echowater project - regional san...• project includes: bulk chemical storage, chemical building...

43
Sacramento Regional County Sanitation District EchoWater Project Contractor Open House January 14, 2014 Vick Kyotani – Program Manager

Upload: others

Post on 10-Oct-2020

2 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: EchoWater Project - Regional San...• Project includes: bulk chemical storage, chemical building with day tanks and feed pumps, control systems, and piping and injection facilities

Sacramento Regional County Sanitation District

EchoWater Project Contractor Open House

January 14, 2014

Vick Kyotani – Program Manager

Page 2: EchoWater Project - Regional San...• Project includes: bulk chemical storage, chemical building with day tanks and feed pumps, control systems, and piping and injection facilities

Sacramento Regional County Sanitation District

Agenda • Welcome, Introductions and Purpose of the Meeting (Ruben) • Overview of EchoWater Project (Vick) • Project Details (Rob)

• Project Descriptions • Schedules/Costs (tabular form)

• Overall Site (Jill) • Plant Access and Security • Project Features • Construction Workforce

• Project Interfaces (Dan) • Procurement Alternatives (Pervaiz) • 3-D Design (Bob) • Contractor Input

Page 3: EchoWater Project - Regional San...• Project includes: bulk chemical storage, chemical building with day tanks and feed pumps, control systems, and piping and injection facilities

Sacramento Regional County Sanitation District

Overview

Page 4: EchoWater Project - Regional San...• Project includes: bulk chemical storage, chemical building with day tanks and feed pumps, control systems, and piping and injection facilities

Sacramento Regional County Sanitation District

Plant Layout for the Future

• Planning for build-out conditions (350 MGD ADWF) • EchoWater Project design is for 181 MGD ADWF • Reserve Areas for the Solids Processing Facilities • Minimize use of the Bufferlands Areas • Plan for the South County Reuse Project

Page 5: EchoWater Project - Regional San...• Project includes: bulk chemical storage, chemical building with day tanks and feed pumps, control systems, and piping and injection facilities

Sacramento Regional County Sanitation District

SRWTP Planned Layout at Buildout

FOG Facility

Dwight Road Extension

Future Secondary Clarifiers

BNR

Future Digesters

Future Primary Clarifiers

Future BNR

Filters

Future Disinfection

Filter Influent Pumping Station (FIPS)

Future Filters

Reserve for Heavy Equipment Maintenance, Bufferlands Storage, and Other Uses

Harvest Crew Building

Future FIPS

ESB-C

ESB-D

Future ESB-F

Primary Effluent Pumping Station

Future Thickener

Disinfection

Page 6: EchoWater Project - Regional San...• Project includes: bulk chemical storage, chemical building with day tanks and feed pumps, control systems, and piping and injection facilities

Sacramento Regional County Sanitation District

Current Projects

• BNR Activated Sludge • Primary Effluent Pumping Station • RAS Pumping System • Flow Equalization Basins • Site Preparation (Utilities, Staging, On-site Roads) • Chemical Storage and Feed System (early conversion

to liquid disinfection) • Filtration & Filter Pump Station

Page 7: EchoWater Project - Regional San...• Project includes: bulk chemical storage, chemical building with day tanks and feed pumps, control systems, and piping and injection facilities

Sacramento Regional County Sanitation District

Current Projects (cont.) • Disinfection Contact Basin • Nitrifying Sidestream Treatment • Main Electrical Switchgear Expansion • Building Relocations (Bufferlands, Harvest Crew,

CMID, PMO and Heavy Maintenance)

Page 8: EchoWater Project - Regional San...• Project includes: bulk chemical storage, chemical building with day tanks and feed pumps, control systems, and piping and injection facilities

Sacramento Regional County Sanitation District

EchoWater Project Layout

Page 9: EchoWater Project - Regional San...• Project includes: bulk chemical storage, chemical building with day tanks and feed pumps, control systems, and piping and injection facilities

