EAST PENNSBORO AREA SCHOOL DISTRICT Additions and Renovations to EAST PENNSBORO ELEMENTARY SCHOOL 840 Panther Parkway, Enola, PA 17025 WEST CREEK HILLS ELEMENTARY SCHOOL 400 Erford Road, Camp Hill, PA 17011 PROGRESS REPORT #3 November 2019 RC Project No. 19-1716 Prepared by: West Creek Hills Elementary School East Pennsboro Elementary School

Upload: others

Post on 24-Jul-2020

2 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: EAST PENNSBORO ELEMENTARY SCHOOL€¦ · Project Manager MC:dlp Attachments cc: File 405 . ... Job Trailer – 80% Addition Footings and Foundation – 100% West Creek Hills Elementary

EAST PENNSBORO AREA SCHOOL DISTRICT

Additions and Renovations to

EAST PENNSBORO ELEMENTARY SCHOOL 840 Panther Parkway, Enola, PA 17025

WEST CREEK HILLS ELEMENTARY SCHOOL

400 Erford Road, Camp Hill, PA 17011

PROGRESS REPORT #3

November 2019 RC Project No. 19-1716

Prepared by:

West Creek Hills Elementary School

East Pennsboro Elementary School

Page 2: EAST PENNSBORO ELEMENTARY SCHOOL€¦ · Project Manager MC:dlp Attachments cc: File 405 . ... Job Trailer – 80% Addition Footings and Foundation – 100% West Creek Hills Elementary

December 10, 2019 Dr. Donna Dunar Superintendent East Pennsboro Area School District 890 Valley Street Enola, PA 17025 RE: East Pennsboro Area School District Additions and Renovations for East Pennsboro and

West Creek Hills Elementary Schools RC Project No. 19-1761 November 2019 – Monthly Report #3 Dear Dr. Dunar, Attached, for your use and information, is Reynolds Construction’s November 2019 Monthly Progress Report #3 for the above-referenced project. If you have any questions or comments regarding this report, please do not hesitate to contact me. Sincerely, REYNOLDS CONSTRUCTION, LLC Mike Cline Project Manager MC:dlp Attachments cc: File 405

Page 3: EAST PENNSBORO ELEMENTARY SCHOOL€¦ · Project Manager MC:dlp Attachments cc: File 405 . ... Job Trailer – 80% Addition Footings and Foundation – 100% West Creek Hills Elementary

Table of Contents Executive Summary ........................................................................................................................ 1

Contractor Updates ....................................................................................................................... 2

Contract No. 301 – General Construction / eciConstruction, LLC .......................................................... 2 Contract No. 302 – Fire Protection / S. A. Comunale, Inc. ..................................................................... 2

Pay Requisition Summary ............................................................................................................. 3

Change Management .................................................................................................................... 4

Change Order Summary .......................................................................................................................... 4 Change Order Log.................................................................................................................................... 5

Project Schedule ............................................................................................................................ 6

Project Considerations ................................................................................................................. 21

Project Photos ..............................................................................................................................22

Page 4: EAST PENNSBORO ELEMENTARY SCHOOL€¦ · Project Manager MC:dlp Attachments cc: File 405 . ... Job Trailer – 80% Addition Footings and Foundation – 100% West Creek Hills Elementary

East Pennsboro Area School District East Pennsboro Elementary School West Creek Hills Elementary School Progress Report #3-November 2019

1 | P a g e

Executive Summary The additions at both East Pennsboro Elementary School (EPE) and West Creek Hills Elementary School (WCH) have been under construction for seven (7) weeks since the Notice to Proceed issued on October 11, 2019. Substantial Completion date for additions and renovations is August 4, 2020. With regards to administrative progress, Reynolds has been assisting the District with administrative work for land easements at WCH. Schrader Group Architects, K & W Engineers and Reynolds have been diligent in reviewing and processing submittals and shop drawings for materials and equipment which will be required in the next few months. Requests for information (RFIs) from all contractors are being processed in a timely manner. On site progress to date includes that foundations for new construction at EPE are nearly complete. Excluding the gymnasium at EPE, concrete slabs on grade at both sites should be completed before the first of the year. Weather has been pleasing for late fall construction.

