ecda process for cased gas transmission pipelines charlie hall manager, special projects mears, cpg

28
ECDA Process for Cased Gas Transmission Pipelines Charlie Hall Manager, Special Projects Mears, CPG

Upload: yesenia-bridges

Post on 14-Dec-2015

227 views

Category:

Documents


3 download

TRANSCRIPT

Page 1: ECDA Process for Cased Gas Transmission Pipelines Charlie Hall Manager, Special Projects Mears, CPG

ECDA Process for Cased Gas Transmission Pipelines

Charlie HallManager, Special Projects

Mears, CPG

Page 2: ECDA Process for Cased Gas Transmission Pipelines Charlie Hall Manager, Special Projects Mears, CPG

Objectives

• Review the ECDA Process From a Technical and Regulatory Perspective

• Review On-Going Validation Efforts and our Casing Test Facility

Page 3: ECDA Process for Cased Gas Transmission Pipelines Charlie Hall Manager, Special Projects Mears, CPG

Technical Basis of the ECDA Process for Cased Pipelines

• Fundamentally the ECDA process seeks to determine if a corrosive situation potentially exists in the casing.– Anode– Cathode– Metallic Path– Electrolytic Path

• If the coating is free of holidays, an external corrosion cell cannot occur (absent disbonded coating issues).

• If a holiday is present, the highest risk of external corrosion occurs when the holiday is in contact with electrolyte.

Page 4: ECDA Process for Cased Gas Transmission Pipelines Charlie Hall Manager, Special Projects Mears, CPG

Technical Basis of the ECDA Process for Cased Pipelines

• If electrolyte is in contact with the holiday and the casing, indirect inspection tools can detect the holiday. Additionally, the holiday would be in the CP circuit and may be receiving adequate CP.

• If the casing is metallically shorted, the holiday will likely not receive any available CP. Available CP will seek the path of lowest resistance, which most likely is the metallic contact.

• These same principles apply to buried un-cased piping.

Page 5: ECDA Process for Cased Gas Transmission Pipelines Charlie Hall Manager, Special Projects Mears, CPG

Technical Basis of the ECDA Process for Cased Pipelines

• Situations that cause external corrosion in cased pipelines– Metallic contact between casing and pipeline– Electrolytic contact between casing and pipeline– Atmospheric Corrosion on pipeline in casing

Reference GRI-05/0200“External Corrosion Probability Assessment for Carrier Pipes Inside

Casings” Casing Corrosion Direct Assessment – ECDALarry G. Rankin and Hussain M. Al MahrousJanuary 2005

Page 6: ECDA Process for Cased Gas Transmission Pipelines Charlie Hall Manager, Special Projects Mears, CPG

Principles of ECDA Process Development

• ECDA is a structured process that is intended to improve safety by assessing and reducing the impact of external corrosion on pipeline integrity.

• ECDA is a continuous improvement process targeted to identify and address locations where corrosion activity has occurred, is occurring, or may occur.

Page 7: ECDA Process for Cased Gas Transmission Pipelines Charlie Hall Manager, Special Projects Mears, CPG

DOT Code Requirements for the ECDA Process

• Per DOT Part 192.921, DA can be used to assess the integrity of gas transmission pipelines for the external, internal, and SCC.

• Per DOT Part 192.921, DA must be performed in accordance with 192.923, 192.925, 192.927, and 192.929, and specifically ECDA in accordance with NACE RP0502.

Page 8: ECDA Process for Cased Gas Transmission Pipelines Charlie Hall Manager, Special Projects Mears, CPG

Application of NACE RP 0502 to Cased Gas Transmission Pipelines

• Per NACE RP0502, Table 1, Cased crossings requires a separate ECDA region.

• Per NACE RP0502, Table 2, indirect testing methods are “applicable” for shorted casings.

• Per NACE RP0502, Table 2, indirect testing methods for cased piping are “Not Applicable: Not applicable to this tool or not applicable without additional considerations.

• The ECDA Process we have developed for Cased Piping addresses the NACE RP0502 requirement for “additional consideration” and fully complies with DOT part 192 and NACE RP0502 protocols.

Page 9: ECDA Process for Cased Gas Transmission Pipelines Charlie Hall Manager, Special Projects Mears, CPG

• Mears solicited a clarification to footnote #3 Table 2 from PHMSA

• Quote from that clarification – one bullet second clarification include in regards to footnote #3

• Answer B – is intended to assess the integrity of the pipe including cased pipelines

Page 10: ECDA Process for Cased Gas Transmission Pipelines Charlie Hall Manager, Special Projects Mears, CPG

The ECDA Process for Cased Pipelines

• The Cased Pipeline ECDA Process looks to find areas where corrosion may have or may be occurring, just like the ECDA process for buried uncased pipelines.