Sacramento Regional County Sanitation District

Program Schedule

Page 10: EchoWater Project - Regional San...• Project includes: bulk chemical storage, chemical building with day tanks and feed pumps, control systems, and piping and injection facilities

Sacramento Regional County Sanitation District

Project Design Procurement Status

Project RFP Release Date Contract Approved

BNR Closed January 23, 2013 Reliability Centered Design Services Closed August 14, 2013 Flow Equalization Closed August 28, 2013 New Facilities-Bufferlands, Harvest Crew, Heavy Equipment Buildings

Closed September 25, 2013

Primary Effluent Pumping Station Closed October 23, 2013 RAS Pumping System Closed November 13, 2013 Site Preparation Closed December 11, 2013 Disinfection Chemical Storage Closed December 11, 2013 Nitrifying Sidestream Treatment December 14, 2013 March 26 , 2014 (est.) Effluent Filtration TBD Filter Influent Pumping Station TBD Disinfection Contact Basin TBD CO Tanks Conversion TBD

Page 11: EchoWater Project - Regional San...• Project includes: bulk chemical storage, chemical building with day tanks and feed pumps, control systems, and piping and injection facilities

Sacramento Regional County Sanitation District

Construction

• 12 Design Projects (may combine and add projects) • Project Construction Values: from $4 M to $420 M • Total Estimated Construction Cost: $1.12 B (escalated to

construction mid-points)

Page 12: EchoWater Project - Regional San...• Project includes: bulk chemical storage, chemical building with day tanks and feed pumps, control systems, and piping and injection facilities

Sacramento Regional County Sanitation District

Period of Intense Construction

Page 13: EchoWater Project - Regional San...• Project includes: bulk chemical storage, chemical building with day tanks and feed pumps, control systems, and piping and injection facilities

Sacramento Regional County Sanitation District

Projects Details

Page 14: EchoWater Project - Regional San...• Project includes: bulk chemical storage, chemical building with day tanks and feed pumps, control systems, and piping and injection facilities

EchoWater Project

• OCIP • PMIS (web-based) • Stringent P6 Scheduling

Requirements • Materials Testing

– Onsite District Lab – Supplement where

necessary

Page 15: EchoWater Project - Regional San...• Project includes: bulk chemical storage, chemical building with day tanks and feed pumps, control systems, and piping and injection facilities

Sacramento Regional County Sanitation District

Flow Equalization Project • Additional 80 MG Storage • Two Pumping Stations –

Washdown water supply and groundwater control

• Concrete Lining • Washdown System • Large Fill/Drain Piping • BNR Mass Excavation • Construction cost ~

$129 M

Flow Equalization Project

ESB-D

ESB-B

ESB-A

BNR/PEPS

Page 16: EchoWater Project - Regional San...• Project includes: bulk chemical storage, chemical building with day tanks and feed pumps, control systems, and piping and injection facilities

Sacramento Regional County Sanitation District

Flow Equalization Basins

• Design complete Dec 2014 • Contractor NTP March 2015

Page 17: EchoWater Project - Regional San...• Project includes: bulk chemical storage, chemical building with day tanks and feed pumps, control systems, and piping and injection facilities

Sacramento Regional County Sanitation District

Biological Nutrient Removal Facility

Page 18: EchoWater Project - Regional San...• Project includes: bulk chemical storage, chemical building with day tanks and feed pumps, control systems, and piping and injection facilities

Sacramento Regional County Sanitation District

Biological Nutrient Removal

• Project includes PEPS • Design Complete ~

August 2015 • Contractor NTP ~

February 2016

Page 19: EchoWater Project - Regional San...• Project includes: bulk chemical storage, chemical building with day tanks and feed pumps, control systems, and piping and injection facilities

Sacramento Regional County Sanitation District

Primary Effluent PS • Constructed with BNR • 330 MGD capacity • Primary effluent (PE) channel • Two enclosed wet wells • Electrical building • Relocate dual 72-inch PE

diversion lines • New 84-inch final effluent

diversion • Odor control facilities • Construction cost~$42 M

Page 20: EchoWater Project - Regional San...• Project includes: bulk chemical storage, chemical building with day tanks and feed pumps, control systems, and piping and injection facilities

