embodied carbon in construction march 2010

Upload: piugabi

Post on 03-Apr-2018

215 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/28/2019 Embodied Carbon in Construction March 2010

    1/81

    whitbybird

    EMBODIED CARBON INCONSTRUCTION

  • 7/28/2019 Embodied Carbon in Construction March 2010

    2/81

    global and local

    over 8,000 employees

    200 offices

    20 countries

    11 offices in the UK and Ireland

    Ramboll is a leading engineering, design and consultancy company at the forefront of

    innovation. From across 200 offices we apply our engineering skills and passion to a wide

    range of projects in the UK and around the world.

    LOCATIONS

  • 7/28/2019 Embodied Carbon in Construction March 2010

    3/81

    Start at the end

    operational CO2 vs embodied CO2

    Schools operational CO2 emissions

    CIBSE Guide F 31 kgCO2/m2/yr

    CIBSE TM46 45 kgCO2/m2/yr

    Part L 2006 25 kgCO2/m2/yr

    Schools embodied CO2

    New build 500 kgCO2/m2

    year 1

    OperationalCO2

    Embodied

    CO2

    year 10

    OperationalCO2

    Embodied

    CO2

    year 20

    OperationalCO2

    Embodied

    CO2

  • 7/28/2019 Embodied Carbon in Construction March 2010

    4/81

    How does embodied CO2 compare?

    as our buildings become more energy efficient

  • 7/28/2019 Embodied Carbon in Construction March 2010

    5/81

    Embodied carbon

    in the press

  • 7/28/2019 Embodied Carbon in Construction March 2010

    6/81

    Phase change materialsCement

    replacement

    Thermal mass

    Lime mortar

    15% construction waste

    Unfired/compressed earth bricks

    Carbon negative timber

    Magnesium oxide cement Post tensioned concrete

    Bubbledeck concrete

    Lean engineeringRammed earth

    Modern methods of

    construction

    Cement production 5% of

    global CO2 emissions

    Construction 10% of

    UK CO2 emissions

    Definition of Embodied Energy/CO2

    and some initial thoughts

    Energy/CO2 required to extract, process, fabricate, transport and erectmaterials on site

    Hemp lime construction

    Re-cycle and re-use

    Adaptable buildings

  • 7/28/2019 Embodied Carbon in Construction March 2010

    7/81

    So how much material do we use?

    in construction

    Concrete

    23,5m tonnes of ready mixed concrete in 2007

    0,3m tonnes of rebar in 2007

    Steel

    1,4m tonnes of constructional steelwork produced in the UK in 2007

    Brick/Block

    38m of clay bricks used and produced in the UK in 2007 99m of concrete blocks/bricks used and produced in the UK in 2007

    Timber

    10,5m m3 of sawn wood used in the UK in 2006

    6,7m m3 of wood based panels used in the UK in 2006

    Summary

    400m tonnes of construction material used annually

    90m tonnes of construction waste annually (of which approximately

    50% is re-cycle as aggregate)

  • 7/28/2019 Embodied Carbon in Construction March 2010

    8/81

    How does embodied CO2 compare?

    office buildings

    Statistics

    32,500m2 NIA or GIA?

    Embodied 765 kgCO2/m2

    Operation 60 90 kgCO2/m2

  • 7/28/2019 Embodied Carbon in Construction March 2010

    9/81

    How does embodied CO2 compare?

    residential buildings

    Statistics

    3 bed house 20 40 tCO2

    Embodied 300 675 kgCO2/m2

    Operation 30 50 kgCO2/m2 ?

  • 7/28/2019 Embodied Carbon in Construction March 2010

    10/81

    How does embodied CO2 compare?

    school buildings

    Statistics

    2 different structure solutions

    Embodied 300 600 kgCO2/m2

    Operation 25 - 35 kgCO2/m2

    -

    0.100

    0.200

    0.300

    0.400

    0.500

    0.600

    0.700

    U-beam school Deltabeam school

    tCO2e/m2

    End of Life

    Maintenance

    Onsite Activities

    Delivery

    Raw Materials

    -10%

    0.579

    0.523

    0%

    10%

    20%

    30%

    40%

    50%

    60%

    70%

    80%

    90%

    100%

    U-beam school Deltabeam school

    tCO 2e/m2

    End of Life

    Maintenance

    Onsite Activities

    Delivery

    Raw Materials

    66% 65%

    4%3%

    14% 13%

    14%13%

    5%5%

    2.070 2.003

    0.5790.523

    -

    0.500

    1.000

    1.500

    2.000

    2.500

    3.000

    U -b eam sch ool De lt ab eam schoo l

    tCO2e/m 2

    Embodied

    Operational

    -5%2.648

    2.527

    78.2% 79.3%

    21.8% 20.7%

    0%

    10%

    20%

    30%

    40%

    50%

    60%

    70%

    80%

    90%

    100%

    U -b eam schoo l De lt abeam sch ool

    tC O2e/ m2

    Embodied

    Operational

  • 7/28/2019 Embodied Carbon in Construction March 2010

    11/81

    How does embodied CO2 compare?

