ef26 risk assessment asbestos management - openshoreopenshore.managementsystem.net.au/risk...

12
0 Low Minor Moderate Major Critical L2 L3 L4 M5 M6 L3 L4 M5 M6 H7 L4 M5 M6 H7 H8 M5 M6 H7 H8 E9 M6 H7 H8 E9 E10 AS AT Monday, 1 February 2016 Asbestos Management EF26 Risk Assessment Hazards Requiring Attention: Next Review Tuesday, 31 January 2017 Total Hazards Recorded 31 Critical Risk Hazards 0 High Risk Hazards 0 Moderate Risk Hazards 17 Low Risk Hazards 14 Almost Certain Risk Matrix - Refer Procedure WHS1 Probability Negligible Unlikely Possible Likely

Upload: duongthuan

Post on 06-Jun-2018

216 views

Category:

Documents


1 download

TRANSCRIPT

Page 1: EF26 Risk Assessment Asbestos Management - Openshoreopenshore.managementsystem.net.au/Risk Assessments/EF26 Asbest… · ls Asbestos Fibre 3 5 H8 Identify suitable location for stockpiling

0

Low Minor Moderate Major Critical

L2 L3 L4 M5 M6L3 L4 M5 M6 H7L4 M5 M6 H7 H8M5 M6 H7 H8 E9M6 H7 H8 E9 E10

AS AT Monday, 1 February 2016

Asbestos ManagementEF26 Risk Assessment

Hazards Requiring Attention:

Next Review Tuesday, 31 January 2017

Total Hazards Recorded 31

Critical Risk Hazards 0

High Risk Hazards 0

Moderate Risk Hazards 17

Low Risk Hazards 14

Almost Certain

Risk Matrix - Refer Procedure WHS1

ProbabilityNegligibleUnlikelyPossibleLikely

Page 2: EF26 Risk Assessment Asbestos Management - Openshoreopenshore.managementsystem.net.au/Risk Assessments/EF26 Asbest… · ls Asbestos Fibre 3 5 H8 Identify suitable location for stockpiling

Activity Hazard

Pro

bab

ility

Co

nse

qu

ence

Ra

nki

ng

Control

Pro

bab

ility

Co

nse

qu

ence

Ra

nki

ng

Site

Pre

par

atio

n

Customers / MOP

approaching the site or

workers

3 4 H7

Erect exclusion zones

and designated

walkways for

pedestrian traffic

around

work site. Ensure that

letterbox drop

completed and nearby

resident's door

knocked.

Ensure prestart

meeting takes place

and

all staff and

subcontractors aware

of

their roles

responsibilities.Ensure

correct asbestos

signage in

place. Nominated

person to ensure that

public do not enter

work area.

2 3 M5

Asbestos Management

Inherent Risk Residual Risk

Page 3: EF26 Risk Assessment Asbestos Management - Openshoreopenshore.managementsystem.net.au/Risk Assessments/EF26 Asbest… · ls Asbestos Fibre 3 5 H8 Identify suitable location for stockpiling

Site

Pre

par

atio

n

Workers/ members of

public hit by movement

of equipment and plant

on top site.

Hit by vehicular traffic

in area.

Exposed to ACM.

Fall hazard.

Exposed to extreme

weather / exposure to

UV / thermals stress

2 5 E9

Only persons with

Asbestos training are

to take part in

asbestos modification

/ removal activities.

Review preliminary

soil screening

assessment for the

site to determine the

soil category and

excess soil

management.

Complete pre start

and hazard

identification

procedures. If

required complete

site specific WMS to

address site specific

hazards. Identify

potential hazards i.e.

extreme weather,

heat stress. Complete

an Asbestos

Removal Control

Plan for the work to

be undertaken. PPE

for task must be

used. This may

1 4 M5

Site

Pre

par

atio

n

Aggressive customers /

members of public.

Dog bite. Bite / sting

from other dangerous

fauna. Fall hazard.

3 4 E9

Follow the process

for notifying affected

residents as outlined

in the Telstra

document

“Communication

Strategy for Activity

on Telstra’s Pit and

Pipe Infrastructure”

(ARU-7102) or NBN

guidelines. Prior to

entering resident’s

property, conduct a

visual inspection of

the customer

premises to identify

potential hazards

such as dogs, waste

material and debris.

