeep Kumar, IAS,
Title: Joint Secretary
Office Number: 011-26701780
Email: [email protected]
Name: A.K.Sanghi,ITS
JS (Mitigation, IT &Comn)
Title: Joint Secretary
Office Number: 011-26701718
Email: [email protected]
Karnataka state Disaster
Management Authority
Name: Srinivas Reddy
Title: Director
Phone:9742204377
Off No: 080- 67355000
Fax: +918067355198
AvailableResources
0
Order of notification
1
3 2
Exe Eng. (Dam)
HemavathyDam Division,
Gorur
Name: Gangadhar
Title: Executive Engineer
Mobile Number: 8618946407
Office Number:08172-256749
Email:
Name: Puttaswamy
Title: Assistant Engineer (PA to
EE)
Mobile Number:9448734343
Office Number: 08172-256749
Email: [email protected]
State Dam safetyOffice (SDSO)
Name: Chikkarayappa
Title: Director
office of director KERS K R sagar
mandya dist.
Office Number: 08236-257223
Email: [email protected]
Owners of Downstream
Dam: Hemavathy
Name: Gangadhar, Title: Executive Engineer
Mobile Number: 8618946407,Office Number:08172-
256749 ,Email: [email protected]
Dam :- Yagachi
Name Ramesh, Title : Executive engineer, office of
Yagachi project dision, Halebeedu road , Belur . Ph :
08177-222293, Mob : 9449294590.
Superintending Engineer
Hemavathy project Circle Office
Cauvery Neeravari Nigam Limited
NameC.Manjappa
Title: Superintending Engineer
Mobile Number9448088467
Office Number:08172-225298
Email: [email protected]
Name C.S Vishwanath
Title: Technical Assistant to S.E.
Mobile Number:9448731989
Office Number:08172-225298 Email: [email protected]
Chief Engineer
Hemavathy project Zone Office
Cauvery Neeravari Nigam Limited
NameC.Manjappa Title: Chief Engineer
Mobile Number9448088467 Office Number: 08172-225437
Email: [email protected]
Name: N.C Prasad
Title: Deputy Chief Engineer
Mobile Number9449993254
Office Number: 08172-225437
Email: [email protected]
Chief Engineer
Water Resource Department Karnataka
Name: Prabhakar Hummigi
Title: Chief Engineer
Mobile Number: 9448290891
Office Number: 080-22871174
Fax:080-22872247 ([email protected])
Email: [email protected]
Name: Pradeep mithra manjunath
Title: Project Director SPMU Drip
Mobile Number:9448270489
Office Number:08182-258872
Email: [email protected]
Managing Director
Cauvery Neeravari Nigam Limited, Bangalore
Name: H.L. Prasanna
Title: Managing Director
Mob No: 9483510818
Off No:080-22352997,
Fax:080-22352998
Mail I.D: [email protected]
Name: SRI. M. BANGARA SWAMY
Title: Technical Director
Mob No:
Off No: 080-22352997
CWC Monitoring(S), Office, Ban-
galore
Contact:
Title: Monitoring (S), CWC, JALA-
SOUDHA
Office No: 080-23376030
Email: Rajan_nair [email protected]
1
Police Control Room,
Hassan :100, 08172-
268000.
Fire Station, Hassan:
101, 268608.
Ambulance, Hassan:
102.
Government Hospi-
tal, Hassan: 08172-
268414.
Radio Station
(Prashar Bharathi)
Hassan: 08172-
246318.
TV, Five star
channel: 08172-
267333.
Emergency Action Plan For Votehole Dam May-2019
Project ID Code KA06HH00154 Page A-9
VOTEHOLE DAM
Project ID Code KA06HH0154
EAP Distribution List
A copy of the EAP has been provided to the following people:
Authority Name, Title, Phone Address
State Dam Safety Organization +
Dam Owner
Prabhakar Hummigi
Chief Engineer Mobile Number: 9448290891
080-22871174
Office of Water Resource
Development Organization, Anand
Rao Circle, Bengaluru.
Dam Owner H.L Prasanna
Managing Director
080-22352997, 9483510818
Office of Cauvery Neeravari Ni-
gam Limited,Anandaraocircle,
Bengaluru.
Dam Owner C,Manjappa
Chief Engineer
08172-225437,
Mob- 9448088467
Office of Hemavathy Project Zone,
Gorur.
Dam Owner C,Manjappa
Superintending Engineer 9448088467
08172-225298
Superintending Engineer
Office of Hemavathy Project Cir-
cle, Gorur.
Dam Operator Gangadhar
Executive Engineer
8618946407
08172-256749
O/O Executive Engineer
Hemavathy dam division, Gorur.
State Public Works Department R Shrinivas
Chief Engineer (South)
Phone No:9483008987
Office No:
080-22212830/2274301
Chief Engineer, Communication &
Buildings(South), K.R. Circle
Bangalore560001.
Hassan District Disaster Manage-
ment Authority
Not Available
District Public Works Department
Hassan District
T.N Chandrashekaraiah
Superintending Engineer
Phone
08172-268437
Superintending Engineer, PWD
Hassan circle, Hassan
Office of District Collector Hassan Shri. Akram Pasha (IAS)
District Collector
9483262111
08172-265028
Office of district collector,
Hassan, Karnataka
Office of District Collector
Chikkamagalore
Name: Sri Rangayya KAS
Title: District Collector
Mob: 9449030402
Off No:08262-230401
Office of district collector,
Chikkamaglore, Karnataka
Downstream Owner
Dam: Hemavathy
Name: Gangadhar, Title: Execu-
tive Engineer
Dam :- Yagachi
Name Ramesh, Title : Executive
engineer,.
Mobile Number: 8618946407,Office
Number:08172-256749 ,Email: Ex-
office of Yagachi project dision, Hale-
beedu road , Belur . Ph : 08177-
222293, Mob : 9449294590
Emergency Action Plan For Votehole Dam May-2019
Project ID Code KA06HH00154 Page A-10
Karnataka state Disaster
Management Authority
Name:
Title: Director
Off No: 080- 67355000
Director, Karnataka State Natural
Disaster Monitoring Centre,
KSNDMC Campus, Major
Sandeep Unnikrishnan Road,Near
Attur Layout, Yelahanka Banga-
lore - 560 064, Karnataka, INDIA,
National Disaster Management Au-
thority
Name: A K Sanghi
Title: Joint Secretary
Mitigation,IT and comn
Office Number:011-26701718
Office Number: 011-26701864
NDMA Bhavan,
A-1,Safdarjung Enclave
New Delhi-110029
Central Dam Safety Organization
L A V Nathan
Chief Engineer CDSO
Phone:9717377808
Room No 313 S, Sewa Bhava R K
puram, New Delhi
Delhi 110066
Ministry of Road Transport De-
partment, Karnataka
Public Relations Officer,
Phone: 080-22210994
E-mail: proctr-trans- [email protected]
Phone: 9449863459
Office of the Commissioner for
Transport, 1st Floor, ‘A’ Block,
TTMC Building,
Shantinagar, Bengaluru - 560027
Superintendent of Police,
Hassan
Name: Prakash gowda, IPS.
Titile: Superintendent of Police
Office Number: 08172-268410
Rangoli Halla, Hassan, Karnataka
573201
CWC Official (DRIP) Name:Pramod Narayan
Title : Director
Office Number: 011-26194604
Phone: 9958975921
Email:[email protected]
Name: Mayank Singh Chetan
Title : Deputy Director
Office Number: 011-26194604
Phone: 9953884319
Email:[email protected]
Central Water Commission, R.K.
Puram, New Delhi.
AvailableResources
Heavy Equipment Service Name:Manjunatha earth movers
Mobile Number: 9844120205
Name :- Best earth movers
Mob;_ 09845924691
sakleshpur
Sand and Gravel Supply
Name: Senior Geologist office,
K.R puram, Hassan.
Mobile Number: 9483949610
Ready Mix Concrete Supply
Name:S.L.V Ready Mix Concrete
Mobile Number:8747844121
Name :- Shivashanker
Mobile :-9448471189,
Votehole Dam
Emergency Action Plan For Votehole Dam May-2019
Project ID Code KA06HH00154 Page A-11
Project ID Code KA06HH0154
Log Sheet of Changes
The following changes have been made to the EAP and revisions have been provided to the people
shown on the EAP Distribution List.
Date Change Made Signature
Emergency Action Plan For Votehole Dam May-2019
Project ID Code KA06HH00154 Page A-12
Votehole Dam
Project ID Code [KA06HH0154]
Approval and Implementation
This Emergency Action Plan is hereby approved. This plan is effective immediately and supersedes
all previous editions.
_________
[Signature]
C.Manjappa, Chief Engineer, Hemavathy Project Zone, Gorur.
I have received a copy of this Emergency Action Plan and concur with the notification procedures.
Gangadhar.
Executive Engineer
G. Hanumanthaiah
Asistant Executive Engineer
Sandeep K
Asst Engineer
Date:
Emergency Action Plan For Votehole Dam May-2019
Project ID Code KA06HH00154 Page A-13
Emergency Action Plan
Votehole Dam
Project ID Code KA06HH0154
1. Purpose
The purpose of this Emergency Action Plan (EAP) is to identify emergency situations that could
threaten Votehole Dam and to plan for an expedited, effective response to prevent failure of the dam
and warn downstream residents of impending danger. This plan defines the notification procedures to
be followed in the event of a potentially hazardous situation. The procedures are intended to protect
lives and prevent property damage from an excessive release of water from the dam spillways or an
uncontrolled outflow of water from the breached portion of dam.
2. Dam Description
2.1. General
Votehole Dam and Reservoir are owned and operated by Cauvery Neeravari Nigam Limited It is lo-
cated on Votehole River which is a tributary of Yagachi River which flows in Cauvery basin in Has-
sanDistrictof Karnataka. The dam was completed in 1985. The reservoir was constructed to serve as
Irrigation project
A vicinity map showing the location of the dam is presented in Tab 1. Inundation mapsshowing the
areas subject to flooding as a result of a dam failure are provided in Tab 2. The inundation area is de-
scribed in further detail in the Inundation Area section of the report. Lastly,a description of the dam,
its spillways, and other features are outlined in the Dam Descriptionin Tab 3.
2.2. Reservoir Operations
Reservoir Features
FRL = 966.05mtr
MWL = 966.05mtr (3169.61 ft)
Road Level = 968.48mtr (3177.58 ft)
Revised Flood Peak = 1606 Cumecs
Sill Level of the Crest gate = 961.476 (3154.60 ft)
The spillway provided with 3 Nos. of crest gates of size 30 ft x 15 ft (Radial lift) to discharge a flood
of 577.346 cumecs (20380 cusecs) having 3 Nos. of Radial lift gates.
As per the CWC guidelines SPF has been worked out and it is approved for 1606 cumecs vide letter
no 1630 dated 19-08-2015 Hence, the spillway adequacy to be assessed with SPF which will be more
than 2.50 maximum observed flood. Hence Additional spillway is required.
RESERVOIR OPERATION DURING FLOODS
The maximum storage capacity of reser voir is 1.51 TMC. It is proposed to have 1.36 tmc storage
capacity as flood absorption below FRL during active monsoon so as to have safe and effective reser-
voirs operation schedule. The gross storage capacity and reservoir level with 1.36 tmc flood absorp-
tion capacity below FRL are as below.
R.L. Capacity in Mcft.
FRL 966.05 mtr (3169.61 ft) 1510 1510 Mcft
RL 965.44 mtr (3167.61 ft) 1363
Emergency Action Plan For Votehole Dam May-2019
Project ID Code KA06HH00154 Page A-14
The rainfall in the catchment area generally starts from 1st week of June and it is very active generally
during July, August and September months. If the flood absorption capacity of 1.36 TMC is main-
tained, the reservoir level has to be kept at 965.44 i.e., 0.60mtrt below FRL. It is better to start the res-
ervoir operation schedule duly predicting the inflow in the reservoir based on gauged discharge at
Balehonnur and also from the daily rainfall records of upstream rain gauge station in the catchment
from 1st week of June itself. However, the reservoir level of RL 965.44 mtr with cushion of 0.60mtr
should maintained till the end of August by suitably matching the inflow and outflow discharges.
During the month of September depending up on the inflow pattern, the reservoir water level may be
raised to safer level (i.e., 0.30 mtr below the FRL). From October and onwards the reservoir water
level may be brought to the FRL level depending up on the inflow pattern and forecast of floods/
monsoon.
If any flash floods or cyclonic floods are expected during October / November, careful prediction
of inflows from the upper gauge stations and from weather forecast should be done and the reservoirs
operation in advance to keep cushion for the inflow has to be carefully done.
Advance warning with quantity of water to be released in the river should be intimated to the
concern deputy commissioners of Hassan/ Superintendent of Police of Hassan, / Tahasildar alur and
Hassan , Chief Engineer, Hemavathy Zone Gorur, Superintending Engineer, Hemavathy Project Cir-
cle Gorur, Executive Engineer Hemavathy Dam Division, Gorur and concerned Tahsildar through
wireless. A wide publicity through radio, T.V., and daily Newspaper to this effect must be issued.
3. Responsibilities
3.1. Dam Owner’s Responsibilities
The dam owner, Cauvery Neeravari Nigam Limited is responsible for all dam operation and mainte-
nance. The EAP will not designate a specific person for a specific responsibility but instead will des-
ignate the person’s duties or job description.
A) Assistant Executive Engineer responsibilities
1. Responsible for conducting routine dam maintenance, such as annual weed control, con-
ducting dam integrity inspections, and notifying Executive Engineer, Hemavathy Dam
Division, CNNL, Gorur for any potential emergency situations.
2. Responsible for contacting emergency personnel if a dam failure be imminent.
3. Responsible for collecting weather forecasts and the inflow forecasts and altering of any
potential emergency situation.
B) Emergency Planning Manager Responsibilities
1. Implimentation of EAP
2. To conduct routine inspection.
3. To classify the events into the emergency alerts.
4. To ensure effective transmission of hydro meteorological and out flow data.
5. To ensure that the current approved version of EAP is functional and available to all
stakeholders.
6. Responsible for the Operation and Maintenance of the Dam.
7. Observing the dam during extreme flooding events, during holidays, on weekends, and
during normal conditions.
8. Responsible for implementing each of the required phases of the EAP.
9. In charge of Emergency response.
10. Communication and coordination channels.
11. Location of the incident command center or emergency operating center.
Emergency Action Plan For Votehole Dam May-2019
Project ID Code KA06HH00154 Page A-15
C) Superintending engineerResponsibilities
Responsible for updating the EAP. An annual EAP review will be conducted to ensure
that contact names and numbers are current on the Notification Flowcharts.
D) Chief EngineerResponsibilities
Directing specific, incident appropriate actions during an emergency, such as opening or clos-
ing water outlets and remedial construction activities such as earth moving, etc. Specific sce-
narios are not listed in this EAP.
3.2. Responsibilities for Notification
The Emergency Planning Manager is responsible for inspecting the dam in a potential emergency
such as the potential threat of high waters or a tropical cyclone. The Emergency Planning Manager
will contact the Hassancity District Police or District Collector.
