EMCal StatusALICE Technical Board

November 20, 2008

NewsSchedule

Page 2: EMCal Status ALICE Technical Board November 20, 2008 News Schedule

EMCal Nomenclature

Module

Approximately projective in and

Strip Module = 12 Modules

Page 3: EMCal Status ALICE Technical Board November 20, 2008 News Schedule

ALICE - EMCal

Single Super Module

US Scope = 7 2/3 Super Modules

EU Scope = 3 Super Modules

Page 4: EMCal Status ALICE Technical Board November 20, 2008 News Schedule

Summary of EMCal SM #1&2 Installation (September, T. Awes)

January 30, 2009 -- Super Modules at Point-2

February 2 – 13, 2009 – Super Module Integrated System testing at CERN

February 16, 2009 -- Ready for Installation

We are still on this schedule.. (details in a few slides)

Page 5: EMCal Status ALICE Technical Board November 20, 2008 News Schedule

Since last update (Sep) : Overview• EMCAL TDR presented at LHCC meeting Sept. 23-24• DOE review at LBL (Berkeley) Oct. 16-17• StripModule production underway in US and EU. US SuperModule assembly/calibration operation moved from Yale to WSU (Detroit). • FEE components produced (FEC, T-card, IPCB, GTL,..)

Examples of past delays/issues – all dealt with.. :• Materials procurement for EU modules• SuperModule crate shipment to US• Counterfeit voltage reference for FEE card from electronics broker..• Issues with APD characteristics (worse gain)

Page 6: EMCal Status ALICE Technical Board November 20, 2008 News Schedule

Module Mass-Production in Progress

Page 7: EMCal Status ALICE Technical Board November 20, 2008 News Schedule

Strip-Module Mass-Production in Progress

Page 8: EMCal Status ALICE Technical Board November 20, 2008 News Schedule

PreAmp and APD

LED Calibration Fiber and APD T-Card

Strong Back

APD and PreAmp

Strip-Module Mass-Production in Progress

Page 9: EMCal Status ALICE Technical Board November 20, 2008 News Schedule

Strip-Module Mass-Production in Progress : US

18 of 20 produced (24 needed) ready for installation in SM#1 Crate

Cosmic Ray testing of StripModules in progress – final cosmic ray calibration awaits integration in SM Crate

Ready for SM Crate Delivery on Nov 19

Breaking news (~12 h ago):Delivered SM Crate has “visible damage”.Impact on schedule if the damage can be repaired locally: +2 days.If not (maximum impact; instead use US SM#2 crate - from Geneva Nov 22): +5 days

Page 10: EMCal Status ALICE Technical Board November 20, 2008 News Schedule

US SM#1 from Oct 17 to installation window

Page 11: EMCal Status ALICE Technical Board November 20, 2008 News Schedule

Modules - On Schedule

Strip ModulesOn Schedule

Super ModuleSlipping

shipping

Super ModuleSlipping – SMCrate Delay

Page 12: EMCal Status ALICE Technical Board November 20, 2008 News Schedule

SM Mechanical Assembly Start Delayed Nov 10 to Nov 19

Currently plan: Add assembly labor by stopping SM#2 module production hold Jan 23 CERN arrival date

Page 13: EMCal Status ALICE Technical Board November 20, 2008 News Schedule

EU Assembly Status• 5 Module assembling stations in full operation (2 LNF, 2 Catania, 1 Nantes) : 128 Modules assembled so far (44% of 1 SM) Rate 25 module/weekEnd of module assembly before Mid January

• WLS fiber station in operation at Frascati : 1100 produced so far (95 % of 1 SM)

• Gluing (Light Guide – APD) station in operation at Catania: 300/week. End of gluing in Mid December

• APD test station in Catania:Mission accomplished (100% of 1 SM)

• Strip Module assembly:Started this week in FrascatiRate = 1 Strip Module/Day when modules/parts are available

• SuperModule (SM) assembly:Insertion of Strip Modules in the SM Crate will start next week in GrenobleCosmic test bench ready to run

Page 14: EMCal Status ALICE Technical Board November 20, 2008 News Schedule

EU Part Delivery Status

Most of the parts for the EU SM have been delivered apart:• Last batch of Lead Tiles (80 modules) by end of November• Last batch of Straps (50 modules) in December• Last batch of Scintillators Tiles (110 modules) : produced but still on the difficult way from Russia• Strong Back (about a half) by end of November• Components for the SM crate : Cable fixation, Shims, LED box• Electronics : FEE crate and cards, LED system

For the installation: • Carriage assembly on the way for 1 SuperModule• Insertion tooling almost ready for use

APD/Module/Stripmodule/SM database in progress

Completion of EU SM still expected by end of January

Page 15: EMCal Status ALICE Technical Board November 20, 2008 News Schedule

EU Sample PicsModule assembled in Nantes

Strip Module assembled in Frascati

LG/APD gluing in CataniaCatania SM Crate in the Grenoble test station

Page 16: EMCal Status ALICE Technical Board November 20, 2008 News Schedule

ACCELERATED Schedule in terms of SM Installation Windows

No. of US Super

Modules Avail.

