eastern cape rural development agency quotation document ... · quotations are requested from...

58
1 EASTERN CAPE RURAL DEVELOPMENT AGENCY QUOTATION DOCUMENT FOR REFURBISHMENT WORK TO ECRDA MTHATHA OFFICES BID NUMBER: RFQ 169-2016/17 FEBRUARY 2017 Compiled for: Eastern Cape Rural Development Agent (ECDRA) Unit 12 D, Beacon Bay Crossing Beacon Bay 5201 Compiled by: FWJK Quantity Surveyors P.O. Box 720 Mthatha 5099

Upload: others

Post on 10-May-2020

4 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: EASTERN CAPE RURAL DEVELOPMENT AGENCY QUOTATION DOCUMENT ... · Quotations are requested from competent and registered contractors with the CIDB Contractor grading of 2GB and 3 GB

1

EASTERN CAPE RURAL DEVELOPMENT AGENCY

QUOTATION DOCUMENT

FOR

REFURBISHMENT WORK TO

ECRDA MTHATHA OFFICES

BID NUMBER: RFQ 169-2016/17

FEBRUARY 2017

Compiled for: Eastern Cape Rural Development Agent (ECDRA)

Unit 12 D, Beacon Bay Crossing Beacon Bay 5201

Compiled by: FWJK Quantity Surveyors P.O. Box 720 Mthatha 5099

Page 2: EASTERN CAPE RURAL DEVELOPMENT AGENCY QUOTATION DOCUMENT ... · Quotations are requested from competent and registered contractors with the CIDB Contractor grading of 2GB and 3 GB

2

QUOTATION NOTICE TO CONTRACTORS BID NUMBER: RFQ 169-2016/17

1. TENDER INVITATION

THE EASTERN CAPE RURAL DEVELOPMENT AGENCY, REQUIRES QUOTATIONS FOR REFURBISHMENT WORK TO ECRDA OFFICES IN MTHATHA. Attached please find Bills of Quantities that needs to be completed.

Quotations are requested from competent and registered contractors with the CIDB Contractor grading of 2GB and

3 GB . Note: A compulsory pre-tender site inspection will be held at 11h00 on Tuesday 28 February 2017 at No.52 Corner Nelson Mandela & Spring Street Mthatha . Prospective tenderers are required to attend this inspection.

Tenders in sealed envelopes labelled “BID NUMBER RFQ 169-2016/17 : “ REFURBISHMENT WORK TO ECRDA OFFICES, MTHATHA” and the name of the firm tendering, should be hand delivered to Eastern Cape Rural Development Agency, Beacon Bay Crossing, Beacon Bay

by 11h00 (noon/midday) on 06 March 2017.

2. TENDER DATA 2.1 The Employer reserves the right to accept or reject any tender and may cancel the tender process and

reject all tender offers at any time before the formation of a contract. The employer shall not accept or incur any liability to a tenderer for such cancellation and rejection, but will give written reasons for such action upon written request to do so.

2.2 The tenderer shall:

a) Tenderers must have a minimum CIDB Contractor grading of 2 GB and 3 GB.

b) Submit a tender offer only if the tenderer complies with the criteria stated in the tender data and the

tenderer, or any of his principals, is not under any restriction to do business with employer.

c) Submit with the quotation a valid SARS Tax Compliance Status certificate (TCS) PIN and a letter of good standing with the Compensation Commissioner. Persons without employees must submit a letter indicating this.

d) Accept that the employer will not compensate the tenderer for any costs incurred in the preparation

and submission of a tender offer.

Page 3: EASTERN CAPE RURAL DEVELOPMENT AGENCY QUOTATION DOCUMENT ... · Quotations are requested from competent and registered contractors with the CIDB Contractor grading of 2GB and 3 GB

3

e) Not make any alterations or additions to the tender documents, except to comply with instructions issued by the employer, or if necessary to correct errors made by the tenderer. All signatories to the tender offer shall initial all such alterations. Erasures and the use of masking fluid are prohibited.

f) Any unauthorized alterations to the Bill of Quantities will lead to the tender being rejected.

g) Accept that tender offers, which do not provide all the data or information requested completely and

in the form required, may be regarded by the employer as non-responsive.

h) Payment shall be determined from the tendered rates in the Bill of Quantities, and shall be deemed

to be full compensation for the work as specified, including setting up the audits and checks, running the programme, quality control, overheads, profit, insurance, risk, and incidental costs incurred for the successful completion of the work.

i) Accept that a non-responsive tender offer may not be subsequently made responsive by correction

or withdrawal of the non-conforming deviation or reservation. This particularly applies to the submission of Tax Compliance Status certificate (TCS) PIN and Letters of Good Standing.

j) Evaluation will be done in terms of the Preferential Procurement Policy Framework Act (Act 5 of

2000), and its regulations as set out in Government Gazette 34350 of 8 June 2011 and the Departments Supply Chain Management Policy. Points will be awarded on an 80 for Price and 20 for B-BBEE status.

k) The Bidder must return the whole of this document, correctly completed. Should the Tenderer wish to submit different figures or any other changes to the Bills of Quantities or other item in this document, they must submit these as a separate document and refer to it on the form for Alterations and Qualifications.

l) The validity period of the tender shall be 90 days from the closing date. ANY ENQUIRIES REGARDING THE BIDDING PROCEDURE MAY BE DIRECTED TO:

Eastern Cape Rural Development Agency (ECDRA) Contact Person: Mr Andile Sibulali Tel: 043 604 7000 E-mail address: [email protected]

ANY ENQUIRIES REGARDING TECHNICAL INFORMATION MAY BE DIRECTED TO: Contact Person: Mr Tony Reedy Tel: 047 532 5512 Fax: 047 532 5296 E-mail address: [email protected]

Page 4: EASTERN CAPE RURAL DEVELOPMENT AGENCY QUOTATION DOCUMENT ... · Quotations are requested from competent and registered contractors with the CIDB Contractor grading of 2GB and 3 GB

4

3. SCOPE OF CONSTRUCTION WORK

Minor refurbishment work to the ECDRA offices in Mthatha including: a) EXTENT OF THE WORKS

Minor refurbishment work to ECRDA OFFICES, MTHATHA.

b) BUILDINGS OCCUPIED

Offices will be occupied, contractor to demarcate areas where they are working

c) ACCESS The offices are situated in Mthatha, 52 Corner Nelson Mandela & Spring Street.

4. EVALUATION OF TENDERS a) First Stage in Evaluation: Compliance with Tender Rules and other Requirements

The Technical Proposals will be checked to ensure that they comply with the Tender Rules and all other requirements of the project document. In particular, the following documentation must be completed and/or included with the Tender:

Copy of completed Invitation to Bid

Certificate of Authority for Signature

Original, valid and certified, Tenderer’s B-BBEE status level verification certificate/SWORN Affidavit.

Valid Tax Compliance Status certificate (TCS) PIN with SARS

Letter of good standing with the Compensation Commissioner or FEM as applicable. In the case of a firm with no employees, a letter confirming this must be attached

A copy of the tenderer’s Insurance

Addenda issued during the tender period

The pricing schedule or Bills of Quantities.

The form of Tender

CV’s of all staff to be involved in the project and the tasks they will be undertaking

Completed Project Reference Forms

Failure to provide valid certificates of good standing with SARS and the Compensation Commissioner with the tender will render the tender invalid.

All information supporting the above forms such as details of ownership, relevant experience, CV’s of staff who will be used on the project and their functions in regard to the contract must be supplied. It should be noted that only staff with acceptable experience in Building and Civil construction as well as Occupational Health and Safety exposure under these conditions will be acceptable.

FORM B: RELEVANT EXPERIENCE The Tenderer shall provide A LIST OF RECENT MAJOR BUILT ENVIRONMENT PROJECTS in which the Tenderer has been involved in. Tenderers need only provide details of projects of a similar size and nature carried out in the past 3 years. It is essential that full details of the projects and of the Employer / Engineer/ Principal Agent references be provided in order for the projects to be evaluated. Failure to provide the necessary information will compromise the Tender.

Page 5: EASTERN CAPE RURAL DEVELOPMENT AGENCY QUOTATION DOCUMENT ... · Quotations are requested from competent and registered contractors with the CIDB Contractor grading of 2GB and 3 GB

5

SBD 1

INVITATION TO BID

YOU ARE HEREBY INVITED TO BID FOR REQUIREMENTS OF EASTERN CAPE RURAL DEVELOPMENT

BID NUMBER: RFQ 169-2016/17 CLOSING DATE: 06 March 2017 CLOSING TIME: 11:00 DESCRIPTION: REFURBS Validity Period : 90 Days DEPOSITED IN THE BID BOX SITUATED AT (STREET ADDRESS): EASTERN CAPE RURAL DEVELOPMENT AGENCY UNIT 12D BEACON BAY CROSSING CORNER N2 & BONZA BAY ROAD BEACON BAY EAST LONDON Bidders should ensure that bids are delivered timeously to the correct address. If the bid is late, it will not be accepted for consideration. The bid box is generally open during working hours, 5 days a week.

ALL BIDS MUST BE SUBMITTED ON THE OFFICIAL FORMS – (NOT TO BE RE-TYPED)

THIS BID IS SUBJECT TO THE PREFERENTIAL PROCUREMENT POLICY FRAMEWORK ACT AND THE PREFERENTIAL PROCUREMENT REGULATIONS, 2011, THE GENERAL CONDITIONS OF CONTRACT (GCC) AND, IF APPLICABLE, ANY OTHER SPECIAL CONDITIONS OF CONTRACT

THE FOLLOWING PARTICULARS MUST BE FURNISHED (FAILURE TO DO SO MAY RESULT IN YOUR BID BEING DISQUALIFIED)

NAME OF BIDDER ……………………………………………………………………………………………………………………… POSTAL ADDRESS …………………………………………………………………………………………………………………. STREET ADDRESS ………………………………………………………………………………………………………………… TELEPHONE NUMBER CODE……………NUMBER………………………………………………………………………………..

CELLPHONE NUMBER ………………………………………………………………………………………………………………… FACSIMILE NUMBER CODE ………… .NUMBER………………………………………………………………………………… E-MAIL ADDRESS ………………………………………………………………………………………………………………….

Page 6: EASTERN CAPE RURAL DEVELOPMENT AGENCY QUOTATION DOCUMENT ... · Quotations are requested from competent and registered contractors with the CIDB Contractor grading of 2GB and 3 GB

6

VAT REGISTRATION NUMBER ………………………………………………………………………………………………………………… HAS AN ORIGINAL AND VALID TAX CLEARANCE CERTIFICATE BEEN SUBMITTED? (SBD 2) YES or NO HAS A B-BBEE STATUS LEVEL VERIFICATION CERTIFICATE OR SWORN AFFIDAVIT FORM BEEN SUBMITTED? (SBD 6.1) YES or NO IF YES, WHO WAS THE CERTIFICATE ISSUED BY? AN ACCOUNTING OFICER AS CONTEMPLATED IN THE CLOSE CORPORATION ACT (CCA)…….…………….………………………… ………... A VERIFICATION AGENCY ACCREDITED BY THE SOUTH AFRICAN ACCREDITATION SYSTEM (SANAS); OR………………………………….… A REGISTERED AUDITOR ………………………………...……….. [TICK APPLICABLE BOX]

(A B-BBEE STATUS LEVEL VERIFICATION CERTIFICATE MUST BE SUBMITTED IN ORDER TO QUALIFY FOR PREFERENCE POINTS FOR B-BBEE)

ARE YOU THE ACCREDITED REPRESENTATIVE

IN SOUTH AFRICA FOR THE GOODS / SERVICES / WORKS OFFERED? YES or NO

[IF YES ENCLOSE PROOF]

SIGNATURE OF BIDDER ……………………………………………………………………………………………………………….. DATE ……………………………………………………………………………………………………………….. CAPACITY UNDER WHICH THIS BID IS SIGNED ……………………………………………………………………………………………

TOTAL BID PRICE…………………………………… TOTAL NUMBER OF ITEMS OFFERED ………………………………… _________________________________________________________________________________________________________

ANY ENQUIRIES REGARDING THE BIDDING PROCEDURE MAY BE DIRECTED TO:

Department: Eastern Cape Rural Development Agency Contact Person: Andile Sibulali Tel: 043 604 7000 E-mail address: [email protected]

ANY ENQUIRIES REGARDING TECHNICAL INFORMATION MAY BE DIRECTED TO: Contact Person: MR Tony Reedy Tel: 047- 532 55120 Fax: 043-532 5296

Page 7: EASTERN CAPE RURAL DEVELOPMENT AGENCY QUOTATION DOCUMENT ... · Quotations are requested from competent and registered contractors with the CIDB Contractor grading of 2GB and 3 GB

7

5. CONTRACT DATA : JBCC 2000 PRINCIPAL BUILDING AGREEMENT (Edition 4.1 of March 2005)

Project title: REFURBISHMENT WORK TO THE ECDRA OFFICES-MTHATHA

Bid No: RFQ 169-2016/17

The Conditions of Contract are clauses 1 to 42 of the JBCC series 2000 Principal Building Agreement (Edition 4.1 of March 2005) prepared by the Joint Building Contracts Committee. Copies of these conditions of contract may be obtained from the Association of South African Quantity Surveyors, Master Builders Association, South African Association of Consulting Engineers, South African Institute of Architects, Association of Construction Project Managers, Building Industries Federation South Africa, South African Property Owners Association or Specialist Engineering Contractors Committee.