If warranted, the Emergency Planning Manager will notify the District collector. The Hassan city Dis-
trict Police will notify downstream residents. The Hassan city District Collector is communications
with the disaster management authorities.
3.3. Emergency Operations Center
In the event of a failure condition, the Emergency Planning Manager will activate the Emergency
Operations Center to serve as the main distribution center for warning and evacuation activities. The
Emergency Operations Center will be established at the Office of Assistant Executive Engineer No-
02 Votehole project sub division, Alur . The Emergency Planning Manager will be responsible for
initiating actions from this location.
3.4. Responsibilities for Evacuation
The Hassan city District Police, district collector, Chief engineer, Superintending engineer, executive
engineer and all department responsibilities;
1.warn the public under emergency condition at the dam.
2. Assist the disaster management authorities during the evacuation operasions.
3. Install barrigades in all effeced bridges. etc
3.5. Responsibilities for Duration, Security, Termination, and Follow-up
The Executive Engineer is responsible for monitoring of emergency situations at the dam and keeping
authorities informed, based on the Notification Flowcharts.
The Executive Engineer and the Hassan city District Collector are responsible for declaring that an
emergency at the dam is terminated. Applicable authorities will be notified based on the Notification
Flowcharts.
The Chief Engineer will ensure that a follow-up evaluation is completed by all participants after the
emergency. The results of the evaluation should be documented in a written report and filed with the
EAP.
3.6. Communications
Local officials and downstream residents will be notified by landline telephone, if available;otherwise
via cell phones or emergency personnel (in person or using their radios). The various networks for
emergency use include the networks of the following:
• The Hassan city District Police
• The Karnataka State Disaster Management Authority
• The Karnataka Ministry of Road Transport and Highways
Emergency Action Plan For Votehole Dam May-2019
Project ID Code KA06HH00154 Page A-16
Sample public announcements appear in Tab 4. Verification or authentication of the situation can be
made by contacting the Emergency Planning Manager officials. Television, Radio and bulk SMS fa-
cilities of the local Mobile Network Operators can be used as much as possible to notify area residents
of the possible dangers. Public announcements are to be issued by the concerned Cauvery Neeravari
Nigam limited officers.
4. Emergency Detection, Evaluation, and Classification
4.1. Emergency Detection
A. Situations
Many dam conditions can lead to emergency situations, not all of which will necessitate the im-
plementation of the EAP. However, if any of them occur, the appropriate actions must be taken.
• Severe Storms/Inclement Weather: Although generally not in themselves a threat to the
dam, severe storms and other inclement weather conditions can contribute to an existing
problem and hinder any remediation efforts. Severe storms also cause the uncontrolled
release of floodwater and increase flow in already rain-swollen areas.
• Tropical cyclones: Tropical cyclones do occur in the area, with the potential for structur-
al damage to the dam, possibly resulting in its failure. If a tropical cyclone has struck in
the area, an inspection of the dam for any signs of damage will be appropriate.
• Earthquakes: Votehole Dam is located in the seismic zoneII.An earthquake is a possibil-
ity, and appropriate post-earthquake inspections should be performed.
• Sabotage: A threat to damage the dam has been made. Appropriate actions must be taken
to protect the dam.
B. Signs of Failure
The Emergency Planning Manageris responsible for conducting routine inspections and identify-
ing conditions that could indicate the onset of problems leading to a dam failure. The early iden-
tification of potentially dangerous conditions can allow time for the implementation of EAPs. It
is important to understand how distress can develop into failure. With appropriate action, distress
need not lead to a catastrophic failure of the dam. The following sections describe some of the
different types of failure which could lead to a dam failure.
• Seepage Failure: Although all earthen embankments allow some minor seepage through
the dam or the foundation, excessive, uncontrolled seepage can result in piping (the
movement of embankment material in the seepage flow) and lead to failure. Piping can
occur for years at a slow rate. If the piping has progressed to a dangerous level, it will be
evident by increased flow or the discharge of muddy water (or both). At that stage, im-
mediate action to stop the piping is needed. Fully developed piping is difficult to control
and is very likely to result in failure. A whirlpool in the reservoir is a sign of uncontrol-
lable piping and necessitates immediate emergency action.
• Embankment or Foundation Sliding: Sliding is usually first apparent when cracks or
bulges in the embankment appear. Slides with progressive movement can cause failure
of the embankment.
• Structural Failure:The structural failure or collapse of any non-overflow portion of the
dam, spillway or spillway gates could result in loss of the reservoir. A structural failure
of a portion of the spillway could cause piping and possibly embankment failure.
Emergency Action Plan For Votehole Dam May-2019
Project ID Code KA06HH00154 Page A-17
• Overtopping Failure: Overtopping of the embankment results in erosion of the dam crest.
Once erosion begins, it is very difficult to stop.
4.2. Emergency Evaluation and Classification
This section lists the conditions and actions which may be used to classify the level of emergency re-
sponse, as a guide for the Emergency Planning Manager. Specific dam observations and correspond-
ing emergency classification levels can be found in the Evidence of Distress table in Tab 5.
Internal Alert ConditionBLUE –A “watch” condition. A problem has been detected at the dam that
requires constant monitoring. At this time, the distress condition is manageable by dam personnel.
The Emergency Planning Managerwill be responsible for monitoring and repair as soon as possible
and implementing the appropriate Notification Flowchart. The following is a list of conditions that-
would initiate this condition:
• Cloudy or dirty seepage or seepage with an increase in flow, boils, piping, or bogs
• Seepage around conduits
• Large sinkholes with corresponding seepage anywhere on the embankment or downstream
from the toe
• Any slide that degrades the crest of the embankment or that is progressively increasing in size
• Cracking or movement of any concrete structure
• An increase in the reservoir level leading to engagement of the emergency spillway
• Exceptionally heavy rainfall in the catchment of the dam reservoir
External Alert ConditionORANGE– This is indicative of adam condition that is progressively get-
ting worse; and there is a high probability of dam failure. Although there is no immediate danger, the
dam could fail if conditions continue to deteriorate.The Emergency Planning Manager will be re-
sponsible for initiating immediate repairs, including lowering the reservoir if appropriate and imple-
menting the appropriate Notification Flowchart. The following is a list of conditions thatwould initiate
this condition:
• Large boils, increasing in size and flow rate, especially if there is flowing muddy water
• Significantly increasing seepage, especially flowing muddy water
• Slides involving a large mass of material that impairs the crest of the dam and is continuing to
move
• Sinkholes with seepage flowing muddy water
• Large cracks, movement or failure of a portion of any major concrete structure that forms an
integral part of the dam
• An increase in the reservoir level to near the top of the dam
• Overtopping of a dam that is not designed for overtopping
• Near to ‘Design Flood’ inflow forecast
External Alert Conditions RED – These are “failure” conditions. Either the dam is in immediate
danger of failing or has already failed. No time remains to implement measures to prevent failure.
Evacuate immediately. Evacuation efforts will continue until the situation is stabilized.The Emergen-
cy Planning Manager is responsible for implementing the appropriate Notification Flowchart. The
following is a list of conditions that would initiate “imminent dam failure” or “dam failure” condi-
tions:
• Rapidly increasing boils or the presence of new, significantly flowing boils, particularly mud-
dy ones near previously identified ones
Emergency Action Plan For Votehole Dam May-2019
Project ID Code KA06HH00154 Page A-18
• Rapidly increasing seepage, especially flowing muddy water
• Slides involving a large mass of material or which have degraded the crest of the embankment
to a level that approaches the water surface level, or if significant seepage is observed through
the slide area
• Settlement that is predicted to degrade to the reservoir level
• Cracks that extend to the reservoir level
• Significant movement or failure of any structure that forms an integral part
of the dam
• Overtopping of an earthen dam
• Uncontrollable release of the reservoir
4.3. Previously Known Problems
As Per the DSRP inspection Report 2014
Sl
No Recommendations. Complience
1
Assess standard project flood (SPF) and
verify the adequacy of the spillway capac-
ity and the existing free board for the dam
based on “ Saville”s method and if it does
not meet the requirement, proposals for
providing auxillary spillway of required
capacity in the saddle existing on the left
flank may be considered and adopted.
The revised peak value of the estimated
SPF considering two alternative critical
sequences works out to 1604 & 1606 cu-
mecs level pool routing of votehole reser-
voir is carried out to examine the adequacy
of the free board considering the two dist
inflow hydrographs the maximum water
level attained in the reservoir during pas-
sage of flood peak value of 1606 cumecs in
a 967.837mt which is 1.787 mt as above
FRL of 966.05mt with a peak discharge
the additional spillway is require in the re-
gard action well be taken.
2
Hydrographic surveys (IBS) of the reser-
voir need to be carried out periodically for
determination of extent of reservoir sedi-
mentation in dead and live storage por-
tions. Based on the survey in 2010-11, the
assessed extent of loss of storage and con-
sequent possible reduction in the annual
benefits point to the need to formulate
schemes for minimization of rate of sedi-
mentation such as adoption of watershed
management techniques like contour
bunding, provision of gully traps anti soil
erosion measures, etc.
Hydrographic surveys have been carried
out during January 2011 by KERS authori-
ties. It is observed that 15.57% of Gross
storage capacity amounting to 0.235 TMC
out of 1.51 TMC has been reduced due to
sedimentation.
Emergency Action Plan For Votehole Dam May-2019
Project ID Code KA06HH00154 Page A-19
3
The reservoir operation schedules should
be developed for the procedure outlined in
IS 7323-1994 or its latest version. The
reservoir should be operated as per opera-
tion schedule so drawn upto to route the
SPF safely without risk of overtopping of
dam.
The same will be done as per SPF value
arrived and flood routing study report is
prepared by director KERS, K.R sagara.
4
Department should also prepare an Emer-
gency Action plan including suitable
communication system of flood forewarn-
ing to the habitants living downstream of
the dam within the zone prohibited for
dwelling. For this purpose Department
should prepare necessary inundation map
of the downstream valley showing flood
contours of different intensities dully de-
marcating “Prohibited Zone”, :Restricted
Zone” and “Caution Zone” to avert possi-
ble hazards to life and property during
release of floods over the spillway.
The inundation map and flood routing is
prepaid by CWC & KERS, The preparation
of EAP is done with co-operation of SPMU
DRIP.
5
Leakage is observed near downstream toe
of the dam at the lateral side of the left
side training wall of the draft channel.
The project Engineers stated that a pipe is
running at the foundation level of the dam
and the leakage observed may be from the
joints of the pipe. This needs to be con-
firmed by excavating upto the pipe level
and plugging leakages.
The work taken up as per direction of
CWC. Due to technical reason not able to
arrest leakage.
6
Seepage from the internal drainage ar-
rangement is not properly entering the toe
drain chamber leading to the mother val-
ley. The toe drain may be properly
cleaned and re-laid for proper disposal of
seepage water.
The work taken up in DRIP-II, proposal
submitted.
7
Provide drainage for the roadway by
providing cross slope of the road surface
towards t he downstream and a longitudi-
nal drain running along the downstream
edge of the roadway to collect the water
falling on the road and diverting the flows
along paved chutes provided at about 40
to 50 m intervals as laid down in the rele-
vant IS.
Work is completed in DRIP work.
8 Collector drains should be provided to
collect water from the chute drains and
The work will be taken up in DRIP-II, pro-
posal submitted.
Emergency Action Plan For Votehole Dam May-2019
Project ID Code KA06HH00154 Page A-20
the water falling on the downstream slope
of the dam and the same may be drained
into the left bank canal.
9
The leakage from the supply pipe needs to
be tackled urgently. For this it is suggest-
ed to sink a well of diameter 1.20 to 1.50
m with prefabricated RCC rings of re-
quired thickness, vertically above the pipe
outlet in the non-overflow dam till it ex-
poses the pipe. While sinking the well, the
underground water should be pumped
continuously by employing a pump of re-
quired size till the water table is lowered
to pipe invert level. After exposing the
pipe, all visible leakage spots should be
sealed off to prevent further leakage to
develop. Thereafter few grout holes
should be drilled into the masonry at
about 0.50 m to 0.60 m along the periph-
eral length of the pipe and grouted with
Bentonite slurry under pressure to seal off
the leakage paths along the pipe inside. A
pump chamber of about 4.00m height
above pipe invert using the well already
sunk may be created which could be
about 1.00 m below ground to facilitate
pumping in future if leakage persists and
thereby rendering the subsoil free from
submergence at all times.
As per DSRP suggestion with 2.40m dia
RCC rings sink the well up to 10 depth fur-
ther it is not able to sink the work because
of the area is fully refilled with hard rock
boulders for back fill of stilling basin re-
taining wall, these H,R borlder are at edges
of the rings it is very difficult to brake the
boulders is watering of shiphy condition
and the leakage water comes out at differ-
ent places as different depth and also out
side of the rings also hence the well sinking
work was stopped.
10
The condition of the stilling basin and its
appurtenant works should be verified un-
der dry conditions by bailing out standing
water and erosion damages if any, should
be repaired for smooth functioning.
The estimate sanctioned and entrust-
ed on tender basis for Rs. 3.00 lakhs. But
contractor not executed the work due to
standing water is the stilling basin, Now
provision is made under DRIP-II for
stilling basing repair and constructing river
training work.
11
Quality of the reservoir water should be
chemically analyzed to assess the quantity
of lime leached out from the cement used
during construction to assess whether the
extent of lime leaching is within the per-
missible limits or not. For this purpose
samples of both seepage water and reser-
voir water should be collected simultane-
ously and their chemical analysis carried
out periodically under different reservoir
levels and data maintained in the suggest-
ed format.
Action will be taken accordingly in
consultancy with KERS, K.R Sagara.
Emergency Action Plan For Votehole Dam May-2019
Project ID Code KA06HH00154 Page A-21
12
Maintain the weekly seepage data
by installing suitable measuring devices
in the drainage gallery.
Action will be taken
13
Install an automatic water level re-
corder with the assistance of the quality
control Division for accurate reservoir
levels measurements and maintain the
readings.
This work proposed under DRIP-I,
now the work is completed. Installed auto-
matic water level recorder to the Dam
14
Details of key trench and foundation
treatment provided should be verified and
suitable remedial action if any required
may be taken accordingly.
Action will be initiated in this regard
15
The quality control Division may be
referred to examine the condition of pie-
zometers and their revival. In case they
have become defunct and cannot be re-
vived, action may be taken to install few
“Casagrande / Electrical piezometers in
the deepest portion of both left and right
bank earthen dams for observing devel-
opment of pore pressures and taking nec-
essary action to ensure safety of dam.
Action is taken by Q.C Division,
Gorur in this regard. By the quality control
officers efforts, The Excising, piezometer
are now is working condition, The chief
engineer WRDO and nodal officer for
DRIP was Inspected on 26-06-2016 and
give direction to no necessity of new in-
strumentation, the excisting piezometer are
is good condition.
16
Clear all vegetative growths noticed
in the spillway, non overflow dams and
spillway training wall.
