electrical audit

Upload: sushil-kumar

Post on 21-Feb-2018

236 views

Category:

Documents


4 download

TRANSCRIPT

  • 7/24/2019 electrical audit

    1/55

    MUMBAI

    ELECTRICAL AUDIT REPORT

    INDIAN OIL BHAVAN (H.O.)

    MUMBAI

    Date of Visit :

    Page 1 of 55

    CONTENTS

    DESCRIPTION PAGE NO.

    1.List of major Electrical Equipments & Electrical System

    2.Executive Summary

    3.ypical Eart! Electro"e

    4.#$servation & %ecommen"ation

    i' 11 (V V)*

    ii' ransformer

    iii' D+ sets

    iv' ,ain Distri$ution *oar"

    v' )apacitor Panel

    vi' Lig!ting System

    vii' Lig!ting Pole & +lo$e

    viii' -) Plant & -./

    ix' Pump .ouse

    x' S Plants

    xi' Lifts

    xii' Eart!ing

    xiii' Lig!tning Protection

    xiv' )anteen -rea

    xv' 0ee"er Pillar Panel ear ,ain +ate'

    Page 1 of 55

  • 7/24/2019 electrical audit

    2/55

    MUMBAI

    ELECTRICAL AUDIT REPORT

    INDIAN OIL BHAVAN (H.O.)

    MUMBAI

    Date of Visit :

    Page 2 of 55

    LIST OF MAJOR ELECTRICAL EQUIPMENTS &

    ELECTRICAL SYSTEM

    Page 2 of 55

  • 7/24/2019 electrical audit

    3/55

    MUMBAI

    ELECTRICAL AUDIT REPORT

    INDIAN OIL BHAVAN (H.O.)

    MUMBAI

    Date of Visit :

    Page 3 of 55

    LIST OF MAJOR ELECTRICAL EQUIPMENTS INSTALLED IN THE BUILDING

    A: SUBSTATION EQUIPMENT

    A.1 11 KV VACCUM CIRCUIT BREAKER.

    The building receives power supply from Reliance at 11KV, through 800

    Amp. HT(11KV) Breaker of Siemens make, which under Reliance control.

    The supply from Breaker is fed to Bus Bars which connected to 2 Nos. 1000

    KVA 11 KV/433V Transformer of Kirlosker make

    A.2 The outgoing from the VCB are connected to 2 Nos. 1000 KVA 11KV/433V

    Transformer designated as:-

    Transformer-1:- Flood Load, Canteen, Domestic Pumps, Lift No.1 & 2.

    IT Centre, Air Conditioning Unit, Capacitor Bank 1.

    Transformer-2:- Small Wing, STP, Large Wing, Lift No.4, 5 & 6, UPS

    room, Capacitor Bank 2.

    A.3 Transformer-1 & 2 :- L.T. Side i.e. 433 Volts are supplying to Main

    Distribution Board.

    Transformer-1 is connected to Main Distribution Board through 6 nos.

    3.5X300 sq.mm Al. PVC Cable to MDB & 1600 Amp. ACB.

    Transformer -2 is connected through 6 nos. of 3.5CX300 sq.mm Al. PVC

    Cable to MDB & 1600 Amp ACB.

    A.4 Main Distribution Boardis having two incomers from transformer 1&2 and

    one number incomer from 500 KVA DG set.

    Page 3 of 55

  • 7/24/2019 electrical audit

    4/55

    MUMBAI

    ELECTRICAL AUDIT REPORT

    INDIAN OIL BHAVAN (H.O.)

    MUMBAI

    Date of Visit :

    Page 4 of 55

    There are Two nos. of Bus coupler (1600 Amp. ACB) one is provided for two

    incomers & one for DG set.

    Section 1 of MDB is supplying power to Lift No.4, 5 &6 through 100 Amp TPN

    switch, also providing power supply to Large, Small Wing & Capacitor Panel-

    2 through 630 AMP, switch. 1000Amp. ACB and also to UPS changer over

    through 400 Amp TPN switch.

    Section 2 of MDB is supplying power to Lift No.1,2 & Freight lift through 100

    Amp TPN switch, also providing power supply to 2ndfloor Micro AC & Air

    Condition unit through 1000Amp TPN switch. Power supply to Canteen,

    Domestic pump, IT Centre 2ndfloor & workshop is feed through 250Amp

    switch. Power supply to Pantry Lift & Flood light through 63 Amp TPN

    switch.

    Section 3 of MDB is supplying power to Fire pump panel through 400 Amp

    TPN switch, also providing power supply to Lift No.3, Building Light, Main

    Gate LDB & Substation Light through 100 Amp TPN switch. Air conditioning

    unit through 1000Amp TPN switch.

    B. D.G. Set:-

    Page 4 of 55

  • 7/24/2019 electrical audit

    5/55

    MUMBAI

    ELECTRICAL AUDIT REPORT

    INDIAN OIL BHAVAN (H.O.)

    MUMBAI

    Date of Visit :

    Page 5 of 55

    B.1 DG Set-1

    Rating : 500KVA

    Make : (Alternator- Stamford)

    (Engine - Cummins)

    Supplies power to Whole office Building

    Cable Size 2 run of 3.5X300 Sq.mm

    B.2 Generator Control Panel:-

    Supplies power from DG (500KVA) connected to DG Generator Control Panel

    installed in the DG Room. Breakers (ACB) are interlocked with 500 KVA DG

    set & a Bus coupler for DG set of ACB 1600A in Main Distribution Board.

    C Air Conditioning Units

    Capacity 800 Ton/hr

    There are two Nos. MCC in the A/C Plant. i.e. MCC-1 & MCC-2 for Main

    AC Unit.

    MCC-1 receives power from MDB Section-II, supplies power & control to

    Chiller Unit 1& 2 and also to AHU Units in different floors.

    MCC-2 receives power from MDB Section-I, supplies power & control to

    Chiller Unit 3 & 4 and also to AHU Units in different floors.

    D. Lightning & Power Supply to Sockets

    D1. There are two Nos. Rising main (Bus Duct) one on Large Wing side and the

    Page 5 of 55

  • 7/24/2019 electrical audit

    6/55

    MUMBAI

    ELECTRICAL AUDIT REPORT

    INDIAN OIL BHAVAN (H.O.)

    MUMBAI

    Date of Visit :

    Page of 55

    other on the Small Wing side.

    Large Wing rising main receives power from Main Distribution Feeder No. B2

    through 630 Amp. MCCB.

    Small Wing rising main receives power from Main Distribution Feeder No. A3

    through 630 Amp. MCCB.

    D2. Lightning for the Floor:-

    At each floor (total 9 Nos.) rising main both Large(North) & Small(South) Wing

    are tapped through 125 Amp. L&T make TPN switch.

    The TPN Switch is mounted on the outer surface of the Bus duct i.e. rising

    main & connected to the Bus Bars by 4CX10 sq.mm cables at the back of

    the switch. The outgoing from the switch are taken in MCB DB. There is one

    63 Amp, 4pole TPN MCB,

    Each phase of the Bus Bars is connected trough 40/25 A RCCB. The

    Outgoing is through LDB-1 & LDB-2, In LDB-1 & 2 the incoming is through

    40 Amp, 4pole TPN MCB & outgoing is distributed in each phase, through

    10A, 20A & 32 A Single pole MCB. The outgoing from single pole switch fuse

    unit is connected to:-

    a). MCB Distribution Box for light.

    b). MCB Distribution Box for power supply to sockets.

    Page of 55

  • 7/24/2019 electrical audit

    7/55

    MUMBAI

    ELECTRICAL AUDIT REPORT

    INDIAN OIL BHAVAN (H.O.)

    MUMBAI

    Date of Visit :

    Page 6 of 55

    In Each Floor there are LDB-1, LDB-2, & One Emergency DB. Each floor has

    different numbers of MCB distribution board.

    E. Earthing

    There are 36 Nos. of Earth Pit on the office premises.

    F. Lightning Protection

    There are 8 Nos. Air Terminal Rods Connected with 25X3 GI strips laid along

    the parapet walls. On the roof 3 Nos. down conductor have been taken from

    the roof G.I. Strips to the Earth Pits.

    Page 6 of 55

  • 7/24/2019 electrical audit

    8/55

    MUMBAI

    ELECTRICAL AUDIT REPORT

    INDIAN OIL BHAVAN (H.O.)