42.0 Part 1: Contract Data completed by the Employer

42.1 CONTRACTING AND OTHER PARTIES

42.1.1 [1.2]

Employer : Eastern Cape Rural Development Agency Postal address: Postal Suite 385 Private Bag X9063 East London 5200 Tel: 043-604 7000 Email:[email protected] Physical address: Unit 12 D, Beacon Bay Crossing Beacon Bay 5201

Page 8: EASTERN CAPE RURAL DEVELOPMENT AGENCY QUOTATION DOCUMENT ... · Quotations are requested from competent and registered contractors with the CIDB Contractor grading of 2GB and 3 GB

8

42.1.2 [1.1, 5.1]

Project Manager: FWJK Quantity Surveyors Agent’s service: Quantity Surveyors Postal address: P.O. Box 8101 Nahoon 5210 Tel: 047-532 5512 Fax: 047-532 5296

42.1.3 [1.1, 5.1]

Agent (1) Agent’s service: Postal address: Tel: Fax:

42.1.4 [1.1, 5.2]

Agent (2) Agent’s service: Postal address: Tel: Fax:

42.1.5 [1.1, 5.2]

Agent (3) Agent’s service: Postal address: Tel: Fax:

42.2 CONTRACT DETAILS

42.2.1 [1.1]

Works description: Refer to document C3 – Scope of Work.

42.2.2 [1.1]

Site description: Refer to document C4 – Site Information.

42.2.4 [41.0]

Specific options that are applicable to a State organ only Where so :

[31.1 #] [31.11.2 #] [31.12.2#] [11.2.#] [31.4.2 #] [40.2.2.#] [26.1.2 #]

1) Interest rate legislation: (a) in respect of interest owed by the employer, the interest rate as determined by the Minister of Justice and Constitutional Development from time to time, in terms of section 1(2) of the Prescribed Rate of Interest Act, 1975 (Act No. 55 of 1975), will apply; and (b) in respect of interest owed to the employer, the interest rate

as determined by the Minister of Finance, from time to time, in terms of section 80(1)(b) of the Public Finance Management

Act, 1999 (Act No. 1 of 1999), will apply 2) Lateral support insurance to be effected by the contractor: 3) Payment will be made for materials and goods on site: Yes No 4) Dispute resolution by mediation Yes No

Yes

No

Yes

No

42.2.6 [15.3]

Period for the commencement of the works after the contractor takes possession of the site: immediately after contract has been signed.

42.2.7 [24.3.1]

For the works as a whole: The date for practical completion shall be 1 Month from the commencement date and the penalty per calendar day shall be 27.5c per R100 of the contract value

Page 9: EASTERN CAPE RURAL DEVELOPMENT AGENCY QUOTATION DOCUMENT ... · Quotations are requested from competent and registered contractors with the CIDB Contractor grading of 2GB and 3 GB

9

[30.1]

42.2.9 [1.2]

The law applicable to this agreement shall be that of the: Republic of South Africa

42.3 INSURANCES

42.3.1 [10.1 #, 10.2 # 12.1 #]

Contract works insurance to be effected by the contractor To the minimum value of the contract sum plus 10% With a deductible not exceeding 5% of each and every claim Or For the minimum sum of R …………………………………………. (insert amount in words) With a deductible not exceeding 5% of each and every claim

42.3.2 [10.1#, 10.2 #, 12.1 #]

Supplementary insurance is required: No

42.3.3 [11.1#, 12.1 #]

Public liability insurance to be effected by the contractor For the sum of R 5 million With a deductible not exceeding 5% of each and every claim Or For the sum of R ………………………………………… (insert amount in words) With a deductible not exceeding 5% of each and every claim

42.3.4 [11.2 #, 12.1 #]

Support insurance to be effected by the contractor For the sum of R ………………………………………N/A……………………………………… (insert amount in words) With a deductible of R ……………………………N/A……………………………………… (insert amount in words)

42.4 DOCUMENTS

42.4.2 [3.7]

Three (3) copies of the construction documents will be supplied to the contractor free of charge

42.4.3 Bills of quantities / Lump sum document schedule of rates drawn up in accordance with: Standard System of Measuring Building Work (sixth edition as amended)

42.4.5 [3.4]

JBCC Engineering General Conditions are to be included in the contract documents: No

42.4.6 [31.5.3] [32.13]

The contract value is to be adjusted using CPAP indices: Where CPAP is applicable, the contract sum will be adjusted in accordance with the JBCC Contract Price Adjustment Provisions (CPAP) as set out in the CPAP Indices Application

Yes No

Page 10: EASTERN CAPE RURAL DEVELOPMENT AGENCY QUOTATION DOCUMENT ... · Quotations are requested from competent and registered contractors with the CIDB Contractor grading of 2GB and 3 GB

10

Manual as prepared by the JBCC Series 2000, code 2118, dated May 2005 and any amendments thereto: 1) Glass etc. measured in specialist section Metalwork, will be adjusted in terms of the index for that work group unless specifically stated otherwise in the bills of quantities 2) All electrical installations in buildings and power distribution systems shall be adjusted in terms of the index for Work Group 160 Electrical Installation. In case of uninterruptible power supplies, elevators, escalators and hoists, generating sets, motor-alternator sets and intercommunication systems shall be in accordance with Work Group 170 3) With reference to Work Group 190 a proportion of the value related preliminaries pro rata to the amount of work excluded from adjustment, shall be excluded from Contract Price Adjustment Provisions, if Option A has been selected for the adjustment of preliminaries 4) Further to clause 3.4.4 of the CPAP Indices Application Manual, the listing of additional items for exclusion by Bidders, will not be permitted 5) Where V results in a negative amount after application of the formula in clause 8.3 of the CPAP Indices Application Manual the factor of 0,55 shall be substituted by 1,45 Alternative Indices: Not Applicable

42.4.7 [3.10]

Details of changes made to the provisions of JBCC standard documentation Clause COMMENCEMENT DATE – means the date that the possession of the site is given to the contractor CONSTRUCTION GUARANTEE – means a guarantee at call obtained by the contractor from an institution approved by the employer in terms of the employer’s construction guarantee form as selected in the schedule. CONSTRUCTION PERIOD – means the period commencing on the commencement date and ending on the date of practical completion CORRUPT PRACTICE – means the offering, giving, receiving or soliciting of anything of value to influence the action of a public official in the procurement process or in contract execution. FRAUDULENT PRACTICE – means a misrepresentation of facts in order to influence a procurement process or the execution of a contract to the detriment of any Bidder, and includes collusive practice among Bidders (prior to and after the Bid submission) designed to establish Bid prices at artificial non-competitive levels and to deprive the Bidder of the benefits of free and open competition. INTEREST – the interest rates applicable on this contract, whether specifically indicated in the relevant clauses or not, will be in terms of the legislation of the Republic of South Africa, and in particular: (a) in respect of interest owed by the employer, the interest rate as determined by

Page 11: EASTERN CAPE RURAL DEVELOPMENT AGENCY QUOTATION DOCUMENT ... · Quotations are requested from competent and registered contractors with the CIDB Contractor grading of 2GB and 3 GB

11

the Minister of Justice and Constitutional Development from time to time, in terms of section 1(2) of the Prescribed Rate of Interest Act, 1975 (Act No. 55 of 1975), will apply; and (b) in respect of interest owed to the employer, the interest rate as determined by the Minister of Finance, from time to time, in terms of section 80(1)(b) of the Public Finance Management Act, 1999 (Act No. 1 of 1999), will apply SECURITY – means the form of security provided by the employer or contractor, as stated in the schedule, from which the contractor or employer may recover expenses or loss. 1.6 Any notice given may be delivered by hand, sent by prepaid registered post or telefax. Notice shall be presumed to have been given when: 1.6.4 No clause 3.2.1 A construction guarantee in terms of 14.0, where so elected in his Bid 3.7 Add at the end thereof: The contractor shall supply and keep a copy of the JBCC Series 2000 Principal Building Agreement and Preliminaries applicable to this contract on the site, to which the employer, principal agent and agents shall have access to at all times. 3.10 Replace the second reference to “principal agent” with the word “employer” 4.3 No clause 5.1.2 under clause 41- Include reference to 32.6.3; 34.3 and 34.4 in terms of which the employer has retained its authority and has not given a mandate to the principal agent and in terms of which the employer shall sign all documents 10.5 Add the following as 10.5 Damage to the works

a) Without in any way limiting the contractor’s obligations in terms of the contract, the contractor shall bear the full risk of damage to and/or destruction of the works by whatever cause during construction of the works and hereby indemnifies and holds harmless the employer against any such damage. The contractor shall take such precautions and security measures and other steps for the protection and security of the works as the contractor may deem necessary

b) The contractor shall at all times proceed immediately to remove or dispose

of any debris arising from damage to or destruction of the works and to build, restore, replace and/or repair the works

c) The employer shall carry the risk of damage to or destruction of the works

and materials paid for by the employer that is the result of the excepted risks as set out in 10.6

d) Where the employer bears the risk in terms of this contract, the contractor

shall, if requested to do so, reinstate any damage or destroyed portions of the works and the costs of such reinstatement shall be measured and valued in terms of 32.0 hereof

Page 12: EASTERN CAPE RURAL DEVELOPMENT AGENCY QUOTATION DOCUMENT ... · Quotations are requested from competent and registered contractors with the CIDB Contractor grading of 2GB and 3 GB

12

10.6 Add the following as 10.6 Injury to Persons or loss of or damage to Properties

a) The contractor shall be liable for and hereby indemnifies the employer against any liability, loss, claim or proceeding whether arising in common law or by statute, consequent upon personal injuries to or the death of any person whomsoever arising out of or in the course of or caused by the execution of the works unless due to any act or neglect of any person for whose actions the employer is legally liable

b) The contractor shall be liable for and hereby indemnifies the employer

against any liability, loss, claim or proceeding consequent upon loss of or damage to any moveable, or immovable or personal property or property contiguous to the site, whether belonging to or under the control of the employer or any other body or person, arising out of or in the course of or by reason of the execution of the works unless due to any act or neglect of any person for whose actions the employer is legally liable

c) The contractor shall upon receiving a contract instruction from the principal

agent cause the same to be made good in a perfect and workmanlike manner at his own cost and in default thereof the employer shall be entitled to cause it to be made good and to recover the cost thereof from the contractor or to deduct the same from amounts due to the contractor.

d) The contractor shall be responsible for the protection and safety of such

portions of the premises placed under his control by the employer for the purpose of executing the works until the issue of the certificate of practical completion.

e) Where the execution of the works involves the risk of removal of or interference with support to adjoining properties including land or structures or any structures to be altered or added to, the contractor, shall and will remain adequately insured or insured against the death of or injury to persons or damage to such property consequent on such removal or interference with the support until such portion of the works has been completed

f) The contractor shall at all times proceed immediately at his own cost to

remove or dispose of any debris and to rebuild, restore, replace and/or repair such property and to execute the works

10.7 Add the following as 10.7 HIGH RISK INSURANCE In the event of the project being executed in a geological area classified as a “High Risk Area”, that is an area which is subject to highly unstable subsurface conditions that might result in catastrophic ground movement evident by sinkhole or doline formation the following will apply: 10.7.1 Damage to the works The contractor shall, from the commencement date of the works until the date of the certificate of practical completion, bear the full risk of and hereby indemnifies and holds harmless the employer against any damage to and/or destruction of the

Page 13: EASTERN CAPE RURAL DEVELOPMENT AGENCY QUOTATION DOCUMENT ... · Quotations are requested from competent and registered contractors with the CIDB Contractor grading of 2GB and 3 GB

