Financial Management, Visibility and Controlwith Primavera
EcoSys
Christen BergerudEcoSys Financial Manager
![Page 2: EcoSys - 2008 Prim Aver a Conference Partner Pres](https://reader031.vdocuments.site/reader031/viewer/2022021200/577d22531a28ab4e1e971411/html5/thumbnails/2.jpg)
8/3/2019 EcoSys - 2008 Prim Aver a Conference Partner Pres
http://slidepdf.com/reader/full/ecosys-2008-prim-aver-a-conference-partner-pres 2/28
![Page 3: EcoSys - 2008 Prim Aver a Conference Partner Pres](https://reader031.vdocuments.site/reader031/viewer/2022021200/577d22531a28ab4e1e971411/html5/thumbnails/3.jpg)
8/3/2019 EcoSys - 2008 Prim Aver a Conference Partner Pres
http://slidepdf.com/reader/full/ecosys-2008-prim-aver-a-conference-partner-pres 3/28
Company Overview
Premier Primavera Technology Partner
EcoSys Financial Manager
Premier Primavera Service Partner
Primavera Implementation Consulting, Training, System Integration
Consulting in Support of Strategic Planning and Execution
Project Portfolio Management/PMO
Long Range Planning / Investment Management
Budgeting/Forecasting Financial Performance Management
Over 160 Customers Globally
![Page 4: EcoSys - 2008 Prim Aver a Conference Partner Pres](https://reader031.vdocuments.site/reader031/viewer/2022021200/577d22531a28ab4e1e971411/html5/thumbnails/4.jpg)
8/3/2019 EcoSys - 2008 Prim Aver a Conference Partner Pres
http://slidepdf.com/reader/full/ecosys-2008-prim-aver-a-conference-partner-pres 4/28
Solution Overview
Whats the secret of a successful Primavera
implementation?
![Page 5: EcoSys - 2008 Prim Aver a Conference Partner Pres](https://reader031.vdocuments.site/reader031/viewer/2022021200/577d22531a28ab4e1e971411/html5/thumbnails/5.jpg)
8/3/2019 EcoSys - 2008 Prim Aver a Conference Partner Pres
http://slidepdf.com/reader/full/ecosys-2008-prim-aver-a-conference-partner-pres 5/28
Solution Overview
Whats the secret of a successful Primavera
implementation?
U
ser Adoption
![Page 6: EcoSys - 2008 Prim Aver a Conference Partner Pres](https://reader031.vdocuments.site/reader031/viewer/2022021200/577d22531a28ab4e1e971411/html5/thumbnails/6.jpg)
8/3/2019 EcoSys - 2008 Prim Aver a Conference Partner Pres
http://slidepdf.com/reader/full/ecosys-2008-prim-aver-a-conference-partner-pres 6/28
Solution Overview
Whats the secret of a successful Primavera
implementation?
U
ser Adoption Requires good implementation strategy (good design, phased
rollouts, quality training, support, and oversight)
![Page 7: EcoSys - 2008 Prim Aver a Conference Partner Pres](https://reader031.vdocuments.site/reader031/viewer/2022021200/577d22531a28ab4e1e971411/html5/thumbnails/7.jpg)
8/3/2019 EcoSys - 2008 Prim Aver a Conference Partner Pres
http://slidepdf.com/reader/full/ecosys-2008-prim-aver-a-conference-partner-pres 7/28
Solution Overview
Whats the secret of a successful Primavera
implementation?
U
ser Adoption Requires good implementation strategy (good design, phased
rollouts, quality training, support, and oversight)
Success virtually assured when Primavera becomes highly
relevant to senior management
![Page 8: EcoSys - 2008 Prim Aver a Conference Partner Pres](https://reader031.vdocuments.site/reader031/viewer/2022021200/577d22531a28ab4e1e971411/html5/thumbnails/8.jpg)
8/3/2019 EcoSys - 2008 Prim Aver a Conference Partner Pres
http://slidepdf.com/reader/full/ecosys-2008-prim-aver-a-conference-partner-pres 8/28
Solution Overview
Whats the secret of a successful Primavera
implementation?