125

 

No. of EU Super

Modules Avail.

1

2*

 

Current anticipated installation schedule

* Requires final INFN funding approval in 2009

Date

2009

2010

2011

 

Page 17: EMCal Status ALICE Technical Board November 20, 2008 News Schedule

EMCal Electronics• EMCal readout infrastructure fully installed in L3 and on CalFrame

• Connections not quite complete• EMCal readout chain fully designed, prototyped, and tested @ CERN PS and SPS in 2007• APD + preamplifiers received for first 2 SM

• Assembly and Testing at Catania and Houston• EMCal PCBs and components:

• T-card, IPCB, GTL, FEE orders placed (Sept-Oct). All items received for first 2 SM, except FEC (under testing; enough for WSU in hand, for Grenoble expected tomorrow), and GTL (expected tomorrow).

• Trigger: TRU and STU prototypes – ongoing work • LED System: Final design being completed

• Prototype available initially for SM assembly sites.• EMCal FEE crate design complete, first two shipped to US, two more (for Grenoble) in production.• Expect to have full FEE crate readout of first 2 SMs ready and operational at SM assembly sites by late November/early December. - Need two more RCUs for Grenoble..

Page 18: EMCal Status ALICE Technical Board November 20, 2008 News Schedule

H.Muller CERN PH –AID-DT

New board layout , New Virtex-5 technology , new ADC 60 MHz 12 bit, reduced powerless noise

New VIRTEX-5 EMCal TRU

Page 19: EMCal Status ALICE Technical Board November 20, 2008 News Schedule

DCS interface

TTCRq

V0 interface

DDL interface

L0 in

4 T

RU

inpu

ts

32 TRU inputs

4 T

RU

inpu

ts

Trig

ger

outp

uts

Summary Trigger Unit

Page 20: EMCal Status ALICE Technical Board November 20, 2008 News Schedule

TRU and STU

• Prototypes exist• Trigger meeting ongoing today• Intense TRU development period (Hans M., Dong W.,

Jo S., Norbert N.,..) • STU development (Olivier B.), incl. communications

with TRU; following ALICE standards (help from Anton J., Pierre VV. appreciated)

Page 21: EMCal Status ALICE Technical Board November 20, 2008 News Schedule

Summary• Module assembly well underway at WSU and in EU.

• Readout Electronics deliveries soon complete.

• LED Calibration system being finalized.

• TRU+STU prototypes completed and being tested.

• Facilities and infrastructure upgrades at SM assembly sites completed, FEE readout+DAQ operating.

• Insertion tooling is ready and tested.

• Production meeting at WSU/Detroit, Dec 1-2

Schedule is tight..

Page 22: EMCal Status ALICE Technical Board November 20, 2008 News Schedule

Extra

Page 23: EMCal Status ALICE Technical Board November 20, 2008 News Schedule

APD+Preamplifier Assembly & Test

• Assembly and test procedure – Assign serial numbers– Measure gain vs bias, temperature dependence– Record in database– Sort according to performance– Attach Light-guide and housing

• Results of measurements of first 500+ APDs @Catania:

V(Gain=30)Catania

V(Gain=50)Hamamatsu

Significantly more APDs with V30>400 V than expected in later batches.. Problem for equalizing at desired gain.

Page 24: EMCal Status ALICE Technical Board November 20, 2008 News Schedule

EMCal Production ScheduleSuper

Module Number

Strip Module

Assembly Complete

US Strip Module at Grenoble

Super Module at Cern (Accel)

1 10/22/08   2/10/09

2 5/26/09   6/11/09

3 9/29/09 11/10/09 10/2/09

4 2/23/10   2/2/10

5 5/18/10 6/30/10 5/17/10

6 8/19/10   8/11/10

7 11/19/10   10/21/10

8 5/4/11 4/15/11 2/18/11

ALICE Installation

Window

No. of Super Modules

Avail. (Accel)

Winter 2009 1+1

Winter 2010 3+1

Winter 2011 4+1

Winter 2012  

Page 25: EMCal Status ALICE Technical Board November 20, 2008 News Schedule