    MUMBAI

    Date of Visit :

    Page 7 of 55

    EXECUTIVE SUMMARY

    EXECUTIVE SUMMARY

    ELECTRIFICATION OF HI-RISE BUILDING

    An important consideration in the layout of electrical in any building or

    installation is safety, besides the consideration for efficiency, convenience and

    provision for future increase in load.

    The fundamental requirement to achieve safety from the electrical equipment

    Page 7 of 55

  • 7/24/2019 electrical audit

    9/55

    MUMBAI

    ELECTRICAL AUDIT REPORT

    INDIAN OIL BHAVAN (H.O.)

    MUMBAI

    Date of Visit :

    Page 8 of 55

    and associated cabling and wiring is to control the occurrence of short circuit or

    fault currents in the system which results in flash-overs, burning of cable

    insulation, and insulating materials of the component.

    It is understood that in the electrification of HI-Rise Bldg. there would be

    complexity of equipment and network of cables of various sizes right upto a

    lowest size 1.5 sq.mm concealed behind the laminated walls and false ceiling

    which are always prone to fire. What is therefore required is to prevent theoccurrence of any short-circuit in the system and if it does occur the same is

    cleared from the circuit or system, by the protection like fuses & relays before

    the wiring cables and other equipment attain a temperature which ignites the

    cable insulation and other materials. For example a 1.5 sq.mm PVC insulated

    copper cable can withstand only about 100 Amp. For 1 sec. before the

    insulation starts melting and catches fire. The protection in the circuit,

    therefore, has to be provided thr HRC fuses so that it disconnects the circuit

    in less time say 100 to 200 msec .i.e. before the cable insulation melts &

    catches fire.

    To prevent the hazards of fire from the faults in electrical equipments it is,

    therefore, imperative that the entire electrical system and installation

    conforms to the following:

    a). Every equipment used should be able to withstand the fault current of the

    system; and where it is not so due to non-availability of the particular

    rated equipment it must be protected thr HRC fuses, so that it cuts off the

    circuit in the shortest possible time.

    Page 8 of 55

  • 7/24/2019 electrical audit

    10/55

    MUMBAI

    ELECTRICAL AUDIT REPORT

    INDIAN OIL BHAVAN (H.O.)

    MUMBAI

    Date of Visit :

    Page 19 of 55

    Use of rewire able fuses in the HI-Rise Building should be totally avoided.

    Only proper rated MCCB & HRC fuses to be used for the protection of

    cables & equipment.

    b). The loose connections to be totally avoided. All the cable terminations to be

    done with proper size and type of tinned copper lugs and hardwares like

    bolts, nuts, washers etc.

    c). The connections to be periodically checked for tightness for which it is

    imperative that enclosure used are of such size that when they are opened,

    the terminals are readily accessible. Furthermore sufficient space shall be

    left in the interior of the enclosure for the accommodation of external

    conductor from the point of entry into the enclosures upto the

    terminals(IS:4237-1967)

    d). The enclosures should always be kept free from the ingress of dust, cobwebs

    etc. since it leads to tracking & subsequent flash-overs. It is necessary that

    after the cabling is done, all the unused holes & openings are plugged &

    sealed. The equipments which are mounted outdoor shall conform to

    degree of protection IP-55 and as far as possible the junction boxes

    installed outdoor shall be made of aluminum or any non-corrosive

    material.

    e). The equipment used should be of proven quality & make. In the vulnerable

    Page 19 of 55

  • 7/24/2019 electrical audit

    11/55

    MUMBAI

    ELECTRICAL AUDIT REPORT

    INDIAN OIL BHAVAN (H.O.)

    MUMBAI

    Date of Visit :

    Page 11 of 55

    areas, cables with elastomeric insulation i.e. EPR, silicon, CSP etc. to be

    used. Such type of cables are used in railways coaches, ships etc. and do

    not catch or propagate fire(Reference IOC Engg. Manual Vol-7 Part II

    Chapter No.14).

    f).Earthing System & Practices:-

    A sound earthing system eliminates more than half of the unsafe

    conditions and prevents unwanted fires. For the discharge of fault

    currents, static electricity and for the operation of protective relays and

    fuses, there is no short cut than to have an exacting, robust and proper

    earthing system.

    An Electrical Audit is a Safety Concept.It identifies the erroneous zones

    (in the entire electrical installation, i.e. equipment & the system) which

    may have crept into the system inadvertently during selection, erection or

    subsequent to energizing/commissioning. Recommendations are made

    after analyzing the deficiencies and update the electrical in its entirety.

    An attempt has been made in this audit to study in detail the deficiencies

    in the system, equipment, cable terminations, earthing system etc.

    Recommendation to eliminate & eradicate the deficiencies are also given

    which when implemented shall achieve the objective of eliminating flash-

    overs and fire hazards from the electrical system.

    Page 11 of 55

  • 7/24/2019 electrical audit

    12/55

    MUMBAI

    ELECTRICAL AUDIT REPORT

    INDIAN OIL BHAVAN (H.O.)

    MUMBAI

    Date of Visit :

    Page 12 of 55

    SUMMARY

    Sl. Equipment Action Priority CategoryNo.

    1. 11 KV Breaer i! Ammeter to "e c#ange $or %r&'. (

    ii! Ru""er mat to "e pro)i*e* (

    iii! Ca"le +i,e+ to "e mare* ((

    '. %ran+$ormer+ i! Replace -%( $or %R&1 ( ii! Silica el to "e replace* (

    iii! Ca"le "o/e+ to "e eart#e* (

    i)! S#e* to "e pro)i*e* o)er ((

    %ran+$ormer

    )! Replace "ot# %ran+$ormer ((

    0. Set+2 i! Routine Maintenance

    enerator Panel ii! Replace 3it# Panel ((

    4. MB 5Main i! Recti$y2Replace Un*er )oltage (

    i+tri"ution Boar*! Relay $or

    ii! Cali"rate t#e protection relay6 ((

    ACB+ etc. yearly

    iii! Routine Maintenance

    i)! Ca"le trenc# to "e e/ten*e* ((

    in *imen+ion

    Sl. Equipment Action Priority CategoryNo.

    7. Capacitor 8 Control i! Replace lig#t o$ $ee*er No&9o$ ((

    Panel panel&'

    ii! :ig#er Rating Contactor o$ (

    ;ee*er No&< o$ panel&1

    =. >ig#tning Sy+tem i! Nomenclature to >B 8 ?utgoing (( MCB to "e gi)en a+ per @oor 8

    Page 12 of 55

  • 7/24/2019 electrical audit

    13/55

    MUMBAI

    ELECTRICAL AUDIT REPORT

    INDIAN OIL BHAVAN (H.O.)

    MUMBAI

    Date of Visit :

    Page 13 of 55

    3ing+ 3i+e.

    ii! Ru""er Mat to "e place* (

    ig#tning Pole+ i! ;aulte* Ca"le+ to "e replace* (

    ii! Corro*e*2 Ru+te* Pole+ 8 B+ ((

    to "e replace*.

    iii! Eart#ing to "e connecte* (

    i)! Stran*e* ca"le to terminate* ((

    3it# tinne* copper lug+ o$

    +uita"le type

    )! Ca+t aluminum (P&77 B to ((

    "e pro)i*e* $or eac# pole 8

    lo"e lig#t

    Sl. Equipment Action Priority CategoryNo.

    . AC Plant i! et ;an B to "e eart#e* (

    ii! Routine Maintenance

    iii! All "reaer+ to "e o)er#aule* ((

    8 relay+ to "e cali"rate*

    9. ;ire Pump :ou+e i! ou"le eart#ing to "e *one (

    ;or trolley pump.

    ii! Replace* *e$ecte* Ammeter (

    in+talle* in Panel+

    iii! Unplugge* ca"le+ entrie+ to "e clo+e* (

    i)! Routine 6maintenance o$ Pump

    8 motor

    1D. S% Plant i! ;or lter pump&' 8 Mono Bloc (

    pump eart#ing to "e *one again

    ii! Replace* *e$ecte* Ammeter (

    8 Voltmeter in Panel

    iii! Unplugge* ca"le+ entrie+ to "e clo+e* (

    i)! Routine maintenance o$ Pump

    Page 13 of 55

  • 7/24/2019 electrical audit

    14/55

    MUMBAI

    ELECTRICAL AUDIT REPORT

    INDIAN OIL BHAVAN (H.O.)

    MUMBAI

    Date of Visit :

    Page 14 of 55

    8 motor

    Sl. Equipment Action Priority CategoryNo.