U
ser Adoption Requires good implementation strategy (good design, phased
rollouts, quality training, support, and oversight)
Success virtually assured when Primavera becomes highly
relevant to senior management Business decisions driven by project data
Integration with core business processes such as strategic
planning and budgeting
Executive visibility into all projects and operations
![Page 9: EcoSys - 2008 Prim Aver a Conference Partner Pres](https://reader031.vdocuments.site/reader031/viewer/2022021200/577d22531a28ab4e1e971411/html5/thumbnails/9.jpg)
8/3/2019 EcoSys - 2008 Prim Aver a Conference Partner Pres
http://slidepdf.com/reader/full/ecosys-2008-prim-aver-a-conference-partner-pres 9/28
Solution Overview
Financial Manager integrates Primavera into core
financial processes
JustifyDepartmentalBudget Basedupon Projects
and Operations
![Page 10: EcoSys - 2008 Prim Aver a Conference Partner Pres](https://reader031.vdocuments.site/reader031/viewer/2022021200/577d22531a28ab4e1e971411/html5/thumbnails/10.jpg)
8/3/2019 EcoSys - 2008 Prim Aver a Conference Partner Pres
http://slidepdf.com/reader/full/ecosys-2008-prim-aver-a-conference-partner-pres 10/28
Solution Overview
Financial Manager integrates Primavera into core
financial processes
JustifyDepartmentalBudget Basedupon Projects
and Operations
which are aligned tostrategic spending
targets
![Page 11: EcoSys - 2008 Prim Aver a Conference Partner Pres](https://reader031.vdocuments.site/reader031/viewer/2022021200/577d22531a28ab4e1e971411/html5/thumbnails/11.jpg)
8/3/2019 EcoSys - 2008 Prim Aver a Conference Partner Pres
http://slidepdf.com/reader/full/ecosys-2008-prim-aver-a-conference-partner-pres 11/28
Solution Overview
Financial Manager provides total financial visibility
Drill down from divisionto project, to account, to
transaction
![Page 12: EcoSys - 2008 Prim Aver a Conference Partner Pres](https://reader031.vdocuments.site/reader031/viewer/2022021200/577d22531a28ab4e1e971411/html5/thumbnails/12.jpg)
8/3/2019 EcoSys - 2008 Prim Aver a Conference Partner Pres
http://slidepdf.com/reader/full/ecosys-2008-prim-aver-a-conference-partner-pres 12/28
Solution Overview
Primavera provides world-class:
Scheduling
Resource Management
Contract Management
Portfolio Management
![Page 13: EcoSys - 2008 Prim Aver a Conference Partner Pres](https://reader031.vdocuments.site/reader031/viewer/2022021200/577d22531a28ab4e1e971411/html5/thumbnails/13.jpg)
8/3/2019 EcoSys - 2008 Prim Aver a Conference Partner Pres
http://slidepdf.com/reader/full/ecosys-2008-prim-aver-a-conference-partner-pres 13/28
Solution Overview
Primavera provides world-class:
Scheduling
Resource Management
Contract Management
Portfolio Management
Not optimized for:
Financial Management
![Page 14: EcoSys - 2008 Prim Aver a Conference Partner Pres](https://reader031.vdocuments.site/reader031/viewer/2022021200/577d22531a28ab4e1e971411/html5/thumbnails/14.jpg)
8/3/2019 EcoSys - 2008 Prim Aver a Conference Partner Pres
http://slidepdf.com/reader/full/ecosys-2008-prim-aver-a-conference-partner-pres 14/28
Solution Overview
The Language of Scheduling:
After leveling the resources,I realized that wed need
to put a Start on or After
constraint onto the first
activity in that WBS and
apply a resource curve.