13

works consequent upon a catastrophic ground movement as mentioned above. The contractor shall take such precautions and security measures and other steps for the protection of the works as he may deem necessary When so instructed to do so by the principal agent, the contractor shall proceed immediately to remove and/or dispose of any debris arising from damage to or destruction of the works and to rebuild, restore, replace and/or repair the works, at the contractor’s own costs 10.7.2 Injury to persons or loss of or damage to property The contractor shall be liable for and hereby indemnifies and holds harmless the employer against any liability, loss, claim or proceeding arising at any time during the period of the contract whether arising in common law or by statute, consequent upon personal injuries to or the death of any person whomsoever resulting from, arising out of or caused by a catastrophic ground movement as mentioned above The contractor shall be liable for and hereby indemnifies the employer against any and all liability, loss, claim or proceeding consequent upon loss of or damage to any moveable, or immovable or personal property or property contiguous to the site, whether belonging to or under the control of the employer or any other body or person whomsoever arising out of or caused by a catastrophic ground movement, as mentioned above, which occurred during the period of the contract 10.7.3 It is the responsibility of the contractor to ensure that he has adequate insurance to cover his risk and liability as mentioned in 10.7.1 and 10.7.2. Without limiting the contractor’s obligations in terms of the contract, the contractor shall, within twenty one (21) calendar days of the commencement date but before commencement of the works, submit to the employer proof of such insurance policy, if requested to do so 10.7.4 The employer shall be entitled to recover any and all losses and/or damages of whatever nature suffered or incurred consequent upon the contractor’s default of his obligations as set out in 10.7.1; 10.7.2 and 10.7.3. Such losses or damages may be recovered from the contractor or by deducting the same from any amounts still due under this contract or under any other contract presently or hereafter existing between the employer and the contractor and for this purpose all these contracts shall be considered one indivisible whole 14.0 Replace the entire clause 14.0 with the following: 14.0 SECURITY 14.1 In respect of contracts with a contract sum up to R1 million, the security to be submitted by the contractor to the employer will be as a payment reduction of five per cent (5%) of the value certified in the payment certificate (excluding VAT) 14.1.1 The payment reduction of the value certified in a payment certificate shall be mutatis mutandi in terms of 31.8(A) 14.1.2 The employer shall be entitled to recover expense and loss from the payment reduction in terms of 33.0 provided that the employer complies with the provisions of 33.4 in which event the employer’s entitlement shall take precedence over his obligations to refund the payment reduction security or portions thereof to the contractor 14.2 In respect of contracts with a contract sum above R1 million, the contractor

Page 14: EASTERN CAPE RURAL DEVELOPMENT AGENCY QUOTATION DOCUMENT ... · Quotations are requested from competent and registered contractors with the CIDB Contractor grading of 2GB and 3 GB

14

shall have the right to select the security to be provided in terms of 14.3, 14.4, 14.5, 14.6,or 14.7 as stated in the schedule. Such security shall be provided to the employer within twenty-one (21) calendar days from commencement date. Should the contractor fail to select the security to be provided or should the contractor fail to provide the employer with the selected security within twenty-one (21) calendar days from commencement date, the security in terms of 14.7 shall be deemed to have been selected. 14.3 Where the security as a cash deposit of ten per cent (10%) of the contract sum (excluding VAT) has been selected: 14.3.1 The contractor shall furnish the employer with a cash deposit equal in value to ten per cent (10%) of the contract sum (excluding VAT) within twenty-one (21) calendar days from commencement date 14.3.2 Within twenty-one (21) calendar days of the date of practical completion of the works the employer shall reduce the cash deposit to an amount equal to three per cent (3%) of the contract value (excluding VAT), and refund the balance to the contractor 14.3.3 Within twenty-one (21) calendar days of the date of final completion of the works the employer shall reduce the cash deposit to an amount equal to one per cent (1%) of the contract value (excluding VAT) and refund the balance to the contractor 14.3.4 On the date of payment of the amount in the final payment certificate, the employer shall refund the remainder of the cash deposit to the contractor 14.3.5 The employer shall be entitled to recover expense and loss from the cash deposit in terms of 33.0 provided that the employer complies with the provisions of 33.4 in which event the employer’s entitlement shall take precedence over his obligations to refund the cash deposit security or portions thereof to the contractor 14.3.6 The parties expressly agree that neither the employer nor the contractor shall be entitled to cede the rights to the deposit to any third party 14.4 Where security as a variable construction guarantee of ten percent (10%) of the contract sum (excluding VAT) has been selected: 14.4.1 The contractor shall furnish the employer with an acceptable variable construction guarantee equal in value to ten per cent (10%) of the contract sum (excluding VAT) within twenty-one (21) calendar days from commencement date 14.4.2 The variable construction guarantee shall reduce and expire in terms of the Variable Construction guarantee form included in the invitation to Bid 14.4.3 The employer shall return the variable construction guarantee to the contractor within fourteen (14) calendar days of it expiring 14.4.4 Where the employer has a right of recovery against the contractor in terms of 33.0, the employer shall issue a written demand in terms of the variable construction guarantee 14.5 Where security as a fixed construction guarantee of five per cent (5%) of the contract sum (excluding VAT) and a five per cent (5%) payment reduction of the value certified in the payment certificate (excluding VAT) has been selected:

Page 15: EASTERN CAPE RURAL DEVELOPMENT AGENCY QUOTATION DOCUMENT ... · Quotations are requested from competent and registered contractors with the CIDB Contractor grading of 2GB and 3 GB

15

14.5.1 The contractor shall furnish a fixed construction guarantee to the employer equal in value to five per cent (5%) of the contract sum (excluding VAT) 14.5.2 The fixed construction guarantee shall come into force on the date of issue and shall expire on the date of the last certificate of practical completion 14.5.3 The employer shall return the fixed construction guarantee to the contractor within fourteen (14) calendar days of it expiring 14.5.4 The payment reduction of the value certified in a payment certificate shall be in terms of 31.8(A) and 34.8 14.5.5 Where the employer has a right of recovery against the contractor in terms of 33.0, the employer shall be entitled to issue a written demand in terms of the fixed construction guarantee or may recover from the payment reduction or may do both 14.6 Where security as a cash deposit of five per cent (5%) of the contract sum (excluding VAT) and a payment reduction of five per cent (5%) of the value certified in the payment certificate (excluding VAT) has been selected: 14.6.1 The contractor shall furnish the employer with a cash deposit equal in value to five per cent (5%) of the contract sum (excluding VAT) within twenty-one (21) calendar days from commencement date 14.6.2 Within twenty-one (21) calendar days of the date of practical completion of the works the employer shall refund the cash deposit in total to the contractor 14.6.3 The payment reduction of the value certified in a payment certificate shall be mutatis mutandi in terms of 31.8(A) 14.6.4 Where the employer has a right of recovery against the contractor in terms of 33.0, the employer may issue a written notice in terms of 33.4 or may recover from the payment reduction or may do both 14.7 Where security as a payment reduction of ten per cent (10%) of the value certified in the payment certificate (excluding VAT) has been selected: 14.7.1 The payment reduction of the value certified in a payment certificate shall be mutatis mutandi in terms of 31.8(B) 14.7.2 The employer shall be entitled to recover expense and loss from the payment reduction in terms of 33.0 provided that the employer complies with the provisions of 33.4 in which event the employer’s entitlement shall take precedence over his obligations to refund the payment reduction or portions thereof to the contractor 14.8 Payments made by the guarantor to the employer in terms of the fixed or variable construction guarantee shall not prejudice the rights of the employer or contractor in terms of this agreement 14.9 Should the contractor fail to furnish the security in terms of 14.2 the employer, in his sole discretion, and without notification to the contractor, is entitled to change the contractor’s selected form of security to that of a ten per cent (10%) payment reduction of the value certified in the payment certificate (excluding VAT), whereafter 14.7 shall be applicable 15.1.1 No clause

Page 16: EASTERN CAPE RURAL DEVELOPMENT AGENCY QUOTATION DOCUMENT ... · Quotations are requested from competent and registered contractors with the CIDB Contractor grading of 2GB and 3 GB

16

15.1.4 Add 15.1.4 as follows: An acceptable health and safety plan, required in terms of the Occupational Health and Safety Act, 1993 (Act 85 of 1993), within twenty-one (21) calendar days of commencement date 15.2.1 Under 41: Amend to read as follows: “Give the contractor possession of the site within ten (10) working days of the contractor complying with the terms of 15.1.2 and 15.1.4 17.1.11 Delete the words ”and the appointment of nominated and selected subcontractors” 20.1.3 No clause 21.0 No clause 29.2.5 No clause 31.5.2 Security adjustments in terms of 14.0 and 31.8 31.8 Amend as follows: 31.8(A) Where a security is selected in terms of 14.1; 14.5 or 14.6, the value of the works in terms of 31.4.1 and of the materials and goods in terms of 31.4.2 shall be certified in full. The value certified shall be subject to the following percentage adjustments: 31.8(A).1 Ninety-five per cent (95%) of such value in interim payment certificates issued up to the date of practical completion 31.8.(A).2 Ninety-seven per cent (97%) of such value in interim payment certificates issued on the date of practical completion and up to but excluding the date of final completion 31.8(A).3 Ninety-nine per cent (99%) of such value in interim payment certificates issued on the date of final completion and up to but excluding the final payment certificate in terms of 34.6 31.8(A).4One hundred per cent (100%) of such value in the final payment certificate in terms of 34.6 except where the amount certified is in favour of the employer. In such an event the payment reduction shall remain at the adjustment level applicable to the final payment certificate. 31.8(B) Where security is a payment reduction in term of 14.7 has been selected the value of the works in terms of 31.4.1 and materials and goods in terms of 31.4.2 shall be certified in full. The value certified shall be subject to the following percentage adjustments: 31.8(B).1 Ninety per cent (90%) of such value in interim payment certificates issued up to the date of practical completion 31.8(B).2 Ninety-seven per cent (97%) of such value in interim payment certificates issued on the date of practical completion and up to but excluding the date of final completion

Page 17: EASTERN CAPE RURAL DEVELOPMENT AGENCY QUOTATION DOCUMENT ... · Quotations are requested from competent and registered contractors with the CIDB Contractor grading of 2GB and 3 GB

17

31.8(B).3 Ninety-nine per cent (99%) of such value in interim payment certificates issued on the date of final completion and up to but excluding the final payment certificate in terms of 34.6 31.8(B).4 One hundred per cent (100%) of such value in the final payment certificate in terms of 34.6 except were the amount certified is in favour of the employer. In such an event the payment reduction shall remain at the adjustment level applicable to the final payment certificate 31.12 Delete the following: “Payment shall be subject to the employer giving the contractor a tax invoice for the amount due.” 32.5.1 Add the following to the end of each of these clauses: “…due to no fault of the 32.5.4 contractor” and 32.5.7 33.2 Add the following clauses 33.2.9 to 33.2.13: 33.2.9 the contractor’s failure or neglect to commence with the works on the dates prescribed in the contract 33.2.10 the contractor’s failure or neglect to proceed with the works in terms of the contract 33.2.11 the contractor’s failure or neglect for any reason to complete the works in accordance with the contract 33.2.12 the contractor’s refusal or neglect to comply strictly with any of the conditions of contract or any contract instructions and/or orders in writing given in terms of the contract 33.2.13 the contractor’s estate being sequestrated; liquidated or surrendered in terms of the insolvency laws in force within the Republic of South Africa 34.13 Replace “seven (7) calendar days” with “twenty one (21) calendar days” and delete the words: “subject to the employer giving the contractor a tax invoice for the amount due” 36.3 Remove reference to “No clause”, and replace “principal agent” with “employer” 36.7 Add the following: “Notwithstanding any clause to the contrary, on cancellation of 37.5 this agreement either by the employer or the and contractor; or for any reason and whatsoever, the contractor shall on written instruction, discontinue with the 38.7 works on a date stated and withdraw himself from the site. The contractor shall not be entitled to refuse to withdraw from the works on the grounds of any lien or right of retention or on the grounds of any other right whatsoever” 37.3.5 Replace “ninety (90)” with “one hundred and twenty (120) and 38.5.4

Page 18: EASTERN CAPE RURAL DEVELOPMENT AGENCY QUOTATION DOCUMENT ... · Quotations are requested from competent and registered contractors with the CIDB Contractor grading of 2GB and 3 GB

18

39.3.5 Add the following words at the end thereof: :”within one hundred and twenty (120) working days of completion of such report” 40.2.2 under clause 41 – Replace “one (1) year” with “three (3) years” 40.6 under clause 41 – Remove reference to no clause 40.7.1 Change “(10)” to “(15)” Add the following to the end thereof: Whether or not mediation resolves the dispute, the parties shall bear their own costs concerning the mediation and equally share the costs of the mediator and related costs.