Sacramento Regional County Sanitation District

Primary Effluent PS

Page 21: EchoWater Project - Regional San...• Project includes: bulk chemical storage, chemical building with day tanks and feed pumps, control systems, and piping and injection facilities

Sacramento Regional County Sanitation District

Site Preparation Project Features • Contractor/CM Complexes • Internal Plant Roadways • Utilities and Process Piping

Installations and Relocations • Security Access Facility • SRWTP Site Cleanup • Grit Landfill Removal • Building Demolition • Utility Abandonment Construction Costs: $40M Design complete Nov. 2014 Contractor NTP Feb. 2015

Page 22: EchoWater Project - Regional San...• Project includes: bulk chemical storage, chemical building with day tanks and feed pumps, control systems, and piping and injection facilities

Sacramento Regional County Sanitation District

Return Activated Sludge Pumping • Replace 48 RAS pumps to

meet the BNR’s higher head requirements.

• Rehabilitate pump cans and RAS piping

• Design Complete ~ February 2016

• Contractor NTP ~ July 2016

• Project Cost $29.3M

Page 23: EchoWater Project - Regional San...• Project includes: bulk chemical storage, chemical building with day tanks and feed pumps, control systems, and piping and injection facilities

Sacramento Regional County Sanitation District

Filter Influent PS / Filtration • 330 MGD capacity • FIPS pumps to three Granular Media

Filter Batteries • Backwash Equalization and

Treatment Facilities • Chemical Feed Systems • Tertiary Control Building • Construction cost ~ $323 M • Design complete ~

February 2017 • Contractor NTP ~

TBD

Page 24: EchoWater Project - Regional San...• Project includes: bulk chemical storage, chemical building with day tanks and feed pumps, control systems, and piping and injection facilities

Sacramento Regional County Sanitation District

Filter Section

Page 25: EchoWater Project - Regional San...• Project includes: bulk chemical storage, chemical building with day tanks and feed pumps, control systems, and piping and injection facilities

Sacramento Regional County Sanitation District

Nitrifying Sidestream Treatment (NST) • Facility Treats SSB overflow

and BRF return • Nitrifying Sequencing Batch

Reactor • NST Influent and Effluent

Pumping • Lime Addition • Construction cost ~ $28.5 M • Design Complete ~ July 2015 • Contractor NTP ~ December

2015

Page 27: EchoWater Project - Regional San...• Project includes: bulk chemical storage, chemical building with day tanks and feed pumps, control systems, and piping and injection facilities

Sacramento Regional County Sanitation District

Disinfection Chemical Storage

Page 29: EchoWater Project - Regional San...• Project includes: bulk chemical storage, chemical building with day tanks and feed pumps, control systems, and piping and injection facilities

Sacramento Regional County Sanitation District

Building Relocations

• Harvest Crew and Bufferlands Staff Buildings to be Relocated • Design Complete ~ May 2014 • Contractor NTP ~ July 2014 • Construction Cost ~ $8.8 M

Page 30: EchoWater Project - Regional San...• Project includes: bulk chemical storage, chemical building with day tanks and feed pumps, control systems, and piping and injection facilities

Sacramento Regional County Sanitation District

Overall Site

Page 31: EchoWater Project - Regional San...• Project includes: bulk chemical storage, chemical building with day tanks and feed pumps, control systems, and piping and injection facilities

Sacramento Regional County Sanitation District

Plant Access and Security

• Dwight Road • New Security Facility • Existing Construction

Access – Sims Road

Page 32: EchoWater Project - Regional San...• Project includes: bulk chemical storage, chemical building with day tanks and feed pumps, control systems, and piping and injection facilities