    11. >i$t+ i! Routine maintenance

    1'. Eart#ing ii! Eart#ing +y+tem nee*+ to "e (

    impro)e* a+ *etaile* out int#e recommen*ation

    10. >ig#tning Protection i! Eart#ing to "e *one "y 07F= ( +trip ((

    ii! Ru+te* lig#tning pole to "e replace* (

    iii! Eart#ing to "e ma*e continuou+ (

    14. Canteen "uil*ing i! Ammeter to "e replace* $or Panel ( ii! Panel to "e replace* (( iii! >ig#t pro)i+ion to "e pro)i*e* (

    i)! re++ing o$ ca"le+ 8 t#e ca"le (( lea*+ to "e *one.

    17. ;ee*er Pillar i! Ca"le i+ to "e re terminate* again ( "y proper crimping 8 3it# lug ii! Panel to "e replace* (( iii! Ca"le glan* to "e pro)i*e* ( i)! re++ing o$ ca"le+ 8 t#e ca"le (( lea*+ to "e *one.

    Page 14 of 55

  • 7/24/2019 electrical audit

    15/55

    MUMBAI

    ELECTRICAL AUDIT REPORT

    INDIAN OIL BHAVAN (H.O.)

    MUMBAI

    Date of Visit :

    Page 15 of 55

    OBSERVATION

    &

    RECOMMENDATION

    OBSERVATIONS AND RECOMMENDATIONS

    1. 11 KV Breakers-1 No. Make Siemens.

    1.1 Observations:-

    Page 15 of 55

  • 7/24/2019 electrical audit

    16/55

    MUMBAI

    ELECTRICAL AUDIT REPORT

    INDIAN OIL BHAVAN (H.O.)

    MUMBAI

    Date of Visit :

    Page 1 of 55

    1.1.1 This Vaccum Circuit Breaker receives supply from Reliance Power through800A Breaker. Each breaker of 800A supplies to 1000 KVA Transformer

    i.e. TR-1 & TR-2.

    1.1.2 The breakers are installed on a separate room adjacent to DG room.

    1.1.3 The Ammeter of TR-2 to be changed as, the CT ratio is 100/1 & the

    installed Ammeter range is 1 to 25 A.

    1.1.4 Double earthing has been provided by GI strip & same was found in goodcondition.

    1.1.5 Rear Side of Breaker there is no rubber mat.

    1.1.6 Cable termination were checked & same was found in healthy condition.

    1.1.7 Relay setting calibration done on 14.06.15.

    1.1.8 Shock treatment chart, fire extinguisher has been provided in the room,

    Lighting in the room was also found adequate.

    1.2 Recommendation:-

    1.2.1 It is recommended that Ammeter to be change having the range of 1 to

    100A for Tr-2.

    1.2.2 At Rear side Rubber mat of 2mm of voltage rating 33 KV at rear side of

    breaker to be provided.

    1.2.3 Danger board/caution plate to be provided on the breaker.

    1.2.4 Cable sizes to be stenciled with white paint on both the breakers.

    Page 1 of 55

  • 7/24/2019 electrical audit

    17/55

    MUMBAI

    ELECTRICAL AUDIT REPORT

    INDIAN OIL BHAVAN (H.O.)

    MUMBAI

    Date of Visit :

    Page 16 of 55

    2.TRANSFORMER- 2 Nos.

    Transformer (TR-1) 1000KVA, 11KV/433V, 52.5/1334A

    Percentage Impedance Z = 4.95%

    Make Kirlosker

    Transformer (TR-2) 1000KVA, 11KV/433V, 52.5/1334A

    Percentage Impedance Z = 4.99%

    Make Kirlosker

    2.1 Observations:-

    2.1.1 Transformer I- is supplying to following area i.e. Flood Load, Canteen,

    Domestic Pumps, Lift No.1 & 2. IT Centre, Air Conditioning Unit,

    Capacitor Bank 1 trough Main Distribution Board. Transformer II is

    supplying Small Wing, STP, Large Wing, Lift No.4, 5 & 6, UPS Room and

    Capacitor Bank 2 through Main distribution board.

    2.1.2 Transformer-1 is connected to Main Distribution Board through 6 nos.

    3.5X300 sq.mm Al. PVC Cable to MDB & 1600 Amp. ACB.

    Transformer -2 is connected through 6 nos. of 3.5CX300 sq.mm Al. PVC

    Cable to MDB & 1600 Amp ACB.

    2.1.3 In both the transformer, Earthing of the neutral & the body was done by

    50X6 mm GI strips & the same was found in healthy condition.

    2.1.4 The Transformers are installed on high concrete plinth in an open area,

    behind the Main LT Panel Room,

    2.1.5 Filtration of transformer oil of both the transformers has been done every

    year as told by the maintenance personals.

    Page 16 of 55

  • 7/24/2019 electrical audit

    18/55

    MUMBAI

    ELECTRICAL AUDIT REPORT

    INDIAN OIL BHAVAN (H.O.)

    MUMBAI

    Date of Visit :

    Page 17 of 55

    2.1.6 Cable terminations were checked & same was found in healthy condition.

    2.1.7 WTI of Transformer-1 was found not working properly.

    2.1.8 Both the Transformer was found rusted very badly.

    2.1.9 Proper fencing with gate has been provided around the transformer to

    avoid entry of unauthorized person.

    2.2 Recommendation:-

    2.2.1 It is recommended to check the di-electric strength of the oil once in a

    year.

    2.2.2 Silica Gel of both the transformer to be re-activated by heating & changed

    when necessary.

    2.2.3 WTI to be changed for Transformer-1.

    2.2.4 A Shed to be provided over both the Transformer, so that rain water can

    be stopped directly falling on transformer.

    2.2.5 Routine maintenance as per I.O.C. Engineering Manual Vol-7 Part-I to be

    done.

    2.2.6 Cable Boxes both H.T. & L.T. to be earthed with main body of the

    transformer

    2.2.7 For long term planning it is recommended to replace both then

    transformer by 1250 KVA transformer of reputed make., since the existing

    transformer is 32 years old & the average life cycle has been completed.

    Page 17 of 55

  • 7/24/2019 electrical audit

    19/55

    MUMBAI

    ELECTRICAL AUDIT REPORT

    INDIAN OIL BHAVAN (H.O.)

    MUMBAI

    Date of Visit :

    Page 18 of 55

    2.3 Healthiness Report of Transformer

    Transformer was checked for healthiness at IOCL (HO) Bandra on 20,

    July, 2015. During the Check up following parameters of both the

    Transformers like Voltage , Current & Temperature were recorded & same

    has been listed below in tabular form:-

    Transformer No.1 Details As per Name Plate:-

    Rating :-1000 KVA, 11/.433 KV, Dyn11, Current HV-52.5A & LV-

    1334 A ,Make-Kirlosker , Year of Manufacture= 1983, Serial No.- 83LD-114/2, Impedance-4.99%.

    On Dated 20.07.15

    Time I/C Voltage in

    Voltage

    Current in

    Ampere

    Temperature in Celsius

    OTI WTI

    02:00 P.M. 405 600 40 *

    02:30 P.M. 400 630 40 *

    03:00 P.M. 415 560 39 *03:30 P.M. 415 540 38 *

    04:00 P.M. 410 620 37 *

    04:30 P.M. 415 635 38 *

    05:00 P.M. 410 630 41 *

    Transformer No.2 Details As per Name Plate:-

    Rating :-1000 KVA, 11/.433 KV, Dyn11, Current HV-52.5A &

    LV- 1334 A ,Make-Kirlosker , Year of Manufacture= 1983, Serial No 83LD-114/1, Impedance-4.99%.

    Page 18 of 55

  • 7/24/2019 electrical audit

    20/55

    MUMBAI

    ELECTRICAL AUDIT REPORT

    INDIAN OIL BHAVAN (H.O.)

    MUMBAI

    Date of Visit :

    Page 29 of 55

    On Dated 20.07.15

    Time I/C Voltage in

    Voltage

    Current in

    Ampere

    Temperature in Celsius

    OTI

    WTI

    02:00 P.M. 400 780 38 41

    02:30 P.M. 400 780 38 41

    03:00 P.M. 415 740 37 40

    03:30 P.M. 415 700 36 39

    04:00 P.M. 410 760 38 41

    04:30 P.M. 415 780 39 4205:00 P.M. 410 760 37 40

    3. DG SET- 1 No:-

    DG Set 500 KVA, 415V, 716 A , 1500 RPM

    Make of Alternator Stamford

    Make of Engine Cummins

    Operation & routine maintenance being done as per the maintenance

    Schedule.