42.0 Part 2: Contract Data provided by the Contractor:

POST-BID INFORMATION Note: All information for this section requires consultation with the contractor. The principal agent shall not pre-select any of the alternatives available to the contractor

42.5 CONTRACT DETAILS

42.5.1 Contractor: Postal address: ………………………………………………………………………………………… ………………………………………………………………………………………… ………………………………………………………………………………………… Tel: ………………………………… Fax: ………………………………… E-mail: ………………………………… TAX / VAT Registration No: ………………………………… Physical address: ………………………………………………………………………………………… ………………………………………………………………………………………… …………………………………………………………………………………………

42.5.2 The accepted contract sum inclusive of tax is R……………………………………………………………………… Amount in words: …………………………………………………………………………………………

42.5.3 [31.3]

The latest day of the month for the issue of an interim payment certificate: …………………………………………………

42.5.4 [32.12]

The preliminaries amounts shall be paid in terms of: Alternative A Alternative B

Page 19: EASTERN CAPE RURAL DEVELOPMENT AGENCY QUOTATION DOCUMENT ... · Quotations are requested from competent and registered contractors with the CIDB Contractor grading of 2GB and 3 GB

19

42.5.5 [32.12]

The preliminaries amounts shall be adjusted in terms of: Alternative A Alternative B

42.5.7 [14]

The security to be provided by the contractor: (a) in respect of contracts up to R1 million, the contractor will provide security in terms of 14.1 (b) in respect of contracts above R1 million, the contractor will provide, as security, one of the following:

NB. Guarantees submitted must be issued by either an insurance company duly registered in terms of the Short-Term Insurance Act, 1998 (Act 35 of 1998) or by a bank duly registered in terms of the Banks Act, 1990 (Act 94 of 1990) on the pro-forma referred to above. No alterations or amendments of the wording of the pro-forma will be accepted.

(1) cash deposit of 10 % of the contract sum Yes No

(2) payment reduction of 10% of the value certified in the payment certificate

Yes No

(3) cash deposit of 5% of the contract sum and a payment reduction of 5% of the value certified in the payment certificate

Yes No

(4) fixed construction guarantee of 5% of the contract sum and a payment reduction of 5% of the value certified in the payment certificate

Yes No

42.5.8 [29.7.2]

The annual building holiday period after the commencement of the construction period: from ……………………………………….. to …………………………………..

42.8 SIGNATURES OF THE CONTRACTING PARTIES

Thus done and signed at ____________________ on ________________________ ____________________________ ______________________________ Name of signatory for and behalf of the Employer who by signature hereof warrants authorization hereto ____________________________ ______________________________ Capacity of signatory as Witness Thus done and signed at ____________________ on ________________________ ____________________________ ______________________________ Name of signatory for and behalf of the Contractor who by signature hereof warrants authorization hereto

Page 20: EASTERN CAPE RURAL DEVELOPMENT AGENCY QUOTATION DOCUMENT ... · Quotations are requested from competent and registered contractors with the CIDB Contractor grading of 2GB and 3 GB

20

____________________________ ______________________________ Capacity of signatory as Witness

Page 21: EASTERN CAPE RURAL DEVELOPMENT AGENCY QUOTATION DOCUMENT ... · Quotations are requested from competent and registered contractors with the CIDB Contractor grading of 2GB and 3 GB

21

6. PRICING INSTRUCTIONS JBCC 2000 PRINCIPAL BUILDING AGREEMENT (Edition 4.1 of March 2005)

Project title: REFURBISHMENT WORK TO ECDRA OFFICES-MTHATHA

Bid No: RFQ 169-2016/17

1. BILLS OF QUANTITIES

The bills of quantities forms part of and must be read and priced in conjunction with all the other documents forming part of the contract documents, the Standard Conditions of Bid, Conditions of Contract, Specifications, Drawings and all other relevant documentation.

2. VALUE ADDED TAX

The bid price must include for Value Added Tax (VAT). All rates, provisional sums, etc. in the bills of quantities must however be net (exclusive of VAT) with VAT calculated and added to the Total Value thereof in the Final Summary.

3. TRADE NAMES Reference to any particular trade name, name, patent, design, type, specific origin or producer is purely to establish a standard for requirements. Products or articles of an equivalent standard may be substituted.

Page 22: EASTERN CAPE RURAL DEVELOPMENT AGENCY QUOTATION DOCUMENT ... · Quotations are requested from competent and registered contractors with the CIDB Contractor grading of 2GB and 3 GB

22

FORM A: CERTIFICATE OF AUTHORITY FOR SIGNATURE

1. CONTRACTOR 1.1 A “Certificate of Authority” to sign all documents in connection with this Tender and any contract or

agreement which may arise there from, duly signed and dated, shall be provided by the Board of Directors of the firm and shall be attached to this page. An example is given below. The letter must be on the letterhead of the Tenderer.

2. JOINT VENTURE - N/A 2.1 The document of formation of the Joint Venture shall be attached to this page. 2.2 A “Certificate of Authority” to sign all documents in connection with this Tender and any contract or

agreement which may arise there from, duly signed and dated, shall be provided by the Boards of Directors of each member of the Joint Venture and shall be attached to this page.

EXAMPLE OF A CERTIFICATE OF AUTHORITY FOR SIGNATORY “By resolution of the board of directors passed at a meeting held on ……………………………………………… Mr/Ms………………………………………..., whose signature appears below, has been duly authorised to sign all documents in connection with the Tender for BID NUMBER : RFQ 168- 2016/17 and any contract which may arise there from on behalf of: (Name of company or JV - block capitals) ………………….…………………………………… SIGNED ON BEHALF OF THE COMPANY ………………….…………………………………… IN HIS/HER CAPACITY AS: ………………….…………………………………… DATE: ………………….…………………………………… SIGNATURE OF SIGNATORY: ………………………….…………………………… WITNESSES: 1. …………………………..………………………..…

2. ……………………………..……………………..… IF THE TENDERER IS A SOLE MEMBER OR OWNER, THEN A LETTER TO THIS EFFECT MUST BE SUPPLIED.

Page 23: EASTERN CAPE RURAL DEVELOPMENT AGENCY QUOTATION DOCUMENT ... · Quotations are requested from competent and registered contractors with the CIDB Contractor grading of 2GB and 3 GB

23

DECLARATION OF INTEREST

Project Title REFURBISHMENT WORK TO ECDRA OFFICES-MTHATHA

Bid No. RFQ 169-2016/17

1. Any legal person, including persons employed by the state¹, or persons having a kinship with

persons employed by the state, including a blood relationship, may make an offer or offers in terms of this invitation to bid (includes a price quotation, advertised competitive bid, limited bid or proposal). In view of possible allegations of favouritism, should the resulting bid, or part thereof, be awarded to persons employed by the state, or to persons connected with or related to them, it is required that the bidder or his/her authorised representative declare his/her position in relation to the evaluating/adjudicating authority where -

- the bidder is employed by the state; and/or - the legal person on whose behalf the bidding document is signed, has a relationship with

persons/a person who are/is involved in the evaluation and or adjudication of the bid(s), or where it is known that such a relationship exists between the person or persons for or on whose behalf the declarant acts and persons who are involved with the evaluation and or adjudication of the bid.

2. In order to give effect to the above, the following questionnaire must be completed and submitted

with the bid. 2.1 Full Name of bidder or his or her representative: ………………………………………………………. 2.2 Identity Number: ………………………………………….………………………………………………… 2.3 Position occupied in the Company (director, trustee, shareholder²): …………….…………………… 2.4 Company Registration Number: ……………………………………………………………….……….… 2.5 Tax Reference Number: ………………………………………………………………….….………….… 2.6 VAT Registration Number: ……………………………………………………………..………............... 2.6.1 The names of all directors / trustees / shareholders / members, their individual identity numbers,

tax reference numbers and, if applicable, employee / persal numbers must be indicated in paragraph 3 below.

¹“State” means – (a) any national or provincial department, national or provincial public entity or constitutional institution

within the meaning of the Public Finance Management Act, 1999 (Act No. 1 of 1999); (b) any municipality or municipal entity; (c) provincial legislature; (d) national Assembly or the national Council of provinces; or (e) Parliament. ²”Shareholder” means a person who owns shares in the company and is actively involved in the

management of the enterprise or business and exercises control over the enterprise. 2.7 Are you or any person connected with the bidder presently YES / NO employed by the state? 2.7.1 If so, furnish the following particulars:

Name of person / director / trustee / shareholder / member: ……....………………………………

Page 24: EASTERN CAPE RURAL DEVELOPMENT AGENCY QUOTATION DOCUMENT ... · Quotations are requested from competent and registered contractors with the CIDB Contractor grading of 2GB and 3 GB

24

Name of state institution at which you or the person connected to the bidder is employed: .……………………………………… Position occupied in the state institution: .……………………………………… Any other particulars: ………………………………………………………………… ………………………………………………………………… …………………………………………………………………

2.7.2 If you are presently employed by the state, did you obtain YES / NO

the appropriate authority to undertake remunerative work outside employment in the public sector?

2.7.2.1 If yes, did you attached proof of such authority to the bid YES / NO

document? (Note: Failure to submit proof of such authority, where applicable, may result in the disqualification of the bid.)

2.7.2.2 If no, furnish reasons for non-submission of such proof: …………………………………………………………………. …………………………………………………………………. ………………………………………………………………….

2.8 Did you or your spouse, or any of the company’s directors / YES / NO trustees / shareholders / members or their spouses conduct business with the state in the previous twelve months?

2.8.1 If so, furnish particulars:

………………………………………………………………….. ………………………………………………………………….. …………………………………………………………………..

2.9 Do you, or any person connected with the bidder, have any YES / NO relationship (family, friend, other) with a person employed by the state and who may be involved with the evaluation and or adjudication of this bid?

2.9.1 If so, furnish particulars. ………………………………………………………….……... ……………………………………………………………...…. ………………………….…………………………….………… 2.10 Are you, or any person connected with the bidder, aware YES/NO

of any relationship (family, friend, other) between any other bidder and any person employed by the state who may be involved with the evaluation and or adjudication of this bid?

2.10.1 If so, furnish particulars:

………………………………………………………………… ………………………………………………………………… …………………………………………………………………

2.11 Do you or any of the directors / trustees / shareholders / members YES/NO

of the company have any interest in any other related companies whether or not they are bidding for this contract?

2.11.1 If so, furnish particulars:

…………………………………………………………………. ………………………………………………………………….

Page 25: EASTERN CAPE RURAL DEVELOPMENT AGENCY QUOTATION DOCUMENT ... · Quotations are requested from competent and registered contractors with the CIDB Contractor grading of 2GB and 3 GB

25

3. Full details of directors / trustees / members / shareholders

Full Name Identity Number Personal Tax

Reference Number

State Employee Number / Persal

Number

4 DECLARATION I, THE UNDERSIGNED (NAME)………………………………………………………………………………

CERTIFY THAT THE INFORMATION FURNISHED IN PARAGRAPHS 2 and 3 ABOVE IS CORRECT.

I ACCEPT THAT THE STATE MAY REJECT THE BID OR ACT AGAINST ME IN TERMS OF PARAGRAPH 23 OF THE GENERAL CONDITIONS OF CONTRACT SHOULD THIS DECLARATION PROVE TO BE FALSE.

………………………………………….. ………………………………………….. Signature Date

………………………………………….. ………………………………………….. Position Name of Bidder

Page 26: EASTERN CAPE RURAL DEVELOPMENT AGENCY QUOTATION DOCUMENT ... · Quotations are requested from competent and registered contractors with the CIDB Contractor grading of 2GB and 3 GB

26

SBD 6.1

PREFERENCE POINTS CLAIM FORM IN TERMS OF THE PREFERENTIAL PROCUREMENT REGULATIONS 2011

This preference form must form part of all bids invited. It contains general information and serves as a claim form for preference points for Broad-Based Black Economic Empowerment (B-BBEE) Status Level of Contribution. NB: BEFORE COMPLETING THIS FORM, BIDDERS MUST STUDY THE GENERAL CONDITIONS,

DEFINITIONS AND DIRECTIVES APPLICABLE IN RESPECT OF B-BBEE, AS PRESCRIBED IN THE PREFERENTIAL PROCUREMENT REGULATIONS, 2011.

1. GENERAL CONDITIONS 1.1 The following preference point systems are applicable to all bids:

- the 80/20 system for requirements with a Rand value of up to R1 000 000 (all applicable taxes included); and

- the 90/10 system for requirements with a Rand value above R1 000 000 (all applicable taxes included).

1.2 The value of this bid is estimated to not exceed R1 000 000 (all applicable taxes included) and

therefore the 80/20 system shall be applicable. 1.3 Preference points for this bid shall be awarded for:

(a) Price; and (b) B-BBEE Status Level of Contribution.