Sacramento Regional County Sanitation District

Project Features

• Contractor/CM Field Office Complex

• Contractor Laydown • Excavations, Hauling

– Scraper Route Provisions

• Onsite Traffic

Page 33: EchoWater Project - Regional San...• Project includes: bulk chemical storage, chemical building with day tanks and feed pumps, control systems, and piping and injection facilities

Sacramento Regional County Sanitation District

Construction Workforce

• Forecasted Peak Construction Workforce

• Concurrent Projects • Contractor Site Access,

Parking, Deliveries

Page 34: EchoWater Project - Regional San...• Project includes: bulk chemical storage, chemical building with day tanks and feed pumps, control systems, and piping and injection facilities

Sacramento Regional County Sanitation District

Project Interfaces

Page 35: EchoWater Project - Regional San...• Project includes: bulk chemical storage, chemical building with day tanks and feed pumps, control systems, and piping and injection facilities

Sacramento Regional County Sanitation District

• Operating Plant – Construction Traffic vs.

Operations Traffic

• Access Requests – Impact to Operations

• Interconnecting Projects – Schedules impact other

contracts – Commissioning phasing

Page 36: EchoWater Project - Regional San...• Project includes: bulk chemical storage, chemical building with day tanks and feed pumps, control systems, and piping and injection facilities

Sacramento Regional County Sanitation District

Major Equipment Procurement Alternatives

Page 37: EchoWater Project - Regional San...• Project includes: bulk chemical storage, chemical building with day tanks and feed pumps, control systems, and piping and injection facilities

Sacramento Regional County Sanitation District

Best Value Selection For Major Equipment Procurements

• Procure equipment based on their long-term costs • In most cases, lowest bid cost selection will apply • For equipment with significant variations in

operational costs, alternative procurement options will be considered

Page 38: EchoWater Project - Regional San...• Project includes: bulk chemical storage, chemical building with day tanks and feed pumps, control systems, and piping and injection facilities

Sacramento Regional County Sanitation District

Alternative Procurement Options

• Bids based on present worth analyses by Contractor • Bids based on equipment pre-selected by the District • Bids based on pre-purchased equipment by the

District • Bids based on pre-purchased equipment

subsequently assigned to the contractor

Page 39: EchoWater Project - Regional San...• Project includes: bulk chemical storage, chemical building with day tanks and feed pumps, control systems, and piping and injection facilities

Sacramento Regional County Sanitation District

3-D Design (BIM)

Page 40: EchoWater Project - Regional San...• Project includes: bulk chemical storage, chemical building with day tanks and feed pumps, control systems, and piping and injection facilities

Sacramento Regional County Sanitation District

Objectives of 3-D Design • Allow stakeholders to visualize finished facilities (layouts,

access, etc.) during design development. • Utilize clash detection to identify and eliminate conflicts

both within and between projects. • Efficiently manage large volume of asset data, including

tag numbers, asset parameters, and maintenance data. • Manage changes to contract documents during

construction and commissioning phases.

Page 41: EchoWater Project - Regional San...• Project includes: bulk chemical storage, chemical building with day tanks and feed pumps, control systems, and piping and injection facilities

Sacramento Regional County Sanitation District

Potential Contractors’ Use of 3-D Design Documents

• 3-D model files may be made available during bid phase, with disclaimer.

• BIM files may be available for 4-D (schedule) and 5-D (cost) management.

• Responsibility for maintaining model files to reflect changes, and “as-built” conditions, during construction TBD.

• Use of asset database for submittals (shop drawings, O&M information, etc.) TBD.

Page 42: EchoWater Project - Regional San...• Project includes: bulk chemical storage, chemical building with day tanks and feed pumps, control systems, and piping and injection facilities

Sacramento Regional County Sanitation District

Contact Information

• Web site: http://www.srcsd.com/business-opportunities.php • PMO CM Lead:

– Dave Conover EchoWater Project Program Management Office [email protected]

Page 43: EchoWater Project - Regional San...• Project includes: bulk chemical storage, chemical building with day tanks and feed pumps, control systems, and piping and injection facilities

Sacramento Regional County Sanitation District

Contractor Input