east rail line update - fastracks home · 2 kevin flynn rtd eagle project public information...
TRANSCRIPT
Construction of Peña Bridge - March 2013
East Rail Line Update FasTracks Citizens Advisory Committee
Dec. 11, 2013
Courtesy of HDR, Inc, © 2013, Keith Philpott
Courtesy of HDR, Inc, © 2013, Keith Philpott
3
Eagle P3 Project
• East Rail Line offers 35-minute travel time to DIA
• Northwest Rail Westminster Segment offers 11-minute travel time to
Westminster
• Gold Line offers 25-minute travel time to Ward Road
• Project capital budget $2.2 billion
4
RTD Board Eagle Project Directors
Eagle Project Area
Bill James
District A – central Denver
Barbara Deadwyler
District B – east-northeast
Denver, DIA, north Aurora
Angie Malpiede
District C – northwest
Denver, DUS, Globeville
Larry Hoy
District J – Westminster
Lorraine Anderson
District L – southwest
Adams County, Arvada
Natalie Menten
District M – Wheat Ridge
5
Eagle P3 Progress • 50 percent complete
• 28 of 32 bridges
under construction
(18 on East)
• 9 of 15 stations under
way (6 on East)
• Nearly 26 of 36 miles
under construction
• All 50 commuter rail
car body shells
complete, first 20 in
Philadelphia for
assembly and testing
Commuter rail vehicle at Hyundai Rotem plant in Philadelphia – October 2013
7
Eagle P3 Progress
Design DBE Design SBE Construction DBE Construction SBE
Actual $18.0 $7.1 $96.8 $22.7
Commitments $19.1 $7.3 $164.7 $41.2
Goal $17.1 $3.0 $172.5 $43.2
111% of goal 239% of goal
95% of goal
96% of goal
$0.0
$20.0
$40.0
$60.0
$80.0
$100.0
$120.0
$140.0
$160.0
$180.0
$200.0
$ m
illio
ns
DBE/SBE Goals
Local/Disadvantaged/Small Business Participation
• $840 million dollars to 390 Colorado businesses
• $232 million to 160 D/SBE businesses
• WIN hiring: 43 local trainees hired on Eagle Project
8
Upcoming Construction
East Rail Line – Work Areas
Josephine St. railroad crossing
Monaco Parkway at Smith Road
Quebec frontage at Smith Road
Smith Rd./Havana St. railroad
I-70 Flyover Bridge at Airport Blvd.
East Rail Upcoming Construction
9
Proposed Station Names
38th & Blake
40th & Colorado
Central Park
Peoria
40th & Airport • Gateway Park (change)
Denver Airport (change)
10
Concurrent Projects
Peoria Crossing
• Bridge piers and
abutments up
• Approach walls
underway
• Frontage Road
connections from
33rd and 39th
avenues
• Demolition along
the northbound
Peoria lanes
Aerial rendering of Peoria Street grade separation
11
Concurrent Projects
DIA Hotel and Transit Center
• New detours on Terminal East public
roads in place until late 2014
• Terminal West detour closures to be
lifted this weekend
• Train platform canopy steel complete,
ironworkers now installing steel for
public plaza canopy
• Concrete work complete to Level 5
including public plaza
• Installation of exterior walls to begin
this month
Train platform plaza, hotel above
12
Construction Progress
Commuter rail maintenance facility, November 2013
RTD commuter rail
maintenance facility
• 230,000-square foot,
four-level building will
house a staff of 240
• Yard storage for up to 80
vehicles
• When completed in 2014,
it will be a LEED Silver
Certified building
• Located at 5151 Fox St.,
in the Globeville
neighborhood of Denver
19
Construction Progress
Girder installation on
Interstate 70 Flyover
bridge, the longest
bridge on the project
at nearly 5,000 feet
22
Construction Progress
Courtesy of HDR, Inc, © 2013, Keith Philpott
East Rail Line track
along Peña
Transportation
Corridor curve
23
Construction Progress
E-470 Bridge, wide
enough for future
double-track, uses
direct-fixation track
over the highway for
a lighter structure
27
Construction Progress
Rail underpass
beneath DIA east and
west terminal under
access roadway “X”
crossover