1.3.1 The maximum points for this bid are allocated as follows:

POINTS

1.3.1.1 PRICE 80 1.3.1.2 B-BBEE STATUS LEVEL OF CONTRIBUTION 20 Total points for Price and B-BBEE must not exceed 100

1.4 Failure on the part of a bidder to fill in and/or to sign this form and submit a B-BBEE Verification

Certificate from a Verification Agency accredited by the South African Accreditation System (SANAS) or a Registered Auditor approved by the Independent Regulatory Board of Auditors (IRBA) or an Accounting Officer as contemplated in the Close Corporation Act (CCA) together with the bid, will be interpreted to mean that preference points for B-BBEE status level of contribution are not claimed.

1.5. The purchaser reserves the right to require of a bidder, either before a bid is adjudicated or at any

time subsequently, to substantiate any claim in regard to preferences, in any manner required by the purchaser.

2. DEFINITIONS 2.1 “all applicable taxes” includes value-added tax, pay as you earn, income tax, unemployment

insurance fund contributions and skills development levies;

Page 27: EASTERN CAPE RURAL DEVELOPMENT AGENCY QUOTATION DOCUMENT ... · Quotations are requested from competent and registered contractors with the CIDB Contractor grading of 2GB and 3 GB

27

2.2 “B-BBEE” means broad-based black economic empowerment as defined in section 1 of the Broad-Based Black Economic Empowerment Act;

2.3 “B-BBEE status level of contributor” means the B-BBEE status received by a measured entity based on its overall performance using the relevant scorecard contained in the Codes of Good Practice on Black Economic Empowerment, issued in terms of section 9(1) of the Broad-Based Black Economic Empowerment Act;

2.4 “bid” means a written offer in a prescribed or stipulated form in response to an invitation by an

organ of state for the provision of services, works or goods, through price quotations, advertised competitive bidding processes or proposals;

2.5 “Broad-Based Black Economic Empowerment Act” means the Broad-Based Black Economic

Empowerment Act, 2003 (Act No. 53 of 2003); 2.6 “comparative price” means the price after the factors of a non-firm price and all unconditional

discounts that can be utilized have been taken into consideration; 2.7 “consortium or joint venture” means an association of persons for the purpose of combining

their expertise, property, capital, efforts, skill and knowledge in an activity for the execution of a contract;

2.8 “contract” means the agreement that results from the acceptance of a bid by an organ of state; 2.9 “EME” means any enterprise with an annual total revenue of R10 million or less; 2.10 “Firm price” means the price that is only subject to adjustments in accordance with the actual

increase or decrease resulting from the change, imposition, or abolition of customs or excise duty and any other duty, levy, or tax, which, in terms of the law or regulation, is binding on the contractor and demonstrably has an influence on the price of any supplies, or the rendering costs of any service, for the execution of the contract;

2.11 “functionality” means the measurement according to predetermined norms, as set out in the bid

documents, of a service or commodity that is designed to be practical and useful, working or operating, taking into account, among other factors, the quality, reliability, viability and durability of a service and the technical capacity and ability of a bidder;

2.12 “non-firm prices” means all prices other than “firm” prices; 2.13 “person” includes a juristic person;

2.14 “rand value” means the total estimated value of a contract in South African currency, calculated

at the time of bid invitations, and includes all applicable taxes and excise duties; 2.15 “sub-contract” means the primary contractor’s assigning, leasing, making out work to, or

employing, another person to support such primary contractor in the execution of part of a project in terms of the contract;

2.16 “total revenue” bears the same meaning assigned to this expression in the Codes of Good

Practice on Black Economic Empowerment, issued in terms of section 9(1) of the Broad-Based Black Economic Empowerment Act and promulgated in the Government Gazette on 9 February 2007;

2.17 “trust” means the arrangement through which the property of one person is made over or

bequeathed to a trustee to administer such property for the benefit of another person; and 2.18 “trustee” means any person, including the founder of a trust, to whom property is bequeathed in

order for such property to be administered for the benefit of another person. 3. ADJUDICATION USING A POINT SYSTEM 3.1 The bidder obtaining the highest number of total points will be awarded the contract.

Page 28: EASTERN CAPE RURAL DEVELOPMENT AGENCY QUOTATION DOCUMENT ... · Quotations are requested from competent and registered contractors with the CIDB Contractor grading of 2GB and 3 GB

28

3.2 Preference points shall be calculated after prices have been brought to a comparative basis taking into account all factors of non-firm prices and all unconditional discounts.

3.3 Points scored must be rounded off to the nearest 2 decimal places. 3.4 In the event that two or more bids have scored equal total points, the successful bid must be the

one scoring the highest number of preference points for B-BBEE. 3.5 However, when functionality is part of the evaluation process and two or more bids have scored

equal points including equal preference points for B-BBEE, the successful bid must be the one scoring the highest score for functionality.

3.6 Should two or more bids be equal in all respects, the award shall be decided by the drawing of

lots. 4. POINTS AWARDED FOR PRICE 4.1 The 80/20 or 90/10 Preference Point Systems A maximum of 80 or 90 points is allocated for price on the following basis: 80/20 or 90/10

or

Where Ps = Points scored for comparative price of bid under consideration Pt = Comparative price of bid under consideration Pmin = Comparative price of lowest acceptable bid 5. POINTS AWARDED FOR B-BBEE STATUS LEVEL OF CONTRIBUTION 5.1 In terms of Regulation 5 (2) and 6 (2) of the Preferential Procurement Regulations, preference points

must be awarded to a bidder for attaining the B-BBEE status level of contribution in accordance with the table below:

B-BBEE Status Level of Contributor

Number of points

(90/10 system)

Number of points

(80/20 system)

1 10 20

2 9 18

3 8 16

4 5 12

5 4 8

6 3 6

7 2 4

8 1 2

Non-compliant contributor

0 0

min

min180

P

PPtPs

min

min190

P

PPtPs

Page 29: EASTERN CAPE RURAL DEVELOPMENT AGENCY QUOTATION DOCUMENT ... · Quotations are requested from competent and registered contractors with the CIDB Contractor grading of 2GB and 3 GB

29

5.2 Bidders who qualify as EMEs in terms of the B-BBEE Act must submit a certificate issued by an

Accounting Officer as contemplated in the CCA or a Verification Agency accredited by SANAS or a

Registered Auditor. Registered auditors do not need to meet the prerequisite for IRBA’s approval for the purpose of conducting verification and issuing EMEs with B-BBEE Status Level Certificates.

5.3 Bidders other than EMEs must submit their original and valid B-BBEE status level verification

certificate or a certified copy thereof, substantiating their B-BBEE rating issued by a Registered Auditor approved by IRBA or a Verification Agency accredited by SANAS.

5.4 A trust, consortium or joint venture, will qualify for points for their B-BBEE status level as a legal

entity, provided that the entity submits their B-BBEE status level certificate. 5.5 A trust, consortium or joint venture will qualify for points for their B-BBEE status level as an

unincorporated entity, provided that the entity submits their consolidated B-BBEE scorecard as if they were a group structure and that such a consolidated B-BBEE scorecard is prepared for every separate bid.

5.6 Tertiary institutions and public entities will be required to submit their B-BBEE status level certificates

in terms of the specialized scorecard contained in the B-BBEE Codes of Good Practice. 5.7 A person will not be awarded points for B-BBEE status level if it is indicated in the bid documents

that such a bidder intends sub-contracting more than 25% of the value of the contract to any other enterprise that does not qualify for at least the points that such a bidder qualifies for, unless the intended sub-contractor is an EME that has the capability and ability to execute the sub-contract.

5.8 A person awarded a contract may not sub-contract more than 25% of the value of the contract to any

other enterprise that does not have an equal or higher B-BBEE status level than the person concerned, unless the contract is sub-contracted to an EME that has the capability and ability to execute the sub-contract.

6. BID DECLARATION 6.1 Bidders who claim points in respect of B-BBEE Status Level of Contribution must complete the

following: 7. B-BBEE STATUS LEVEL OF CONTRIBUTION CLAIMED IN TERMS OF PARAGRAPHS 1.3.1.2

AND 5.1 7.1 B-BBEE Status Level of Contribution: ………… = ………… (maximum of 20 points)

(Points claimed in respect of paragraph 7.1 must be in accordance with the table reflected in paragraph 5.1 and must be substantiated by means of a B-BBEE certificate issued by a Verification Agency accredited by SANAS or a Registered Auditor approved by IRBA or an Accounting Officer as contemplated in the CCA).

8. SUB-CONTRACTING 8.1 Will any portion of the contract be sub-contracted? YES / NO (delete which is not applicable) 8.1.1 If yes, indicate: (i) what percentage of the contract will be subcontracted? ...……............……………….…% (ii) the name of the sub-contractor? ….………………………………………………..……….. (iii) the B-BBEE status level of the sub-contractor? …………………………………………….. (iv) whether the sub-contractor is an EME? …….YES / NO (delete which is not applicable) 9. DECLARATION WITH REGARD TO COMPANY / FIRM 9.1 Name of company / firm : ……………………………………………………………………………

Page 30: EASTERN CAPE RURAL DEVELOPMENT AGENCY QUOTATION DOCUMENT ... · Quotations are requested from competent and registered contractors with the CIDB Contractor grading of 2GB and 3 GB

30

9.2 VAT registration number : ……………………………………………………………………………

9.3 Company registration number : ……………………………………………………………………………

9.4 TYPE OF COMPANY / FIRM

Partnership/Joint Venture / Consortium

One person business/sole propriety

Close corporation

Company

(Pty) Limited [TICK APPLICABLE BOX]

9.5 DESCRIBE PRINCIPAL BUSINESS ACTIVITIES

………….. .................................................................................................................................................

……………… ............................................................................................................................................

…………….. .............................................................................................................................................

9.6 COMPANY CLASSIFICATION

Manufacturer

Supplier

Professional service provider

Other service providers, e.g. transporter, etc. [TICK APPLICABLE BOX]

9.7 Total number of years the company / firm has been in business? …..…………………………………… 9.8 I / we, the undersigned, who is / are duly authorised to do so on behalf of the company/firm, certify

that the points claimed, based on the B-BBE status level of contribution indicated in paragraph 7 of the foregoing certificate, qualifies the company / firm for the preference(s) shown and I / we acknowledge that:

(i) The information furnished is true and correct; (ii) The preference points claimed are in accordance with the General Conditions as indicated

in paragraph 1 of this form. (iii) In the event of a contract being awarded as a result of points claimed as shown in

paragraph 7, the contractor may be required to furnish documentary proof to the satisfaction of the purchaser that the claims are correct;

(iv) If the B-BBEE status level of contribution has been claimed or obtained on a fraudulent

basis or any of the conditions of contract have not been fulfilled, the purchaser may, in addition to any other remedy it may have –

(a) disqualify the person from the bidding process; (b) recover costs, losses or damages it has incurred or suffered as a result of that

person’s conduct; (c) cancel the contract and claim any damages which it has suffered as a result of

having to make less favourable arrangements due to such cancellation;

(d) restrict the bidder or contractor, its shareholders and directors, or only the shareholders and directors who acted on a fraudulent basis, from obtaining business from any organ of state for a period not exceeding 10 years, after the audi alteram partem (hear the other side) rule has been applied; and

(e) forward the matter for criminal prosecution

Page 31: EASTERN CAPE RURAL DEVELOPMENT AGENCY QUOTATION DOCUMENT ... · Quotations are requested from competent and registered contractors with the CIDB Contractor grading of 2GB and 3 GB

31

WITNESSES: 1. ……………………………………… …………………………………… SIGNATURE(S) OF BIDDER(S) 2. ……………………………………… DATE: …………………………………….….. ADDRESS: ………………………………….. ………………………………….. .………………………………….

Page 32: EASTERN CAPE RURAL DEVELOPMENT AGENCY QUOTATION DOCUMENT ... · Quotations are requested from competent and registered contractors with the CIDB Contractor grading of 2GB and 3 GB

32

TAX CERTIFICATE; LETTER OF GOOD STANDING WITH THE COMPENSATION COMMISSIONER; PROOF OF PROFESSIONAL INDEMNITY a) The Tenderer shall attach to the tender a valid Tax Compliance Status certificate (TCS) PIN b) The Tenderer shall attach to the tender a valid letter of good standing with the Compensation

Commissioner of FEM. c) The Tenderer shall provide proof of his insurance showing the scope of that insurance. The Policy

insurance shall be valid until the anticipated end of the design and Tender stage. This shall be attached to the separate technical proposal. In the event of annual insurance policy certificates being issued, updated proof shall be supplied to the Employer as required. If the required information as listed above is not provided, then the Tender will be deemed to be non-responsive and therefore rejected.