Where unrestrained

dog is identified, DO

NOT ENTER the

premises until contact

with the owner has

been achieved and

the dog has been

restrained /secured or

isolated. If resident

becomes agitated or

1 4 M5

Page 4: EF26 Risk Assessment Asbestos Management - Openshoreopenshore.managementsystem.net.au/Risk Assessments/EF26 Asbest… · ls Asbestos Fibre 3 5 H8 Identify suitable location for stockpiling

Site

Pre

par

atio

n

Exposure to dust 2 5 H7

Measure and mark

out the area to be

broken-in with a

pencil I marker so

that

breakage will be

minimised where

possible

Apply gel/paste to

marked out area on

either side of the

marked break point

(e.g. RSS

Encapsulate Gel)

1 2 L3

Site

Pre

par

atio

n

ACM - airborne fibre

release2 5 H7

Thoroughly wet down

both inside and

outside surfaces of the

ACM pit using a

hand pressure water

sprayer with a PVA

I water solution. Lay

poly sheeting inside

and outside of the pit,

lightly spray with PVA I

water solution

1 2 L3

Pit Break In Cuts and

abrasions3 4 H7

Break the pit in the

marked location

using bolster /chisel

and ball pein

hammer wearing

gloves

1 2 L3

ACM-airborne fibre

release2 3 M5

Seal the edges of the

break-in point with a

solution of PVA I water1 3 L4

Dri

llin

g In

AC

M

Breaking of ACM 2 5 H7

Measure and mark out

the area to be

broken-in with a pencil

I marker so that

breakage will be

minimised where

possible. Apply

gel/paste/ shaving

foam to marked out

area on either side of

the marked break point

(e.g. RSS Encapsulate

Gel)

Break the pit in the

marked location using

bolster /chisel and ball

pein hammer

1 5 M6

Pit Break In

Page 5: EF26 Risk Assessment Asbestos Management - Openshoreopenshore.managementsystem.net.au/Risk Assessments/EF26 Asbest… · ls Asbestos Fibre 3 5 H8 Identify suitable location for stockpiling

Dri

llin

g In

AC

M

ACM-airborne fibre

release2 5 H7

Thoroughly wet down

both inside and outside

surfaces of the ACM pit

using a water pressure

pack (knap pack) with a

PVA I water solution

Seal the edges of the

break-in point with

mortar on the inside

and outside of the pit

1 5 M6

Drilling In ACMWorking with power /

pneumatic tools3 4 H7

Allow only competent

personnel to use power

tools, pneumatic tools

should not be used.

Use only low speed

battery powered drills.

Where possible control

air

flow from the drill

1 4 M5

Exca

vati

on

- H

and

To

ols

Live Services 4 4 H8

Identify suitable

location for stockpiling

excavated soil. Place

200 micron poly

sheeting for excavated

soil to be placed on.

Tools should be

selected to minimise

the risk of striking

concrete pits resulting

in ACM debris being

released. E.g. Shovels

(non-conductive

handle) Mattocks (non-

conductive handle)

Digging Bars (non-

conductive handle – if

live electrical services

are identified) The

following PPE must be

worn by workers when

undertaking hand

digging: Protective

Gloves Protective

1 4 M5

Page 6: EF26 Risk Assessment Asbestos Management - Openshoreopenshore.managementsystem.net.au/Risk Assessments/EF26 Asbest… · ls Asbestos Fibre 3 5 H8 Identify suitable location for stockpiling

Exca

vati

on

- H

and

To

ols

Asbestos Fibre 3 5 H8

Identify suitable

location for stockpiling

excavated soil. Place

200 micron poly

sheeting for excavated

soil to be placed on.

Tools should be

selected to minimise

the risk of striking

concrete pits resulting

in ACM debris being

released. E.g. Shovels

(non-conductive

handle) Mattocks (non-

conductive handle)

Digging Bars (non-

conductive handle – if

live electrical services

are identified). If ACM

debris is identified in

the soil during digging

STOP DIGGING AND

FOLLOW THE SWMS

ACM - Waste disposal.

Do not excavate around

the pit. Refer ACM-

Break-up and removal

of pits.

1 5 M6

Exca

vati

on

-

Me

chan

ical

Plant rollover

Plant failure

Plant damage

3 5 H8

WHERE THE ITEM OF

PLANT DOES NOT

REQUIRE A LICENCE,

DO NOT OPERATE THE

PLANT UNLESS YOU

HAVE BEEN TRAINED

AND HOLD A

CERTIFICATE /

STATEMENT OF

COMPETENCY. Where

an item of plant does

not require a licence,

1 5 M6

Excavation -

MechanicalStriking workers /

MOPs 3 5 H8

Ensure that Workers

are not in proximity to

Plant when

dismounting the plant

from a truck or trailer.