• The Cased Pipeline ECDA Process uses the same 4 steps as used for buried uncased pipelines.

Page 11: ECDA Process for Cased Gas Transmission Pipelines Charlie Hall Manager, Special Projects Mears, CPG

The ECDA Process for Cased Pipelines

• The Cased Pipeline ECDA Process meets the same protocol requirements as for buried uncased pipelines (ie. immediate, schedule, monitored conditions, minimum excavation requirements, etc.).

• The Cased Pipeline ECDA Process utilizes Guided Wave Ultrasonic Inspection as an additional Indirect Inspection Tool concurrent with ALL Direct Examinations.

• The Cased Pipeline ECDA Process is being designed using the knowledge gained from the smart pig results of 1201 cased pipelines

• The process is being validated both in the field and using a newly constructed Casing Test Bed

Page 12: ECDA Process for Cased Gas Transmission Pipelines Charlie Hall Manager, Special Projects Mears, CPG

Pre-Assessment

• Collect all required data elements (additional elements have been identified for cased pipelines)

• Must be Feasible to perform ECDA on cased pipeline– Must be able to indirectly examine– Must be able to directly examine both ends (if

necessary) and comply with all of the PHMSA guided wave target items

– Must establish meaningful segments and regions for cased pipelines that pass the “red face test”

Page 13: ECDA Process for Cased Gas Transmission Pipelines Charlie Hall Manager, Special Projects Mears, CPG

Indirect Inspection

Indirect inspection tools can detect metallic or electrolytic shorted conditions

• PCM (NACE RP 0502)• PCM with A-FRAME (NACE RP 0502)• P/S & C/S Potentials (including CIS both sides)• Internal Resistance (NACE RP 0200)• Cycling the Rectifier (NACE RP 0200)• Pipe/Cable Locator (NACE RP 0200)• Panhandle Eastern Method (AGA)

Has the ability to detect corrosion wall loss

• Guided Wave (Guided Wave UT Target Items)

Page 14: ECDA Process for Cased Gas Transmission Pipelines Charlie Hall Manager, Special Projects Mears, CPG

Are Tools Complimentary?

• The word complementary can mean different things to different people.

• Typically “complimentary” suggests something that adds value, reinforces, or supplements something else.

• When someone says you and your spouse compliment one another, it suggests that the two of you are better as a whole, and you make up for each others’ strengths and weaknesses.

Page 15: ECDA Process for Cased Gas Transmission Pipelines Charlie Hall Manager, Special Projects Mears, CPG

Are Tools Complimentary?

• The IITs for Casings are complimentary.

• The tools look for the same potential corrosive conditions, but they do so in slightly different manners.

• This can help to account for the strengths and limitations of each tool.

• This is also true for the IITs that are used to assess buried pipelines.

Page 16: ECDA Process for Cased Gas Transmission Pipelines Charlie Hall Manager, Special Projects Mears, CPG

CASED PIPELINE INDIRECT INSPECTION METHOD INDICATIONS & SEVERITY GUIDE

COMMON NAME OF TOOL TYPE OF TOOL

MINOR (NO PATH INDICATED)

MODERATE (ELECTROLYTIC PATH)

SEVERE (METALLIC CONTACT)

P/S & C/S POTENTIALS

ELECTRICAL POTENTIAL

P/S & C/S "ON" DIFFER BY MORE THAN 100 mV

P/S & C/S "ON" DIFFER BY 10 mV TO 100 mV

P/S & C/S "ON" DIFFER BY LESS

THAN 10 mV

PIPE CURRENT MAPPER

AC CURRENT ATTENUATION

CURRENT LOSS ACROSS CASING < 5%

CURRENT LOSS ACROSS CASING 5%-25%

CURRENT LOSS ACROSS CASING >

25%

PCM WITH A-FRAME

AC VOLTAGE GRADIENT

NO INDICATION AT EITHER END INDICATION < 80 dBmA

INDICATION > 80 dBmA

INTERNAL RESISTANCE

ELECTRICAL RESISTANCE

PIPE-TO-CASING RESISTANCE > 0.5 OHM

P-C RESISTANCE 0.01 TO 0.5 OHM

P-C RESISTANCE < 0.01 OHM

CYCLING THE RECTIFIER

COMPARE P/S & C/S POTENTIAL

SHIFTS

>100 mV DIFFERENCE C/S SHIFT < 25% P/S

SHIFT

10 mV-100 mV DIFF. & C/S 25%-75% OF P/S

SHIFT

< 10 mV DIFF. & C/S > 75% OF P/S

SHIFT

PIPE/CABLE LOCATOR RADIO SIGNAL

NO SIGNIFICANT SIGNAL LOSS

MODERATE SIGNAL LOSS

NEAR TOTAL SIGNAL LOSS

PANHANDLE EASTERN METHOD

REVERSE CURRENT APPLIED

TO CASINGADDITIONAL TESTING REQUIRED TO DEFINE

ADDITIONAL TESTING REQUIRED TO DEFINE

PIPE-TO-CASING RES. < 0.01 OHM

CASING/PIPE CAPACITANCE

TINKER & RASOR MODEL CE-IT "CLEAR" DISPLAY NONE "SHORTED" DISPLAY

Indirect Inspection Severity Guide

Page 17: ECDA Process for Cased Gas Transmission Pipelines Charlie Hall Manager, Special Projects Mears, CPG