SIGNED ON BEHALF OF THE TENDERER: …………………………………………………………………..……

Page 33: EASTERN CAPE RURAL DEVELOPMENT AGENCY QUOTATION DOCUMENT ... · Quotations are requested from competent and registered contractors with the CIDB Contractor grading of 2GB and 3 GB

33

SBD 9

CERTIFICATE OF INDEPENDENT BID DETERMINATION

1 This Standard Bidding Document (SBD) must form part of all bids¹ invited. 2 Section 4 (1) (b) (iii) of the Competition Act No. 89 of 1998, as amended, prohibits an agreement

between, or concerted practice by, firms, or a decision by an association of firms, if it is between parties in a horizontal relationship and if it involves collusive bidding (or bid rigging).² Collusive bidding is a pe se prohibition meaning that it cannot be justified under any grounds.

3 Treasury Regulation 16A9 prescribes that accounting officers and accounting authorities must take

all reasonable steps to prevent abuse of the supply chain management system and authorizes accounting officers and accounting authorities to:

a. disregard the bid of any bidder if that bidder, or any of its directors have abused the

institution’s supply chain management system and or committed fraud or any other improper conduct in relation to such system.

b. cancel a contract awarded to a supplier of goods and services if the supplier committed any

corrupt or fraudulent act during the bidding process or the execution of that contract. 4 This SBD serves as a certificate of declaration that would be used by institutions to ensure that,

when bids are considered, reasonable steps are taken to prevent any form of bid-rigging. 5 In order to give effect to the above, the attached Certificate of Bid Determination (SBD 9) must be

completed and submitted with the bid: ¹ Includes price quotations, advertised competitive bids, limited bids and proposals. ² Bid rigging (or collusive bidding) occurs when businesses, that would otherwise be expected to compete, secretly conspire to raise prices or lower the quality of goods and / or services for purchasers who wish to acquire goods and / or services through a bidding process. Bid rigging is, therefore, an agreement between competitors not to compete.

Page 34: EASTERN CAPE RURAL DEVELOPMENT AGENCY QUOTATION DOCUMENT ... · Quotations are requested from competent and registered contractors with the CIDB Contractor grading of 2GB and 3 GB

34

SBD 9

CERTIFICATE OF INDEPENDENT BID DETERMINATION I, the undersigned, in submitting the accompanying bid: ______________________________________________________________________________________

(Bid Number and Description) in response to the invitation for the bid made by: INDEPENDENT DEVELOPMENT TRUST (IDT) do hereby make the following statements that I certify to be true and complete in every respect: I certify, on behalf of: _______________________________________________________ that:

(Name of Bidder)

1. I have read and I understand the contents of this Certificate;

2. I understand that the accompanying bid will be disqualified if this Certificate is found not to be true and complete in every respect;

3. I am authorized by the bidder to sign this Certificate, and to submit the accompanying bid, on behalf

of the bidder;

4. Each person whose signature appears on the accompanying bid has been authorized by the bidder

to determine the terms of, and to sign the bid, on behalf of the bidder;

5. For the purposes of this Certificate and the accompanying bid, I understand that the word

“competitor” shall include any individual or organization, other than the bidder, whether or not affiliated with the bidder, who:

(a) has been requested to submit a bid in response to this bid invitation; (b) could potentially submit a bid in response to this bid invitation, based on their qualifications,

abilities or experience; and (c) provides the same goods and services as the bidder and/or is in the same line of business

as the bidder 6. The bidder has arrived at the accompanying bid independently from, and without consultation,

communication, agreement or arrangement with any competitor. However communication between partners in a joint venture or consortium³ will not be construed as collusive bidding.

7. In particular, without limiting the generality of paragraphs 6 above, there has been no consultation,

communication, agreement or arrangement with any competitor regarding:

(a) prices; (b) geographical area where product or service will be rendered (market allocation) (c) methods, factors or formulas used to calculate prices; (d) the intention or decision to submit or not to submit, a bid; (e) the submission of a bid which does not meet the specifications and conditions of the bid; or (f) bidding with the intention not to win the bid.

8. In addition, there have been no consultations, communications, agreements or arrangements with

any competitor regarding the quality, quantity, specifications and conditions or delivery particulars of the products or services to which this bid invitation relates.

Page 35: EASTERN CAPE RURAL DEVELOPMENT AGENCY QUOTATION DOCUMENT ... · Quotations are requested from competent and registered contractors with the CIDB Contractor grading of 2GB and 3 GB

35

9. The terms of the accompanying bid have not been, and will not be, disclosed by the bidder, directly or indirectly, to any competitor, prior to the date and time of the official bid opening or of the awarding of the contract.

³ Joint venture or Consortium means an association of persons for the purpose of combining their expertise, property, capital, efforts, skill and knowledge in an activity for the execution of a contract. 10. I am aware that, in addition and without prejudice to any other remedy provided to combat any

restrictive practices related to bids and contracts, bids that are suspicious will be reported to the Competition Commission for investigation and possible imposition of administrative penalties in terms of Section 59 of the Competition Act No. 89 of 1998 and or may be reported to the National Prosecuting Authority (NPA) for criminal investigation and or may be restricted from conducting business with the public sector for a period not exceeding ten (10) years in terms of the Prevention and Combating of Corrupt Activities Act No 12 of 2004 or any other applicable legislation.

………………………………………………… …………………………………

Signature Date …………………………………………………. …………………………………

Position Name of Bidder

Page 36: EASTERN CAPE RURAL DEVELOPMENT AGENCY QUOTATION DOCUMENT ... · Quotations are requested from competent and registered contractors with the CIDB Contractor grading of 2GB and 3 GB

36

TENDER QUALIFICATIONS AND ALTERNATIVE TENDERS Should the Tenderer wish to make any departure from the Conditions of Contract, Scope of Services or Pricing Schedule, or to qualify his Tender in any way, he shall set out his proposals clearly in the table below. Alternatively the Tenderer may state the departures or qualifications in a covering letter attached to his Tender and referred to below. If there is no entry or reference made in the table below, then the Tender will be deemed to have no qualifications or alternatives. A copy of this form shall be included in the Technical Proposal.

PAGE DESCRIPTION

SIGNED ON BEHALF OF THE TENDERER: ..................................................................

Page 37: EASTERN CAPE RURAL DEVELOPMENT AGENCY QUOTATION DOCUMENT ... · Quotations are requested from competent and registered contractors with the CIDB Contractor grading of 2GB and 3 GB

37

Compulsory Enterprise Questionnaire

The following particulars must be furnished. In the case of a joint venture, separate enterprise questionnaires in respect of each partner must be completed and submitted, otherwise the tender will be declared non-responsive.

Section 1: Name of enterprise: . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .. . . .

Section 2: VAT registration number, if any: . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

Section 3: CIDB registration number, if any: . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

Section 4: Particulars of sole proprietors and partners in partnerships

Name* Identity number* Personal income tax number*

* Complete only if sole proprietor or partnership and attach separate page if more than 3 partners

Section 5: Particulars of companies and close corporations

Company registration number . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

Close corporation number . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

Tax reference number . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

Section 6: Record in the service of the state

Indicate by marking the relevant boxes with a cross, if any sole proprietor, partner in a partnership or director, manager, principal shareholder or stakeholder in a company or close corporation is currently or has been within the last 12 months in the service of any of the following:

a member of any municipal council

a member of any provincial legislature

a member of the National Assembly or the National Council of Province

a member of the board of directors of any municipal entity

an official of any municipality or municipal entity

an employee of any provincial department, national or provincial public entity or constitutional institution within the meaning of the Public Finance Management Act, 1999 (Act 1 of 1999)

a member of an accounting authority of any national or provincial public entity

an employee of Parliament or a provincial legislature

If any of the above boxes are marked, disclose the following:

Name of sole proprietor, partner, director, manager,

principal shareholder or stakeholder

Name of institution, public office, board or organ of state and position

held

Status of service (tick appropriate

column)

Current Within last 12 months

Page 38: EASTERN CAPE RURAL DEVELOPMENT AGENCY QUOTATION DOCUMENT ... · Quotations are requested from competent and registered contractors with the CIDB Contractor grading of 2GB and 3 GB

38

*insert separate page if necessary

Section 7: Record of spouses, children and parents in the service of the state

Indicate by marking the relevant boxes with a cross, if any spouse, child or parent of a sole proprietor, partner in a partnership or director, manager, principal shareholder or stakeholder in a company or close corporation is currently or has been within the last 12 months been in the service of any of the following:

a member of any municipal council

a member of any provincial legislature

a member of the National Assembly or the National Council of Province

a member of the board of directors of any municipal entity

an official of any municipality or municipal entity

an employee of any provincial department, national or provincial public entity or constitutional institution within the meaning of the Public Finance Management Act, 1999 (Act 1 of 1999)

a member of an accounting authority of any national or provincial public entity

an employee of Parliament or a provincial legislature

Name of spouse, child or parent

Name of institution, public office, board or organ of state and position

held

Status of service (tick appropriate

column)

Current Within last 12 months

*insert separate page if necessary

The undersigned, who warrants that he / she is duly authorised to do so on behalf of the enterprise: i) authorizes the Employer to obtain a tax clearance certificate from the South African Revenue Services

that my / our tax matters are in order; ii) confirms that the neither the name of the enterprise or the name of any partner, manager, director or

other person, who wholly or partly exercises, or may exercise, control over the enterprise appears on the Register of Tender Defaulters established in terms of the Prevention and Combating of Corrupt Activities Act of 2004;

iii) confirms that no partner, member, director or other person, who wholly or partly exercises, or may exercise, control over the enterprise appears, has within the last five years been convicted of fraud or corruption;

iv) confirms that I / we are not associated, linked or involved with any other tendering entities submitting tender offers and have no other relationship with any of the tenderers or those responsible for compiling the scope of work that could cause or be interpreted as a conflict of interest; and

iv) confirms that the contents of this questionnaire are within my personal knowledge and are to the best of my belief both true and correct.

Signed

Date

Name

Position

Enterprise name

Page 39: EASTERN CAPE RURAL DEVELOPMENT AGENCY QUOTATION DOCUMENT ... · Quotations are requested from competent and registered contractors with the CIDB Contractor grading of 2GB and 3 GB

39

EASTERN CAPE RURAL DEVELOPMENT AGENCY TENDER NO: BID NUMBER: RFQ 169-2016/17 REFURBISHMENT WORKTO ECDRA OFFICES-MTHATHA Eastern Cape Rural Development Agency Unit 12 D, Beacon Bay Crossing Beacon Bay East London 5201 Sir REFURBISHMENT WORKS TO ECDRA OFFICES-MTHATHA:

DATE OF PUBLICATION OF QUOTATION

CLOSING DATE AND TIME FOR SUBMISSION OF QUOTATION

THIS QUOTATION IS VALID FOR ACCEPTANCE UNTIL

17 February 2017

03 March 2017 @ 12h00 90 calendar Days from date of closing

FORM OF OFFER AND ACCEPTANCE OFFER The Employer, identified in the Acceptance signature block, has solicited offers to enter into a contract for the procurement of: “CONTRACTOR FOR THE ............................... ............................................................................................... The Bidder, identified in the Offer signature block, has examined the documents listed in the bid data and addenda thereto as listed in the bid schedules, and by submitting this offer has accepted the Conditions of Bid. By the representative of the Bidder, deemed to be duly authorized, signing this part of this Form of Offer and Acceptance, the Bidder offers to perform all the obligations and liabilities of the Contractor under the Contract including compliance with all its terms and conditions according to their true intent and meaning for an amount to be deemed in accordance with the Conditions of Contract identified in the Contract Data. The offered total of the prices inclusive of value-added tax is: ……………………………..………………………………………………………….Rand (in word); R…………………………………………………………………………………………...(in figures) This Offer may be accepted by the Employer by signing the Acceptance part of this Form of Offer and Acceptance and returning one copy of this document to the Bidder before the end of the period of validity stated in the Bid Data, whereupon the Bidder becomes the party named as the Contractor in terms of the Conditions of Contract identified in the Contract Data. Signature ……………………………… Date ……………………………… Name ……………………………… Capacity ……………………………… For the Bidder (Name and address of organization) …………………………………………………………

Page 40: EASTERN CAPE RURAL DEVELOPMENT AGENCY QUOTATION DOCUMENT ... · Quotations are requested from competent and registered contractors with the CIDB Contractor grading of 2GB and 3 GB