    3.1 Observations:-

    3.1.1 500 KVA DG Set is installed in DG room, which is without acoustic

    enclosure, DG set is operated through a DG panel of Narendra Switchgear

    make, having 1000A ACB in incomer side. The supply is feed to Main

    Distribution Board through bus coupler of 1600A, providing inter locking

    with main supply.

    3.1.2The DG sets has been properly installed in the DG room, cable from DG

    set to DG control Panel has been laid and cable termination has been

    done properly. No loose connection observed.

    Page 29 of 55

  • 7/24/2019 electrical audit

    21/55

    MUMBAI

    ELECTRICAL AUDIT REPORT

    INDIAN OIL BHAVAN (H.O.)

    MUMBAI

    Date of Visit :

    Page 21 of 55

    3.1.3 Body earthing & neutral earthing has been provided by 50x6 mm GI strip

    and connection was found healthy.

    3.1.4 In DG Control panel, cable termination checked & same was found in

    healthy condition.

    3.1.5 Condition of Gasket of panel was found deteriorated in the DG Panel.

    Neoprene type gasket shall be fitted at the door of the panel.

    3.1.6 Under Voltage/Over Voltage/ Earth fault Relay installed in the DG Control

    Panel, were found not in working condition.

    3.1.7When the DG is in Running Condition, then there is lot of noise created

    by the DG sets.

    3.2 Recommendation:-

    3.2.1 New DG panel to be installed having all the protection like Under

    Voltage/Over Voltage/ Earth fault Relay, so that the panel can work

    efficiently without any hazard.

    3.2.2 For Long Run, a new DG of 630 KVA Can be installed having acoustic

    enclosure as per latest CPCB norms. This will take entire load of Building

    at the time of emergency.

    3.2.3 It was observed there were dust & cob webs inside the panel, so it is

    recommended, that from hot air blower blowing to be done in once in a

    month.

    3.2.4 It is recommended, that cable terminal nut bolts to be tightening to be donein once in a three month.

    Page 21 of 55

  • 7/24/2019 electrical audit

    22/55

    MUMBAI

    ELECTRICAL AUDIT REPORT

    INDIAN OIL BHAVAN (H.O.)

    MUMBAI

    Date of Visit :

    Page 22 of 55

    4. MAIN DISTRIBUTION BOARD (MDB):-

    The MDB has mainly three sections i.e. Section-I, Section-II & Section-III

    coupled through Bus Coupler 1600 Amp. ACB.

    Section-I consist of :-

    Incomer from 1000 KVA Transformer TR-2- 1600Amp. ACB

    Outgoing:-

    Page 22 of 55

  • 7/24/2019 electrical audit

    23/55

    MUMBAI

    ELECTRICAL AUDIT REPORT

    INDIAN OIL BHAVAN (H.O.)

    MUMBAI

    Date of Visit :

    Page 23 of 55

    to Air Conditioning Plant II - 1000 Amp. SFU

    to Small Wing, Large Wing & Capacitor Bank-2 - 630 Amp. SFU

    to UPS changeover 2ndFloor & Spare - 400 Amp. SFU

    to STP - 250 Amp. SFU

    to Lift No. 4, 5 & 6 and Spare - 100 Amp. SFU

    to spare - 63 Amp. SFU

    Section-II consist of :-

    Incomer from 1000 KVA Transformer TR-1- 1600Amp. ACB

    Outgoing:-

    to Air Conditioning Plant-I - 1000 Amp. SFU

    to Small Wing, Large Wing & Capacitor Bank-1 - 630 Amp. SFU

    to Canteen, MLTP 1 & 2, Workshop - 250 Amp. SFU

    & Domestic Pump

    to Lift No. 1, 2 & Freight Lift & Spare - 100 Amp. SFU

    Pantry Lift & Flood Light & Spare - 63 Amp. SFU

    Section-III consist of :-

    Incomer from 500 KVA DG Set- 1600Amp. ACB

    Outgoing:-

    to Air Conditioning Plant - 1000 Amp. SFU

    Page 23 of 55

  • 7/24/2019 electrical audit

    24/55

    MUMBAI

    ELECTRICAL AUDIT REPORT

    INDIAN OIL BHAVAN (H.O.)

    MUMBAI

    Date of Visit :

    Page 24 of 55

    to Fire Pump Panel - 400 Amp. SFU

    to Lift No. 3 & Building light, Main Gate LDB - 100 Amp. SFU

    & Sub station

    4.1 Observations:-

    4.1.1All thebreakers are of ABB make. It was reported that servicing of the

    breaker are being periodically done by M/s. Spark Electrical.

    4.1.2 The protection relays of the breakers are in operation. Maintenance of

    MDB & other equipments being done by M/s. Spark Electrical.

    4.1.3 Under voltage Relay 2 Nos. of DG section i.e. H4 feeder is found not in

    working condition.

    4.1.4 Cable termination were checked & same was found in healthy condition.

    4.1.5 Condition of feeder were checked and found in healthy condition. No

    heating / flash over observed / reported.

    4.1.6 Shock treatment Chart, Rubber Mat, Fire Extinguishers has been provided

    in the panel room. Illumination level of the room was found adequate.

    4.1.7 Double earthing has been provided by GI strip for the panel & same was

    found in healthy condition.

    4.1.8 It was observed there were dust & cob webs inside the panel.

    4.1.9 Load Current were measured in voltmeter for Tr-1 is 700 Amp. & for

    Transformer Tr-2 is 600 Amp.

    4.1.10 The load current capacity in several feeders were checked and found the

    cables are able to carry the load current without any heating.

    4.1.11 In the feeders, Phase current were checked and found the load a generally

    Page 24 of 55

  • 7/24/2019 electrical audit

    25/55

    MUMBAI

    ELECTRICAL AUDIT REPORT

    INDIAN OIL BHAVAN (H.O.)

    MUMBAI

    Date of Visit :

    Page 25 of 55

    balanced & vary only 10%.

    4.1.12 It was observed that the Cable trench were filled with cables and there is

    no more space in the trench to put more cables.

    4.1.13 Necessary interlocking was provided in the panel.

    4.2 Recommendations:-

    4.2.1 It is recommended to have the calibration of the relays done & operation of the relays/ breakers checked by Secondary injection test method through

    any reliable & approved contractor/agency.

    4.2.2 Cleaning of the panels interior & tightening of the connections to be done.

    4.2.3 Under Voltage Relay of DG section to be changed/rectified.

    4.2.4 It was observed there were dust & cob webs inside the panel, so it is

    recommended, that from hot air blower blowing to be done in once in a

    month.

    4.2.5 It is recommended at the time of revamping the cable trench to be made of

    1.2 mtr in width & 1 mtr. in depth. The cable to be dressed properly in

    trench.

    Page 25 of 55

  • 7/24/2019 electrical audit

    26/55

    MUMBAI

    ELECTRICAL AUDIT REPORT

    INDIAN OIL BHAVAN (H.O.)

    MUMBAI

    Date of Visit :

    Page 2 of 55

    5. CAPACITOR (APFC) PANEL:-

    Nos. 320 KVAR each have been installed recently for the improvement of

    power factor.

    Make of the panels :- ABB

    Capacitor :- Unistar

    5.1 Observation:-

    5.1.1 In each panel, there are different rating of capacitor bank feeder, capacitor

    bank feeders are segregated as of 50 KVAR 2 Nos., 8 nos. of 25KVAR and

    2 nos. 10 KVAR in both the panel.

    5.1.2 The capacitor are brought into the circuit i.e. switched ON & OFF through

    automatic P.F. correction relays mounted on the MDB.

    5.1.3 The contractor used in the modules for the switching ON or OFF, were

    found working satisfactory.

    5.1.4 Cable terminations of banks were checked & same was found in healthy

    condition.

    5.1.5 Shock treatment Chart, Rubber Mat, Fire Extinguishers has been provided

    in the panel room. Illumination level of the room was found adequate.

    5.1.6 Double earthing has been provided by GI strip for both the panel & same

    was found in healthy condition.

    5.1.7 Capacitor Panel was found working condition properly and PF is being

    maintained around 0.99.

    5.1.8 In Capacitor Panel No.2, Feeder No-9, the Capacitor OFF button light is

    Page 2 of 55

  • 7/24/2019 electrical audit

    27/55

    MUMBAI

    ELECTRICAL AUDIT REPORT

    INDIAN OIL BHAVAN (H.O.)