West Creek Hills Elementary School

East Pennsboro Elementary School

Page 5: EAST PENNSBORO ELEMENTARY SCHOOL€¦ · Project Manager MC:dlp Attachments cc: File 405 . ... Job Trailer – 80% Addition Footings and Foundation – 100% West Creek Hills Elementary

East Pennsboro Area School District East Pennsboro Elementary School West Creek Hills Elementary School Progress Report #3-November 2019

2 | P a g e

Contractor Updates Contract No. 301 – General Construction / eciConstruction, LLC

Work Completed through November 2019: East Pennsboro Elementary School

➢ Job Trailer – 80% ➢ Addition Footings and Foundation – 100%

West Creek Hills Elementary School

➢ Job Trailer – 100% ➢ Modular Classroom Demolition – 100% ➢ Addition Footings – 100%

Contract No. 302 – Fire Protection / S. A. Comunale, Inc.

Work Completed Through October 2019:

➢ Administrative documents – 100% ➢ No work onsite to date

Page 6: EAST PENNSBORO ELEMENTARY SCHOOL€¦ · Project Manager MC:dlp Attachments cc: File 405 . ... Job Trailer – 80% Addition Footings and Foundation – 100% West Creek Hills Elementary

East Pennsboro Area School District East Pennsboro Elementary School West Creek Hills Elementary School Progress Report #3-November 2019

3 | P a g e

Pay Requisition Summary

Contract

Number Contractor Name

Period

To

App

Num

Original

Contract

Net Change by

Change Order

Contract Sum to

Date

Total Compl +

Stored To Date Retainage

Total Earned

Less Retain.

Previous

Applications

Current

Payment Due

Balance To Finish

+ Retain.

Pct

Comp

301 eciConstruction, LLC 7,304,500.00$ -$ 7,304,500.00$ -$ -$ -$ -$ -$ 7,304,500.00$ 0.0%

302 S. A. Comunale, Inc. 217,580.00$ -$ 217,580.00$ -$ -$ -$ -$ -$ 217,580.00$ 0.0%

7,522,080.00$ -$ 7,522,080.00$ -$ -$ -$ -$ -$ 7,522,080.00$ 0.0%Summary Totals:

Requisition Summary Totals

By ContractEPASD

Job No:19-1716

East Pennsboro Elementary School & West Creek Hills Elementary School

Additions and Renovations

Page 7: EAST PENNSBORO ELEMENTARY SCHOOL€¦ · Project Manager MC:dlp Attachments cc: File 405 . ... Job Trailer – 80% Addition Footings and Foundation – 100% West Creek Hills Elementary

East Pennsboro Area School District East Pennsboro Elementary School West Creek Hills Elementary School Progress Report #3-November 2019

4 | P a g e

Change Management Change Order Summary

East Pennsboro Area School District East Pennsboro & West Creek Hills Elementary Schools

Construction Contingency $261,810.00

Total of all Executed Change Orders $0.00

Total of all November Change Orders ($7,287.00)

Remaining Contingency Balance $269,097.00

Approved Change Orders, please see attached log. Currently the following Potential Change Orders are under review and/or processing.

1. Delete furnishing and installing one batting cage at EPE 2. Remove plaster ceiling above suspended ceiling at connector at WCH 3. Storm water outfall redesign at WCH

Page 8: EAST PENNSBORO ELEMENTARY SCHOOL€¦ · Project Manager MC:dlp Attachments cc: File 405 . ... Job Trailer – 80% Addition Footings and Foundation – 100% West Creek Hills Elementary

East Pennsboro Area School District East Pennsboro Elementary School West Creek Hills Elementary School Progress Report #3-November 2019

5 | P a g e

Change Order Log

Change

Management #

Contract

or COR #

Scho

ol Description

Cost Issue

Received Date

Proposed/Quoted

Amount

Negotiated

Amount

Architect

Approval

Final Change Order

Amount Status

CO Amount to

Contractor CO # Date Issued

ECI SAC

1 1 EPE Delete furnishing & installing one Batting Cage (8,769.00)$ 10.31.19 (8,769.00)$ (8,769.00)$ 11.05.19 (8,769.00)$ OFS (8,769.00)$ 01-01 11.05.19

2 1 WCH Remove plaster ceiling above suspended ceiling at connector 1,482.00$ 12.03.19 1,482.00$ 1,482.00$ 12.06.19 1,482.00$ OFS 1,482.00$ 01-02 12.09.19

3 1 WCH Storm w ater outfall redesign

Project Totals (7,287.00)$ -$ (7,287.00)$ (7,287.00)$ (7,287.00)$ (7,287.00)$

ECI original Contract Sum = $7,304,500.00 7,297,213.00$ BEING NEGOTIATED BN

SAC original Contract Sum = $217,580.00 217,580.00$ OUT FOR SIGNATURE OFS

FULLY EXECUTED FE

VOID/REJECTED V

CLOSED C

Errors & Omissions E&O

KEY

Contractor

Additions and Renovations to East Pennsboro & West Creek Hills Elementary Schools