40

Witness 1 Signature ……………………………… Date ……………….. Name ……………………… Witness 2 Signature ……………………………… Date ……………….. Name ……………………… ACCEPTANCE By signing this part of this Form of Offer and Acceptance, the Employer accepts the Bidder’s Offer. In consideration thereof, the Employer shall pay the Contractor the amount due in accordance with the Conditions of Contract identified in the Contract Data. Acceptance of the Bidder’s Offer shall form an agreement between the Employer and the Bidder upon the terms and conditions contained in this agreement and in the Contract that is the subject of this agreement. Deviations from and amendments to the documents listed in the Bid Data and any addenda thereto, as listed in the Bid Schedules, as well as any changes to the terms of the Offer agreed by the Bidder and the Employer during this process of offer and acceptance, are contained in the Schedule of Deviations attached to and forming part of this Agreement. No amendments to or deviations from said documents are valid unless contained in this schedule, which shall be signed by the authorized representative(s) of both parties. The Bidder shall, within two weeks of receiving a completed copy of this Agreement including the Schedule of Deviations, (if any), contact the Employer’s agent (whose details are given in the Contract Data) to arrange the delivery of any bonds, guarantees, proof of insurance and any other documentation to be provided in terms of the Conditions of Contract identified in the Contract Data on, or just after, the date on which this Agreement comes into effect. Failure to fulfil any of the obligations in accordance with those terms shall constitute a repudiation of this Agreement. Notwithstanding anything contained herein, this Agreement comes into effect on the date when the Bidder receives one fully completed original copy of this document, including the Schedule of Deviations (if any). Unless the Bidder (now Contractor), within 5 days of the date of such receipt, notifies the Employer in writing of any reason why he cannot accept the contents of this Agreement, this Agreement shall constitute a binding contract between the parties. Signature ……………………..………………… Date ……………………..………………… Name ……………………..………………… Capacity ……………………..………………… For the Employer ……………………………………………………………………… (Name and address of organization) AS WITNESSES Witness 1 Signature ……………………………… Date ……………….. Name ……………………… Witness 2 Signature ……………………………… Date ……………….. Name ………………………

Page 41: EASTERN CAPE RURAL DEVELOPMENT AGENCY QUOTATION DOCUMENT ... · Quotations are requested from competent and registered contractors with the CIDB Contractor grading of 2GB and 3 GB

41

PROJECT REFERENCE RETURNABLE 1 OF 3

NOTE: This returnable document must be completed by the person who was the principal agent on the infrastructure project of similar value and complexity that was completed

successfully by the tenderer.

I, ___________________________________________________ (name and surname) of

_____________________________________________________ (company name) declare

that I was the principal agent on the following building construction project successfully

executed by _______________________________________________ (name of tenderer):

Project name: ____________________________________________________________

Project location: __________________________________________________________

Construction period: _____________________ Completion date: ____________________

Contract value: _____________________________

A. Please evaluate the performance of the Tenderer on the abovementioned project, on which you were the principal agent, by inserting “Yes” in the relevant box below:

Very

Poor 1

Poor

2

Fair

3

Good

4

Excellent

5

1. Project performance / time

management / programming

2. Quality of workmanship

3. Resources: Personnel

4. Resources: Plant

5. Financial management /

payment of subcontractors / cash flow, etc

B. Would you consider / recommend this tenderer again:

YES NO

C. Any other comments:

___________________________________________________________________________

__________________________________________________________________________

Project title: REFURBISHMENT WORK TO ECRDA OFFICES-MTHATHA

Bid no: RFQ 169-2016/17

Page 42: EASTERN CAPE RURAL DEVELOPMENT AGENCY QUOTATION DOCUMENT ... · Quotations are requested from competent and registered contractors with the CIDB Contractor grading of 2GB and 3 GB

42

D. My contact details are:

Telephone: __________________ Cellphone: __________________ Fax: _______________

E-mail: ________________________________

Thus signed at __________________________ on this _______ day of ____________ 2017

_________________________ Signature of principal agent

NOTE: If reference cannot be verified due to the inability to contact the referee or failure on his/her part to respond to a written request to do so, that reference will not score any points.

_____________________________________________________________________________

Name of Tenderer

_________________________ _______________________

Signature of Tenderer Date

COMPANY STAMP

Page 43: EASTERN CAPE RURAL DEVELOPMENT AGENCY QUOTATION DOCUMENT ... · Quotations are requested from competent and registered contractors with the CIDB Contractor grading of 2GB and 3 GB

43

PROJECT REFERENCE RETURNABLE 2 OF 3

NOTE: This returnable document must be completed by the person who was the principal agent on the infrastructure project of similar value and complexity that was completed

successfully by the tenderer. I, ___________________________________________________ (name and surname) of

_____________________________________________________ (company name) declare

that I was the principal agent on the following building construction project successfully

executed by _______________________________________________ (name of tenderer):

Project name: ____________________________________________________________

Project location: __________________________________________________________

Construction period: _____________________ Completion date: ____________________

Contract value: _____________________________

A. Please evaluate the performance of the Tenderer on the abovementioned project, on which you were the

principal agent, by inserting “Yes” in the relevant box below:

Very

Poor

1

Poor

2

Fair

3

Good

4

Excellent

5

1. Project performance / time

management / programming

2. Quality of workmanship

3. Resources: Personnel

4. Resources: Plant

5. Financial management /

payment of subcontractors / cash flow, etc

B. Would you consider / recommend this tenderer again:

YES NO

C. Any other comments:

________________________________________________________________________

Project title: REFURBISHMENT WORK TO ECRDA OFFICES-MTHATHA

Bid no: RFQ 169-2016/17

Page 44: EASTERN CAPE RURAL DEVELOPMENT AGENCY QUOTATION DOCUMENT ... · Quotations are requested from competent and registered contractors with the CIDB Contractor grading of 2GB and 3 GB

44

_______________________________________________________________________

D. My contact details are:

Telephone: __________________ Cellphone: __________________ Fax: _______________

E-mail: ________________________________

Thus signed at __________________________ on this _______ day of ____________ 2017

_________________________ Signature of principal agent

NOTE: If reference cannot be verified due to the inability to contact the referee or failure on his/her part to respond to a written request to do so, that reference will not score any points.

_____________________________________________________________________________

Name of Tenderer

_______________________ _______________________

Signature of Tenderer Date

COMPANY STAMP

Page 45: EASTERN CAPE RURAL DEVELOPMENT AGENCY QUOTATION DOCUMENT ... · Quotations are requested from competent and registered contractors with the CIDB Contractor grading of 2GB and 3 GB

45

PROJECT REFERENCE RETURNABLE 3 OF 3

NOTE: This returnable document must be completed by the person who was the principal agent on the infrastructure project of similar value and complexity that was completed

successfully by the tenderer.

I, ___________________________________________________ (name and surname) of

_____________________________________________________ (company name) declare

that I was the principal agent on the following building construction project successfully

executed by _______________________________________________ (name of tenderer):

Project name: ____________________________________________________________

Project location: __________________________________________________________

Construction period: _____________________ Completion date: ____________________

Contract value: _____________________________

A. Please evaluate the performance of the Tenderer on the abovementioned project, on which you were the

principal agent, by inserting “Yes” in the relevant box below:

Very Poor

1

Poor

2

Fair

3

Good

4

Excellent

5

1. Project performance / time management / programming

2. Quality of workmanship

3. Resources: Personnel

4. Resources: Plant

5. Financial management / payment of subcontractors /

cash flow, etc

B. Would you consider / recommend this tenderer again:

YES NO

C. Any other comments:

________________________________________________________________________

Project title: REFURBISHMENT WORK TO ECRDA OFFICES-MTHATHA

Bid no: RFQ 169-2016/17

Page 46: EASTERN CAPE RURAL DEVELOPMENT AGENCY QUOTATION DOCUMENT ... · Quotations are requested from competent and registered contractors with the CIDB Contractor grading of 2GB and 3 GB

46

_______________________________________________________________________

D. My contact details are:

Telephone: __________________ Cellphone: __________________ Fax: _______________

E-mail: ________________________________

Thus signed at __________________________ on this _______ day of ____________ 2017

_________________________ Signature of principal agent

NOTE: If reference cannot be verified due to the inability to contact the referee or failure on his/her part to respond to a written request to do so, that reference will not score any points. _____________________________________________________________________________

Name of Tenderer

_______________________________________________ _______________________

Signature of Tenderer Date

COMPANY STAMP

Page 47: EASTERN CAPE RURAL DEVELOPMENT AGENCY QUOTATION DOCUMENT ... · Quotations are requested from competent and registered contractors with the CIDB Contractor grading of 2GB and 3 GB

RFQ169-2016/17

Item Quantity Rate AmountNo

BILL No. 1

BUILDING WORKS - ALL TRADES

Note:

For Preambles see "Model Preambles for Trades" as publishedby the Association of South African Quantity Surveyors (2008Edition).

PRELIMINARIES

The Preliminaries to be included in the Contract will be JBCCPreliminaries Code 2103, May 2005 edition for use with theJBCC Principal Building Agreement Edition 4.1 Code 2101,March 2005.

For ease of purpose for the quotation, only the salient clauseshave been included for pricing by the Contractor.

1 A12.0 EFFECTING INSURANCES

Clause 12.0

Fixed:____________ Value related:____________ Timerelated:____________ Item

The Contractor is to provide the insurances or proof thereof inaccordance with Clause 42.3 contained in the Contract Data:

2 A14.0 SECURITY

Clause 14.0

Clauses 14.1 - 14.8 are amended by replacing them with thefollowing:

14.1 In respect of contracts with a contract sum up to R1million, the security to be provided by the contractor to theemployer will be a payment reduction of five per cent (5%) ofthe value certified in the payment certificate (excluding VAT)

Fixed:____________ Value related:____________ Timerelated:____________

Item

Carried to Collection R Bill No. 1PRELIMINARIESREFURBISHMENT WORK TO ECRDA OFFICES - MTHATHA

- 1 -

Page 48: EASTERN CAPE RURAL DEVELOPMENT AGENCY QUOTATION DOCUMENT ... · Quotations are requested from competent and registered contractors with the CIDB Contractor grading of 2GB and 3 GB

RFQ169-2016/17

1 B3.4 Existing premises occupied

Fixed:____________ Value related:____________ Timerelated:____________ Item

2 B3.8 Services - unknown

Fixed:____________ Value related:____________ Timerelated:____________ Item

3 B4.1 Management of the works

Fixed:____________ Value related:____________ Timerelated:____________ Item

4 B4.5 Labour and plant records

Fixed:____________ Value related:____________ Timerelated:____________ Item

5 B6.1 Deposits and fees

Fixed:____________ Value related:____________ Timerelated:____________ Item

6 B6.2 Enclosure of the works

Fixed:____________ Value related:____________ Timerelated:____________ Item

7 B6.4 Plant, equipment, sheds and offices

Fixed:____________ Value related:____________ Timerelated:____________ Item

8 B7.2 Water

Fixed:____________ Value related:____________ Timerelated:____________

Option C (by employer - metered)Item

9 B7.3 Electricity

Fixed:____________ Value related:____________ Timerelated:____________

Option C (by employer - metered)Item

Carried to Collection R Bill No. 1PRELIMINARIESREFURBISHMENT WORK TO ECRDA OFFICES - MTHATHA

- 2 -

Page 49: EASTERN CAPE RURAL DEVELOPMENT AGENCY QUOTATION DOCUMENT ... · Quotations are requested from competent and registered contractors with the CIDB Contractor grading of 2GB and 3 GB

RFQ169-2016/17

1 B7.4 Telecommunication facilities

Fixed:____________ Value related:____________ Timerelated:____________

TelephoneYES

FacsimileYES

E-mailYES Item

2 B7.5 Ablution facilities

Fixed:____________ Value related:____________ Timerelated:____________

Option B (by employer)

Item

3 B11.3 Security of the works

Fixed:____________ Value related:____________ Timerelated:____________ Item

4 B11.7 Works cleaning and clearing

Fixed:____________ Value related:____________ Timerelated:____________ Item

Carried to Collection R Bill No. 1PRELIMINARIESREFURBISHMENT WORK TO ECRDA OFFICES - MTHATHA

- 3 -

Page 50: EASTERN CAPE RURAL DEVELOPMENT AGENCY QUOTATION DOCUMENT ... · Quotations are requested from competent and registered contractors with the CIDB Contractor grading of 2GB and 3 GB

RFQ169-2016/17

1 C11.0 OCCUPATIONAL HEALTH AND SAFETY ACT

The contractor shall comply with all the requirements set out inthe Construction Regulations, 2003 issued under theOccupational Health and Safety Act, 1993 (Act No 85 of 1993)

It is required of the contractor to thoroughly study the Healthand Safety Specification that must be read together with and isdeemed to be incorporated under this Section of the bills ofquantities / lump sum document

The contractor must take note that compliance with theOccupational Health and Safety Act, Construction Regulationsand Health and Safety Specification is compulsory. In the eventof partial or total non-compliance, the principal agent,notwithstanding the provisions of clause A31.0 of Section A orany other clause to the contrary, reserves the right to delayissuing any progress payment certificate until the contractorprovides satisfactory proof of compliance. The contractorshall not be entitled to any compensation of whatsoever nature,including interest, due to such delay of payment

