eastern promenade rejuvenation project - smcgov.org...• ceqa and other permits approved and...
TRANSCRIPT
![Page 1: Eastern Promenade Rejuvenation Project - smcgov.org...• CEQA and other permits approved and secured in August 2009 •Project split into Western and Eastern Promenade in 2010. •Phase](https://reader033.vdocuments.site/reader033/viewer/2022060516/5f93cfc26954f22dde5e720d/html5/thumbnails/1.jpg)
Coyote Point Recreation Area Eastern Promenade Rejuvenation Project
Parks and Recreation Commission MeetingApril 7, 2016
![Page 2: Eastern Promenade Rejuvenation Project - smcgov.org...• CEQA and other permits approved and secured in August 2009 •Project split into Western and Eastern Promenade in 2010. •Phase](https://reader033.vdocuments.site/reader033/viewer/2022060516/5f93cfc26954f22dde5e720d/html5/thumbnails/2.jpg)
Coyote Point Recreation Area Eastern Promenade Project
Project Team
San Mateo County Parks DepartmentSan Mateo County Public Works Department
San Mateo County Parks Foundation
Design Team:
BKF Engineers
MIG | TRA
Moffatt & Nichol
![Page 3: Eastern Promenade Rejuvenation Project - smcgov.org...• CEQA and other permits approved and secured in August 2009 •Project split into Western and Eastern Promenade in 2010. •Phase](https://reader033.vdocuments.site/reader033/viewer/2022060516/5f93cfc26954f22dde5e720d/html5/thumbnails/3.jpg)
Coyote Point Recreation Area Eastern Promenade Project
Presentation Overview
• Project History
• Project Features
• Project Update and Schedule
• CEQA and Permit Status
• Questions and Answers
![Page 4: Eastern Promenade Rejuvenation Project - smcgov.org...• CEQA and other permits approved and secured in August 2009 •Project split into Western and Eastern Promenade in 2010. •Phase](https://reader033.vdocuments.site/reader033/viewer/2022060516/5f93cfc26954f22dde5e720d/html5/thumbnails/4.jpg)
Coyote Point Recreation Area Eastern Promenade Project
Project History• Coyote Point Promenade Project was launched in 2009.
• CEQA and other permits approved and secured in August 2009
• Project split into Western and Eastern Promenade in 2010.
• Phase 1 – Western Promenade, constructed Fall 2014
• Phase 2 – Eastern Promenade, now at 90% level of design
![Page 5: Eastern Promenade Rejuvenation Project - smcgov.org...• CEQA and other permits approved and secured in August 2009 •Project split into Western and Eastern Promenade in 2010. •Phase](https://reader033.vdocuments.site/reader033/viewer/2022060516/5f93cfc26954f22dde5e720d/html5/thumbnails/5.jpg)
Coyote Point Recreation Area Eastern Promenade Project
Proposed Site Plan
Beach
Promenade
Parking Areas
![Page 6: Eastern Promenade Rejuvenation Project - smcgov.org...• CEQA and other permits approved and secured in August 2009 •Project split into Western and Eastern Promenade in 2010. •Phase](https://reader033.vdocuments.site/reader033/viewer/2022060516/5f93cfc26954f22dde5e720d/html5/thumbnails/6.jpg)
Coyote Point Recreation Area Eastern Promenade Project
Beach and Restroom
![Page 7: Eastern Promenade Rejuvenation Project - smcgov.org...• CEQA and other permits approved and secured in August 2009 •Project split into Western and Eastern Promenade in 2010. •Phase](https://reader033.vdocuments.site/reader033/viewer/2022060516/5f93cfc26954f22dde5e720d/html5/thumbnails/7.jpg)
Coyote Point Recreation Area Eastern Promenade Project
New Parking Area
![Page 8: Eastern Promenade Rejuvenation Project - smcgov.org...• CEQA and other permits approved and secured in August 2009 •Project split into Western and Eastern Promenade in 2010. •Phase](https://reader033.vdocuments.site/reader033/viewer/2022060516/5f93cfc26954f22dde5e720d/html5/thumbnails/8.jpg)
Coyote Point Recreation Area Eastern Promenade Project
Project Update and Schedule• Conceptual Design Complete, September 2015
• 60% Design Complete, January 2016
• 90% Design Nearly Complete, April 2016Plans, specifications, cost estimates being reviewed.Potential grantors are contacted.
• 100% Design Anticipated Completion, May/June 2016
• Construction funds are secured. 2016 to 2017
• Construction date is TBA. Potentially 2017 to 2019
![Page 9: Eastern Promenade Rejuvenation Project - smcgov.org...• CEQA and other permits approved and secured in August 2009 •Project split into Western and Eastern Promenade in 2010. •Phase](https://reader033.vdocuments.site/reader033/viewer/2022060516/5f93cfc26954f22dde5e720d/html5/thumbnails/9.jpg)
Coyote Point Recreation Area Eastern Promenade Project
CEQA and Permit Status• California Environmental Quality Act (CEQA) IS/MND approved, August
2009.
• Draft Addendum to approved CEQA IS/MND prepared to include climate change plan and to address mitigation measures such as an additional parking area and to add tree and pier removals, March 2016
• Addendum to be submitted to regulatory agencies to close-out Environmental Documentation process.
![Page 10: Eastern Promenade Rejuvenation Project - smcgov.org...• CEQA and other permits approved and secured in August 2009 •Project split into Western and Eastern Promenade in 2010. •Phase](https://reader033.vdocuments.site/reader033/viewer/2022060516/5f93cfc26954f22dde5e720d/html5/thumbnails/10.jpg)
Coyote Point Recreation Area Eastern Promenade Project
Questions?
Thank you.