Cleared
17
The standby power should be made
functional to enable periodical operation
of the gates even in the event of power
shutdowns.
Diesel Generator provided
18
Gate operations and maintenance
schedule should be prepared and adopted
for regular maintenance.
Gate operation and maintenance
schedule is prepared and the same adopted
for regular maintenance.
19
The seals provided to the gates
should be replaced wherever they become
worn out so that leakages if any are
stopped.
Provision in made DRIP-II and pro-
posal submitted
20
The gates and hoisting mechanism
should be maintained periodically by
painting, oiling and greasing.
Provision in made DRIP-II and pro-
posal submitted
21
Trash racks should be provided at
the entry of sluice vents to prevent float-
ing objects entering and blocking the
sluice vent.
Provision in made DRIP-I and work
completed.
Emergency Action Plan For Votehole Dam May-2019
Project ID Code KA06HH00154 Page A-22
5. Preparedness
Preparedness actions are to be taken both before and following the development of emergency
conditions and should identify ways of preparing for an emergency, increasing response readiness in a
uniform and coordinated manner, and helping to reduce the effects of a dam failure. The following are
some steps that could prevent or delay failure after an emergency is first discovered.
Surveillance:Emergency Planning Manager will monitor the dam during emergency situations such
as a severe storm event.
Response on forecast of excessive inflow: Emergency Planning Manager will warn the down stream
population and down stream dams, initiate 24 h monitoring etc indicate all the responsible to coordi-
nate and execute such tasks , after release excessive inflow forecast by way of controlled spillway
releases.
Response during weekends and holidays: Emergency Planning Manager and site office engineers
will be available for 24 h at emergency response during weekends and holidays and can be present at
the dam site within short time [15 minutes] of an emergency condition.
Response during periods of darkness and adverse weather: During period of darkness and ad-
verse weater 45 KVA generator is installed in dam site for emergency condition.. Emergency Plan-
ning Manager will be able to access the site during adverse weather conditions by foot or any other
utility vehicle
Access to the site: Alternate access routes should be planned in the event of an emergency at the dam.
Route No.-1. Hassan-Alur to Votehole dam via bikod-belur road, This road is connected to right
embankment side of dam (Alur to dam site – 16 km)
Route No-2.Belur-Bikod to Votehole dam,This road is connected to left embankment side of dam.
(Belur to dam site – 17 km)
Preventive measures can be taken in an emergency to prevent the catastrophic failure of the dam, but
such repairs should be undertaken with extreme caution. The repairs are only temporary, and a per-
manent repair should be designed by an engineer as soon as possible.
The following actions should only be undertaken under the direction of a professional engineer or
contractor. In all cases, the appropriate Notification Flowchart must be implemented and the person-
nel of the SDSO must be notified.
Consider the following preparedness actions if the dam’s integrity is threatened by:
Seepage Failure
• Plug the flow with whatever material is available (hay, bentonite, or plastic) if the entrance
is in the reservoir.
• Lower the water level in the reservoir by using the low flow outlet and pumping if neces-
sary, until the flow decreases to a non-erosive velocity or until it stops. Place an inverted
filter (a protective layer of sand and gravel) on the exit area to hold the material in place.
• Continue operating at a lower level until a repair is made.
Embankment or Foundation Sliding
• Lower the water level in the reservoir byusing the low flow outletand pumping if neces-
sary at a rate and to an elevation considered safe, given the slide condition.
• Stabilize the slide, if on the downstream slope, by weighting the toe area below the slide
with soil, rock, or gravel.
• Continue operating at a lower level until a repair is made.
Structural Failure
Emergency Action Plan For Votehole Dam May-2019
Project ID Code KA06HH00154 Page A-23
• Implement temporary measures to protect the damaged structure, such as placing rock
riprap in the damaged area.
• Lower the water level to a safe elevation through the low flow outlet and by pumping if
necessary.
6.Supplies and Resources
6.1. Contracts
Should Cauvery Neeravari Nigam limited personnel and resources prove to be inadequate during an
emergency, requests will be made for assistance from other local jurisdictions, other agencies, and
industry, as needed. Such assistance may include equipment, supplies, or personnel. All agreements
will be entered into by authorized officials and should be in writing whenever possible. The Executive
Engineer shall have the authority to enter into agreements as deemed necessary to prevent the failure
of the dam.
6.2. Equipment and Supplies
Equipment that is available for use and local contractors that can be contacted to provide equipment
during an emergency event are listed in Tab 6.
6.3. Reports
Technical Data
Pre-monsoon (for the month of may )and post-monsoon( for the month of November) inspections of
the dam will be made to evaluate its structural safety, stability, and operational adequacy by assistant
executive engineer, executive engineer, superintendent engineer, chief engineer. In the event of an
abnormal occurrence, reference to these reports, particularly the photographs, can be beneficial in the
evaluation of a potential problem.
Technical records such as drawings and inspection reports should be stored and carefully maintained
at the Cauvery Neeravari Nigam Limited Site offices. Alternate personnel will be familiar with the
location of the documents in the event of an emergency situation.
Emergency Operations Center Activity Log
Any unusual or emergency condition should be documented, including the following:
• Activation or deactivation of emergency facilities
• Emergency notifications to other local governments and to state and centralgovernment agen-
cies
• Significant changes in the emergency
• Major commitments of resources or requests for additional resources from
external sources
• Telephone calls should be recorded in chronological order
• Issuance of protective action recommendations to the public
• Evacuations
• Casualties
• Termination of the incident
Costs of the Emergency Operations Center
For major emergencies, the emergency operations center will maintain detailed records of costs ex-
pended. These records may be used to recover costs from the responsible party or insurers, or as a ba-
Emergency Action Plan For Votehole Dam May-2019
Project ID Code KA06HH00154 Page A-24
sis for requesting financial assistance for certain allowable response and recovery costs from the state
or central government. Documented costs should include:
• Personnel costs, especially overtime
• Equipment operation
• Equipment leasing and rental
• Contract services to support emergency operations
• Specialized supplies expended in emergency operations
7. Inundation Area
The inundation map illustrates the areas subject to flooding from a failure of the dam and can be
found in Tab 2. The map was prepared using the results of a full breach analysis.
After examining the results of the breach analysis of Votehole Dam, it has been determined that there
were a significant number of structures that could be affected due to a design flood or sunny-day dam
breach. Hassan District, can suffer a significant impact from a breach of the dam, others structure like
bridges, schools, high ways, culverts atc. In addition, water resulting from a breach, and associated
damages, can, under certain circumstances, travel down the Votehole River affecting near by
Districts.
The breach analysis contains profiles of the peak flood levels expected, as well as an estimation of the
time from the beginning of the breach to the peak flood elevations. A comparison of the areas that are
likely to be flooded with the plots showing the times from the start of the breach to the flooding shows
the areas of evacuation and the time constraints involved. Figures in the breach analysis include in-
formation on the estimated impact of flooding on the bridges along the Yagachi River. These struc-
tures may suffer such impacts before the peak elevation of the flood wave.
7.1. Local Evacuation Plan
If imminent failure of the dam with uncontrolled downstream flooding is anticipated, local disaster
management and law enforcement personnel should notify those downstream, forevacuation in the
most expedient manner possible. The organizations and personnel on the Notification Flowchart
should be contacted immediately. Local law enforcement officials, along with local mobile network
operators, radio and television stations can best spread the notice for evacuation. The immediate im-
pact will be to areas along Yagachi river downstream of the dam. For sunny-day and design flood
breaches, the following actions should be taken:
• Barricading all bridges that could possibly be flooded to prevent access to the affected area.
These bridges include the Yagachi River Crossings See the Inundation Map in Tab 2 to de-
termine appropriate barricade locations.
• The District Disaster Management office can assist with the notification of all persons and
agencies involved, with the possibility of additional support—including contacting others not
accessible by radio or telephone.
• District officials are generally familiar with developed areas in their jurisdiction. Such
knowledge, coupled with the requirements of state law that they respond to disasters, make
them the logical officials to be notified and to spread the warning message to all areas subject
to flooding.
8. Implementation
8.1. Development
The draft EAP was sent to the SDSO for review, and agency comments were incorporated into this
document, a copy of which is currently on file with the SDSO.
8.2. Updating
Emergency Action Plan For Votehole Dam May-2019
Project ID Code KA06HH00154 Page A-25
Copies of the EAP have been provided to the appropriate persons and the EAP has been approved and
signed by the owner and the person(s) in charge of emergency response, as shown on the Distribution
List and Approval and Implementation sheets at the front of the report. This plan will be reviewed and
updated annually by Executive Engineer and personnel from local disaster management agencies in
conjunction with Executive Engineer’s annual maintenance inspection of the dam. The Executive
Engineerwill review and complete all items on theAnnual EAP Evaluation Checklist in Tab 7. After
the annual update is complete, a newApproval and Implementation sheet will be attached and the an-
nual update will be documented on the Plan Review and Update sheet in Tab 8.
If revisions to the EAP are made as a result of the annual update, such changes will be recorded on the
Log Sheet of Changes form at the front of the report. A copy of the updated portions of the EAP will
be sent to the SDSO and all other concerned as per the EAP Distribution List. If the EAP was re-
viewed and revisions were not required, the Cauvery Neeravari Nigam Limited will submit written
notification to all concernedthat no updates to the EAP have been adopted or implemented.
8.3. Testing
A table top drill will be conducted at least once every five years. The table top drill involves a meet-
ing of Executive Engineerwith local and state disaster management officials in a conference room.
The drill begins with a description of some simulated event and proceedswith discussions by the par-
ticipants to evaluate the EAP and response procedures, and to resolve concerns regarding coordination
and responsibilities. Any problems identified during a drill should be included in revisions to the
EAP. Records of training and drills will be maintained in Tab 9.
8.4. Training
All people involved in the EAP will be trained to ensure that they are thoroughly familiar with its el-
ements, the availability of equipment, and their responsibilities and duties under the plan. Personnel
will be trained in problem detection, evaluation, and appropriate corrective measures. This training is
essential for proper evaluation of developing situations at all levels of responsibility. Training records
will be maintained in Tab 9.
Emergency Action Plan For Votehole Dam May-2019
Project ID Code KA06HH00154 Page A-26
Tab 1
Vicinity Map
•
Emergency Action Plan For Votehole Dam May-2019
Project ID Code KA06HH00154 Page A-27
Tab 2
Inundation Map
Flood Inundation Maps for Votehole Dam
March 14, 2017
Mar - 17
Emergency Action Plan For Votehole Dam May-2019
Project ID Code KA06HH00154 Page A-28
Flood Inundation Maps for
Votehole Dam, Karnataka
Doc. No. CDSO_MAP_DS_61
CENTRAL WATER COMMISSION, MINISTRY OF WATER RESSOURCES 3rd Floor, New Library Building, R.K. Puram, New Delhi 110066
Emergency Action Plan For Votehole Dam May-2019
Project ID Code KA06HH00154 Page A-29
Flood Inundation Maps for Votehole Dam Mar - 17
Quality Control:
Version
1
Date
14/03/17
Writers/Contributors
David Froehlich (DF)
David González (DG)
Sunil Kumar (SK)
Subhodip Mukherjee (SM)
Checked by
David Froehlich (DF)
Issued/Copied to:
I/C
Issued
Date
14/03/17
Name
Shri Pramod Narayan
Organization
Central Water Commission
Doc. No. CDSO_MAP_DS_61 Page i
Emergency Action Plan For Votehole Dam May-2019
Project ID Code KA06HH00154 Page A-30
Flood Inundation Maps for Votehole Dam Mar - 17
Table of Contents
Overview ......................................................................................................................................................... 1
Dam Breach Floods .................................................................................................................................... 1
Large Controlled Release Flood ................................................................................................................. 1
Inundation Maps ............................................................................................................................................. 1
Digital Elevation Model Description............................................................................................................. 1
DVD Directory Structure ................................................................................................................................. 2
Flood Hazard Reference Values..................................................................................................................... 2
Estimated Population .................................................................................................................................. 2
References ..................................................................................................................................................... 4
Appendix A – Flood Inundation Maps ..........................................................................................................A-1
Appendix B - DVD........................................................................................................................................B-1
Doc. No. CDSO_MAP_DS_61 Page ii
Emergency Action Plan For Votehole Dam May-2019
Project ID Code KA06HH00154 Page A-31
Flood Inundation Maps for Votehole Dam Mar - 17
Project Identification
Dam Owner
Dam Operator
Project ID Code
Project Name
Karnataka Water Resources Department
KAWRD
KA06HH0154
Votehole Dam
Project Location
State
District
River/Stream
Latitude
Longitude
Karnataka
Hassan
Votehole
13° 3'29.75"
75°54'36.22"
OVERVIEW
Flood inundation maps that can be used to prepare Tier 1 Emergency Action Plans (EAPs) for Votehole Dam are herewith transmitted on the accompanying DVD. See the Guidelines for Preparing Emergency Action Plans for Dams (CWC 2016) for a description of Tier 1 EAPs. Also included on the DVD are all data used to simulate flooding using the HEC-RAS computer model (Brunner 2016).
Inundation maps have been prepared for the following three causes of flooding:
1. A dam failure caused by overtopping from the inflow design flood leading to breaching and uncontrolled release of impounded water.
2. A non-flood dam failure caused by internal erosion (piping) with the reservoir at full supply level (often called a “fair-weather failure”) leading to breaching and uncontrolled release of impounded water.
3. A large controlled-release flood without dam failure.
Dam Breach Floods
Dam failure floods resulting in breaching from overtopping by floodwaters and from internal erosion (piping) were simulated by solving numerically the two-dimensional, depth-averaged flow equations on an unstructured computational mesh using the HEC-RAS computer program (Brunner 2016). Breaches were modeled as trapezoidal openings that form at the crest of the dam and then grow in size, first vertically downward until the specified breach bottom elevation is reached, and then horizontally as outflows continue to widen the opening . Breach parameters required by the model are summarized in Table 1.
Large Controlled Release Flood
Flooding caused by a steady large controlled-release (LCR) from the reservoir was simulated to provide an idea of the hazard produced by a non-failure event. For Votehole Dam, the LCR discharge was the published spillway capacity of 577 m3/s (Revised Flood Routing)
INUNDATION MAPS
Inundation maps showing 1) maximum water depth, 2) maximum water velocity, and 3) maximum water-surface elevation were prepared for each of the three flooding cases considered. An additional map showing the time of arrival of the flood wave since the start of failure (that is, since the initiation of breaching) is provided for each of the dam breach floods (overtopping and piping). All flood inundation maps are attached to this report as Appendix A.
Digital Elevation Model Description
The digital elevation model (DEM) used to prepare the two-dimensional computational mesh used to simulate flooding was derived from the Japan Aerospace Exploration Agency (JAXA) global digital surface model (DSM) dataset with a horizontal resolution of approximately 30 meters (1 arc-sec) (Takaku et al. 2014). The dataset is based on the DSM dataset (5-meter mesh version) of the "World 3D Topographic Data", which is the most precise global-scale elevation data at this time, and its elevation precision is also at a world-leading level as a 30-meter mesh version (Tadono et al. 2014). The height accuracy of the 30-meter DEM is 5 meters (root-mean-square-error).