Establish an exclusion

1 5 M6

Page 7: EF26 Risk Assessment Asbestos Management - Openshoreopenshore.managementsystem.net.au/Risk Assessments/EF26 Asbest… · ls Asbestos Fibre 3 5 H8 Identify suitable location for stockpiling

Exca

vati

on

- M

ech

anic

al

Striking overhead

services 3 5 H8

Undertake a visual

inspection of the work

site to identify if the

excavator’s slew range

may contact overhead

services or property. If

within 5m of overhead

electrical asset contact

your supervisor. Safety

observer/spotter shall

wear a hard hat where

required. A competent

safety observer/spotter

whose sole duty is to

monitor proximity to

overhead infrastructure

shall be engaged while

working in proximity to

infrastructure

1 5 M6

Exca

vati

on

- M

ech

anic

al

ACM-airborne fibre

release2 5 H7

Where practical, a

toothless bucket is to

be used ensuring that

the bucket safety pin is

installed.

To avoid damaging the

pit with the mechanical

plant, maintain a

minimum of 50mm

distance between the

excavation and the pit.

The remaining 50mm is

to be removed using a

hand digging method

such as a shovel once

excavator has ceased

operation whilst

wearing Asbestos

removal PPE

requirements. If

excavation results in

damage to an

underground service

immediately contact

your supervisor and

emergency services if

required. If ACM debris

is identified in the soil

1 5 M6

Page 8: EF26 Risk Assessment Asbestos Management - Openshoreopenshore.managementsystem.net.au/Risk Assessments/EF26 Asbest… · ls Asbestos Fibre 3 5 H8 Identify suitable location for stockpiling

Pit

Co

llar

Re

mo

val

ACM-airborne fibre

release2 5 H7

Only persons with a ‘B’

Class removal licence

are to take part in

asbestos modification /

removal activities.

Thoroughly wet down

both inside and outside

surfaces of the ACM pit

with PVA / water

solution using a knap

sack. Measure and

mark out a line around

the pit with a pencil /

marker where the

break is to occur so

that breakage is

minimised where

possible and: Apply

gel/paste to marked

out area on either side

of the marked break

point (e.g. RSS

Encapsulate Gel). Break

along the marked line

using bolster /chisel

and ball pein hammer

break the pit lip

inwards, so that

1 2 L3

Pit

Co

llar

Re

mo

val

Clean Up - Fibre

Release2 5 H7

Mix and lay concrete

mortar base around Pit.

Lay collar on newly laid

mortar ensuring top of

collar is level with

existing ground surface.

Place mortar / plaster

inside of pit between

bottom of collar and

top of pit ensuring no

newly broken ACM is

exposed. Lay a bed of

mortar around the

outside of the pit collar

at least 20mm high.

Wipe down the

remainder of the pit

surface with a damp

cloth and dispose of

the cloth into the ACM

disposal bag(s). Prior to

removing the poly

sheeting from the

inside and outside of

the pit, lightly spray

with water. Carefully

fold poly sheeting,

capturing any ACM

1 2 L3

Page 9: EF26 Risk Assessment Asbestos Management - Openshoreopenshore.managementsystem.net.au/Risk Assessments/EF26 Asbest… · ls Asbestos Fibre 3 5 H8 Identify suitable location for stockpiling

Site Clean UpACM-airborne fibre

release2 3 M5

Carefully fold poly

sheeting, capturing

any ACM debris. Place

the sheeting into

asbestos disposal bag.

Ensure correct

documentation

completed to track

ACM disposal

1 3 L4

De

con

tam

inat

ion

General Contamination

by ACM2 3 M5

A separate

decontamination area

shall be established by

using (where

practicable) a second

sheet of plastic for

decontamination

activities. Where this is

not possible due to

wind or restricted

access then a larger

sheet of plastic may be

used, it shall we

weighted down and

two separate areas

identified by a marked

line or similar. One area

shall be used for work

and the second area for

decontaminated items.

The decontamination

area shall be as close as

possible to the work

area.