19-1716-EPE & 19-1716-WCH

C O S T I S S U E S U M M A R Y

Page 9: EAST PENNSBORO ELEMENTARY SCHOOL€¦ · Project Manager MC:dlp Attachments cc: File 405 . ... Job Trailer – 80% Addition Footings and Foundation – 100% West Creek Hills Elementary

East Pennsboro Area School District East Pennsboro Elementary School West Creek Hills Elementary School Progress Report #3-November 2019

6 | P a g e

Project Schedule

Substantial Completion dates for each phase are as follows:

Phase 1 (Construct New Additions & Erosion Control) .........................................August 4, 2020 Phase 2 (Perform Renovations & Final Sitework) .................................................August 4, 2020

Page 10: EAST PENNSBORO ELEMENTARY SCHOOL€¦ · Project Manager MC:dlp Attachments cc: File 405 . ... Job Trailer – 80% Addition Footings and Foundation – 100% West Creek Hills Elementary

. Description DaysPlan

Dur %Comp

DaysLeft

Start Finish TotalFloat

East Pennsboro Elementary SchoolEast Pennsboro Elementary SchoolEast Pennsboro Elementary SchoolEast Pennsboro Elementary SchoolEast Pennsboro Elementary SchoolEast Pennsboro Elementary SchoolEast Pennsboro Elementary SchoolEast Pennsboro Elementary School

ec.sc Substantial Completion - Area C Renovations - NLT Aug-4-20 0 0% 0 Jul-29-20* 4

en.sc Substantial Completion - Addition - NLT Aug-4-20 0 0% 0 Aug-04-20* 0

ea.sc Substantial Completion - Area A Renovations - NLT Aug-4-20 0 0% 0 Aug-04-20* 0

General Mobilization and Start UpGeneral Mobilization and Start UpGeneral Mobilization and Start UpGeneral Mobilization and Start UpGeneral Mobilization and Start UpGeneral Mobilization and Start UpGeneral Mobilization and Start UpGeneral Mobilization and Start Up

eg.2 Temporary Lighting and Power 5 0% 5 Nov-20-19 Nov-26-19* -7

eg.6 Last Day of School 1 0% 1 Jun-08-20* Jun-08-20 0

Site WorkSite WorkSite WorkSite WorkSite WorkSite WorkSite WorkSite Work

es.7 Survey and Layout 3 70% 1 Nov-12-19 A Nov-20-19 0

es.5 Demo Stormwater System 5 0% 5 Jun-09-20 Jun-15-20 2

es.6 Install Fire Hydrant Pipe and Structure 5 0% 5 Jun-09-20* Jun-15-20 17

es.13 Concrete Pads, Stairs, Walkways, Ramps, and Curbs 10 0% 10 Jun-09-20 Jun-22-20 7

es.14 Infiltration Basin Work 15 0% 15 Jun-09-20 Jun-29-20 7

es.10 Install Stormwater Pipes and Structures 10 0% 10 Jun-16-20 Jun-29-20 2

es.16 Handrail Systems 4 0% 4 Jun-23-20 Jun-26-20 24

es.17 Grading and Topsoil 5 0% 5 Jun-30-20 Jul-07-20 2

es.18 Grass Seeding / Landscape 5 0% 5 Jul-08-20 Jul-14-20 2

es.19 Steel Bollards 3 0% 3 Jul-15-20 Jul-17-20 10

es.21 Remove Field Offices and Storage Trailers 5 0% 5 Jul-15-20* Jul-21-20 2

es.20 Reinstall Benches, Picnic Tables 2 0% 2 Jul-20-20 Jul-21-20 10

es.22 Paving Base and Wear Coats 5 0% 5 Jul-22-20 Jul-28-20 2

es.15 4" Chain Link Fence and Gate 5 0% 5 Jul-22-20 Jul-28-20 5

es.12 Basketball Rims, Posts, and Backboards 3 0% 3 Jul-29-20* Jul-31-20 2

es.23 Paving Striping: Handicap, Parking, Basketball 3 0% 3 Jul-29-20 Jul-31-20 2

New Addition (Area C)New Addition (Area C)New Addition (Area C)New Addition (Area C)New Addition (Area C)New Addition (Area C)New Addition (Area C)New Addition (Area C)