Doc. No. CDSO_MAP_DS_61 Page 1 of 5
Emergency Action Plan For Votehole Dam May-2019
Project ID Code KA06HH00154 Page A-32
Flood Inundation Maps for Votehole Dam
TABLE 1. Trapezoidal Dam Breach Model Parametersa and Calculated Dam Breach Flood Peak Discharges
Dam Failure Mode
Breach parameter Units Overtopping
Height
Bottom width
Average side slope (horz : vert)
Formation time
Calculated peak discharge
a
Mar - 17
Internal erosion (piping)
44.48
56
0.7 : 1
0.82
9,946
m
m
--
h
m3/s
44.48
80
1:1
0.85
13,315
Parameters of the trapezoidal dam breach model used in HEC-RAS (Brunner 2016)
DVD DIRECTORY STRUCTURE
All data needed to carry out two-dimensional depth-averaged flow simulations of the three flooding cases using the HEC-RAS computer program, solution output files, and output maps prepared using generated solutions are included on the accompanying DVD. Files on DVD are organized in folders as shown in Figure 1.
Dam Name – State o Common Data o Model Data Large Controlled Release Overtopping Failure Piping Failure o Output Maps Large Controlled Release Overtopping Failure Piping Failure
Figure 1. DVD Directory structure of Tier 1 EAP data for the dam
The Common Data folder contains information that was used in all three flood simulations including digital terrain models, and land use/land cover data used to assign roughness coefficients to the computational mesh.
The DVD is attached to this report as Appendix B.
FLOOD HAZARD REFERENCE VALUES
Flood hazard reference values consisting of maximum water depth, maximum depth-averaged velocity, and flood wave arrival time at various locations downstream from Votehole Dam are presented in Table 2. Reference values were determined close to the identified positions and represent the degree of danger that would be created by the flood. Flood wave arrival times are provided only for the two dam breach scenarios (that is, failures caused by overtopping and internal erosion.)
Estimated Population
The estimated population for each settlement was obtained using the fourth version of “The Gridded Population of the World” (GPWv4), which is a gridded data product of globally-integrated national population data from the 2010 round of Population and Housing Censuses. The gridded data sets are constructed from national or subnational input
Doc. No. CDSO_MAP_DS_61 Page 2 of 5
Emergency Action Plan For Votehole Dam May-2019
Project ID Code KA06HH00154 Page A-33
Flood Inundation Maps for Votehole Dam Mar - 17
administrative units. GPWv4 is gridded with an output resolution of 30 arc-seconds, or ~1 km at the equator. (CIESIN, 2016)
The grids represent persons per square kilometer for each of the five target years: 2000, 2005, 2010, 2015, and 2020. For Votehole Dam the population density extrapolated to the year 2020 was used.
Doc. No. CDSO_MAP_DS_61 Page 3 of 5
Emergency Action Plan For Votehole Dam May-2019
Project ID Code KA06HH00154 Page A-34
Flood Inundation Maps for Votehole Dam Mar - 17
REFERENCES
Brunner, G. W. (2016). “HEC-RAS River Analysis System User’s Manual, Version 5.0.” Report Number CPD-68, U.S. Army Corps of Engineers, Institute for Water Resources, Hydrologic Engineering Center, Davis, California.
CIECIN - Columbia University (Center for International Earth Science Information Network), (2016). “Documentation for the Gridded Population of the World, Version 4 (GPWv4)”. Palisades NY: NASA Socioeconomic Data and Applications Center (SEDAC).
CWC (Central Water Commission) (2016). “Guidelines for Preparing Emergency Action Plans for Dams.” Document Number CDSO_GUD_DS_01_v2.0, Ministry of Water Resources, River Development & Ganga Rejuvenation, New Delhi, India.
Tadono, T., Ishida, H., Oda, F., Nait, S., Minakawa, K., and Iwamoto, H. (2014). “Precise Global DEM Generation by ALOS PRISM.” Proceedings of the ISPRS Technical Commission IV Symposium, 14–16 May 2014, Suzhou, China, Vol. II-4, 71-76.
Takaku, J., Tadono, T., and Tsutsui, K. (2014). “Generation of High Resolution Global DSM from ALOS PRISM.” Proceedings of the ISPRS Technical Commission IV Symposium, 14–16 May 2014, Suzhou, China, Vol. XL-4, 243-248.
Doc. No. CDSO_MAP_DS_61 Page 4 of 5
Emergency Action Plan For Votehole Dam May-2019
Project ID Code KA06HH00154 Page A-35
Flood Inundation Maps for Votehole Dam Table 2. Flood Hazard Reference Values
Overtopping Failure
Location Distancea downstream from dam (km)
Estimated populationb (people)
Maximum depthc (m)
Maximum velocityc (m/s)
Flood wave arrival timed (hh:mm)
Non-flood Failure
Maximum depthc (m)
Maximum velocityc (m/s)
Flood wave arrival timed (hh:mm)
Mar - 17
Large Controlled Release
Maximum depthc (m)
Maximum velocityc (m/s)
Nilavagilu Paduvalalu Kuppe Hosahalli Doddihalli 1 Doddihalli 2 Doddihalli / Jannapura Bommenahalli Chikkanagalu Bellur Bandithimmanahalli Mudigere Agasarahatti Mavanoor 1 Mavanoor 3 Mavanoor 4 N.D.R.K. Institute Of Technology Thimmanahalli 1 Kandali 1 Kandali 2 Uppahalli 4 Uppahalli 2 Uppahalli 1 Kadalu
a b
2.3 2.5 3.2 3.9 4.3 4.9 5.2 7.4 9.3 10.4 12.5 13 14.4 15.1 15.2 15.3 15.8 16.7 16.9 16.9 17.8 18 18.6
20 7 22 9 2 17 4 3 22 1 5 53 2 2 17 45 25 2 19 2 3 2 4
0.63 1.07 3.57 2.88 2.98 0.07 3.93 4.92 5.13 2.02 5.54 0.78 5.62 4.19 6.1 5.74 2.29 0.03 3.03 0.28 4.34 0.01 1.87
0.61 3.01 1.89 2.32 1.8 2.8 1.32 2.13 0.94 1.2 1.16 0.52 1.16 1.73 1.11 1.11 0.82 0.63 0.22 0.67 1.29 0.1 1.62
00:48 00:41 00:48 00:55 00:54 01:05 01:03 01:29 01:48 02:23 02:40 04:02 03:00 03:32 03:18 03:25 03:59 05:25 04:23 04:52 04:22 05:22 06:13
0.2 0.63 3.14 2.45 2.53 ‐‐‐ 3.58 4.62 4.8 1.65 5.09 0.38 5.17 3.75 5.66 5.36 2.08 ‐‐‐ 2.85 0.06 4.13 ‐‐‐ 1.48
0.55 2.28 1.8 2.19 1.7 ‐‐‐ 1.27 2.05 0.89 1.15 1.12 0.37 1.12 1.68 1.07 1.03 0.75 ‐‐‐ 0.18 0.61 1.17 ‐‐‐ 1.55
01:00 00:50 00:56 01:04 01:02 ‐‐‐ 01:11 01:38 01:57 02:34 02:51 04:32 03:12 03:45 03:30 03:38 04:15 ‐‐‐ 04:39 05:13 04:38 ‐‐‐ 06:37
‐‐‐d ‐‐‐ ‐‐‐ ‐‐‐ ‐‐‐ ‐‐‐ 0.08 1.8 2.73 ‐‐‐ 3.25 ‐‐‐ 3.64 2.33 4.23 4.06 1.47 ‐‐‐ 2.37 ‐‐‐ 3.1 ‐‐‐ 0.47
‐‐‐ ‐‐‐ ‐‐‐ ‐‐‐ ‐‐‐ ‐‐‐ 0.46 1.22 0.42 ‐‐‐ 0.52 ‐‐‐ 0.54 1.03 0.57 0.58 0.33 ‐‐‐ 0.05 ‐‐‐ 0.75 ‐‐‐ 1.21
Approximate shortest distance downstream from dam. Estimated population within the assumed settlement boundaries. cMaximum value near the specified location, which usually occurs near the center of the stream. dFlood wave arrival time is the time since the initiation of the dam breach until the settlement is inundated. eLocation not inundated.
Doc. No. CDSO_MAP_DS_61 Page 5 of 5
Emergency Action Plan For Votehole Dam May-2019
Project ID Code KA06HH00154 Page A-36
Flood Inundation Maps for Votehole Dam Mar - 17
APPENDIX A – FLOOD INUNDATION MAPS
Attached to this report are flood inundation maps showing 1) maximum water depth, 2) maximum water velocity, and 3) maximum water-surface elevation were prepared for each of the three flooding cases considered. An additional map showing the time of arrival of the flood wave since the start of failure (i.e., since the initiation of breaching) is provided for each of the dam breach floods (overtopping and piping). Each map consists of two panels.
Doc. No. CDSO_MAP_DS_61 Page A-1
Emergency Action Plan For Votehole Dam May-2019
Project ID Code KA06HH00154 Page A-37
Flood Inundation Maps for Votehole Dam Mar - 17
APPENDIX B - DVD
All data needed to carry out two-dimensional depth-averaged flow simulations of the three flooding cases using the HEC-RAS computer program, solution output files, and output maps prepared using generated solutions are included on the accompanying DVD.
Doc. No. CDSO_MAP_DS_61
Emergency Action Plan For Votehole Dam May-2019
Project ID Code KA06HH00154 Page A-38
75°55'E 75°56'E 75°57'E 75°58'E 75°59'E 76°E 76°1'E 76°2'E 76°3'E
¯
YEDEHALLI THENDEGERECHATRANAHALLI
PADUVALALU RAJANAHALLI / CHENNENAHALLI
JINIGENAHALLIBOMMENAHALLI
Votehole Dam NILAVAGILU DODDIHALLI / JANNAPURA
13°6'N VOTEHOLE DAM, KARNATAKA
OVERTOPPING FAILURE
FLOOD WAVE ARRIVAL TIME*
13°5'N Arrival Time (Hrs.)
0-1 1-2 2-3 3-4 4-5 5-6 6-7 7-8 8-9 9 - 10 RAILWAYS ROADS SETTLEMENTS
13°3'N
13°4'N
DODDIHALLI 1 KUPPE HOSAHALLIDODDIHALLI 2
13°2'N CHIKKANAGALU
*Time since initiation of breach Locator Map
13°1'N 1
BELLUR BELLUR 2
BANDITHIMMANAHALLI 13°N
MUDIGERE 0
BASAVANAPURA
Source: Esri, DigitalGlobe, GeoEye, Earthstar Geographics, CNES/Airbus DS, USDA, USGS,
0.5 1 2 Km
Central Project Management Unit AGASARAHATTI
MAVANOOR 1 12°59'N
Dam Rehabilitation and Improvement Project Doc. No. CDSO_MAP_DS_61 Date : March 2017
Map No. KANDALI 2 MAVANOOR 4 Source: Esri, DigitalGlobe, GeoEye, Earthstar Geographics, CNES/Airbus DS, USDA, USGS, AeroGRID, IGN, and the GIS UserMAVANOOR 3 Community THIMMANAHALLI 1
75°55'E 75°56'E 75°57'E 75°58'E 75°59'E 76°E 76°1'E 76°2'E 76°3'E
1/2
Emergency Action Plan For Votehole Dam May-2019
Project ID Code KA06HH00154 Page A-39
75°59'E 76°E
BANDITHIMMANAHALLI
76°1'E 76°2'E 76°3'E 76°4'E 76°5'E 76°6'E 76°7'E
13°N MUDIGERE
BASAVANAPURA
AGASARAHATTI MAVANOOR 1
¯
MAVANOOR 3 THIMMANAHALLI 1 KANDALI 1 THIMMANAHALLI 2
MAVANOOR 4 KANDALI 2
UPPAHALLI 4
UPPAHALLI 3 HALUVAGILU UPPAHALLI 2HALUVAGILU UPPAHALLI 1
VOTEHOLE DAM, KARNATAKA
OVERTOPPING FAILURE
FLOOD WAVE ARRIVAL TIME*
Arrival Time (Hrs.) 0-1 1-2 2-3 3-4 4-5 5-6 6-7 7-8 8-9 9 - 10
12°59'N
N D R K INSTITUTE OF TECHNOLOGY
12°58'N
RAILWAYS ROADS SETTLEMENTS
12°56'N
12°57'N KIRAGADALU
*Time since initiation of breach KADALU Locator Map
1 12°55'N
2
Source: Esri, DigitalGlobe, GeoEye, Earthstar Geographics, CNES/Airbus DS, USDA, USGS,
12°54'N 0 0.5 1 2
Km
Dam Rehabilitation and Improvement Project Date : March 2017 Doc. No. CDSO_MAP_DS_61
Central Project Management Unit
12°53'N Source: Esri, DigitalGlobe, GeoEye, Earthstar Geographics, CNES/Airbus DS, USDA, USGS, AeroGRID, IGN, and the GIS User Community
75°59'E 76°E 76°1'E 76°2'E 76°3'E 76°4'E 76°5'E 76°6'E 76°7'E
2/2 Map No.
Emergency Action Plan For Votehole Dam May-2019
Project ID Code KA06HH00154 Page A-40
75°55'E
13°6'N
75°56'E 75°57'E 75°58'E 75°59'E 76°E 76°1'E 76°2'E 76°3'E
¯
YEDEHALLI THENDEGERECHATRANAHALLI
PADUVALALU RAJANAHALLI / CHENNENAHALLI
JINIGENAHALLIBOMMENAHALLI
Votehole Dam NILAVAGILU DODDIHALLI / JANNAPURA
VOTEHOLE DAM, KARNATAKA
OVERTOPPING FAILURE
MAXIMUM DEPTH 13°5'N Depth (m)
0-1 1-2 2-3 3-4 4-5 5-6 6-7 7-8 8-9 9 - 10
13°4'N
10 - 11 11 - 12 RAILWAYS ROADS SETTLEMENTS 13°3'N
DODDIHALLI 1 KUPPE HOSAHALLIDODDIHALLI 2
13°2'N CHIKKANAGALU
Locator Map
13°1'N 1
BELLUR BELLUR 2
BANDITHIMMANAHALLI 13°N MUDIGERE
BASAVANAPURA
AGASARAHATTI MAVANOOR 1
KANDALI 2 MAVANOOR 4 Source: Esri, DigitalGlobe, GeoEye, Earthstar Geographics, CNES/Airbus DS, USDA, USGS, AeroGRID, IGN, and the GIS UserMAVANOOR 3 Community THIMMANAHALLI 1 75°59'E 76°E 76°1'E 76°2'E 76°3'E
0
Source: Esri, DigitalGlobe, GeoEye, Earthstar Geographics, CNES/Airbus DS, USDA, USGS,
0.5 1 2 Km
Dam Rehabilitation and Improvement Project Date : March 2017 Doc. No. CDSO_MAP_DS_61
Central Project Management Unit
12°59'N 1/2 Map No.