Provision for pricing of the Occupational Health and Safety Act,Construction Regulations and Health and Safety Specificationis made under this clause and it is explicitly pointed out that allrequirements of the aforementioned are deemed to be pricedhereunder and no additional claims in this regard shall beentertained

Fixed:_____________ Value related:____________ Timerelated:______________ Item

REMOVALS

WATERPROOFING

2 Strip from flat roof and cart away torch-on waterproofingcomplete including turn-ups and turn-downs. m2 269

CEILINGS

3 Take down and cart away 600 x 1200mm vinyl fissuredsuspended ceiling panels from existing grid (to remain)approximately 3000mm from ground level. m2 20

FLOOR COVERINGS

4 Strip from screeded surfaces and cart away carpet tiles. m2 5

Carried to Collection R Bill No. 1PRELIMINARIESREFURBISHMENT WORK TO ECRDA OFFICES - MTHATHA

- 4 -

Page 51: EASTERN CAPE RURAL DEVELOPMENT AGENCY QUOTATION DOCUMENT ... · Quotations are requested from competent and registered contractors with the CIDB Contractor grading of 2GB and 3 GB

RFQ169-2016/17

1 Take out from timber door and cart away, cylinder or morticelockset. No 8

2 Take off from timber door and cart away, lever furniture set. No 8

PLUMBING AND DRAINAGE

3 Take down and cart away white glazed cistern includingtemporary stopping off of water supply. No 2

4 Take off and cart away flushmaster from white glazed urinalincluding temporary stopping off of water supply. No 1

5 Take off and cart away toilet flap and seat. No 2

6 Take off and cart away sanitary tissue dispenser. No 4

7 Take off and cart away sanitary bin. No 4

8 Take off and cart away soap dispenser. No 4

GLAZING

9 Demolish and cart away mirror, size 500mm long x 600mmhigh. No 2

SERVICING/CHECKING EXISTING

ROOF COVERINGS

10 The Contractor is to allow hereunder for the thoroughinspection of the insitu "Kliplok" roof coverings, ridge cappings,accessories, etc. to ensure water tightness and completeintegrity thereof including for replacement of missing drivescrews, etc. (Measured on flat) m2 1 008

11 The Contractor is to allow hereunder for the thoroughinspection of the insitu galvanised sheet iron flashings, valleylinings, etc. to ensure water tightness and complete integritythereof including for replacement of missing drive screws, etc. m 109

12 Repair and re-seal overlap joint of profiled metal roof covering,by loosening, lifting, cleaning out and inserting 8 x 3mmpreformed bitumen impregnated flexible foam sealing strip. m 504

13 Replace drive screw on metal roof covering with new 80mmapproved proprietary roofing screw with polypropylene coneand rubber seal. No 100

Carried to Collection R Bill No. 1PRELIMINARIESREFURBISHMENT WORK TO ECRDA OFFICES - MTHATHA

- 5 -

Page 52: EASTERN CAPE RURAL DEVELOPMENT AGENCY QUOTATION DOCUMENT ... · Quotations are requested from competent and registered contractors with the CIDB Contractor grading of 2GB and 3 GB

RFQ169-2016/17

CEILINGS

1 Check suspended grid system, to suit 600 x 1200mm vinyl cladceiling panels, thoroughly for alignment including resecuring,replacing proprietary suspension hangers as necessary notexceeding 1000mm from timber trusses. m2 20

IRONMONGERY

2 Service door ironmongery by oiling hinges, lockset, leverfurniture mechanism, replace missing screws, etc. and leave inperfect working order. No 70

3 Service window by oiling hinges, easing catches, etc. and leavein perfect working order. No 20

TILING

Walls

4 Strip or hack white glazed tiling from plastered wall and cartaway including preparing plaster to receive new tiling(elsewhere). m2 7

PLUMBING AND DRAINAGE

5 Service tap, mixer, etc. including changing washers and leavein perfect working condition. No 12

6 Service gatevalve, stoptap, etc. of varying sizes includingchanging washers and leave in perfect working condition. No 2

7 Service white glazed WC cistern including replacing rubberoutlet seal, checking ball float valve mechanism complete andleave in perfect working condition. No 6

8 Tighten loose or replace missing bolts to hanger brackets, etc.to white glazed wash hand basin and leave secure oncompletion. No 6

Jet or high pressure cleaning to be carried out on guttering tobe carried out to the complete satisfaction of the PrincipalAgent.

9 Existing aluminium or galvanised sheet iron guttering. m 120

Carried to Collection R Bill No. 1PRELIMINARIESREFURBISHMENT WORK TO ECRDA OFFICES - MTHATHA

- 6 -

Page 53: EASTERN CAPE RURAL DEVELOPMENT AGENCY QUOTATION DOCUMENT ... · Quotations are requested from competent and registered contractors with the CIDB Contractor grading of 2GB and 3 GB

RFQ169-2016/17

WATERPROOFING

Sheet or membrane waterproofing to roofs

Waterproofing of flat roof structures is to be carried out by anaccredited application agent and a Ten Year Guarantee is to beprovided for the works undertaken

4mm "ABE Unigum Biarmato" MS reinforced plastomericpolymer- bitumen waterproof membrane to be applied by anaccredited waterproofing specialist

1 On flat roofs including turn-ups or turn-downs not exceeding300mm girth. m2 269

2 Acrylic sealing membrane at turn-ups or turn-downs. m 64

3 Additional membrane including dressing into outlets. No 2

Protection

Two coats aluminium paint on

4 On waterproofing membrane, turnups, etc. (elsewhere). m2 269

CEILINGS, PARTITIONS & ACCESS FLOORING

12.5mm Thick vinyl-clad gypsum, white embossed fissuredceiling tiles size 600 x 1200mm in existing exposed grid.

5 Set into suspended ceiling individual tile to replace similardamaged tile (removed elsewhere) to match existing ceiling. No 28

FLOOR COVERINGS

CARPETING

"Belgotex Fringe Range" Tufted multi scroll loop pile carpet tiles

6 500 x 500 x 7mm Thick tiles sealed to prepared floors withadhesive in patterns to match existing. m2 5

Carried to Collection R Bill No. 1PRELIMINARIESREFURBISHMENT WORK TO ECRDA OFFICES - MTHATHA

- 7 -

Page 54: EASTERN CAPE RURAL DEVELOPMENT AGENCY QUOTATION DOCUMENT ... · Quotations are requested from competent and registered contractors with the CIDB Contractor grading of 2GB and 3 GB

RFQ169-2016/17

IRONMONGERY

IRONMONGERY TO TIMBER

Handles

1 CB612-13SC Satin chrome lever handle on backplate withcylinder lockset cutout. (Pair) No 8

Locksets, etc. provided with two keys and to be masterkeyed

2 2 x 8 SCMKD Satin chrome single cylinder masterkeyed lockmechanism. No 8

Lockcases, conversion sets, escutcheons, etc.

3 L - 2241 - 78SS Oval cylinder lock case to receive cylinder lock(elsewhere measured). No 8

METALWORK

Fencing

4 500mm Diameter flat wrap of galvanised razor barbed tape wirefixed vertically to and including two rows of double strandedbarbed wire to steel posts secured to straining wire (elsewhere)with and including 2.5mm diameter galvanised binding wire at300mm centres. m 52

5 10mm Hot dipped galvanised after manufacture flat plate informing welded support brackets holed for bolts (elsewhere). kg 45

6 10 x 85mm masonry anchor. No 104

TILING

WALL TILING

Grade 1 white glazed ceramic tiles size 200 x 200mm sealed toplastered surfaces with 4mm wide joints and grouted in whitegrout with fungicidal solution additive :

7 On walls in patches. m2 7

Carried to Collection R Bill No. 1PRELIMINARIESREFURBISHMENT WORK TO ECRDA OFFICES - MTHATHA

- 8 -

Page 55: EASTERN CAPE RURAL DEVELOPMENT AGENCY QUOTATION DOCUMENT ... · Quotations are requested from competent and registered contractors with the CIDB Contractor grading of 2GB and 3 GB

RFQ169-2016/17

PLUMBING AND DRAINAGE

Solid cast brass taps, valves, etc.

1 "Flushmaster Junior FJ 1.210" or other equal approved 32mmchromium plated exposed type top-entry flush valve withintegral vacuum breaker, non hold-open feature and non-returnvalve, inlet control stop and wall plate. No 1

Sanitary fittings

2 9 Litre white glazed cistern size 450 x 192 x 343mm highcomplete with lid and fitments. No 2

Sundries

3 Heavy-duty double-flap hinged toilet seat and cover. No 2

Sanitary fitting sundries

4 SQ3 Toilet tissue dispenser, plugged to wall. No 4

5 Code 427112 Sanitary disposal bin fixed in accordance withmanufacturer's specifications to walls. No 4

6 Professional Series I Twinpak Skincare soap dispenser,plugged to wall. No 4

GLAZING

MIRRORS

7 4mm Thick polished float glass mirror, size 500 x 600mm high,four times plugged to wall with and including chromium plateddome headed screws. No 2

PAINTWORK

REDECORATION OF EXISTING

PREVIOUSLY PAINTED CONCRETE, PLASTER, ETC

Scrape down loose or peeling paint, clean off surfacecontaminants with a sugar soap solution, allow to dry, stop allholes, minor cracks, etc. and apply one coat primer and twocoats PEM 1000 TLS paint on:

8 Internal plastered walls. m2 3 492

Carried to Collection R Bill No. 1PRELIMINARIESREFURBISHMENT WORK TO ECRDA OFFICES - MTHATHA

- 9 -

Page 56: EASTERN CAPE RURAL DEVELOPMENT AGENCY QUOTATION DOCUMENT ... · Quotations are requested from competent and registered contractors with the CIDB Contractor grading of 2GB and 3 GB

RFQ169-2016/17

PREVIOUSLY PAINTED TIMBER

Sand down to remove flaking varnish and apply two coatssemi-matt clear interior quality varnish, lightly sanded betweencoats on :

1 Timber doors. m2 274

2 Timber door frames. m2 89

3 Skirtings not exceeding 300mm girth. m 279

PREVIOUSLY PAINTED METALWORK

Lightly sand and apply two coats gloss enamel on :

4 Security grille gates. m2 15

5 Steel windows (both sides measured). m2 120

ELECTRICAL WORK

6 Allow the Provisional Sum of R10 000.00 (Ten Thousand Rand)for electrical repairs and servicing of fittings to be carried out bya specialist electrician. Item 10 000 00

7 Allow for attendance on the specialist electrician. Item

8 Allow for profit on the specialist electrician. Item

MECHANICAL WORK

9 Allow the Provisional Sum of R10 000.00 (Ten Thousand Rand)for servicing of airconditioning units to be carried out by aspecialist. Item 10 000 00

10 Allow for attendance on the specialist. Item

11 Allow for profit on the specialist. Item

Carried to Collection R Bill No. 1PRELIMINARIESREFURBISHMENT WORK TO ECRDA OFFICES - MTHATHA

- 1 0 -

Page 57: EASTERN CAPE RURAL DEVELOPMENT AGENCY QUOTATION DOCUMENT ... · Quotations are requested from competent and registered contractors with the CIDB Contractor grading of 2GB and 3 GB

RFQ169-2016/17

Bill No. 1

PRELIMINARIES

COLLECTION

Page AmountNo

Total Brought Forward from Page No. -1-

-2-

-3-

-4-

-5-

-6-

-7-

-8-

-9-

-10-

Carried to Summary R Bill No. 1PRELIMINARIESREFURBISHMENT WORK TO ECRDA OFFICES - MTHATHA

- 1 1 -

Page 58: EASTERN CAPE RURAL DEVELOPMENT AGENCY QUOTATION DOCUMENT ... · Quotations are requested from competent and registered contractors with the CIDB Contractor grading of 2GB and 3 GB

RFQ169-2016/17

FINAL SUMMARY

Bill Page AmountNo No

1 -11-PRELIMINARIES

Sub-Total R

CONTINGENCY PROVISIONS

Allow the Budgetary Provision of R 30 000,00 (Thirty ThousandRand) for construction contingencies of a general nature andfor the finalisation of design detailing. This sum, or any portionthereof, shall be expended at the sole discretion of the PrincipalAgent. Any residual balance remaining subsequent to suchexpenditure shall be deducted in its entirety from the ContractSum. Item 30 000 00

Sub-Total R

Add Value - Added Tax at the rate applicable as at Tenderclosing date. R

Carried to Form of Tender R REFURBISHMENT WORK TO ECRDA OFFICES - MTHATHA