efficacy of liability cap against third party losses

Upload: ajn

Post on 26-Feb-2018

213 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/25/2019 Efficacy of Liability Cap Against Third Party Losses

    1/2

    Drafting an effective liability cap against thirdparty losses can be problematic, as has beendemonstrated in the recently decided case of

    Westerngeco Ltd -v- ATP Oil & Gas (UK) Ltd.1

    While this case arose in the context of a contract for the

    provision of offshore seismic survey work under the LOGIC

    CRINE standard terms for the UK oil and gas industry, it

    raises important issues of general application which are

    particularly relevant to anyone dealing with the provision

    of services by contractors, including for example, in the

    context of PFI/PPP projects and/or where a party to a

    contract takes a contractual responsibility for third party

    losses.

    Broadly, the case demonstrates that where a contractoragrees with a company that it will accept liability for third

    party losses up to a specified amount then, unless the

    company agrees to indemnify the contractor for losses in

    excess of that cap, the contractor will be unable to recover

    such losses should the third party sue the contractor direct.

    By contrast, the limit on liability will be effective to limit

    the contractor's liability should the third party sue the

    company. The case also provides a useful insight into the

    court's approach to construing contractual terms.

    Facts

    In March 2004, ATP Oil & Gas (UK), a company engaged in

    offshore oil and gas development and production activities

    (the company) entered into a contract with Westerngeco

    (the contractor) for the provision by the latter of seismic

    survey work. The contract was based on the LOGIC CRINE

    standard terms for the UK offshore oil and gas industry,

    with some amendments.

    Under the standard provisions of the contract, the

    contractor was responsible for third party losses (i.e.

    personal injury or property damage) arising from the

    performance of the contract to the extent that such losses

    were caused by its negligence, and was also obliged toindemnify the company for losses arising in this way.

    The contract also followed the standard LOGIC CRINE

    "knock-for-knock" liability framework, whereby each party

    was responsible for, and had to indemnify the other in

    respect of, any damage to its own property, theinjury/death of its own employees, pollution emanating

    from its own property/equipment/reservoir and its own

    consequential losses, regardless of fault.

    Crucially, the parties specifically negotiated and inserted

    into the contract a clause seeking to cap the contractor's

    liability, under which the "Contractor's liability under this

    Contract" was not to exceed the aggregate amount of

    payments received by it for the work done and the

    company was to indemnify the contractor for any amounts

    in excess thereof.

    During the course of carrying out its work, the contractor

    damaged a wellhead marker buoy belonging to Total E & P

    UK Plc (Total), a third party. It was common ground that the

    damage was caused by the contractor's negligence.

    Total brought a claim against the contractor and the

    contractor sought a declaration that in accordance with the

    contractor's liability cap clause, the company was liable to

    indemnify the contractor for the amount of the contractor's

    liability to Total which was in excess of the aggregate

    amount of payments received by the contractor for the

    work it performed.

    The issue before the court was whether the meaning of the

    phrase "liability under this Contract" within the contractor's

    liability cap clause was wide enough to extend to the

    contractor's liability to Total.

    Held

    In giving his judgment, Aikens J adopted the approach to

    construing contracts set out in BCCI -v- Ali2, namely that the

    objective of the court is to give effect to the parties'

    intentions and that in order to ascertain the parties'

    intentions, the court will:

    January 2007

    Commercial Contracts Update

    Efficacy of a contractor's liability capagainst third party losses

    Brussels Dubai Frankfurt London Madrid Milan Munich New Delhi New York Paris Singapore Stockholm Tokyo

  • 7/25/2019 Efficacy of Liability Cap Against Third Party Losses

    2/2

    read the terms of the contract as a whole;

    give the words used their natural and ordinary meaning

    in the context of the agreement; and

    consider the parties' relationship and all the other

    relevant facts surrounding the transaction so far as

    known to the parties at the time it was made.