75°55'E 75°56'E 75°57'E 75°58'E
Emergency Action Plan For Votehole Dam May-2019
Project ID Code KA06HH00154 Page A-41
75°59'E 76°E
BANDITHIMMANAHALLI
76°1'E 76°2'E 76°3'E 76°4'E 76°5'E 76°6'E 76°7'E
13°N MUDIGERE
BASAVANAPURA
AGASARAHATTI MAVANOOR 1
¯
MAVANOOR 3 THIMMANAHALLI 1 KANDALI 1 THIMMANAHALLI 2
MAVANOOR 4 KANDALI 2
UPPAHALLI 4
UPPAHALLI 3 HALUVAGILU UPPAHALLI 2HALUVAGILU UPPAHALLI 1
VOTEHOLE DAM, KARNATAKA
OVERTOPPING FAILURE
MAXIMUM DEPTH Depth (m)
0-1 1-2 2-3 3-4 4-5 5-6 6-7 7-8 8-9 9 - 10
12°59'N
N D R K INSTITUTE OF TECHNOLOGY
12°58'N 10 - 11 11 - 12 RAILWAYS ROADS
12°56'N
12°57'N KIRAGADALU SETTLEMENTS
KADALU Locator Map
1 12°55'N
2
Source: Esri, DigitalGlobe, GeoEye, Earthstar Geographics, CNES/Airbus DS, USDA, USGS,
12°54'N 0 0.5 1 2
Km
Dam Rehabilitation and Improvement Project Date : March 2017 Doc. No. CDSO_MAP_DS_61
Central Project Management Unit
12°53'N Source: Esri, DigitalGlobe, GeoEye, Earthstar Geographics, CNES/Airbus DS, USDA, USGS, AeroGRID, IGN, and the GIS User Community
75°59'E 76°E 76°1'E 76°2'E 76°3'E 76°4'E 76°5'E 76°6'E 76°7'E
2/2 Map No.
Emergency Action Plan For Votehole Dam May-2019
Project ID Code KA06HH00154 Page A-42
75°55'E
13°6'N
75°56'E 75°57'E 75°58'E 75°59'E 76°E 76°1'E 76°2'E 76°3'E
¯
YEDEHALLI THENDEGERECHATRANAHALLI
PADUVALALU RAJANAHALLI / CHENNENAHALLI
JINIGENAHALLIBOMMENAHALLI
Votehole Dam NILAVAGILU DODDIHALLI / JANNAPURA
VOTEHOLE DAM, KARNATAKA
OVERTOPPING FAILURE
MAXIMUM VELOCITY Velocity (m/s)
0-1 1-2 2-3 3-4 4-5 5-6 6-7 RAILWAYS ROADS SETTLEMENTS
13°3'N
13°4'N
13°5'N
DODDIHALLI 1 KUPPE HOSAHALLIDODDIHALLI 2
13°2'N CHIKKANAGALU
Locator Map
13°1'N 1
BELLUR BELLUR 2
BANDITHIMMANAHALLI 13°N MUDIGERE
BASAVANAPURA
AGASARAHATTI MAVANOOR 1
KANDALI 2 MAVANOOR 4 Source: Esri, DigitalGlobe, GeoEye, Earthstar Geographics, CNES/Airbus DS, USDA, USGS, AeroGRID, IGN, and the GIS UserMAVANOOR 3 Community THIMMANAHALLI 1 75°59'E 76°E 76°1'E 76°2'E 76°3'E
0
Source: Esri, DigitalGlobe, GeoEye, Earthstar Geographics, CNES/Airbus DS, USDA, USGS,
0.5 1 2 Km
Dam Rehabilitation and Improvement Project Date : March 2017 Doc. No. CDSO_MAP_DS_61
Central Project Management Unit
12°59'N 1/2 Map No.
75°55'E 75°56'E 75°57'E 75°58'E
Emergency Action Plan For Votehole Dam May-2019
Project ID Code KA06HH00154 Page A-43
75°59'E 76°E
BANDITHIMMANAHALLI
76°1'E 76°2'E 76°3'E 76°4'E 76°5'E 76°6'E 76°7'E
13°N MUDIGERE
BASAVANAPURA
AGASARAHATTI MAVANOOR 1
¯
MAVANOOR 3 THIMMANAHALLI 1 KANDALI 1 THIMMANAHALLI 2
MAVANOOR 4 KANDALI 2
UPPAHALLI 4
UPPAHALLI 3 HALUVAGILU UPPAHALLI 2HALUVAGILU UPPAHALLI 1
VOTEHOLE DAM, KARNATAKA
OVERTOPPING FAILURE
MAXIMUM VELOCITY Velocity (m/s)
0-1 1-2 2-3 3-4 4-5 5-6 6-7 RAILWAYS ROADS SETTLEMENTS
12°59'N
N D R K INSTITUTE OF TECHNOLOGY
12°58'N
12°56'N
12°57'N KIRAGADALU
KADALU Locator Map
1 12°55'N
2
Source: Esri, DigitalGlobe, GeoEye, Earthstar Geographics, CNES/Airbus DS, USDA, USGS,
12°54'N 0 0.5 1 2
Km
Dam Rehabilitation and Improvement Project Date : March 2017 Doc. No. CDSO_MAP_DS_61
Central Project Management Unit
12°53'N Source: Esri, DigitalGlobe, GeoEye, Earthstar Geographics, CNES/Airbus DS, USDA, USGS, AeroGRID, IGN, and the GIS User Community
75°59'E 76°E 76°1'E 76°2'E 76°3'E 76°4'E 76°5'E 76°6'E 76°7'E
2/2 Map No.
Emergency Action Plan For Votehole Dam May-2019
Project ID Code KA06HH00154 Page A-44
75°55'E
13°6'N
75°56'E 75°57'E 75°58'E 75°59'E 76°E 76°1'E 76°2'E 76°3'E
¯
YEDEHALLI
953
VOTEHOLE DAM, KARNATAKA
OVERTOPPING FAILURE
MAXIMUM WATER SURFACE ELEVATION
WSE ( m - MSL ) 894 - 898 898 - 902 902 - 906 906 - 909 909 - 913 913 - 917 917 - 920 920 - 924 924 - 927 927 - 931
13°5'N
13°4'N 959 956 THENDEGERECHATRANAHALLI
948 962
935 BOMMENAHALLI
94 6 931 - 934 934 - 938 938 - 942 942 - 945 945 - 949 949 - 953 953 - 957 957 - 961
933
93 2
13°3'N Votehole Dam NILAVAGILU
944
94 1
93 9 934
KUPPE HOSAHALLI 942 961 - 963 CONTOUR RAILWAYS ROADS 13°2'N SETTLEMENTS
93 0 Locator Map
929
13°1'N 92 7
1
2
92 6
BELLUR
13°N 925
Source: Esri, DigitalGlobe, GeoEye, Earthstar Geographics, CNES/Airbus DS, USDA, USGS,
924 BASAVANAPURA
AGASARAHATTI
923
0 0.5 1 2 Km
Dam Rehabilitation and Improvement Project Date : March 2017 Doc. No. CDSO_MAP_DS_61
Central Project Management Unit
12°59'N
75°55'E 75°56'E 75°57'E 75°58'E Source: Esri, DigitalGlobe, GeoEye, Earthstar Geographics, CNES/Airbus DS, USDA, USGS, AeroGRID, IGN, and the GIS UserMAVANOOR 3 Community THIMMANAHALLI 1 75°59'E 76°E 76°1'E 76°2'E 76°3'E
MAVANOOR 4 KANDALI 2 1/2 Map No.
Emergency Action Plan For Votehole Dam May-2019
Project ID Code KA06HH00154 Page A-45
75°59'E 76°E
BANDITHIMMANAHALLI
76°1'E 76°2'E 76°3'E 76°4'E 76°5'E 76°6'E 76°7'E
BASAVANAPURA
AGASARAHATTI
923
¯
MAVANOOR 4 KANDALI 2 MAVANOOR 3 THIMMANAHALLI 1 KANDALI 1
92 2 921
13°N 924
VOTEHOLE DAM, KARNATAKA
OVERTOPPING FAILURE
MAXIMUM WATER SURFACE ELEVATION
WSE ( m - MSL ) 894 - 898 898 - 902 902 - 906 906 - 909 909 - 913 913 - 917 917 - 920 920 - 924
12°59'N
925
N D R K INSTITUTE OF TECHNOLOGY
918 12°58'N 5
924 - 927 927 - 931 931 - 934 934 - 938 938 - 942 942 - 945 945 - 949 949 - 953 953 - 957 957 - 961 961 - 963
913
KIRAGADALU 12°57'N 907
91
909
906 905 CONTOUR
RAILWAYS ROADS
12°56'N 904
SETTLEMENTS
Locator Map 900 90
90 2 3
899 1
12°55'N 898 2
897
895 12°54'N
Source: Esri, DigitalGlobe, GeoEye, Earthstar Geographics, CNES/Airbus DS, USDA, USGS,
0 0.5 1 2 Km
89 6
Dam Rehabilitation and Improvement Project Date : March 2017 Doc. No. CDSO_MAP_DS_61
Central Project Management Unit
12°53'N Source: Esri, DigitalGlobe, GeoEye, Earthstar Geographics, CNES/Airbus DS, USDA, USGS, AeroGRID, IGN, and the GIS User Community
75°59'E 76°E 76°1'E 76°2'E 76°3'E 76°4'E 76°5'E 76°6'E 76°7'E
2/2 Map No.
Emergency Action Plan For Votehole Dam May-2019
Project ID Code KA06HH00154 Page A-46
75°55'E 75°56'E 75°57'E 75°58'E 75°59'E 76°E 76°1'E 76°2'E 76°3'E
¯
YEDEHALLI THENDEGERECHATRANAHALLI
PADUVALALU RAJANAHALLI / CHENNENAHALLI
JINIGENAHALLIBOMMENAHALLI
Votehole Dam NILAVAGILU DODDIHALLI / JANNAPURA
13°6'N VOTEHOLE DAM, KARNATAKA
NON - FLOOD FAILURE
FLOOD WAVE ARRIVAL TIME*
13°5'N Arrival Time (Hrs.)
0-1 1-2 2-3 3-4 4-5 5-6 6-7 7-8 8-9 9 - 10 RAILWAYS ROADS SETTLEMENTS
13°3'N
13°4'N
DODDIHALLI 1 KUPPE HOSAHALLIDODDIHALLI 2
13°2'N CHIKKANAGALU
*Time since initiation of breach Locator Map
13°1'N 1
BELLUR BELLUR 2
BANDITHIMMANAHALLI 13°N
MUDIGERE 0
BASAVANAPURA
Source: Esri, DigitalGlobe, GeoEye, Earthstar Geographics, CNES/Airbus DS, USDA, USGS,
0.5 1 2 Km
Central Project Management Unit AGASARAHATTI
MAVANOOR 1 12°59'N
Dam Rehabilitation and Improvement Project Doc. No. CDSO_MAP_DS_61 Date : March 2017
Map No. KANDALI 2 MAVANOOR 4 Source: Esri, DigitalGlobe, GeoEye, Earthstar Geographics, CNES/Airbus DS, USDA, USGS, AeroGRID, IGN, and the GIS UserMAVANOOR 3 Community THIMMANAHALLI 1
75°55'E 75°56'E 75°57'E 75°58'E 75°59'E 76°E 76°1'E 76°2'E 76°3'E
1/2
Emergency Action Plan For Votehole Dam May-2019
Project ID Code KA06HH00154 Page A-47
75°59'E 76°E 76°1'E 76°2'E 76°3'E 76°4'E 76°5'E 76°6'E 76°7'E
BANDITHIMMANAHALLI 13°N MUDIGERE
BASAVANAPURA ¯
MAVANOOR 1 MAVANOOR 4
MAVANOOR 3 THIMMANAHALLI 1 KANDALI 1 THIMMANAHALLI 2
KANDALI 2
UPPAHALLI 4
UPPAHALLI 3 HALUVAGILU UPPAHALLI 2HALUVAGILU UPPAHALLI 1
VOTEHOLE DAM, KARNATAKA
NON - FLOOD FAILURE
FLOOD WAVE ARRIVAL TIME*
Arrival Time (Hrs.) 0-1 1-2 2-3 3-4 4-5 5-6 6-7 7-8 8-9 9 - 10 RAILWAYS ROADS SETTLEMENTS
AGASARAHATTI
12°59'N
N D R K INSTITUTE OF TECHNOLOGY
12°58'N
12°56'N
12°57'N KIRAGADALU
*Time since initiation of breach Locator Map
KADALU
1 12°55'N
2
Source: Esri, DigitalGlobe, GeoEye, Earthstar Geographics, CNES/Airbus DS, USDA, USGS,
12°54'N 0 0.5 1 2
Km Central Project Management Unit
Dam Rehabilitation and Improvement Project Doc. No. CDSO_MAP_DS_61 Date : March 2017
Map No. 12°53'N Source: Esri, DigitalGlobe, GeoEye, Earthstar Geographics, CNES/Airbus DS, USDA, USGS, AeroGRID, IGN, and the GIS User
Community 75°59'E 76°E 76°1'E 76°2'E 76°3'E 76°4'E 76°5'E 76°6'E 76°7'E
2/2
Emergency Action Plan For Votehole Dam May-2019
Project ID Code KA06HH00154 Page A-48
75°55'E 75°56'E 75°57'E 75°58'E 75°59'E 76°E 76°1'E 76°2'E 76°3'E
¯
YEDEHALLI THENDEGERECHATRANAHALLI
PADUVALALU RAJANAHALLI / CHENNENAHALLI
JINIGENAHALLIBOMMENAHALLI
Votehole Dam NILAVAGILU DODDIHALLI / JANNAPURA
13°6'N VOTEHOLE DAM, KARNATAKA
NON - FLOOD FAILURE
MAXIMUM DEPTH 13°5'N Depth (m)
0-1 1-2 2-3 3-4 4-5 5-6 6-7 7-8 8-9 9 - 10 10 - 11 11 - 12 RAILWAYS ROADS SETTLEMENTS 13°3'N
13°4'N
DODDIHALLI 1 KUPPE HOSAHALLIDODDIHALLI 2
13°2'N CHIKKANAGALU
Locator Map
13°1'N 1
BELLUR BELLUR 2
BANDITHIMMANAHALLI 13°N
MUDIGERE 0
BASAVANAPURA
Source: Esri, DigitalGlobe, GeoEye, Earthstar Geographics, CNES/Airbus DS, USDA, USGS,
0.5 1 2 Km
Central Project Management Unit AGASARAHATTI
MAVANOOR 1 12°59'N
Dam Rehabilitation and Improvement Project Doc. No. CDSO_MAP_DS_61 Date : March 2017
Map No. KANDALI 2 MAVANOOR 4 Source: Esri, DigitalGlobe, GeoEye, Earthstar Geographics, CNES/Airbus DS, USDA, USGS, AeroGRID, IGN, and the GIS UserMAVANOOR 3 Community THIMMANAHALLI 1
75°55'E 75°56'E 75°57'E 75°58'E 75°59'E 76°E 76°1'E 76°2'E 76°3'E
1/2
Emergency Action Plan For Votehole Dam May-2019
Project ID Code KA06HH00154 Page A-49
75°59'E 76°E 76°1'E 76°2'E 76°3'E 76°4'E 76°5'E 76°6'E 76°7'E
BANDITHIMMANAHALLI 13°N MUDIGERE
BASAVANAPURA ¯
MAVANOOR 1 MAVANOOR 4
MAVANOOR 3 THIMMANAHALLI 1 KANDALI 1 THIMMANAHALLI 2
KANDALI 2
UPPAHALLI 4
UPPAHALLI 3 HALUVAGILU UPPAHALLI 2HALUVAGILU UPPAHALLI 1
VOTEHOLE DAM, KARNATAKA
NON - FLOOD FAILURE
MAXIMUM DEPTH Depth (m)
0-1 1-2 2-3 3-4 4-5 5-6 6-7 7-8 8-9 9 - 10 10 - 11 11 - 12 RAILWAYS ROADS SETTLEMENTS
AGASARAHATTI
12°59'N
N D R K INSTITUTE OF TECHNOLOGY
12°58'N
12°56'N
12°57'N KIRAGADALU
Locator Map KADALU
1 12°55'N
2
Source: Esri, DigitalGlobe, GeoEye, Earthstar Geographics, CNES/Airbus DS, USDA, USGS,
12°54'N 0 0.5 1 2
Km Central Project Management Unit
Dam Rehabilitation and Improvement Project Doc. No. CDSO_MAP_DS_61 Date : March 2017
Map No. 12°53'N Source: Esri, DigitalGlobe, GeoEye, Earthstar Geographics, CNES/Airbus DS, USDA, USGS, AeroGRID, IGN, and the GIS User
Community 75°59'E 76°E 76°1'E 76°2'E 76°3'E 76°4'E 76°5'E 76°6'E 76°7'E
