Construction of Peña Bridge - March 2013 East Rail Line Update FasTracks Citizens Advisory Committee Dec. 11, 2013 Courtesy of HDR, Inc, © 2013, Keith Philpott Courtesy of HDR, Inc, © 2013, Keith Philpott

Upload: truonghanh

Post on 01-Nov-2018

215 views

Category:

Documents


0 download

TRANSCRIPT

Construction of Peña Bridge - March 2013

East Rail Line Update FasTracks Citizens Advisory Committee

Dec. 11, 2013

Courtesy of HDR, Inc, © 2013, Keith Philpott

Courtesy of HDR, Inc, © 2013, Keith Philpott

2

Kevin Flynn RTD Eagle Project Public Information Manager

East Rail Line Update

3

Eagle P3 Project

• East Rail Line offers 35-minute travel time to DIA

• Northwest Rail Westminster Segment offers 11-minute travel time to

Westminster

• Gold Line offers 25-minute travel time to Ward Road

• Project capital budget $2.2 billion

4

RTD Board Eagle Project Directors

Eagle Project Area

Bill James

District A – central Denver

Barbara Deadwyler

District B – east-northeast

Denver, DIA, north Aurora

Angie Malpiede

District C – northwest

Denver, DUS, Globeville

Larry Hoy

District J – Westminster

Lorraine Anderson

District L – southwest

Adams County, Arvada

Natalie Menten

District M – Wheat Ridge

5

Eagle P3 Progress • 50 percent complete

• 28 of 32 bridges

under construction

(18 on East)

• 9 of 15 stations under

way (6 on East)

• Nearly 26 of 36 miles

under construction

• All 50 commuter rail

car body shells

complete, first 20 in

Philadelphia for

assembly and testing

Commuter rail vehicle at Hyundai Rotem plant in Philadelphia – October 2013

6

Eagle P3 Progress

Unloading commuter

rail car body shell at

Port of Philadelphia,

Sept. 23, 2013

7

Eagle P3 Progress

Design DBE Design SBE Construction DBE Construction SBE

Actual $18.0 $7.1 $96.8 $22.7

Commitments $19.1 $7.3 $164.7 $41.2

Goal $17.1 $3.0 $172.5 $43.2

111% of goal 239% of goal

95% of goal

96% of goal

$0.0

$20.0

$40.0

$60.0

$80.0

$100.0

$120.0

$140.0

$160.0

$180.0

$200.0

$ m

illio

ns

DBE/SBE Goals

Local/Disadvantaged/Small Business Participation

• $840 million dollars to 390 Colorado businesses

• $232 million to 160 D/SBE businesses

• WIN hiring: 43 local trainees hired on Eagle Project

8

Upcoming Construction

East Rail Line – Work Areas

Josephine St. railroad crossing

Monaco Parkway at Smith Road

Quebec frontage at Smith Road

Smith Rd./Havana St. railroad

I-70 Flyover Bridge at Airport Blvd.

East Rail Upcoming Construction

9

Proposed Station Names

38th & Blake

40th & Colorado

Central Park

Peoria

40th & Airport • Gateway Park (change)

Denver Airport (change)

10

Concurrent Projects

Peoria Crossing

• Bridge piers and

abutments up

• Approach walls

underway

• Frontage Road

connections from

33rd and 39th

avenues

• Demolition along

the northbound

Peoria lanes

Aerial rendering of Peoria Street grade separation

11

Concurrent Projects

DIA Hotel and Transit Center

• New detours on Terminal East public

roads in place until late 2014

• Terminal West detour closures to be

lifted this weekend

• Train platform canopy steel complete,

ironworkers now installing steel for

public plaza canopy

• Concrete work complete to Level 5

including public plaza

• Installation of exterior walls to begin

this month

Train platform plaza, hotel above

12

Construction Progress

Commuter rail maintenance facility, November 2013

RTD commuter rail

maintenance facility

• 230,000-square foot,

four-level building will

house a staff of 240

• Yard storage for up to 80

vehicles

• When completed in 2014,

it will be a LEED Silver

Certified building

• Located at 5151 Fox St.,

in the Globeville

neighborhood of Denver

13

Construction Progress

Union Station CRT

Platform

14

Construction Progress

Smith Road

reconstruction,

Colorado Boulevard

to Kearney Street

15

Construction Progress

Overhead power pole

installation, Smith

Road

16

Construction Progress

Sandown Substation

transformer

installation

17

Construction Progress

Central Park Station

platform construction

18

Construction Progress

Track hardening

along Smith Road at

I-225

19

Construction Progress

Girder installation on

Interstate 70 Flyover

bridge, the longest

bridge on the project

at nearly 5,000 feet

20

Construction Progress

Airport/40th Station

platform construction

21

Construction Progress

Track installation and

joint welding, East Rail

Line at 64th Avenue

22

Construction Progress

Courtesy of HDR, Inc, © 2013, Keith Philpott

East Rail Line track

along Peña

Transportation

Corridor curve

23

Construction Progress

E-470 Bridge, wide

enough for future

double-track, uses

direct-fixation track

over the highway for

a lighter structure

24

Construction Progress

Construction on 1,953-

foot Peña Boulevard

Bridge, East Rail Line

25

Construction Progress

Gantry used for direct

fixation track on Peña

Bridge

26

Construction Progress

Track installation along

78th Avenue, parallel to

Runway 7/25

27

Construction Progress

Rail underpass

beneath DIA east and

west terminal under

access roadway “X”

crossover

28

Construction Progress

DIA Station approach

and platform, looking

south

29

Canopy construction

over the passenger

platform at DIA

Construction Progress

30

Construction of DIA Station Canopy, September 2013

Questions?