    MUMBAI

    Date of Visit :

    Page 26 of 55

    not glowing.

    5.1.9 In Capacitor Panel No.1, Feeder No-7, the Capacitor contractor found

    burnt.

    5.2 Recommendation:-

    5.2.1 In Capacitor Panel No.2, Feeder No-9, the Capacitor OFF button light top

    be replaced.

    5.2.2 In Capacitor Panel No.1, Feeder No-7, the Capacitor contractor to be

    changed with higher rating contractor.

    5.2.3 Cleaning of the panels interior & tightening of the connections to be done.

    Page 26 of 55

  • 7/24/2019 electrical audit

    28/55

    MUMBAI

    ELECTRICAL AUDIT REPORT

    INDIAN OIL BHAVAN (H.O.)

    MUMBAI

    Date of Visit :

    Page 27 of 55

    6 LIGHTING SYSTEM:-

    The lightning & power supply to different floors of the entire building is

    made through 2 nos. rising mains one of the Large Wing(North) & other is

    small Wing(South). At each floor the rising mains are tapped by 125Amp.

    TPN switch mounted on the metal frame of the rising mains and the

    terminal of the switch are connected to Bus-Bar of the rising main by cable.

    The outgoing from the 100Amp. Switch is connected to a MCB DB panel.

    This panel is used for phase splitting i.e. 3 phase to single phase.

    Each phase of the Bus Bars is connected trough 40/25 A RCCB. The

    Outgoing is through LDB-1 & LDB-2, In LDB-1 & 2 the incoming is through

    40 Amp, 4pole TPN MCB & outgoing is distributed in each phase, through

    10A, 20A & 32 A Single pole MCB.

    In Each Floor there are LDB-1, LDB-2, & One Emergency DB. Each floor

    has different numbers of MCB distribution board.

    All the LDB are recently installed in each floor, the conditions of DB were

    observed in good shape.

    LDB

    Page 27 of 55

  • 7/24/2019 electrical audit

    29/55

    MUMBAI

    ELECTRICAL AUDIT REPORT

    INDIAN OIL BHAVAN (H.O.)

    MUMBAI

    Date of Visit :

    Page 28 of 55

    Make ETC Energy

    Incomer - 40A TPN, MCB

    Outgoing - 4 Nos.-10 A, 3 Nos.- 20A, 1 No.- 32 A MCB for each phase

    & 1 no, RCCB of 25A/40 A

    Similar type of LDBs are installed in each floors on Large & Small Wings.

    6.1 Observations :-

    6.1.1 The LDBs installed in the floors are found in good condition.

    6.1.2 The earthing of DBs are done by double earthing.

    6.1.3 In some of the floors, frequent tripping was occurred as reported by

    M/s. IOCL, in that case the RCCB was changed from 25 A to 40 A, due to

    which no further tripping was reported.

    6.1.4 Outdated rubber mat has been used in front of the rising mains.

    6.1.5 Cable terminations were checked & same was found in health conditions.

    No heating/flash over were observed/reported.

    6.1.6 In LDB proper identification was not been given for each LDB according to

    floor & wing.

    6.1.7 Also, in each DB, identification/nomenclature for outgoing MCB were not

    given for the easy of operation.

    6.1.8 In LDBs no unplugged entries & dust was observed.

    6.2 Recommendation:-

    6.2.1 Cleaning of the DBs interior & tightening of the connections to be done.

    Page 28 of 55

  • 7/24/2019 electrical audit

    30/55

    MUMBAI

    ELECTRICAL AUDIT REPORT

    INDIAN OIL BHAVAN (H.O.)

    MUMBAI

    Date of Visit :

    Page 39 of 55

    6.2.2 So it is recommended, that from hot air blower blowing to be done in once in a month.

    6.2.3 Rubber Mat as per IS 15652, to be used for safety purpose.

    6.2.4 In LDB proper identification to be given for each LDB according to floor

    & wing for ease of operation & maintenance.

    6.2.5 Also, in each DB, identification/nomenclature for outgoing MCB to be

    given for the easy of operation.

    6.2.6 Cable termination to be checked & tightened in every 3 months.

    7 LIGHTNING POLE & GLOBE LIGHT :-

    There are aprrox 20 Nos. lightning poles fitted with 1 X 250 Watts Metal

    Halides lamps in each fitting. & 7 Nos. of lightning fitting pole fitted with

    1 X 150 watts Metal Halides lamps of Bajaj & Philips make.There are

    approx 51 Nos. of Dome light having 70 watt sodium vapor lamps installed

    in the IOCL Office Compound.

    Page 39 of 55

  • 7/24/2019 electrical audit

    31/55

    MUMBAI

    ELECTRICAL AUDIT REPORT

    INDIAN OIL BHAVAN (H.O.)

    MUMBAI

    Date of Visit :

    Page 31 of 55

    7.1 Observation:-

    7.1.1 Dome Light in Building area, the cable laid are very old, they were found

    ruptured many times, as per the information given by site personnel.

    7.1.2 The sheet metal of Junction boxes are totally rusted & corroded. Terminals

    hard wares are also badly rusted.

    7.1.3 Cable insulation were found weak.

    7.1.4 It was observed in some of the poles i.e. 5 Nos. the bottom is rusted very badly.

    7.1.5 At some place, the earthing was found disconnected of lightning poles.

    7.1.6 Garden Light (LED Type) of 6 Watt , some of the fitting found missing/

    defective.

    7.1.7 There are 8 to 10 nos. of pole which are found rusted due to which

    mounting is not possible.

    7.1.8 The incoming/outgoings cables mounted in the recesses at the bottom of

    the poles are badly corroded/rusted which give rise to loose connection &

    failure.

    7.2 Recommendation:-

    7.2.1 Dome Light in Building area, the cable laid over there, which are ruptured

    & have less insulation , the same to be changed/replaced, so that no

    Accident can take place.

    7.1.2 JB conduits were found rusted, so it is recommended to replace it.

    7.1.4 It is recommended to change all the poles which are rusted & defective.

    Page 31 of 55

  • 7/24/2019 electrical audit

    32/55

    MUMBAI

    ELECTRICAL AUDIT REPORT

    INDIAN OIL BHAVAN (H.O.)

    MUMBAI

    Date of Visit :

    Page 32 of 55

    7.1.5 Earthing to be connected of lightning poles where every found

    disconnected.

    7.1.6 It is recommended to provide cast AL, IP-55 Junction Boxes at the base

    of the poles fitted with fuses/terminal block etc.

    7.1.7 The cabling to be done with gland & terminals with Cu lugs.

    Page 32 of 55

  • 7/24/2019 electrical audit

    33/55

    MUMBAI

    ELECTRICAL AUDIT REPORT

    INDIAN OIL BHAVAN (H.O.)

    MUMBAI

    Date of Visit :

    Page 33 of 55

    8 AIR CONDITIONING PLANT:-

    The New Air Conditioning Plant is installed which is nearly one year old.

    There are 4 nos. of AC Plant of 200 Tonnes/Hr. Each chiller plant have

    have two units each of 100 Tonnes/ Hr. The Unit receive power supply

    from two new Panels installed in the Air Conditioning room.

    8.1 Observation:-

    8.1.1 Following Equipments has been installed in AC Plant.

    Sr. No. Description Rating Make Qty.

    1) Centrifugal Unit 756 KW Blue Star 4

    2) Condenser Pump Motor 30 KW Kirloskar 4

    3) Chiller Pump Motor 30 KW Kirloskar 4

    4) MCC Panel 415 V Industrial 2

    Electrical

    5) JB for Condenser Pump 415V Industrial 4

    Electrical

    6) JB for Chiller Pump 415V Industrial 4

    Electrical

    7) Air handling Unit at 24

    Different floor

    8.1.2 All the equipments were new and recently installed, they all are in good

    shape.

    8.1.3 All the equipments were found Double earthing has been provided by GI

    Strip/ Flexible Copper cable for both the panel & same was found in

    healthy condition.

    Page 33 of 55

  • 7/24/2019 electrical audit

    34/55

    MUMBAI

    ELECTRICAL AUDIT REPORT

    INDIAN OIL BHAVAN (H.O.)

    MUMBAI

    Date of Visit :

    Page 34 of 55

    8.1.4 There are two panels which receive power from MDB, there are two nos.

    630 Amp SFU in each panel for Chiller Plant 1 to 4. And outgoing was

    To Chiller pumps, motors, cooling tower & AHU Units in all the floors.

    8.1.5 Emergency Stop Push Button is installed for each Condenser & Chiller

    Motor.