2/2
Emergency Action Plan For Votehole Dam May-2019
Project ID Code KA06HH00154 Page A-50
75°55'E 75°56'E 75°57'E 75°58'E 75°59'E 76°E 76°1'E 76°2'E 76°3'E
¯
YEDEHALLI THENDEGERECHATRANAHALLI
PADUVALALU RAJANAHALLI / CHENNENAHALLI
JINIGENAHALLIBOMMENAHALLI
Votehole Dam NILAVAGILU DODDIHALLI / JANNAPURA
13°6'N VOTEHOLE DAM, KARNATAKA
NON - FLOOD FAILURE
MAXIMUM VELOCITY 13°5'N Velocity (m/s)
0-1 1-2 2-3 3-4 4-5 5-6 RAILWAYS ROADS SETTLEMENTS
13°3'N
13°4'N
DODDIHALLI 1 KUPPE HOSAHALLIDODDIHALLI 2
13°2'N CHIKKANAGALU
Locator Map
13°1'N 1
BELLUR BELLUR 2
BANDITHIMMANAHALLI 13°N
MUDIGERE 0
BASAVANAPURA
Source: Esri, DigitalGlobe, GeoEye, Earthstar Geographics, CNES/Airbus DS, USDA, USGS,
0.5 1 2 Km
Central Project Management Unit AGASARAHATTI
MAVANOOR 1 12°59'N
Dam Rehabilitation and Improvement Project Doc. No. CDSO_MAP_DS_61 Date : March 2017
Map No. KANDALI 2 MAVANOOR 4 Source: Esri, DigitalGlobe, GeoEye, Earthstar Geographics, CNES/Airbus DS, USDA, USGS, AeroGRID, IGN, and the GIS UserMAVANOOR 3 Community THIMMANAHALLI 1
75°55'E 75°56'E 75°57'E 75°58'E 75°59'E 76°E 76°1'E 76°2'E 76°3'E
1/2
Emergency Action Plan For Votehole Dam May-2019
Project ID Code KA06HH00154 Page A-51
75°59'E 76°E 76°1'E 76°2'E 76°3'E 76°4'E 76°5'E 76°6'E 76°7'E
BANDITHIMMANAHALLI 13°N MUDIGERE
BASAVANAPURA ¯
MAVANOOR 1 MAVANOOR 4
MAVANOOR 3 THIMMANAHALLI 1 KANDALI 1 THIMMANAHALLI 2
KANDALI 2
UPPAHALLI 4
UPPAHALLI 3 HALUVAGILU UPPAHALLI 2HALUVAGILU UPPAHALLI 1
VOTEHOLE DAM, KARNATAKA
NON - FLOOD FAILURE
MAXIMUM VELOCITY Velocity (m/s)
0-1 1-2 2-3 3-4 4-5 5-6 RAILWAYS ROADS SETTLEMENTS
AGASARAHATTI
12°59'N
N D R K INSTITUTE OF TECHNOLOGY
12°58'N
12°56'N
12°57'N KIRAGADALU
Locator Map KADALU
1 12°55'N
2
Source: Esri, DigitalGlobe, GeoEye, Earthstar Geographics, CNES/Airbus DS, USDA, USGS,
12°54'N 0 0.5 1 2
Km Central Project Management Unit
Dam Rehabilitation and Improvement Project Doc. No. CDSO_MAP_DS_61 Date : March 2017
Map No. 12°53'N Source: Esri, DigitalGlobe, GeoEye, Earthstar Geographics, CNES/Airbus DS, USDA, USGS, AeroGRID, IGN, and the GIS User
Community 75°59'E 76°E 76°1'E 76°2'E 76°3'E 76°4'E 76°5'E 76°6'E 76°7'E
2/2
Emergency Action Plan For Votehole Dam May-2019
Project ID Code KA06HH00154 Page A-52
75°55'E 75°56'E 75°57'E 75°58'E 75°59'E 76°E 76°1'E 76°2'E 76°3'E
934 ¯
THENDEGERECHATRANAHALLI
13°6'N VOTEHOLE DAM, KARNATAKA
NON - FLOOD FAILURE
MAXIMUM WATER SURFACE ELEVATION
WSE ( m - MSL ) 894 - 897 897 - 901 901 - 904 904 - 907 907 - 911 911 - 915
13°5'N
YEDEHALLI 13°4'N 951
954 958 956 915 - 919 919 - 923 923 - 926 926 - 930 930 - 933
PADUVALALU 961
946 JINIGENAHALLI
Votehole Dam NILAVAGILU 93
9
BOMMENAHALLI 93 5 933 - 936
936 - 941 941 - 944 944 - 948 948 - 952 952 - 955
13°3'N DODDIHALLI / JANNAPURA 943
94 1
KUPPE HOSAHALLI 933 955 - 959 959 - 962 CONTOUR RAILWAYS ROADS
CHIKKANAGALU 13°2'N 932
SETTLEMENTS
13°1'N
928 Locator Map
92 7 1
BELLUR BELLUR 2
92 6
92 13°N
5
924 MUDIGERE 0
Source: Esri, DigitalGlobe, GeoEye, Earthstar Geographics, CNES/Airbus DS, USDA, USGS,
0.5 1 2 Km BASAVANAPURA
923 Central Project Management Unit
Dam Rehabilitation and Improvement Project Doc. No. CDSO_MAP_DS_61 AGASARAHATTI
MAVANOOR 1 12°59'N
Date : March 2017 MAVANOOR 4 KANDALI 2 Map No.
Source: Esri, DigitalGlobe, GeoEye, Earthstar Geographics, CNES/Airbus DS, USDA, USGS, AeroGRID, IGN, and the GIS User 922Community
75°55'E 75°56'E 75°57'E 75°58'E 75°59'E 76°E 76°1'E 76°2'E 76°3'E
1/2
Emergency Action Plan For Votehole Dam May-2019
Project ID Code KA06HH00154 Page A-53
75°59'E 76°E 92 5
76°1'E 76°2'E 76°3'E 76°4'E 76°5'E 76°6'E 76°7'E
13°N
BASAVANAPURA 923
924 MUDIGERE ¯
MAVANOOR 4 KANDALI 2
VOTEHOLE DAM, KARNATAKA
NON - FLOOD FAILURE
MAXIMUM WATER SURFACE ELEVATION
WSE ( m - MSL ) 894 - 897 897 - 901 901 - 904 904 - 907 907 - 911
AGASARAHATTI MAVANOOR 1
12°59'N 922 THIMMANAHALLI 1
KANDALI 1
921 N D R K INSTITUTE OF TECHNOLOGY 920 911 - 915
915 - 919 919 - 923 923 - 926 926 - 930 930 - 933 933 - 936 936 - 941 941 - 944
12°58'N 915
917 913
12°57'N KIRAGADALU 944 - 948 948 - 952 952 - 955
90 8
906 955 - 959 959 - 962 CONTOUR RAILWAYS
904 12°56'N
ROADS SETTLEMENTS
903 899 Locator Map
902
898 12°55'N
1
2 897
894 12°54'N
Source: Esri, DigitalGlobe, GeoEye, Earthstar Geographics, CNES/Airbus DS, USDA, USGS,
0 0.5 1 2 Km
89 6
895
Central Project Management Unit Dam Rehabilitation and Improvement Project Doc. No. CDSO_MAP_DS_61 Date : March 2017
Map No. 12°53'N Source: Esri, DigitalGlobe, GeoEye, Earthstar Geographics, CNES/Airbus DS, USDA, USGS, AeroGRID, IGN, and the GIS User
Community 75°59'E 76°E 76°1'E 76°2'E 76°3'E 76°4'E 76°5'E 76°6'E 76°7'E
2/2
Emergency Action Plan For Votehole Dam May-2019
Project ID Code KA06HH00154 Page A-54
75°55'E 75°56'E 75°57'E 75°58'E 75°59'E 76°E 76°1'E 76°2'E 76°3'E
¯
YEDEHALLI THENDEGERECHATRANAHALLI
PADUVALALU RAJANAHALLI / CHENNENAHALLI
JINIGENAHALLIBOMMENAHALLI
Votehole Dam NILAVAGILU DODDIHALLI / JANNAPURA
13°6'N VOTEHOLE DAM, KARNATAKA
LARGE CONTROLLED RELEASE
MAXIMUM DEPTH 13°5'N
Depth (m) 0-1 1-2 2-3 3-4 4-5 5-6 RAILWAYS ROADS SETTLEMENTS
13°3'N
13°4'N
DODDIHALLI 1 KUPPE HOSAHALLIDODDIHALLI 2
13°2'N CHIKKANAGALU
Locator Map
13°1'N 1
BELLUR BELLUR 2
BANDITHIMMANAHALLI 13°N
MUDIGERE 0
BASAVANAPURA
Source: Esri, DigitalGlobe, GeoEye, Earthstar Geographics, CNES/Airbus DS, USDA, USGS,
0.5 1 2 Km
Central Project Management Unit AGASARAHATTI
MAVANOOR 1 12°59'N
Dam Rehabilitation and Improvement Project Doc. No. CDSO_MAP_DS_61 Date : March 2017
Map No. KANDALI 2 MAVANOOR 4 Source: Esri, DigitalGlobe, GeoEye, Earthstar Geographics, CNES/Airbus DS, USDA, USGS, AeroGRID, IGN, and the GIS UserMAVANOOR 3 Community THIMMANAHALLI 1
75°55'E 75°56'E 75°57'E 75°58'E 75°59'E 76°E 76°1'E 76°2'E 76°3'E
1/2
Emergency Action Plan For Votehole Dam May-2019
Project ID Code KA06HH00154 Page A-55
75°59'E 76°E 76°1'E 76°2'E 76°3'E 76°4'E 76°5'E 76°6'E 76°7'E
BANDITHIMMANAHALLI 13°N MUDIGERE
BASAVANAPURA ¯
MAVANOOR 1 MAVANOOR 4
MAVANOOR 3 THIMMANAHALLI 1 KANDALI 1 THIMMANAHALLI 2
KANDALI 2
UPPAHALLI 4
UPPAHALLI 3 HALUVAGILU UPPAHALLI 2HALUVAGILU UPPAHALLI 1
VOTEHOLE DAM, KARNATAKA
LARGE CONTROLLED RELEASE
MAXIMUM DEPTH Depth (m)
0-1 1-2 2-3 3-4 4-5 5-6 RAILWAYS ROADS SETTLEMENTS
AGASARAHATTI
12°59'N
N D R K INSTITUTE OF TECHNOLOGY
12°58'N
12°56'N
12°57'N KIRAGADALU
Locator Map KADALU
1 12°55'N
2
Source: Esri, DigitalGlobe, GeoEye, Earthstar Geographics, CNES/Airbus DS, USDA, USGS,
12°54'N 0 0.5 1 2
Km Central Project Management Unit
Dam Rehabilitation and Improvement Project Doc. No. CDSO_MAP_DS_61 Date : March 2017
Map No. 12°53'N Source: Esri, DigitalGlobe, GeoEye, Earthstar Geographics, CNES/Airbus DS, USDA, USGS, AeroGRID, IGN, and the GIS User
Community 75°59'E 76°E 76°1'E 76°2'E 76°3'E 76°4'E 76°5'E 76°6'E 76°7'E
2/2
Emergency Action Plan For Votehole Dam May-2019
Project ID Code KA06HH00154 Page A-56
75°55'E 75°56'E 75°57'E 75°58'E 75°59'E 76°E 76°1'E 76°2'E 76°3'E
¯
YEDEHALLI THENDEGERECHATRANAHALLI
PADUVALALU RAJANAHALLI / CHENNENAHALLI
JINIGENAHALLIBOMMENAHALLI
Votehole Dam NILAVAGILU DODDIHALLI / JANNAPURA
13°6'N VOTEHOLE DAM, KARNATAKA
LARGE CONTROLLED RELEASE
MAXIMUM VELOCITY 13°5'N
Velocity (m/s) 0 - 0.5 0.5 - 1.0 1.0 - 1.5 1.5 - 2.0 2.0 - 2.5 2.5 - 3.0 RAILWAYS ROADS SETTLEMENTS
13°3'N
13°4'N
DODDIHALLI 1 KUPPE HOSAHALLIDODDIHALLI 2
13°2'N CHIKKANAGALU
Locator Map
13°1'N 1
BELLUR BELLUR 2
BANDITHIMMANAHALLI 13°N
MUDIGERE 0
BASAVANAPURA
Source: Esri, DigitalGlobe, GeoEye, Earthstar Geographics, CNES/Airbus DS, USDA, USGS,
0.5 1 2 Km
Central Project Management Unit AGASARAHATTI
MAVANOOR 1 12°59'N
Dam Rehabilitation and Improvement Project Doc. No. CDSO_MAP_DS_61 Date : March 2017
Map No. KANDALI 2 MAVANOOR 4 Source: Esri, DigitalGlobe, GeoEye, Earthstar Geographics, CNES/Airbus DS, USDA, USGS, AeroGRID, IGN, and the GIS UserMAVANOOR 3 Community THIMMANAHALLI 1
75°55'E 75°56'E 75°57'E 75°58'E 75°59'E 76°E 76°1'E 76°2'E 76°3'E
1/2
Emergency Action Plan For Votehole Dam May-2019
Project ID Code KA06HH00154 Page A-57
75°59'E 76°E 76°1'E 76°2'E 76°3'E 76°4'E 76°5'E 76°6'E 76°7'E
BANDITHIMMANAHALLI 13°N MUDIGERE
BASAVANAPURA ¯
MAVANOOR 1 MAVANOOR 4
MAVANOOR 3 THIMMANAHALLI 1 KANDALI 1 THIMMANAHALLI 2
KANDALI 2
UPPAHALLI 4
UPPAHALLI 3 HALUVAGILU UPPAHALLI 2HALUVAGILU UPPAHALLI 1
VOTEHOLE DAM, KARNATAKA
LARGE CONTROLLED RELEASE
MAXIMUM VELOCITY Velocity (m/s)
0 - 0.5 0.5 - 1.0 1.0 - 1.5 1.5 - 2.0 2.0 - 2.5 2.5 - 3.0 RAILWAYS ROADS SETTLEMENTS
AGASARAHATTI
12°59'N
N D R K INSTITUTE OF TECHNOLOGY
12°58'N
12°56'N
12°57'N KIRAGADALU
Locator Map KADALU
1 12°55'N
2
Source: Esri, DigitalGlobe, GeoEye, Earthstar Geographics, CNES/Airbus DS, USDA, USGS,
12°54'N 0 0.5 1 2
Km Central Project Management Unit
Dam Rehabilitation and Improvement Project Doc. No. CDSO_MAP_DS_61 Date : March 2017
Map No. 12°53'N Source: Esri, DigitalGlobe, GeoEye, Earthstar Geographics, CNES/Airbus DS, USDA, USGS, AeroGRID, IGN, and the GIS User
Community 75°59'E 76°E 76°1'E 76°2'E 76°3'E 76°4'E 76°5'E 76°6'E 76°7'E
2/2
Emergency Action Plan For Votehole Dam May-2019
Project ID Code KA06HH00154 Page A-58
75°55'E 75°56'E 75°57'E 75°58'E 75°59'E 76°E 76°1'E 76°2'E 76°3'E
¯
YEDEHALLI 95
0 948
13°6'N VOTEHOLE DAM, KARNATAKA
LARGE CONTROLLED RELEASE
MAXIMUM WATER SURFACE ELEVATION
WSE ( m - MSL ) 890 - 895 895 - 900 900 - 905 905 - 910 910 - 915 915 - 920
13°4'N
13°5'N
THENDEGERECHATRANAHALLI 9 44
1 94
931
920 - 925 925 - 930 930 - 935 935 - 940 940 - 945 945 - 950 950 - 955 CONTOUR 13°3'N Votehole Dam NILAVAGILU
DODDIHALLI / JANNAPURA 929
93 9
6 93
953
JINIGENAHALLI
937 RAILWAYS ROADS SETTLEMENTS DODDIHALLI 1
DODDIHALLI 2 KUPPE HOSAHALLI
13°2'N 928
13°1'N
92 Locator Map 6
925 1
BELLUR BELLUR
924 2
92 13°N
3
MUDIGERE 922
Source: Esri, DigitalGlobe, GeoEye, Earthstar Geographics, CNES/Airbus DS, USDA, USGS,
0 0.5 1 2 Km BASAVANAPURA
Central Project Management Unit AGASARAHATTI Dam Rehabilitation and Improvement Project
Doc. No. CDSO_MAP_DS_61 Date : March 2017
12°59'N KANDALI 2 MAVANOOR 4 Source: Esri, DigitalGlobe, GeoEye, Earthstar Geographics, CNES/Airbus DS, USDA, USGS, AeroGRID, IGN, and the GIS User MAVANOOR 3 Community THIMMANAHALLI 1