    school buildings

    Steel industry research

    22.5m 10,000m2

    Embodied 300 350 kgCO2/m2

    Operation 27 kgCO2/m2

    Structure 10% cost, 60% CO2

  • 7/28/2019 Embodied Carbon in Construction March 2010

    12/81

    How does embodied CO2 compare?

    Ramboll and UoC study

    Peterborough School

    975m2 Sportshall and Studio

    Timber LCA -40tCO2

    Steel LCA 220tCO2

    Embodied CO2 of structure only

  • 7/28/2019 Embodied Carbon in Construction March 2010

    13/81

    Drivers

    lots to read

  • 7/28/2019 Embodied Carbon in Construction March 2010

    14/81

    The Government Departments

    all in on the act

    www.decc.gov.uk

    Department for Energy and Climate Change

    The UK Low Carbon Transition Plan July 2009

    www.communities.gov.uk/planningandbuilding/theenvironment

    Communities and Local Government

    Building a Greener Future July 2007

    Code for Sustainable Homes Consultations on definition of zero carbon

    EPCs and DECs

    www.zerocarbonhub.org

    www.berr.gov.uk/whatwedo/sectors/construction

    Department for Business, Innovation and Skills

    Strategy for Sustainable Construction June 2008

    Construction Innovation and Growth Team

  • 7/28/2019 Embodied Carbon in Construction March 2010

    15/81

    Zero carbon timetable

    is it possible?

    2016

    All new homes

    2018 All new public sector buildings

    2019

    All new buildings

  • 7/28/2019 Embodied Carbon in Construction March 2010

    16/81

    Embodied CO2 and policy / regulation

    what is coming?

  • 7/28/2019 Embodied Carbon in Construction March 2010

    17/81

  • 7/28/2019 Embodied Carbon in Construction March 2010

    18/81

    Recent studies on embodied CO2

    ODA

  • 7/28/2019 Embodied Carbon in Construction March 2010

    19/81

    Telford Homes / Waugh Thistleton Architects

    Solid timber construction, 180tCO2 stored

    29 apartments, operational CO2 29kgCO2/m2

    10% renewables obligation waived by Hackney

    Embodied CO2 off settings renewables

    Stadthaus, Hackney

  • 7/28/2019 Embodied Carbon in Construction March 2010

    20/81

    More action

    more to read

  • 7/28/2019 Embodied Carbon in Construction March 2010

    21/81

    BREEAM, CfSH and BRE

    status of materials

  • 7/28/2019 Embodied Carbon in Construction March 2010

    22/81

    BRE GREEN GUIDE TO SPECIFICATIONstatus of materials

    Embodied CO2 figures given

    Floors -18 to 150 kgCO2/m2

    Roofs -4 to 290 kgCO2/m2

    External walls -3 to 370 kgCO2/m2

  • 7/28/2019 Embodied Carbon in Construction March 2010

    23/81

    Strategic Forum for Constructionaspirations

  • 7/28/2019 Embodied Carbon in Construction March 2010

    24/81

    Calculate your own embodied CO2what is out there?

    Industry claims

    Steel (SCI) 762 kgCO2/t

    RC (Concrete Centre) 115 kgCO2/t

    Timber (Wood for Good) -900 kgCO2/t

  • 7/28/2019 Embodied Carbon in Construction March 2010

    25/81

    Calculate your own embodied CO2what is out there?

    Edinburgh Centre for CarbonManagement

    Steel 2300 kgCO2/t

    RC 250 kgCO2/t

    Timber -1000 kgCO2/t

    Bath University ICE Steel 1440 kgCO2/t

    RC 210 kgCO2/t

    Timber 390 kgCO2/t

  • 7/28/2019 Embodied Carbon in Construction March 2010

    26/81

    -800kg

    CO2

    +275kg

    CO2

    +800kg

    CO2

    2500KWhr

    1m3

    +275kg

    CO2

    +300kgCO2

    +700kgCO2

    2500KWhr

    1m3

    +1000kgCO2

    Sequestered CO2 and TimberTimber and concrete 1m3 analysis

  • 7/28/2019 Embodied Carbon in Construction March 2010

    27/81

    Combating Climate Changea role for UK forests

    UK Forestry Commission report

    UK Woodland could provide 10% GHG abatement.