    8.1.6 Cable termination were checked & same was found in healthy condition.

    8.1.7 The Motors for Chiller & Condenser Units were checked and found ok.

    8.1.8 No problem has been observed/reported in MCC panel.

    8.1.9 In front of MCC Panel( chiller 3 & 4 unit) there was no rubber mat.

    8.1.10Jet Fan DB which is wall mounted having 16A three pole MCB were

    found not earthed.

    8.2 Recommendation:-

    8.2.1 All the terminals to be checked and tightened in every three months.

    8.2.2 Rubber mat to be provided in front of MCC Panel(Chiller 3 & 4)

    8.2.3 Jet Fan DB to be double earthed with flexible cooper cables.

    8.2.4 Regular maintenance to be done as per IOCL maintenance schedule.

    Page 34 of 55

  • 7/24/2019 electrical audit

    35/55

    MUMBAI

    ELECTRICAL AUDIT REPORT

    INDIAN OIL BHAVAN (H.O.)

    MUMBAI

    Date of Visit :

    Page 35 of 55

    9 FIRE PUMP HOUSE :-

    9.1 Observation:-

    9.1.1 Following motors has been installed in Fire Pump House.

    Sr. No. Description Rating Make Qty.

    1) Fire Engine 89.5 KW Kirloskar 1

    2) Hydrant Motor 60 KW Kirloskar 1

    3) Sprinkler Motor 60 KW Kirloskar 1

    4) Jockey Pump Motor 11 KW Kirloskar 1

    5) Trolley Pump 3.7 KW Induscom 1

    6) Sump Pump ----- ------ 2

    9.1.2 In Fire Pump House the cable coming to Panel was not properly dressed

    on the cable tray/ wall. There are lying in haphazard manner.

    9.1.3 The Ammeter of Main Fire Panel and other panel installed adjacent to

    Fire Panel was found not in working condition.

    Page 35 of 55

  • 7/24/2019 electrical audit

    36/55

    MUMBAI

    ELECTRICAL AUDIT REPORT

    INDIAN OIL BHAVAN (H.O.)

    MUMBAI

    Date of Visit :

    Page 3 of 55

    9.1.4 The Jockey Pump was kept in Auto Mode & at set pressure of 7kg/cm. sq.

    9.1.5 There is a proposal on one new Jockey Pump. The motor has been

    brought but not yet installed.

    9.1.6 The earthing of Jockey Pump, Sprinkler & Hydrant Pump were done by

    25X3mm GI strips, & same was found in health condition.

    9.1.7 Cable entry in terminal box of Sprinkler motor was found loose, i.e. proper

    glanding is not done.

    9.1.8 The condition of Fire engine was found in good shape, same is kept in

    manual mode. The battery condition found healthy.

    9.1.9 In DC panel for Fire Engine, unused cable entry observed at the bottom

    of the gland plate.

    9.1.10 The trolley pump have single body earthing.

    9.1.11 In DOL starter & 16 Amp. Fuse Unit for Trolley Motor, cable entry is

    without any gland. And the terminal box of motor also does not have any

    gland.

    9.1.12 Cable armour were found cut of Sump Pump motor.

    9.1.13 Condition of Gasket of Panels were found deteriorated.

    9.2 Recommendation:-

    9.2.1 All the terminals of motors to be checked and tightened in every three

    months.

    9.2.2 All the defective Ammeter to be replaced as per the rating in Panel.

    Page 3 of 55

  • 7/24/2019 electrical audit

    37/55

    MUMBAI

    ELECTRICAL AUDIT REPORT

    INDIAN OIL BHAVAN (H.O.)

    MUMBAI

    Date of Visit :

    Page 36 of 55

    9.2.3 Trolley Pump to be double earthed with flexible cooper cables.

    9.2.4 All the cable in the Fire Pump house are to be properly dressed/cladded.

    9.2.5 Proper Cable glanding to be done in all the motors terminal boxes.

    9.2.6 It is advised to plug all such unused spaces/blanks by using blanker to

    avoid entry of dust, lizards etc.

    9.2.7 Neoprene type gasket shall be fitted at the door of the Panels.

    9.2.8 Cable to be cutted & ret terminated for Sump Pump Motor.

    10 ST PLANT :-

    10.1 Observation:-

    10.1.1 Following motors has been installed in Fire Pump House.

    Sr. No. Description Rating Make Qty.

    1) Filter Pump1-2 7.5 KW Bharat Bijlli 2

    2) Carifiled Water Pump1-2 3.7 KW Toshio 2

    3) Dewatering Pump 2.2 KW Bharat Bijlli 1

    4) Return Sludge Pump 2.2 KW BB & Siemens 2

    Page 36 of 55

  • 7/24/2019 electrical audit

    38/55

    MUMBAI

    ELECTRICAL AUDIT REPORT

    INDIAN OIL BHAVAN (H.O.)

    MUMBAI

    Date of Visit :

    Page 37 of 55

    5) Air Blower 3.7 KW Usha 2

    6) Aerator 2.2 KW ------ 1

    10.1.2 The panel of ST Plant, receives power from MDB , the Incomer has 250A

    SFU & the outgoing is to Pumps, Blower etc.

    10.1.3 The Ammeter & Voltmeter of Panel was found not in working condition.

    10.1.4 Red & Blue Phase indicator of Panel was not glowing brightly.

    10.1.5 Condition of Gasket of Panel was found deteriorated.

    10.1.6 Earthing of Pumps were done by 10 sq.mm flexible copper cable.

    10.1.7 Earthing for Filter Pump No.2 found disconnected & Earthing of Mono

    Block Pump2(Carfiled) was done in foundation buried in motor platform.

    10.1.8 In Return Sludge Pump of Siemens make the glanding of Cable terminal

    were found not done.

    10.2 Recommendation:-

    10.2.1 All the terminals of motors to be checked and tightened in every three

    months.

    10.2.2 All the defective Ammeter & Voltmeter to be replaced as per the rating in

    Panel.

    10.2.3 Earthing for Filter Pump No.2 to be connected & Earthing of Mono

    Block Pump 2(Carfiled) to be done on motor not in foundation.

    Page 37 of 55

  • 7/24/2019 electrical audit

    39/55

    MUMBAI

    ELECTRICAL AUDIT REPORT

    INDIAN OIL BHAVAN (H.O.)

    MUMBAI

    Date of Visit :

    Page 38 of 55

    10.2.4 The Red & Blue indication lamps to be replaced in ST Panel.

    10.2.5 Proper Cable glanding to be done in all the motors terminal boxes.

    10.2.6 Neoprene type gasket shall be fitted at the door of the Panel.

    11 LIFTS :-

    11.1 Observation:-

    11.1.1 Following Lifts has been installed in IOCL Building.

    Page 38 of 55

  • 7/24/2019 electrical audit

    40/55

    MUMBAI

    ELECTRICAL AUDIT REPORT

    INDIAN OIL BHAVAN (H.O.)

    MUMBAI

    Date of Visit :

    Page 49 of 55

    Sr. No. Description Capacity Make Qty.

    1) Passenger Lift 1-6 20 person Otis 6

    2) Freight Lift 15 person Otis 1

    3) Pantry Lift ------ Otis 1

    11.1.2 All the passenger lift were well maintained. The lift license is valid.

    11.1.3 The Door Sensors were found working satisfactory.

    11.1.4 The Emergency Fan & light were working.

    11.1.5 Necessary Control Panel & interlocking relays are of Otis make &

    installed in the lift room. Lifts are being serviced & maintained by

    M/s. Otis representative.

    11.2 Recommendation:-

    11.2.1 There is no recommendation. The Lifts are working satisfactory.

    12. EARTHING & EARTHING SYSTEM:-

    Page 49 of 55

  • 7/24/2019 electrical audit

    41/55

    MUMBAI

    ELECTRICAL AUDIT REPORT

    INDIAN OIL BHAVAN (H.O.)

    MUMBAI

    Date of Visit :

    Page 41 of 55

    The earthing system of the plant was found good. The earth pits of plant randomly checked & following observations noted-

    a.Construction of the earth pit in sub- station area & pump house area was

    found in good condition. No rusting was observed, Earth Pit Resistance was

    checked on random basis & pit resistance was found in the range of 0.5 to 1.5

    Ohm. The measured value of the pit resistance were found within the

    acceptable range.

    b. In most of the pits C type clamps used in the pits & the connection werefound ok.

    c. Earth Pit Resistance is being measured and records are maintained.

    d.4 Nos. of New Earth Pit has to be constructed for New installation of

    transformer.

    e.There are 4 Nos. of chemical earthing in front of LT Panel room. The electrode

    is buried in the ground. There is no pits made for easy of maintenance.