92 1 Map No. 1/2
75°55'E 75°56'E 75°57'E 75°58'E 75°59'E 76°E 76°1'E 76°2'E 76°3'E
Project ID Code KA06HH00154 Page A-59
75°59'E 76°E 92 3
76°1'E 76°2'E 76°3'E 76°4'E 76°5'E 76°6'E 76°7'E
13°N MUDIGERE 922
BASAVANAPURA ¯
92
VOTEHOLE DAM, KARNATAKA
LARGE CONTROLLED RELEASE
MAXIMUM WATER SURFACE ELEVATION
AGASARAHATTI
12°59'N MAVANOOR 4 MAVANOOR 3 THIMMANAHALLI 1 KANDALI 1 THIMMANAHALLI 2
KANDALI 2 WSE ( m - MSL ) 890 - 895 895 - 900 900 - 905 905 - 910 910 - 915 915 - 920
920 N D R K INSTITUTE OF TECHNOLOGY
1
91 9 920 - 925
925 - 930 930 - 935
911
12°58'N UPPAHALLI 3
UPPAHALLI 2 HALUVAGILU 935 - 940 940 - 945 945 - 950 950 - 955 CONTOUR RAILWAYS ROADS SETTLEMENTS
908
12°57'N KIRAGADALU
905
90 4
903 12°56'N
90 899 2
90 1 897
12°55'N
896
89 89
3 5
0 12°54'N 894
Central Project Management Unit Dam Rehabilitation and Improvement Project Doc. No. CDSO_MAP_DS_61 Date : March 2017
12°53'N Source: Esri, DigitalGlobe, GeoEye, Earthstar Geographics, CNES/Airbus DS, USDA, USGS, AeroGRID, IGN, and the GIS User Community
75°59'E 76°E 76°1'E 76°2'E 76°3'E 76°4'E 76°5'E 76°6'E 76°7'E
Emergency Action Plan For Votehole Dam May-2019
Project ID Code KA06HH00154 Page A-60
Tab 3
Dam Description
Official Dam Name: Votehole Dam
Name of Stream: Votehole River
Dam Location: near Lakkenahally village, Belur taluk, Hassan Dist.
Latitude/Longitude: Lat 130 3’ 30” N, Lon 750 55’ 00” E
Seismic Zone: Zone III
Year of Starting of Dam Construction: 1976
Year of First Impoundment:1991-92
Year of Commissioning of Dam Project: 2008
Name of Immediate Upstream Dam: No Upstream project
Name of Immediate Downstream Dam: Hemavathy dam, Gorur
Dam Owner: Managing Director, Cauvery Neeravari Nigam Limited, Bengaluru.
Phone Number: 080-22352997,
Dam Owner’s Address: O/O Chief Engineer, CNNL Hemavathy Project Zone, Gorur.
Main Dam
Type Central masonry spillway with side non-overflow
dam with earth flanks.
Year Constructed 1976-1986
Length 900 .00meters
Maximum Height 44.48metres (146’) (from deepest Foundation)
Top Width 5.49 meters
Top of Embankment Elevation 968.48 meters -msl
Main spillway Arrangements
Type : Controlled ogee weir
Location :Centre of the main dam
Crest Level of Spillway :961.476 mtrs
Top Level of Spillway : 966.05 mtrs
Type of Spillway : Ogee Type
Type of gate : Radial gates.
No. of Bays : 3
Size of the gate : Height=4.57mtrs width =9.14 mtrs
Total Spillway capacity of all the Bays : 577.346 Cumecs
Energy Dissipation arrangement :Stilling Basin
Emergency Spillway- Not Available
Embankment
Saddle Dam-1
Emergency Action Plan For Votehole Dam May-2019
Project ID Code KA06HH00154 Page A-61
Type Earthen embankment
(comprising of zoned section having impervious central zone and semi pervious outer zone)
Year Constructed 1976-1986
Length 175.00meters
Maximum Height 26.00meters
Top Width 5.49 meters
Top of Embankment Elevation 968.48 metres-msl
No Spillway Arrangements for Embankment Portion
Inlet-Outlet Works
Right Bank Irrigation Sluice Gates
Type Vertical Lifting with Hoisting Arrangements
Numbers 1 nos
Location Right Bank
Gates 1 Service gate and 1 Emergency gates
Invert Elevation (Inlet) 953.235 metres-msl
Invert Elevation (Outlet) 953.135 metres-msl
Original Capacity 3.88 cumecs
Designed discharge 4.114 Cumecs
Left Bank Sluice Gates
Type Vertical Lifting with Hoisting Arrangments
Numbers 1 nos
Location Left Flank
Gates 1 Service gate and 1 Emergency gates
Invert Elevation (Inlet) 955.00 metres-msl
Invert Elevation (Outlet) 949.90 metres-msl
Original Capacity 0.358 cumecs
River Sluice Gates
Type 0.3 metredia pipe
Numbers 1 nos
Location Left Flank
Gates/valve Valve arrangements
Invert Elevation (Inlet) 941.23 metres-msl
Invert Elevation (Outlet) 940.55 metres-msl
Reservoir
Elev. Top of Conservation Pool 968.48 metres-msl
Capacity Conservation Pool (Normal Pool) 42.75 Mcum (1.51 TMC)
Capacity at Top of Dam (Maximum) 2.85 million of cubic metres
Catchment Area 110.33 Sq Km
Surface area 1468 Acres
Emergency Action Plan For Votehole Dam May-2019
Project ID Code KA06HH00154 Page A-62
Tab 4
Sample Public Announcements
Note:These messages are communicated to downstream residents to alert the public of impending
danger. The Cauvery Neeravari Nigam Limited should coordinate with the India Meteorological De-
partment, the Hassan DistrictDisaster Management Authority, and the District Magistrate/Collector
for Hassan prior to release. Messages can be communicated via radio, television, bulk SMSs of local
mobile networks, and other media outlets.
Announcement for a Slowly Developing “Watch” Condition (BLUE Emergency Level)
Cauvery Neeravari Nigam Limited has declared a BLUE Level “Watch” condition forVotehole Dam,
Project Identification Code [KA06HH0154] as of [time and date]. [Briefly describe the problem or
condition.] Although there is no immediate danger of the dam failing, [Describe what actions are be-
ing taken to monitor and control the situation.] [State the quantity of any releases from the reservoir.]
Announcement for a Worsening “Watch” Condition (BLUE`Emergency Level)
Cauvery Neeravari Nigam Limited has declared a BLUE Level “Watch” condition for Votehole Dam,
Project Identification Code [KA06HH0154] as of [time and date]. [Briefly describe the problem or
condition.] Although there is no immediate danger of the dam failing a possibility now exists that the
dam will fail if correction efforts are unsuccessful. Describe what actions are being taken to monitor
and correct the situation.] [State the quantity of any releases from the reservoir]. Additional news will
be made available as soon as it is received.
Announcement for aProbable“Failure” Condition (ORANGE Emergency Level)
Urgent! This is an emergency message Cauvery Neeravari Nigam Limited has announced that Vote-
hole Dam ,KA06HH0154 is probably going to fail. [Describe what actions are being taken to monitor
and control the situation.] It is possible that the dam will fail in [##] hours. Residents in low lying are-
as along the [Stream], the [Stream], and the [Stream], as well as the town of [Name], should prepare
for immediate evacuation. Additional news will be made available as soon as it is received.
Announcement of an Impending“Failure” Condition (REDEmergency Level)
Emergency! This is an emergency message. Votehole Dam,KA06HH0154is going to fail at any mo-
ment. Residents who have not yet done so should immediately evacuate the city of [Name] and low-
lying areas along the [Stream], the [Stream], and the [Stream]. The flood waters have already reached
[Highway] and [Road]. Additional news will be made available as soon as it is received.
Announcement of an Ongoing “Failure” Condition (REDEmergency Level)
Emergency! This is an emergency message. Votehole Dam, KA06HH0154 failed at [time and date].
Residents who have not yet done so should immediately evacuate the city of [Name] and low-lying
areas along the [Stream], the [Stream], and the [Stream]. The flood waters have already reached
[Highway] and [Road]. Additional news will be made available as soon as it is received.
Emergency Action Plan For Votehole Dam May-2019
Project ID Code KA06HH00154 Page A-63
Tab 5
Evidence of Distress
General
observa-
tion
Specific
observation
Emergency
condition
level
Emergency action Equip-
ment,
material,
and sup-
plies
Data to
record
Boil
s
Small boils, no in-
crease of water flow,
flowing clear water.
BLUE
Closely check all of down-
stream toe, especially in the
vicinity of boil for additional
boils, wet spots, sinkholes, or
seepage. Closely monitor en-
tire area for changes or flow
rate increases.
None Site and
location,
approx-
imate
flow
Large or additional
boils near previously
identified ones, with-
out increasing flow
rate, but carrying
small amount of soil
particles.
BLUE
Initiate 24-hour surveillance.
Monitor as described above.
Construct sandbag ring dikes
around boils, to cover them
with water to retard the
movement of soil particles.
Filter cloth may be used to
retard soil movement, but do
not retard the flow of water.
Sandbags,
filter cloth
Site and
location,
approx-
imate
flow
Large or additional
boils near previously
identified ones, in-
creasing flow rate,
carrying soil parti-
cles.
ORANGE
Continue 24-hour surveil-
lance. Continue monitoring
and remedial action as de-
scribed above. Initiate emer-
gency lowering of the reser-
voir. Issue a warning to down-
stream residents.
Sandbags,
pump
Site and
location,
approx-
imate
flow
Rapidly increasing
size of boils and flow
increasing and mud-
dy water.
RED
Downstream evacuation. Em-
ploy all available equipment to
attempt to construct a large
ring dike around the boil area.
Dozer,
shovels,
source of
earth fill
Site and
location,
approx-
imate
flow
See
pa
ge
Minor seepage of
clear water at toe, on
slope of embank-
ment, or at the abut-
ments.
BLUE
Closely check entire embank-
ment for other seepage areas.
Use wooden stakes or flagging
to delineate seepage area. Try
to channel and measure flow.
Look for upstream whirlpools.
Wooden
stakes,
flagging
Site, lo-
cation,
approx-
imate
flow
Additional seepage
areas observed flow-
ing clear water and/or
increasing flow rate. BLUE
Initiate 24-hour surveillance.
Monitor as described above.
Construct measuring weir and
channel all seepage through
weir. Attempt to determine
source of seepage.
Dozer,
shovels
Site, lo-
cation,
approx-
imate
flow
Seriously or rapidly
increasing seepage,
under-seepage, or
drain flow.
ORANGE
Continue 24-hour monitoring
and remedial action as de-
scribed above. Initiate emer-
gency lowering of the reser-
voir. Construct a large ring
Dozer,
shovels,
source of
fill mate-
rial
Site loca-
tion, ap-
proxi-
mate
flow
Emergency Action Plan For Votehole Dam May-2019
Project ID Code KA06HH00154 Page A-64
General
observa-
tion
Specific
observation
Emergency
condition
level
Emergency action Equip-
ment,
material,
and sup-
plies
Data to
record
dike around the seepage area.
Additional seepage
areas with rapid in-
crease in flow and
muddy water.
RED
Downstream evacuation. Em-
ploy all available equipment to
attempt to construct a large
ring dike around the seepage
area.