![Page 15: EcoSys - 2008 Prim Aver a Conference Partner Pres](https://reader031.vdocuments.site/reader031/viewer/2022021200/577d22531a28ab4e1e971411/html5/thumbnails/15.jpg)
8/3/2019 EcoSys - 2008 Prim Aver a Conference Partner Pres
http://slidepdf.com/reader/full/ecosys-2008-prim-aver-a-conference-partner-pres 15/28
Solution Overview
The Language of Finance:
Ah, so a 2% decrease incapitalized internal labor
in October?
![Page 16: EcoSys - 2008 Prim Aver a Conference Partner Pres](https://reader031.vdocuments.site/reader031/viewer/2022021200/577d22531a28ab4e1e971411/html5/thumbnails/16.jpg)
8/3/2019 EcoSys - 2008 Prim Aver a Conference Partner Pres
http://slidepdf.com/reader/full/ecosys-2008-prim-aver-a-conference-partner-pres 16/28
Solution Overview
Integrating Corporate Finance and Planning Processeswith Project Management
![Page 17: EcoSys - 2008 Prim Aver a Conference Partner Pres](https://reader031.vdocuments.site/reader031/viewer/2022021200/577d22531a28ab4e1e971411/html5/thumbnails/17.jpg)
8/3/2019 EcoSys - 2008 Prim Aver a Conference Partner Pres
http://slidepdf.com/reader/full/ecosys-2008-prim-aver-a-conference-partner-pres 17/28
Solution Overview
Runs on any browser
Oracle / SQ L Server Database
Fully integrated with Primavera through API : all costsand units import from Primavera
![Page 18: EcoSys - 2008 Prim Aver a Conference Partner Pres](https://reader031.vdocuments.site/reader031/viewer/2022021200/577d22531a28ab4e1e971411/html5/thumbnails/18.jpg)
8/3/2019 EcoSys - 2008 Prim Aver a Conference Partner Pres
http://slidepdf.com/reader/full/ecosys-2008-prim-aver-a-conference-partner-pres 18/28
Solution Overview
Main users
Executives
Finance, Financial Planning and Analysis, Departmental Finance
Portfolio Managers, Investment Managers, Capital Budgeting Division, Department Managers
Program/Project Managers, Project Cost Analysts
PMOs
![Page 19: EcoSys - 2008 Prim Aver a Conference Partner Pres](https://reader031.vdocuments.site/reader031/viewer/2022021200/577d22531a28ab4e1e971411/html5/thumbnails/19.jpg)
8/3/2019 EcoSys - 2008 Prim Aver a Conference Partner Pres
http://slidepdf.com/reader/full/ecosys-2008-prim-aver-a-conference-partner-pres 19/28
Value Pr oposition
Drive budgeting and strategic planning from projects
and initiatives
Integrated project cost management Budgeting/funding
Forecasting
Performance Reporting
Financial Visibility
Financial Controls
![Page 20: EcoSys - 2008 Prim Aver a Conference Partner Pres](https://reader031.vdocuments.site/reader031/viewer/2022021200/577d22531a28ab4e1e971411/html5/thumbnails/20.jpg)
8/3/2019 EcoSys - 2008 Prim Aver a Conference Partner Pres
http://slidepdf.com/reader/full/ecosys-2008-prim-aver-a-conference-partner-pres 20/28
Value Pr oposition
Return on Investment
Reduced errors
Government agency under-requested $20MM due to an Excel
spreadsheet error.
Bank underreported IT spending by $18 MM.