    12.1 EARTHING RECOMMENDATIONS & PRACTICES:-

    Recommended practices for an earthing system to attain acceptable level

    of safety:-

    a.To provide a very low resistance path to ground for the discharge of

    fault current, lightning current and statics charges.

    b. Mechanical strength and corrosions resistance to various

    environmental conditions so that the system remains intact

    throughout the working life of the plant.

    c.Loose contacts to be totally avoided so that there are hot spots

    developed during the passage of fault current or lightning current

    which can be 200KA or more.

    d.Minimum Spacing between two electrodes shall be 10 meters or twice the length of the electrode.

    Page 41 of 55

  • 7/24/2019 electrical audit

    42/55

    MUMBAI

    ELECTRICAL AUDIT REPORT

    INDIAN OIL BHAVAN (H.O.)

    MUMBAI

    Date of Visit :

    Page 42 of 55

    e.Earth grid shall be 1.5 meter away from the building column and to be

    buried at a depth of 600 mm.

    f.Interconnection of GI Strips in the earth grid should be done by welding

    instead of bolting, and the welded portion should be painted with zinc-

    rich paint (Epilux-4) or black bitumen paint to avoid rusting.

    g.The connection of the grid strips with the earth electrodes shall be

    made in such a way through C type clamps grouted on the side walls

    of the earth pit, that it shall be possible to isolate the earth electrode

    and measure its earth resistance.

    h.All the earthing pits shall be interconnected so as to obtain a minimum

    earth resistance of 1 ohm.

    i.Equipment earthing should always be crimped in suitable lugs if done

    with stranded Aluminum or GI wire ropes. Usage of solid conductor to

    be avoided, as it gives rise to loose connection with crimped socket.

    j.All earth connections to be checked for tightness. Loose connections or

    bolted joints lead to hot spot & sparking which can become a source or

    fire/explosion in the hazardous areas.

    k.Rusted connections to be rectified by applying zinc-rich or black

    bitumen paints.

    l.All lighting fixtures made of metal should be earthed. It is necessary

    that lighting fixtures installed in the plant areas shall be earthed

    externally. External earthing to be done by using a 2.5 sq. mm.

    stranded copper wire or 6 sq.mm. GI stranded wire.

    m.The neighboring soil to the earth electrode shall be kept moist by

    pouring water in the immediate vicinity of the earth electrode.

    Page 42 of 55

  • 7/24/2019 electrical audit

    43/55

    MUMBAI

    ELECTRICAL AUDIT REPORT

    INDIAN OIL BHAVAN (H.O.)

    MUMBAI

    Date of Visit :

    Page 43 of 55

    13 LIGHTNING PROTECTION (Ref IS - 2309):-

    13.1 Observation:-

    13.1.1 There are 8 Nos. Air Terminal Rods Connected with 25X3 GI strips laid

    along the parapet walls. On the roof 3 Nos. down conductor have been

    taken from the roof G.I. Strips to the Earth Pits.

    13.1.2 Lightning arrestor above machine room is found rusted.

    13.1.3 Earthing strip found rusted near the incoming door of roof.

    13.1.4 At some places, there is discontinuity of earthing strip, in the roof area.

    13.1.5 The nos. of lightning arrestor were sufficient as per the covered area.

    13.2 Recommendation :-

    13.2.1 The existing earthing to be changed with 35X6 GI strip.

    13.2.2 Lightning arrestor which are rusted is to be changed with new one.

    13.2.3 Earthing strip to be made in continuous through out the roof area.

    Page 43 of 55

  • 7/24/2019 electrical audit

    44/55

    MUMBAI

    ELECTRICAL AUDIT REPORT

    INDIAN OIL BHAVAN (H.O.)

    MUMBAI

    Date of Visit :

    Page 44 of 55

    14 CANTEEN AREA POWER SUPPLY:-

    Panel No.1

    Make - Star Engineer

    Incomer from Substation -3.5 X95 sq.mm cable

    Incomer switch of 125 A make L&T

    Outgoing to 5 nos. SFU of 16 Amp. & through switch fuse of 63 Amp(L&T)

    MCB DB in Canteen (Power):-

    Incomer - 40 Amp 4 pole MCB for panel.

    Outgoing 20 A, 5 Nos. 10A, 6 Nos. 32, 1 No. MCB in each phase.

    14.1 Observation:-

    14.1.1 It was observed in the panel that the Ammeter was not working condition.

    14.1.2 No provision of lighting was provided in the panel area.

    14.1.3 The way to panel was full of obstruction.

    14.1.4 The dust & cob web full in the panel.

    Page 44 of 55

  • 7/24/2019 electrical audit

    45/55

    MUMBAI

    ELECTRICAL AUDIT REPORT

    INDIAN OIL BHAVAN (H.O.)

    MUMBAI

    Date of Visit :

    Page 45 of 55

    14.1.5 Unused holes on the gland plate are not plugged.

    14.1.6 The cables leads inside the boxes are not properly dressed.

    14.1.7 In Fuse DB there is Bus Bar arrangement, 30 Nos. of HRC Fuse for

    outgoing for distribution.

    14.1.8 There are 3 feeders in the DB which are not in use, they are in

    non-functional condition.

    14.2 Recommendation :-

    14.2.1 Panel room to be properly made with proper peripheries, show that safety

    measure to be kept in mind.

    14.2.2 Panel way to be cleaned, all the kitchen goods to be removed in front of the

    panel.

    14.2.3 Cable glanding to be provided were ever is required & the unused entries

    to be plugged & sealed.

    14.2.4 Cleaning is required in the panel & near by area.

    14.2.5 Provision for proper lightning to be made, so that there will be adequate

    light to work.

    14.2.6 It is recommended that from hot air blower blowing to be done in once in a

    month.

    14.2.7 The dressing of cables & the cable leads to be done.

    14.2.8 For, long term planning a new panel to be installed.

    Page 45 of 55

  • 7/24/2019 electrical audit

    46/55

    MUMBAI

    ELECTRICAL AUDIT REPORT

    INDIAN OIL BHAVAN (H.O.)

    MUMBAI

    Date of Visit :

    Page 4 of 55

    15. FEEDER PILLAR PANEL (NEAR MAIN GATE):-

    Main Gate DB

    Incomer - of 100 A 3 pole MCB, make L&T

    Outgoing to 10 nos. MCB of 32 Amp. & 40 Amp. The outgoing is to Dome

    light, Cabin Light, fountain light, outdoor light.

    MCB DB for Fountain (Power):-

    Incomer - 40 Amp 4 pole MCB for panel.

    Outgoing to fountain Starter Motor approx 10 HP.

    15.1 Observation:-

    Page 4 of 55

  • 7/24/2019 electrical audit

    47/55

    MUMBAI

    ELECTRICAL AUDIT REPORT

    INDIAN OIL BHAVAN (H.O.)

    MUMBAI

    Date of Visit :

    Page 46 of 55

    15.1.1 Incomer DB enclosure is very small, i.e. the space is less due to which

    there is problem of doing maintenance.

    15.1.2 Available DB is very old & the condition is very critical.

    15.1.3 Heating in cable is observed in the incomer side of the cable.

    15.1.4 The MCB DB was full of dust & cob web.

    15.1.5 Unused holes on the gland plate are not plugged.

    15.1.6 The cables leads inside the boxes are not properly dressed.

    15.1.7 In Fountain DB, the space for mounting of cable terminal not in proper

    Way.

    15.1.8 Condition of Gasket of DB was found deteriorated.

    15.1.9 Flashover observed in incoming cable terminal in Fountain DB.

    15.2 Recommendation :-

    15.2.1 It is recommended that the cable is to be re-terminated again by proper crimping & with lug.

    15.2.2 Cable glanding to be provided were ever is required.

    15.2.3 It is recommended that from hot air blower blowing to be done in once in a

    month.

    15.2.4 For, long term planning a new DBs to be installed so that no problem is

    being faced at the time of maintenance.

    15.2.5 Neoprene type gasket shall be fitted at the door of the Panel.

    Page 46 of 55

  • 7/24/2019 electrical audit

    48/55

    MUMBAI

    ELECTRICAL AUDIT REPORT

    INDIAN OIL BHAVAN (H.O.)