Building EnclosureBuilding EnclosureBuilding EnclosureBuilding EnclosureBuilding EnclosureBuilding EnclosureBuilding EnclosureBuilding Enclosure

ene.1 Prep and Pour Foundations 20 30% 14 Nov-14-19 A Dec-12-19 0

ene.2 Foundation Masonry Walls 20 0% 20 Nov-21-19 Dec-23-19 0

ene.3 Underground Sanitary Rough In and Backfill 15 0% 15 Nov-22-19 Dec-17-19 0

ene.4 Underground Electrical Rough In and Backfill 5 0% 5 Nov-25-19 Dec-04-19 0

ene.5 Underground Fire Protection Rough In and Backfill 5 0% 5 Nov-26-19 Dec-05-19 0

ene.6 Roof Drain Pipe Rough In and Backfill 10 0% 10 Nov-27-19 Dec-13-19 0

ene.7 Insulate and Backfill Foundation Walls 5 0% 5 Dec-13-19 Dec-20-19 0

ene.8 CMU Door Frames 3 0% 3 Dec-20-19 Dec-26-19 17

N Dec Jan F Mar Apr M J Jul A S Oct N D

2020

Substantial Compl

Substantial Comp

Substantial Comp

Temporary Lighting and Power

Last Day of School

Survey and Layout

Demo Stormwater System

Install Fire Hydrant Pipe a

Concrete Pads, Stairs, W

Infiltration Basin Work

Install Stormwater Pipe

Handrail Systems

Grading and Topsoil

Grass Seeding / Landscape

Steel Bollards

Remove Field Office

Reinstall Benches, P

Paving Base and Wear Coats

4" Chain Link Fenc

Basketball Rims, P

Paving Striping: H

Prep and Pour Foundations

Foundation Masonry Walls

Underground Sanitary Rough In and Backfill

Underground Electrical Rough In and Backfill

Underground Fire Protection Rough In and Backfill

Roof Drain Pipe Rough In and Backfill

Insulate and Backfill Foundation Walls

CMU Door Frames

East Pennsboro Elementary School

Construction Schedule (1716e r1a)Data Date Nov-19-19

Schedule ID 1716e r1a

Run Date Dec-09-19

Page 1 of 9

Page 11: EAST PENNSBORO ELEMENTARY SCHOOL€¦ · Project Manager MC:dlp Attachments cc: File 405 . ... Job Trailer – 80% Addition Footings and Foundation – 100% West Creek Hills Elementary

. Description DaysPlan

Dur %Comp

DaysLeft

Start Finish TotalFloat

ene.9 CMU Walls to Steel Bearing 20 0% 20 Dec-20-19 Jan-21-20 0

ene.10 Prep and Pour Slab on Grade - LGI and Other Areas 5 0% 5 Jan-21-20 Jan-28-20 0