Catch project overruns in advance
Global Manufacturer reduces $80MM in capital project
overruns by 4% in first year
Time Savings
Automates financial management processes previously
performed in Excel & MS Access
Expedites financial processes (budgeting, capitalization,
financial closes, regulatory compliance)
![Page 21: EcoSys - 2008 Prim Aver a Conference Partner Pres](https://reader031.vdocuments.site/reader031/viewer/2022021200/577d22531a28ab4e1e971411/html5/thumbnails/21.jpg)
8/3/2019 EcoSys - 2008 Prim Aver a Conference Partner Pres
http://slidepdf.com/reader/full/ecosys-2008-prim-aver-a-conference-partner-pres 21/28
Industry Representative Customer
Public
Sector
Utilities
Aerospace/
Defense
Financial
Technology
Target Markets
![Page 22: EcoSys - 2008 Prim Aver a Conference Partner Pres](https://reader031.vdocuments.site/reader031/viewer/2022021200/577d22531a28ab4e1e971411/html5/thumbnails/22.jpg)
8/3/2019 EcoSys - 2008 Prim Aver a Conference Partner Pres
http://slidepdf.com/reader/full/ecosys-2008-prim-aver-a-conference-partner-pres 22/28
Customer Success Stories
Customer Business Area Highlights
Capital Programs Annual Budgeting
5 Year Budgeting
Program Cost
Management
Financial Management
integrated with P6
Engineering Division 5 Year Planning
integrated with Primavera
Funds Management
Performance Reporting
IT Project and Core
Operations Financials
Integrated with
Primavera and Oracle
Budgeting and
Forecasting
Capitalization
Financial Controls and
Reporting
![Page 23: EcoSys - 2008 Prim Aver a Conference Partner Pres](https://reader031.vdocuments.site/reader031/viewer/2022021200/577d22531a28ab4e1e971411/html5/thumbnails/23.jpg)
8/3/2019 EcoSys - 2008 Prim Aver a Conference Partner Pres
http://slidepdf.com/reader/full/ecosys-2008-prim-aver-a-conference-partner-pres 23/28
Customer Success Stories
Fiscal BudgetsDriven by Primavera
Schedules
Budgeting
![Page 24: EcoSys - 2008 Prim Aver a Conference Partner Pres](https://reader031.vdocuments.site/reader031/viewer/2022021200/577d22531a28ab4e1e971411/html5/thumbnails/24.jpg)
8/3/2019 EcoSys - 2008 Prim Aver a Conference Partner Pres
http://slidepdf.com/reader/full/ecosys-2008-prim-aver-a-conference-partner-pres 24/28
Customer Success Stories
Project Cost Management
Compare Program Costsagainst Prior Versions
![Page 25: EcoSys - 2008 Prim Aver a Conference Partner Pres](https://reader031.vdocuments.site/reader031/viewer/2022021200/577d22531a28ab4e1e971411/html5/thumbnails/25.jpg)
8/3/2019 EcoSys - 2008 Prim Aver a Conference Partner Pres
http://slidepdf.com/reader/full/ecosys-2008-prim-aver-a-conference-partner-pres 25/28
Customer Success Stories
Financial Reporting
![Page 26: EcoSys - 2008 Prim Aver a Conference Partner Pres](https://reader031.vdocuments.site/reader031/viewer/2022021200/577d22531a28ab4e1e971411/html5/thumbnails/26.jpg)
8/3/2019 EcoSys - 2008 Prim Aver a Conference Partner Pres
http://slidepdf.com/reader/full/ecosys-2008-prim-aver-a-conference-partner-pres 26/28
Customer Success Stories
MonthlyFinancialCloseout
Syncs withPrimavera
Project Codes
Fiscal YearBudgeting
Capitaland
ExpenseTracking
Financial Controls and Visibility
![Page 27: EcoSys - 2008 Prim Aver a Conference Partner Pres](https://reader031.vdocuments.site/reader031/viewer/2022021200/577d22531a28ab4e1e971411/html5/thumbnails/27.jpg)
8/3/2019 EcoSys - 2008 Prim Aver a Conference Partner Pres
http://slidepdf.com/reader/full/ecosys-2008-prim-aver-a-conference-partner-pres 27/28
Customer Success Stories
A mtrakFunding
OtherPeoplesMoney
Funds Management
![Page 28: EcoSys - 2008 Prim Aver a Conference Partner Pres](https://reader031.vdocuments.site/reader031/viewer/2022021200/577d22531a28ab4e1e971411/html5/thumbnails/28.jpg)
8/3/2019 EcoSys - 2008 Prim Aver a Conference Partner Pres
http://slidepdf.com/reader/full/ecosys-2008-prim-aver-a-conference-partner-pres 28/28
THANK YOU