1 3 L4

Page 10: EF26 Risk Assessment Asbestos Management - Openshoreopenshore.managementsystem.net.au/Risk Assessments/EF26 Asbest… · ls Asbestos Fibre 3 5 H8 Identify suitable location for stockpiling

De

con

tam

inat

ion

Contamination of Work

Area2 3 M5

Where pit was in close

proximity to a structure

such as a fence,

building or post box,

use a damp cloth to

wipe down the

structure. Dispose of

cloths in an asbestos

disposal bag.

Do not resoak rags in a

bucket of water as this

will contaminate the

water. Instead, fold the

rag so that a clean

surface is exposed or

use another rag. Place

contaminated rag in

asbestos waste plastic

bag.

1 3 L4

De

con

tam

inat

ion

Contamination of Tools 2 3 M5

All hand tools used

during the breaking up

of the pit and scraping

of top layer (20mm) of

soil, must be

decontaminated.

Workers involved in the

ACM removal work and

are wearing the

required PPE may

participate in

decontamination.

Stand on poly sheeting,

hand tools are wiped

down using damp

cloths (unless tool is

being disposed). Tools

placed in the dedicated

sealable container or in

an asbestos disposal

bag.

1 3 L4

De

con

tam

inat

ion

Contaminated Cloths 2 3 M5

Cloths used for

decontamination are

disposed of in an

asbestos disposal bag.

Tools placed on plastic

sheeting to prevent

contamination. Place

contaminated rag in

plastic asbestos waste

bag.

1 3 L4

Page 11: EF26 Risk Assessment Asbestos Management - Openshoreopenshore.managementsystem.net.au/Risk Assessments/EF26 Asbest… · ls Asbestos Fibre 3 5 H8 Identify suitable location for stockpiling

De

con

tam

inat

ion

Disposal of ACM Into

Bags3 3 M6

Place poly sheeting in

the excavation area to

capture any loose

pieces. Keep pieces as

large as possible and

place into double

bagged asbestos

disposal bags. If pieces

will not fit into the

asbestos disposal bags

DO NOT BREAK UP

FURTHER, double wrap

them in 200 micron

poly sheeting. a. Wrap

piece of ACM in poly

sheeting like a present

and tape up. b. Repeat

the process above, c.

Use asbestos warning

tape or other

appropriate asbestos

identifier to label the

outer layer of poly

sheeting. If it was

possible to have poly

sheeting under the

duct, lightly spray the

sheeting with water

1 3 L4

De

con

tam

inat

ion

Manual Handling -

Personal Injury4 3 H7

Do not overfill bags

beyond half full.

Make sure bags are 20-

25kg in weight. When

lifting poly sheeting or

asbestos disposal bags

that are heavy, ensure

manual handling

techniques are

followed.

2 3 M5

DecontaminationExcess Soil - Exposure

to ACM4 3 H7

All excess soil from pit

remediation works be

disposed of as if the

excess soil contains

ACM.

2 3 M5

De

con

tam

inat

ion

Vacuum Truck -

Exposure to ACM4 3 H7

If a vacuum truck

contains ACM waste

the entire contents of

the truck shall be taken

to an approved facility

for processing. At this

time a sample shall be

taken from the truck

for testing. Depending

on the outcome of the

testing waste will need

to be disposed of in the

correct manner.

2 3 M5

Page 12: EF26 Risk Assessment Asbestos Management - Openshoreopenshore.managementsystem.net.au/Risk Assessments/EF26 Asbest… · ls Asbestos Fibre 3 5 H8 Identify suitable location for stockpiling

De

con

tam

inat

ion

Transport of ACM 3 2 M5

Asbestos waste bags

shall be protected

during transport. The

load should not be

carried inside the

passenger

compartment of a

vehicle. ACM bags shall

be covered with shade

cloth and all materials

in a trailer and ute shall

be covered by a mesh

restraint (50 x 50mm

hole size). Loads up to

250 kg may be carried

in unlicensed vehicles

under the current EPA

exemption. ACM

material is to be

transported off site as

soon as reasonably

practicable. At the end

of each day if the

asbestos waste cannot

be secured at the

removal site it shall be

returned to base.

Attach location tag and

1 2 L3

Slips, trips, falls 3 3 M6

Ensure that the work

area is kept clean and

clear of debris at all

times.

2 3 M5

Manual Handling 3 3 M6Follow manual handling

training1 3 L4

Erosion /

contamination2 5 H7

Where inclement

weather is impending

then Geotextile fabric

silt barriers shall be

erected around spoils

stockpile to prevent

erosion /

contamination.

1 5 M6

Mis

cella

no

us

Task

s