E.Clément Novembre 2011 E.Clément GANIL AGATA Days February 2013

AGATA Campaign at GANIL

Setup to be integrated

AGATA@GANIL: Project Organization and Planning

Status of the installation

E.Clément Novembre 2011

Charged particle array for transfer reaction MUST2/TIARA : (d,p) etc … program with SIB and RIB

Charged particle array for prompt tagging : DIAMANT Neutron detector (Nwall) Charged particle array for Recoil Decay Tagging : MUSETT

Scintillator : BaF2 array, LaBr3 Future detector : NEDA (n) , GASPARD ( ?), PARIS (LaBr3)

In G1 coupled to VAMOS (+ EXOGAM2): SIBs, RIBs

AGATA 1p at GANIL : Ancillary devices

At 0° as separator (vaccum/gas-filled)

Angles >10 deg for fission & MNT

E.Clément GANIL AGATA Days February 2013

E.Clément Novembre 2011

VAMOS(disp); 20; 29%

VAMOS(gfm); 15; 21%

VAMOS(foc); 2; 3%

NWALL; 18; 26%

DSSD; 11; 16%

DIAMANT Solo; 2; 3% MUST2; 1; 1% AGATA solo; 1; 1% VAMOS(disp)

VAMOS(gfm)

VAMOS(foc)

NWALL

DSSD

DIAMANT Solo

MUST2

AGATA solo

plunger; 16; 19%

spectro; 70; 81%

plunger

spectro

E.Clément GANIL AGATA Days February 2013

o We have received 47 Letters of Intents

o The equivalent of ~2006 UT are proposed 16048 hours of beam on target (669 days)o 4 main setups

o Vamos in magnetic spectrometero Vamos in gas-filledo Nwall + Diamanto DSSSD

We need to organize sub-campaigns by setup and investigate the technical issues case by case : Working Group, leader to be identified during the workshopPlanning of upgrade of some ancillaries (gas-filled, NWALL, DIAMANT)

AGATA will increase in efficiency during the campaignNot all experiments will benefit from the 1p

E.Clément Novembre 2011

100Mo; 3; 4% 120Sn; 1; 1%164Dy; 2;

3%

170Er; 1; 1%

176Yb; 1; 1%

181Ta; 1; 1%

198Pt; 1; 1%

208,207,206Pb; 1; 1%

238U; 11; 16%

24Mg; 2; 3%28Si; 2; 3%

45Sc; 1; 1%46Ti; 1; 1%

40Ca; 2; 3%48Ca; 3; 4%50Cr; 3; 4%54,56Fe; 2; 3%58Ni; 3; 4%

70Zn; 10; 14%

76Ge; 3; 4%

6,7Li; 2; 3%93Nb; 2; 3%

96,94Zr; 1; 1%

9Be; 3; 4%

H; 3; 4%

150,154Sm; 1; 1% 160Gd; 2; 3% 2; 3%

12C 100Mo

120Sn 164Dy

170Er 176Yb

181Ta 198Pt

208,207,206Pb 238U

24Mg 28Si

45Sc 46Ti

40Ca 48Ca

50Cr 54,56Fe

58Ni 70Zn

76Ge 6,7Li

93Nb 96,94Zr

9Be H

150,154Sm 160GdTarget

208Pb; 4; 6%136Xe; 4; 6%

18,19O; 2; 3%22,26,27Mg;

3; 4%

238U; 13; 18%

25Na; 2; 3%

28Si; 2; 3%

32,36S; 2; 3%33,36,40,44,45Ar; 8; 11%

37Cl; 1; 1%38m,45K; 2;

3%

40,48Ca; 12; 17%

50Ti; 3; 4%

54Fe; 4; 6%

58Ni; 5; 7%

76,78,86Kr; 4; 6% 92Mo; 1; 1%208Pb

136Xe

18,19O

22,26,27Mg

238U

25Na

28Si

32,36S

33,36,40,44,45Ar

37Cl

38m,45K

40,48Ca

50Ti

54Fe

58Ni

76,78,86Kr

92MoBeamE.Clément GANIL AGATA Days February 2013

GANIL cannot produce all of them : Metallic 238U 48Ca target is a challenge Plunger Target Joa’s talk To be discussed within the Working Group

You might be invited to provide expensive isotopes for the accelerator (48Ca, 70Zn…)

GANIL have some limitation for low beam energy40,48Ca and 56Ni beams issues to be discussed in the WG

CSS1; 45; 74%

CSS2; 1; 2%

SPI-RAL1 new;

6; 10%

SPI-RAL1 exis-tant;

9; 15%

CSS1

CSS2

SPIRAL1 new

SPIRAL1 existant

E.Clément Novembre 2011 E.Clément GANIL Scientific Council February 2013

EXOGAM, LaBr3, BaF2 …

AGATA Configurations at GANILE

. Farnea et al, N

uclear Instruments and

Methods in P

hysics Research A

621 (2010) 331–343

See Johan’s talk

E.Clément Novembre 2011

Local organization doneTasks distribution and their detailed description were distributedGANIL project :

Set of spec delivered, detailed planning, resources evaluation, budget, development plan, PBS, WBS distributed

Security/safety : Installation description for DIRC01 :

1st draft released, risk analysis beginning of 2013

The call for tender, to be launched by May 2013 after GANIL management review, are under preparation

Specific infrastructure to be delivered in December 2013

In 2012, ~4 FTE have worked on the project (20 persons involved at GANIL)For 2013-2014, ~80 m.month are evaluated

Organisation

E.Clément GANIL AGATA Days February 2013

E.Clément Novembre 2011

Schedule (assuming that material from GSI arrive on Jan-Feb 2014)

Gas-filled installation expected in mid-2015 if funded in 2013 GANISOL beams available for physics beginning of 2016 No SPIRAL1 beam in 2014-2015

GANIL has requested the host of AGATA until end of 2016

T2-12 T3-12 T4-12 T1-13 T2-13 T3-13 T4-13 T1-14 T2-14 T3-14 T4-14 … T4-16

                       

Mechanics   STFC Design  

GANIL Impl   

IPHC construc  

Mounting         

Infrastructure det    

GANIL Studies    

Collecting items    

Installation       

LN2, AF   

GANIL Studies     Collecting items

Installation Test       

DAQ Hardware   

GANIL Studies    

Collecting items  

Installation Test       

DAQ Software         

Prep.   