    Scottish forests remove 12% of CO2 emissions.

    UK forest carbon sink reducing from 16mtCO2 in

    2004 to 5mtCO2 in 2020.

    Wood fuel potential to save 7mtCO2 in UK.

    Estimated 70mtCO2 stored in timber housing in UK.

    Stern review and UK Low carbon transition plan

    recognise woodland creation as cost effective.

  • 7/28/2019 Embodied Carbon in Construction March 2010

    28/81

    Embodied CO2related to structural performance

    But..60kgCO2 stored in timber beam

    Timber beam 15kgCO2

    Concrete beam 50kgCO2

    Steel beam 60kgCO2

  • 7/28/2019 Embodied Carbon in Construction March 2010

    29/81

  • 7/28/2019 Embodied Carbon in Construction March 2010

    30/81

    In summarywhere are we with embodied CO2?

    DIY

    Using Bath University ICE

    BRE Green Guide to Specification Link to BREEAM

    Specialist consultants

    Dcarbon8, ECCM, Davis Langdon etc.

    but no embodied CO2 regulation at present or in foreseeable future

  • 7/28/2019 Embodied Carbon in Construction March 2010

    31/81

    Reducing embodied carbonand advice and case studies

  • 7/28/2019 Embodied Carbon in Construction March 2010

    32/81

    Reducing embodied carbonwhere to concentrate

    Structure

    50%-60%

  • 7/28/2019 Embodied Carbon in Construction March 2010

    33/81

    Reducing embodied carbonin building structures

    Lean design

    Re-cycled materials

    Renewable materials

    Minimise waste

    Design for long life

    Holistic design

  • 7/28/2019 Embodied Carbon in Construction March 2010

    34/81

    Reducing embodied carbonin building structures

    Lean design

    Re-cycled materials

    Renewable materials

    Minimise waste

    Design for long life

    Holistic design

  • 7/28/2019 Embodied Carbon in Construction March 2010

    35/81

    MOSSBOURNE ACADEMY

    Exposed timber frame

    22.5m new build secondary school

    960m3 timber, 800t CO2 stored

    Equivalent to 10% renewables for 20 years?

  • 7/28/2019 Embodied Carbon in Construction March 2010

    36/81

  • 7/28/2019 Embodied Carbon in Construction March 2010

    37/81

  • 7/28/2019 Embodied Carbon in Construction March 2010

    38/81

  • 7/28/2019 Embodied Carbon in Construction March 2010

    39/81

  • 7/28/2019 Embodied Carbon in Construction March 2010

    40/81

  • 7/28/2019 Embodied Carbon in Construction March 2010

    41/81

  • 7/28/2019 Embodied Carbon in Construction March 2010

    42/81

  • 7/28/2019 Embodied Carbon in Construction March 2010

    43/81

    RESEARCH AND DEVELOPMENT

  • 7/28/2019 Embodied Carbon in Construction March 2010

    44/81

    RESEARCH AND DEVELOPMENT

    Timber concrete composite floors

    Direct competition to steel frame?

    3x stiffer and 2x stronger

    UNIVERSITY OF CAMBRIDGE

  • 7/28/2019 Embodied Carbon in Construction March 2010

    45/81

    UNIVERSITY OF CAMBRIDGE

    Exposed timber frame

    10m new build faculty of education

    240m3 timber, 200t CO2 stored

    Equivalent to 6% renewables for 20 years?

  • 7/28/2019 Embodied Carbon in Construction March 2010

    46/81

  • 7/28/2019 Embodied Carbon in Construction March 2010

    47/81

  • 7/28/2019 Embodied Carbon in Construction March 2010

    48/81

  • 7/28/2019 Embodied Carbon in Construction March 2010

    49/81

    Reducing embodied carbon

  • 7/28/2019 Embodied Carbon in Construction March 2010

    50/81

    Reducing embodied carbonin building structures

    Lean design

    Re-cycled materials

    Renewable materials

    Minimise waste

    Design for long life

    Holistic design

    CAMBRIDGE UNIVERSITY

  • 7/28/2019 Embodied Carbon in Construction March 2010

    51/81

    CAMBRIDGE UNIVERSITY

    Physics for Medicine

    Exposed concrete frame teaching and labs

    Low Carbon concrete mix

    Equivalent to 3% renewables over 20 years?