    MUMBAI

    Date of Visit :

    Page 47 of 55

    15.2.6 The dressing of cables & the cable leads to be done.

    Page 47 of 55

  • 7/24/2019 electrical audit

    49/55

    MUMBAI

    ELECTRICAL AUDIT REPORT

    INDIAN OIL BHAVAN (H.O.)

    MUMBAI

    Date of Visit :

    Page 48 of 55

    Docume!" Re#$e%

    1).Document:-Documents as per Tender requirements were reviewed at IOCL

    Head Office. Following Equipments Documents were reviewed as

    listed below.

    1.1 Earthing :-Earth resistance of earth pit in IOCL Office Compound

    was taken by Spark Electrical Contractor on 03/06/2015.

    The reports submitted by M/s. Spark were reviewed.

    Following were theObservations:-

    Page 48 of 55

  • 7/24/2019 electrical audit

    50/55

    MUMBAI

    ELECTRICAL AUDIT REPORT

    INDIAN OIL BHAVAN (H.O.)

    MUMBAI

    Date of Visit :

    Page 59 of 55

    1.1.1 Individual Value of Earth Pit resistance was observed from 0.4 to 0.8 ohm

    for Pit No. 1 to 14.

    1.1.2 Individual Value of Earth Pit resistance was observed from 0.4 to 0.8 ohm

    for Pit No. 15 to 31.

    1.1.3 There are 8 nos. of Earth pit at Transformer yard, the value lies from 0.4

    to 1.6 2 ohm, for Pit No. 7 the resistance value is 1.3 ohm & Pit No. 8 it is

    1.62 ohm.

    1.1.4 There are 9 nos. of Old Earth pit at Building side, the value lies from 0.4

    to 1. 2 ohm, for Pit No.6 have the maximum value of resistance was

    recorded i.e. 1.2 ohm.

    1.1.5 There are 6 nos. of Neutral earthing , 2 for DG & Two nos. for each

    transformer, the value lies from 0.2 to .4 ohm.

    2.1 Battery Charger:-Battery Charger for 11 KV Breaker was serviced by

    M/s. Spark on 14.06.15 . And the report dated 16.06.15

    were reviewed. Following were theObservations:-

    2.1.1 Operational & Functional checks were found satisfactory.

    2.1.2Condition of battery found good & there were no open entry.

    3.1 LT Panel :-LT Panel servicing was done on 14.06.15 by M/s. Spark. And

    the report dated 16.06.15 were reviewed. Following were the

    Observations:-

    Page 59 of 55

  • 7/24/2019 electrical audit

    51/55

    MUMBAI

    ELECTRICAL AUDIT REPORT

    INDIAN OIL BHAVAN (H.O.)

    MUMBAI

    Date of Visit :

    Page 51 of 55

    3.1.1 Cleaning, ON OFF operation of MCCB were checked & found satisfactory.

    3.1.2Tightening of power & control cable was done.

    3.1.3 Operating handle of MCCB of G5 i.e.( Pantry Lift) feeder were found

    broken.

    4.1 HT Panel :-HT Panel servicing was also done on 14.06.15 by M/s. Spark.

    And the report dated 16.06.15 was issued & same was

    reviewed. Following were theObservations:-

    4.1.1 Cleaning, Tripping of relays were checked & found satisfactory.

    4.1.2Tightening of Bus Bar was done.

    4.1.3 HT Cable Termination & CT/PT connection were checked & found Ok.

    5.1 Transformer:-Servicing of Transformer was done by M/s. Spark on

    14.06.15 and the report dated 16.06.15 was issued & same

    was reviewed. Following were theObservations:-

    5.1.1 Cleaning, Tripping of relays were checked & found satisfactory.

    5.1.2 HT Cable Termination were checked & found Ok.

    5.1.3 Breather of both the transformer were found broken.

    Page 51 of 55

  • 7/24/2019 electrical audit

    52/55

    MUMBAI

    ELECTRICAL AUDIT REPORT

    INDIAN OIL BHAVAN (H.O.)

    MUMBAI

    Date of Visit :

    Page 52 of 55

    5.1.4 Dielectric Test of Transformer Oil was done & the results is given below:-

    Transformer Before Filtration Value After Filtration Value

    Transformer-1 25 KV 60KV

    Transformer-2 20 KV 60KV

    6.1 HT Breaker :-Servicing of Breaker was done by M/s. Spark on

    14.06.15 and the report dated 16.06.15 was issued & same

    was reviewed. Following were theObservations:-

    6.1.1 HT Breaker of Incomer Side & Both Outgoing side. Following test were

    carried out i.e. Closing & Tripping of Breaker, Mechanical Operation,

    spring charging of motor were checked & found satisfactory.

    6.1.2 Indication of Relay, Breaker Tripping from Relay were found working

    satisfactory.

    6.1.3 Insulation Resistance in ON & OFF condition were checked and following

    points were noted:-

    Breakers side Phase to Phase Value Phase to Earth Value

    Incomer Side 1500 M.Ohm 2000M.Ohm

    Transformer-1 1000 M.Ohm 1500M.Ohm

    Transformer-2 1500 M.Ohm 2000M.Ohm

    Page 52 of 55

  • 7/24/2019 electrical audit

    53/55

    MUMBAI

    ELECTRICAL AUDIT REPORT

    INDIAN OIL BHAVAN (H.O.)

    MUMBAI

    Date of Visit :

    Page 53 of 55

    7.1 ACB in MDB :-Servicing of ACB was done by M/s. Spark on

    14.06.15 and the report dated 16.06.15 was issued & same

    was reviewed. Following were theObservations:-

    7.1.1 Closing & Tripping of ACB, Mechanical Operation, were checked & found

    satisfactory.

    7.1.2 After servicing working conditions of ACBs were found satisfactory.

    7.1.3 Main & Auxiliary Contacts found ok.

    7.1.4 Insulation Resistance in ON & OFF condition were checked and following

    points were noted:-

    ACB ratings Phase to Phase Value Phase to Earth Value

    ACB 1600 TR-2 200 M.Ohm 200M.Ohm

    ACB 1600 B-C 100 M.Ohm 200M.Ohm

    ACB 1600 TR-1 200 M.Ohm 100M.Ohm

    ACB 1600 B-C RHS 200 M.Ohm 200M.Ohm

    ACB 1000 B-C LHS 200 M.Ohm 200M.Ohm

    8.1 Relay :-Servicing of Relays was done by M/s. Spark on 14.06.15

    and the report dated 16.06.15 was issued & same was reviewed. Following were theObservations:-

    Page 53 of 55

  • 7/24/2019 electrical audit

    54/55

    MUMBAI

    ELECTRICAL AUDIT REPORT

    INDIAN OIL BHAVAN (H.O.)

    MUMBAI

    Date of Visit :

    Page 54 of 55

    8.1.1 Relay Characteristic & functional has been checked & found ok.

    8.1.2 After servicing working conditions of Relays were found satisfactory.

    8.1.3 Flag indication, Alarm & Trip function of auxiliary relays were checked &

    found ok.

    8.1.4 Setting of different relays were done & the setting were found ok.

    ForCT Ratio 100/1following settings are shown:-

    Relay Ratings Setting Instantaneous Setting

    Phase R 0.5 - 2.0 1.5/.2 17 A

    Phase Y 0.5 - 2.0 1.5/.2 17 A

    Phase B 0.5 - 2.0 1.5/.2 17 A

    Earth Fault 0.1 - 0.4 0.2/.05 6.8 A

    ForCT Ratio 40/1following settings are shown:-

    Relay Ratings Setting Instantaneous Setting

    Phase R 0.5 - 2.0 1.5/.2 17 A

    Phase Y 0.5 - 2.0 1.5/.2 17 A

    Phase B 0.5 - 2.0 1.5/.2 17 A

    Earth Fault 0.1 - 0.4 0.2/0.1 6.8 A

    ForCT Ratio 25/1following settings are shown:-

    Page 54 of 55

  • 7/24/2019 electrical audit

    55/55

    MUMBAI

    ELECTRICAL AUDIT REPORT

    INDIAN OIL BHAVAN (H.O.)

    MUMBAI

    Date of Visit :

    Page 55 of 55

    Relay Ratings Setting Instantaneous Setting

    Phase R 0.5 - 2.0 1.5/.2 17 A

    Phase Y 0.5 - 2.0 1.5/.2 17 A

    Phase B 0.5 - 2.0 1.5/.2 17 A

    Earth Fault 0.1 - 0.4 0.2/0.1 6.8 A