Indirect Inspection

Classification of Indirect Inspection Testing

Indirect Inspection ResultsDE Prioritization

Any indication of a Metallic Short or Electrolytic Path

Immediate

NO indication of either a Metallic Short or Electrolytic

PathMonitored1

1For casings that were identified with some history of either a Metallic Short or Electrolytic Path but are not presently indicating the same , the DE Priority will be moved to the Immediate category and require direct examination during the first application of the ECDA process..

Page 18: ECDA Process for Cased Gas Transmission Pipelines Charlie Hall Manager, Special Projects Mears, CPG

Direct Examination

• Must be performed per NACE RP0502.• Minimum direct examinations per NACE

RP0502 protocols (ie. All immediates, 2 worst case monitored for 1st time through)

• Guided Wave ultrasonic indirect inspections must be performed during all Direct Examinations. Any metallic shorts or indications of electrolytic paths must be cleared prior to inspection.

Page 19: ECDA Process for Cased Gas Transmission Pipelines Charlie Hall Manager, Special Projects Mears, CPG

Direct Examination

• Guided Wave must comply with all of the PHMSA Guided Wave Target Items, or exceptions documented with technical basis.

Page 20: ECDA Process for Cased Gas Transmission Pipelines Charlie Hall Manager, Special Projects Mears, CPG

Post Assessment

• Must comply with NACE RP0502

Page 21: ECDA Process for Cased Gas Transmission Pipelines Charlie Hall Manager, Special Projects Mears, CPG

Summary of Smart Pig Results

• 1201 cased pipelines smart pigged from 2004 to 2006.

• 144 of the 1201 cased pipelines (12%) had anomalies with metal loss detected > 20%.

• 20 of the 144 cased pipelines with metal loss >20% (1.6 % of all cased pipelines) were found with anomalies > 80 feet from the nearest end of the casing.

Page 22: ECDA Process for Cased Gas Transmission Pipelines Charlie Hall Manager, Special Projects Mears, CPG

Summary of Smart Pig Results

• The lowest Pf/MAOP for any anomaly was 1.67, and the anomaly was within .1 feet of the end of the casing.

• The lowest Pf/MAOP for all anomalies > 80 feet from the end of the casing was 1.79 (anomaly 27% deep, 5.3” long).

• The results strongly suggest that external corrosion is not a significant threat to cased pipelines.

Page 23: ECDA Process for Cased Gas Transmission Pipelines Charlie Hall Manager, Special Projects Mears, CPG

Validating the Process - Casing Test Facility

Page 24: ECDA Process for Cased Gas Transmission Pipelines Charlie Hall Manager, Special Projects Mears, CPG

Validating the ProcessCasing Test Facility

Page 25: ECDA Process for Cased Gas Transmission Pipelines Charlie Hall Manager, Special Projects Mears, CPG
Page 26: ECDA Process for Cased Gas Transmission Pipelines Charlie Hall Manager, Special Projects Mears, CPG

Example of IIT Results on Casing Test Facility - PCM

Distance70

Clear Condition

Simulated Elect Short

Simulated Metallic Short

Actual Elect Short

100 ft 231 760 1700 482

50 ft 217 680 1550 471

0 ft 194 593 1340 395

0 ft 191 231 0 218

50 ft 152 149 0 146

100 ft 104 89 0 80

All readings in milli-amps, out of a total of 2 ampsPCM A-Frame detected location of 20%, 50%, and 80% anomalies in shorted conditions

North

South

Page 27: ECDA Process for Cased Gas Transmission Pipelines Charlie Hall Manager, Special Projects Mears, CPG

Summary

• The ECDA process and the NACE RP 0502 is applicable to cased pipelines.

• The process will improve the safety of cased pipelines by identifying when potential corrosive conditions occur, requiring direct examinations and remediation, in the same manner as required when applying ECDA on buried pipelines.

• The process will continue to improve, as the tools and the process are continually improved.

Page 28: ECDA Process for Cased Gas Transmission Pipelines Charlie Hall Manager, Special Projects Mears, CPG

Comments/Discussion

Thank You

Charlie Hall