Dozer,
shovels,
source of
fill mate-
rial
Site loca-
tion, ap-
proxi-
mate
flow
Sli
des
or s
ever
e er
osi
on
Skin slide or slough
on slope of embank-
ment. No further
movement of slide
and embankment
crest not degraded.
BLUE
Examine rest of embankment
for other slides. Place stakes in
slide material and adjacent to
it for determining if further
movement is taking place.
Stakes,
tape
measure
Distance
between
stakes
Slide or erosion in-
volving large mass of
material, crest of em-
bankment is degrad-
ed, no movement or
very slow continuing
movement.
BLUE
Initiate 24-hour surveillance.
Mobilize all available re-
sources and equipment for
repair operations to increase
freeboard and to protect the
exposed embankment materi-
al. Start filling sandbags and
stockpile near slide area.
Dozer,
shovels,
sources of
fill mate-
rial, sand-
bags
Distance
between
stakes
Slide or erosion in-
volving large mass of
material, crest of em-
bankment is degrad-
ed, progressively in-
creasing in size.
ORANGE
Continue monitoring and re-
medial actions as described
above. Place additional mate-
rial at the toe of the slope to
stop the slide.
Dozer,
shovels,
source of
fill mate-
rial, pump
Distance
between
stakes
Slide or erosion in-
volving large mass of
material, crest of em-
bankment is severely
degraded, movement
of slide is continuing
and may reach pool
level.
RED
Downstream evacuation. Uti-
lize all available equipment
and personnel to sandbag the
degraded slide area to prevent
it from overtopping.
Dozer,
shovels,
sandbags,
pump
Distance
between
stakes
Sin
kh
ole
s
Sinkholes anywhere-
on the embankmentor
within 150 me-
tresdownstream from
the toe.
BLUE
Carefully walk the entire em-
bankment and downstream
area looking for additional
sinkholes, movement, or seep-
age.
Stakes,
flagging
Size,
location
Sinkholes with corre-
sponding seepage
anywhere on the em-
bankment or down-
stream from the toe.
BLUE
Initiate 24-hour surveillance.
Monitor as above. Construct
sandbag dike around the seep-
age exit point to reduce the
flow rate. Start filling sand-
bags and stockpile near sink-
hole.
Dozer,
shovels,
pump
Size,
location
Large sinkholes with
corresponding seep-
age anywhere on the
ORANGE
Continue monitoring and re-
medial action as described
above. Utilize sandbags to
Sandbags,
dozer,
pump
Size,
location
Emergency Action Plan For Votehole Dam May-2019
Project ID Code KA06HH00154 Page A-65
General
observa-
tion
Specific
observation
Emergency
condition
level
Emergency action Equip-
ment,
material,
and sup-
plies
Data to
record
embankment or
downstreamfrom the
toe.
increase the freeboard on the
dam if necessary.
Sinkholes rapidly
getting worse, seep-
age flowing muddy
water and increasing
flow.
RED
Downstream evacuation. Uti-
lize all available equipment
and personnel to attempt to
construct a large ring dike
around the area.
Dozer,
shovels,
pump
Size,
location
Set
tlem
ent
Obvious settlement
of the crest of the
embankment, espe-
cially adjacent to
concrete structures.
BLUE
Look for bulges on slope or
changes in crest alignment.
None Size,
location
Settlement of crest of
embankment that is
progressing, especial-
ly adjacent to con-
crete structures or if
any corresponding
seepage is present.
BLUE
Initiate 24-hour surveillance.
Mobilize all available re-
sources for repair operations
to increase freeboard. Fill and
stockpile sandbags. Identify
any boils near settlement
points for flowing material
and pursue
action for boils.
Sandbags,
dozer,
shovels,
source of
fill mate-
rial
Size,
location
Settlement of crest of
embankment that is
rapidly progressing
especially adjacent to
concrete structures or
if any corresponding
seepage is flowing
muddy water or in-
creasing flow.
ORANGE
Continue monitoring and re-
medial actions as described
above. Use sandbags to in-
crease the freeboard on the
dam if necessary.
Sandbags,
shovels,
dozer,
source of
fill mate-
rial
Size,
location
Progressing settle-
ment that is expected
to degrade the em-
bankment to reser-
voir level. RED
Downstream evacuation. Uti-
lize all available equipment
and personnel to build up the
crest in the area that is set-
tling. Identify any boils near
settlement points for flowing
material and pursue action for
boils.
Dozer,
shovels,
source of
fill mate-
rial, sand-
bags
Size,
location
Cra
ckin
g
Cracks in the em-
bankment crest
or on slopes.
BLUE
Walk on entire crest and slope
and check for additional
cracking.
Stakes,
tape
measure
Size,
location
Numerous cracks in
crest that are enlarg-
ing, especially those
perpendicular to the
BLUE
Initiate 24-hour surveillance.
Carefully monitor and meas-
ure cracking to determine the
speed and extent of the prob-
Stakes,
tape
measure,
dozer,
Size,
location
Emergency Action Plan For Votehole Dam May-2019
Project ID Code KA06HH00154 Page A-66
General
observa-
tion
Specific
observation
Emergency
condition
level
Emergency action Equip-
ment,
material,
and sup-
plies
Data to
record
centerline of the dam. lem. Mobilize to fill cracks.
Cracks parallel to the center-
line indicate a slide. Follow
remedial action
for slides.
shovels,
source of
fill mate-
rial
Large cracks in the
crest that are rapidly
enlarging, especially
those perpendicular
to the centerline of
the dam.
ORANGE
Continue monitoring and re-
medial action as described
above.
Dozer,
shovels,
source of
fill mate-
rial
Size,
location
Cracking that extends
to pool elevation.
RED
Downstream evacuation. Con-
tinue remedial actions as de-
scribed above.
Dozer,
shovels,
source of
fill mate-
rial
Size,
location
Cra
ckin
g o
r m
ovem
ent
of
con
cret
e st
ruct
ure
Minor cracking
and/or movement.
BLUE
Immediately install measuring
device to monitor movement.
Crack
Monitors,
stakes,
tape
measure
Size,
location
Significant cracking
and/or movement.
BLUE
Initiate 24-hour surveillance.
Lower burlap on upstream
face of crack to reduce flow of
soil particles. Dump large rock
on downstream of moving
concrete structure monolith to
resist the movement.
Burlap,
rock, doz-
er, shov-
els
Size,
location,
flow rate
Serious cracking
and/or movement ORANGE
Prepare for evacuation. Con-
tinue monitoring and remedial
action as described above.
Dozer,
rock, bur-
lap, crack
monitors
Size,
move-
ment,
flow rate
Major cracking
and/or movement RED
Downstream evacuation. Dam
failure is imminent. Continue
monitoring and remedial ac-
tions as described above.
Dozer,
shovels,
rock
Size,
location,
flow rate
Up
stre
am
wh
irl-
po
ol
Whirlpool in the lake
in the vicinity of the
embankment
RED
Downstream evacuation. At-
tempt to plug the entrance of
the whirlpool with riprap from
the slope of the embankment.
Search downstream for an exit
point and construct a ring dike
to retard the flow of soil parti-
cles.
Dozer, fill
material,
sandbags,
filter
cloth,
straw,
rocks
Size,
location,
flow rate
Emergency Action Plan For Votehole Dam May-2019
Project ID Code KA06HH00154 Page A-67
General
observa-
tion
Specific
observation
Emergency
condition
level
Emergency action Equip-
ment,
material,
and sup-
plies
Data to
record
Ma
lfu
nct
ion
of
gate
Structural member of
a gate or gate opera-
tor broken or severe-
ly damaged so as to
prevent operation
of the gate
ORANGE
Initiate 24-hour surveillance.
Immediately place stop logs in
front of gate and initiate nec-
essary actions to get gate re-
paired.
Crane and
welder
Type of
problem,
location
Ra
pid
ly
risi
ng
lak
e
Lake level rising and
rain continuing BLUE
Initiate 24-hour surveillance
of lake level and rainfall.
Generate inflow forecasts eve-
ry 12 hours.
Lake
level,
rainfall
Over
top
pin
g
Water flowing over
the dam and lake
continuing to rise. No
significant erosion of
downstream em-
bankment.
ORANGE
Prepare for evacuation. Con-
tinue monitoring.
Generate inflow forecasts eve-
ry 3 hours.
Dozer, fill
material,
sandbags,
filter
cloth,
rocks
Lake
level,
rainfa
Water flowing over
the dam, the lake
continuing to rise,
and significant ero-
sion of downstream
embankment with
development of head-
cuts encroaching on
the dam crest, or sig-
nificant movement of
sections of concrete
or masonry portions
of the dam.
RED
Immediate evacuation. Dam
failure is imminent or ongo-
ing.
Cameras. Status of
breach
for-
mation.
Width of
breach as
it enlarg-
es.
Project ID Code KA06HH0058.0 Page B-1
Tab 6
Supplies and Resources
The following equipment and supplies may be necessary for use during a dam emergency.
Contact information for local contractors who can provide
the following items during an emergency is listed below. For supplies owned by the dam owner, the
dam owner’s name and the specific location of the supplies have been denoted.
Equipment/Supplies Location Dam Owner Information
Backhoes Dump trucks
Portable welding equipment Generators Bulldozers Excavators
Loaders Motor graders
S.Narayanareddy Class-1 Contractor,
Channarayapatna, Hassan Dist.
Mob:- 9448350350
Manjunatha earth movers
Mobile Number: 9844120205
Executive Engineer, Cauvery Neeravari Nigam Limited Hemavathy Dam Division, Gorur.
Name: Gangadhar
Title: Executive Engineer
Mobile Number: 8618946407
Office Number:08172-256749
Name: Puttaswamy
Title: Asistatnt Engineer (PA to EE)
Mobile Number:9448734343
Office Number: 08172-256749
Crane S.Narayanareddy Class-1 Contractor,
Channarayapatna, Hassan Dist.
Mob:- 9448350350
Manjunatha earth movers
Mobile Number: 9844120205
Executive Engineer, Cauvery Neeravari Nigam Limited Hemavathy Dam Division, Gorur.
Name: Gangadhar
Title: Executive Engineer
Mobile Number: 8618946407
Office Number:08172-256749
Name: Puttaswamy
Title: Asistatnt Engineer (PA to EE)
Mobile Number:9448734343
Office Number: 08172-256749
Sandbags S.Narayanareddy Class-1 Contractor,
Channarayapatna, Hassan Dist.
Mob:- 9448350350
Sri Banashankari Traders, Tanniruhalla, Hassan.
Mob.9980310323
Executive Engineer, Cauvery Neeravari Nigam Limited Hemavathy Dam Division, Gorur.
Name: Gangadhar
Title: Executive Engineer
Mobile Number: 8618946407
Office Number:08172-256749
Name: Puttaswamy
Title: Asistatnt Engineer (PA to EE)
Mobile Number:9448734343
Office Number: 08172-256749
Rock riprap a) S.Narayanareddy Class-1 Contractor,
Executive Engineer, Cauvery Neeravari Nigam Limited
Project ID Code KA06HH00154 Page A-2
Channarayapatna, Hassan Dist. Mob:- 9448350350
b) Dananjaya
Class-1 Contractor,
Gorur.
Mob-9448742983
C) B.G.thimmegowda
Class-1 Contractor,
Basavanayakanahalli,
Holenarasipuratq,
Hassan dist. Mob :- 9945981020
Hemavathy Dam Division, Gorur.
Name: Gangadhar
Title: Executive Engineer
Mobile Number: 8618946407
Office Number:08172-256749
Name: Puttaswamy
Title: Asistatnt Engineer (PA to EE)
Mobile Number:9448734343
Office Number: 08172-256749
Fill Material a) S.Narayanareddy Class-1 Contractor,
Channarayapatna, Hassan Dist. Mob:- 9448350350
b) Dananjaya
Class-1 Contractor,
Gorur
Mob-9448742983
C) B.G.thimmegowda
Class-1 Contractor,
Basavanayakanahalli,
Holenarasipuratq,
Hassan dist. Mob :- 9945981020
Executive Engineer, Cauvery Neeravari Nigam Limited Hemavathy Dam Division, Gorur.
Name: Gangadhar
Title: Executive Engineer
Mobile Number: 8618946407
Office Number:08172-256749
Name: Puttaswamy
Title: Asistatnt Engineer (PA to EE)
Mobile Number:9448734343
Office Number: 08172-256749
Other: a) S.Narayanareddy Class-1 Contractor,
Channarayapatna, Hassan Dist. Mob:- 9448350350
Executive Engineer, Cauvery Neeravari Nigam Limited Hemavathy Dam Division, Gorur.
Name: Gangadhar
Title: Executive Engineer
Mobile Number: 8618946407
Office Number:08172-256749
Name: Puttaswamy
Title: Asistatnt Engineer (PA to EE)
Mobile Number:9448734343
Office Number: 08172-256749
Project ID Code KA06HH00154 Page A-3
Tab 7
Annual EAP Evaluation Checklist
Was the annual dam inspection con-
ducted?
□ Yes
□ No
If yes, has the EAP been revised
to include any signs of failures
observed during the inspection?
□ Yes
□ No
Was weed clearing, animal burrow
removal, or other maintenance re-
quired?
□ Yes
□ No
If yes, describe actions taken and date:
Was the outlet gate operable? □ Yes
□ No
If no, describe actions taken and date:
Does the Notification Flowcharts re-
quire revision?
(Note that revision of the contact in-
formation will not require EAP ap-
proval; however, the revised contact
information pages will need to be re-
distributed as replacement pages.)
□ Yes
□ No
If yes, list the dates of the contact information
revision and redistribution:
Was annual training or a tabletop drill
conducted?
□ Yes
□ No
Circle: training drill
Date conducted:
Are inspection and training records
included in the EAP?
□ Yes
□ No
Was the EAP reviewed? □ Yes
□ No
If yes, review date:
Were changes required to the EAP? □ Yes
□ No
If yes, date of revised EAP approval:
Chief Engineer
CNNL HPZ Gorur Date:
Project ID Code KA06HH00154 Page A-4
Tab 8
Plan Review and Update
This plan will be reviewed and updated annually and tabletop drills will be carried out at least once
every five years. Document these reviews below.
Date of review: Participants:
Date of review: Participants:
Date of review: Participants:
Date of review: Participants:
Date of tabletop drill: Participants:
Project ID Code KA06HH00154 Page A-5
Tab 9
Training Record
Use this form to record training sessions. File the completed form in the appropriate Tab of the EAP.
All items in the EAP should be thoroughly reviewed during training. Appropriate [Dam Owner] em-
ployees and EAP team members should attend a training session annually (or participate in a simulat-
ed drill).
TRAINING LOCATION:
DATE: TIME: INSTRUCTOR:
CLASS SIGN-IN:
Type of Simulation Conducted: Circle Emergency Type:
Emergency water release
Watch condition
Possible dam failure
Imminent dam failure
Actual dam failure
Comments, Results of Drill:
Revisions Needed to EAP Based on Results of Drill?
□ Yes □ No If yes, list revisions required:
Project ID Code KA06HH0058.0 Page B-6