    The court does not enquire into the parties' subjective

    states of mind but makes an objective judgment based on

    the issues identified above.

    Interestingly, Aikens J specifically noted the fact that both

    parties were sophisticated market players in an industrywhere legal advice was usually taken over contracts which

    were subsequently drafted with great care. This was an

    important element in ascertaining the parties' intentions. It

    was clear how responsibility was to be divided; the parties

    had obviously allocated the various risks (and duties to

    insure against them) very carefully between them.

    Although the clause in question was specifically negotiated

    for that particular contract, it must be construed in this

    light.

    In applying the above principles, it was held that the

    natural meaning of "liability under this Contract" was, first,a legal (as opposed to some moral or non-legal) liability.

    Secondly, the phrase had to mean a legal liability to the

    counterparty (i.e. the company) as opposed to someone

    who is not a party to the contract or who could not take the

    benefit of its terms. Thirdly, the phrase contemplated a

    liability to pay over money.

    Given that the terms of the contract stipulated that, as

    between the contractor and the company, the contractor

    was responsible for third party losses arising from its

    negligence, there was no legal liability on the contractor to

    pay anything over to the company in respect of such losses.

    That being so, there was nothing in respect of which the

    company was obliged to indemnify the contractor if there

    was an excess above the aggregate payments received by

    the contractor for the work done under the contract.

    Therefore, the contractor was not entitled to the

    declaration sought, nor to an indemnity from the company.

    Comment

    The case shows the difficulty in limiting a contractor's

    liability against third party claims.To do so effectively in

    circumstances where the contractor takes the responsibility

    for third party claims arising from its own negligence, clearwords are required to provide the contractor with an

    indemnity from the company in respect of the amounts

    that the contractor may have to pay to the third party as a

    result of the negligent acts of the contractor.3

    Failing to use clear words to this effect would mean that

    the operation of the liability cap will depend on the

    external decision of a third party as to whether to sue the

    company or the contractor. If the third party chooses to sue

    the company and the company incurs financial loss by

    having to pay the third party claim, then the contractor will

    be protected by the liability cap. This is because the

    obligation of the contractor to indemnify the company in

    respect of such losses will constitute a "contractual liability"as opposed to a mere "responsibility". By contrast, if the

    third party chooses to sue the contractor, the contractor will

    not be able to rely on its liability cap in the absence of an

    express contractual counter-indemnity from the company.

    Arguably, the same analysis could be adopted in respect of

    "knock-for-knock" liabilities where, for example, the

    contractor's employees bring a claim against the contractor

    and not the company. In line with the above analysis (and

    putting aside any employee insurance issues), the

    contractor would not be able to rely on its liability cap

    unless a counter-indemnity from the company is expresslyincluded in the contract.

    The reference to the sophistication of the parties reinforces

    the general approach of the courts that the more

    commercially and legally experienced the parties are, the

    more emphasis will be given to the precise words of the

    contract and all the subtleties those chosen words entail.

    Notes:

    1 [2006] EWHC 1164.

    2 [2002] 1 AC 251.

    3 This reflects the principle stated in Brown -v- Drake International Ltd and

    Southampton Container Terminals [2004] EWCA Civ 1629 that an

    indemnity will not readily be given to a party against a loss caused by itsown negligence.

    This update is not intended to be a comprehensive review of all developments in the law and practice, or to cover all aspects of those referred to.Readers should take legal advice before applying the information contained in this publication to specific issues or transactions.

    For more information please contact us at Broadwalk House 5 Appold Street London EC2A 2HA Tel +44 (0)20 7638 1111 Fax +44 (0)20 7638 1112www.ashurst.com 2006 Ashurst Ref:DTP/4355 Jan 07

    Contacts

    Geoffrey Picton-Turbervill

    Head of Global Energy

    T: +44 (0)20 7859 1209

    E: [email protected]

    Ruth Jaun

    Professional Development Lawyer

    T: +44 (0)20 7859 1166E: [email protected]