    Reducing embodied carbon

  • 7/28/2019 Embodied Carbon in Construction March 2010

    52/81

    gin building structures

    Lean design

    Re-cycled materials

    Renewable materials

    Minimise waste

    Design for long life

    Holistic design

    NORWICH ACADEMY

  • 7/28/2019 Embodied Carbon in Construction March 2010

    53/81

    UKs largest timber frame

    22m new build secondary school

    3500m3 timber, 2900t CO2 stored

    Equivalent to 30% renewables for 20 years?

  • 7/28/2019 Embodied Carbon in Construction March 2010

    54/81

  • 7/28/2019 Embodied Carbon in Construction March 2010

    55/81

    NORWICH ACADEMY

  • 7/28/2019 Embodied Carbon in Construction March 2010

    56/81

  • 7/28/2019 Embodied Carbon in Construction March 2010

    57/81

  • 7/28/2019 Embodied Carbon in Construction March 2010

    58/81

  • 7/28/2019 Embodied Carbon in Construction March 2010

    59/81

    ST JOHN FISHER SCHOOL

  • 7/28/2019 Embodied Carbon in Construction March 2010

    60/81

    Solid timber panel construction

    11m extension and refurbishment

    1000m3 timber, 800t CO2 stored

    Equivalent to 30% renewables for 20 years?

  • 7/28/2019 Embodied Carbon in Construction March 2010

    61/81

  • 7/28/2019 Embodied Carbon in Construction March 2010

    62/81

  • 7/28/2019 Embodied Carbon in Construction March 2010

    63/81

  • 7/28/2019 Embodied Carbon in Construction March 2010

    64/81

  • 7/28/2019 Embodied Carbon in Construction March 2010

    65/81

  • 7/28/2019 Embodied Carbon in Construction March 2010

    66/81

    Reducing embodied carbonin building structures

  • 7/28/2019 Embodied Carbon in Construction March 2010

    67/81

    in building structures

    Lean design

    Re-cycled materials

    Renewable materials

    Minimise waste

    Design for long life

    Holistic design

    SHEFFIELD UNIVERSITY

  • 7/28/2019 Embodied Carbon in Construction March 2010

    68/81

    Hybrid concrete system

    17m new build LRC using bubbledeck

    110,000 balls 550m3 of RC saved or 175t CO2

    Equivalent to 2% renewables for 20 years?

  • 7/28/2019 Embodied Carbon in Construction March 2010

    69/81

  • 7/28/2019 Embodied Carbon in Construction March 2010

    70/81

  • 7/28/2019 Embodied Carbon in Construction March 2010

    71/81

    Reducing embodied carbonin building structures

  • 7/28/2019 Embodied Carbon in Construction March 2010

    72/81

    g

    Lean design

    Re-cycled materials

    Renewable materials Minimise waste

    Design for long life

    Holistic design

    1 SOUTHAMPTON ROW

  • 7/28/2019 Embodied Carbon in Construction March 2010

    73/81

    Innovative cassette raft

    1500m3 concrete saved, 550tCO2

    Long span steel structure 600t steel premium

    Concrete 550tCO2 saving, steel 1150tCO2 gain

  • 7/28/2019 Embodied Carbon in Construction March 2010

    74/81

    Reducing embodied carbonin building structures

  • 7/28/2019 Embodied Carbon in Construction March 2010

    75/81

    Lean design

    Re-cycled materials

    Renewable materials Minimise waste

    Design for long life

    Holistic design

    BGS, NOTTINGHAM

  • 7/28/2019 Embodied Carbon in Construction March 2010

    76/81

    UKs first timber termodeck building

    5m new build offices

    450m3 timber, 365t CO2 stored

    Equivalent to 7% renewables for 20 years?

  • 7/28/2019 Embodied Carbon in Construction March 2010

    77/81

  • 7/28/2019 Embodied Carbon in Construction March 2010

    78/81

    Reducing embodied carbonin building structures

  • 7/28/2019 Embodied Carbon in Construction March 2010

    79/81

    Lean design

    Post tension concrete

    Suitable floor spans

    Re-cycled materials Cement replacement

    Renewable materials

    Timber structures

    Minimise waste Prefabrication

    Design for long life

    Low maintenance, adaptable

    Reduction in concrete and rebar

    Approx 23% saving in ECO2

    Approx 33 kgCO2/m2

    Reduction is steel content

    Approx 28% saving in ECO2

    Approx 62 kgCO2/m2

    Reduction in cement content

    Approx 22% saving in ECO2

    Approx 46 kgCO2/m2

    Carbon negative?

    Approx 32% (205)saving in ECO2

    Approx 52 (335) kgCO2/m2

  • 7/28/2019 Embodied Carbon in Construction March 2010

    80/81

  • 7/28/2019 Embodied Carbon in Construction March 2010

    81/81