Test       

Processing Room      

Renov Aire Proj   AGATA 

infra              

Detector             

  Mounting       

Source & Commi                          Expt                       …  

E.Clément GANIL AGATA Days February 2013

E.Clément Novembre 2011 E.Clément GANIL AGATA Days February 2013

E.Clément Novembre 2011

~150 k€

~17k€

Processing room 019Upgrade ~ 102k€

Detector lab infrastructure ~15 k€

Cryogenic upgrade, connection ~25 k€

Total investment cost ~380 k€

Optical fibers links ~70k€

E.Clément GANIL AGATA Days February 2013

E.Clément Novembre 2011

Budget : Total cost investment ~380k€

237 k€ guaranteed by GANIL for 2013 to be completed in the 2014 request

IPHC requested 90k€ from IN2P3-AP for the mechanic

ANR (French Research Funding Agency) request for the gas-filled mode submitted by the Saclay and GANIL group (PI : Ch. Theisen & Ch. Schmitt)

Loan of material from LNL & GSI (cooled cabinet, racks, water distribution, Optical link) under evaluation

E.Clément GANIL AGATA Days February 2013

E.Clément Novembre 2011

Detectors support design done by STFC Daresbury in close collaboration with GANIL GANIL designs the additional platform GANIL takes in charge the integration work Projection T1 -2013 9 months of construction estimated starting by T1-2013

On-going collaboration with the IPHC workshop for the construction of the support

Workshop for the extended platform not yet defined

I. Burrows (STFC) M. Ozille, P. Gangnant (GANIL)

Mechanic

E.Clément GANIL AGATA Days February 2013

E.Clément Novembre 2011 I. Burrows (STFC) M. Ozille (GANIL) G. Gaudiot (IPHC)

Mechanic

First 2D projections have been released in January On-going validation and fine cost estimate Mechanical stress and rigidity calculations validated

E.Clément GANIL AGATA Days February 2013

E.Clément Novembre 2011 M. Ozille (GANIL)

Mechanic

E.Clément GANIL AGATA Days February 2013

E.Clément Novembre 2011

M. Ozille, P. Gangnant, G. Fremont (GANIL)

GANIL is in charge of the beam section and target chamber design for most of the experiment

Specific configurations will be treated case by case

Target loader :Detailed design on going by GANILFinal decision will be taken after the workshop

Target loader and beam line

E.Clément GANIL AGATA Days February 2013

VAMOS(disp); 20; 29%

VAMOS(gfm); 15; 21%

VAMOS(foc); 2; 3%

NWALL; 18; 26%

DSSD; 11; 16%

DIAMANT Solo; 2; 3%MUST2; 1; 1%AGATA solo; 1; 1%

E.Clément Novembre 2011

Salle G1

AGATA

EXOGAM Elec.

AGATA Elec.

DSS

300 optical wires

Water cooling 26° 8 bars

27 kW UPS

L. Menager, J. Ropert, JL. Foucher (GANIL)

Integration

Cryogenic distribution

E.Clément GANIL AGATA Days February 2013

E.Clément Novembre 2011

L. Menager, M. Jean , N. Menard (GANIL)

The foreseen room required important investment (refurbishment, electricity, water cooling, air conditioning …)

G1 cave

Integration

E.Clément GANIL AGATA Days February 2013

E.Clément Novembre 2011

Performance simulations : on-going (see Johan’s talk)

Electronic coupling: on-going (several meeting already done, transfer of knowledge in GSI during 2013)

Detector: starting (transfer of knowledge in GSI during 2013)

Data flow, DAQ: on-going (several meeting already done, no problem anticipated)

Mechanic design : on-going (final design review)

Optical link : on-going (Call for tender expected by April)

Data analysis : starting (first meeting on the first week of Dec.)

AutoFill-cryogenic : on-going (definition of the installation, call for tender in April)

Infrastructure : on-going (final design review on going)

E.Clément GANIL AGATA Days February 2013

E.Clément Novembre 2011

Conclusion Physics objectives will be presented at the next CS for evaluation (Campaign definition) Sub-campaigns to be discussed and adjusted with upgrade planning

2014-mid 2015 : AGATA-VAMOS+ “light” ancillary2015 : gas-filled, NWALL2016 : SPIRAL1 beams

The AGATA project at GANIL made progress in all different items with a particular attention on the mechanic and the integration

The transfer of knowledge on detectors and electronic will be organized in 2013 during off and on-beam period at GSI with GANIL technical staff.

Mechanical construction should start soon, delivery by end of 2013

Call for tender are expected to be sent by May 2013 for infrastructure

Data Acquisition and Data analysis preparation will progress over 2013

GANIL technical involvement is already significant

Budget guaranteed by GANIL for 2013 to be completed in the 2014 request