ene.11 Folding Partition Steel 3 0% 3 Jan-28-20 Jan-31-20 7

ene.12 Bar Joists, Columns, and Decking 10 0% 10 Jan-28-20 Feb-11-20 0

ene.13 Parapet Walls 5 0% 5 Feb-11-20 Feb-18-20 7

ene.15 Prep and Pour Slab on Grade - Gym 5 0% 5 Feb-11-20 Feb-18-20 27

ene.18 Roof Curbing 5 0% 5 Feb-11-20 Feb-18-20 27

ene.16 Exterior Metal Framing 8 0% 8 Feb-11-20 Feb-21-20 0

ene.17 Roof Drains 8 0% 8 Feb-11-20 Feb-21-20 24

ene.19 Roof System and Walking Pads 20 0% 20 Feb-18-20 Mar-17-20 7

ene.20 Brick Veneer and Insulation 25 0% 25 Feb-21-20 Mar-27-20 0

ene.22 Stair Case Metal Pans 5 0% 5 Mar-03-20 Mar-10-20 27

ene.23 Pour Concrete at Staircase 5 0% 5 Mar-10-20 Mar-17-20 27

ene.14 HVAC RTU Steel 5 0% 5 Mar-17-20 Mar-24-20 83

ene.21 Set HVAC RTUs 3 0% 3 Mar-24-20 Mar-27-20 83

ene.24 Exterior Windows 12 0% 12 Mar-25-20 Apr-10-20 0

ene.25 Aluminum Roof Coping and Metal Caps 10 0% 10 Mar-27-20 Apr-10-20 60

ene.26 Building Weathertight 1 0% 1 Apr-10-20 Apr-13-20 0

ene.27 Temporary Lighting and Power in Place 4 0% 4 Apr-13-20 Apr-17-20 0

ene.28 Temporary Heating and Dehumidifying In Place 2 0% 2 Apr-17-20 Apr-21-20 0

ene.29 Pre-Fab Canopies 5 0% 5 Apr-24-20 May-01-20 60

ene.30 Permanent Electrical Power in Place 2 0% 2 Jun-10-20 Jun-12-20 29

ene.31 HVAC Rooftop and Interior Unit Start Up 2 0% 2 Jul-17-20 Jul-21-20 5

GymGymGymGymGymGymGymGym

eng.1 Interior Masonry Walls and Chases 20 0% 20 Mar-17-20 Apr-14-20 7

eng.2 Aluminum Wall Panels 10 0% 10 Apr-10-20 Apr-24-20 60

eng.4 Mechanical Pipe and Duct Overhead Rough In / Insulation / Tagging 20 0% 20 Apr-20-20 May-18-20 0

eng.3 Electrical Overhead Rough In / Labeling 8 0% 8 Apr-21-20 May-01-20 2

eng.5 Install Mechanical Interior Unit 5 0% 5 May-01-20 May-08-20 2

eng.7 Fire Protection Overhead Rough In / Labeling 8 0% 8 May-08-20 May-20-20 2

eng.8 Interior Metal Framing 4 0% 4 May-15-20 May-21-20 2

eng.6 Paint Gym Ceiling 5 0% 5 May-15-20 May-22-20 0

eng.9 Wood Blocking 2 0% 2 May-20-20 May-22-20 2

eng.10 Interior Door Frames, Windows, Storefronts 4 0% 4 May-20-20 May-27-20 23

N Dec Jan F Mar Apr M J Jul A S Oct N D

2020

CMU Walls to Steel Bearing

Prep and Pour Slab on Grade - LGI and Other Areas

Folding Partition Steel

Bar Joists, Columns, and Decking

Parapet Walls

Prep and Pour Slab on Grade - Gym

Roof Curbing

Exterior Metal Framing

Roof Drains

Roof System and Walking Pads

Brick Veneer and Insulation

Stair Case Metal Pans

Pour Concrete at Staircase

HVAC RTU Steel

Set HVAC RTUs

Exterior Windows

Aluminum Roof Coping and Metal Caps

Building Weathertight

Temporary Lighting and Power in Place

Temporary Heating and Dehumid

Pre-Fab Canopies

Permanent Electrical Power in Place

HVAC Rooftop and

Interior Masonry Walls and Chases

Aluminum Wall Panels

Mechanical Pipe and Duct Ov

Electrical Overhead Rough In / Labeling

Install Mechanical Interior Unit

Fire Protection Overhead Ro

Interior Metal Framing

Paint Gym Ceiling

Wood Blocking

Interior Door Frames, Windo

East Pennsboro Elementary School

Construction Schedule (1716e r1a)Data Date Nov-19-19

Schedule ID 1716e r1a

Run Date Dec-09-19

Page 2 of 9

Page 12: EAST PENNSBORO ELEMENTARY SCHOOL€¦ · Project Manager MC:dlp Attachments cc: File 405 . ... Job Trailer – 80% Addition Footings and Foundation – 100% West Creek Hills Elementary

. Description DaysPlan

Dur %Comp

DaysLeft

Start Finish TotalFloat

eng.12 Hang and Finish Drywall 5 0% 5 May-21-20 May-29-20 2

eng.11 Primer and First Coat Paint 8 0% 8 May-22-20 Jun-04-20 0

eng.13 Electrical In Wall Rough Ins 10 0% 10 May-27-20 Jun-10-20 23

eng.14 Plumbing In Wall Rough Ins 10 0% 10 May-28-20 Jun-11-20 23

eng.15 Electrical Cable Trays 5 0% 5 May-29-20 Jun-05-20 7

eng.16 Resinous Epoxy Flooring 5 0% 5 May-29-20 Jun-05-20 12

eng.17 Mechanical In Wall Rough Ins 10 0% 10 May-29-20 Jun-12-20 23

eng.18 Fire Protection In Wall Rough Ins 10 0% 10 Jun-01-20 Jun-15-20 23

eng.20 Ceiling Grid 5 0% 5 Jun-02-20 Jun-09-20 7

eng.21 Sprinkler Heads 10 0% 10 Jun-03-20 Jun-17-20 14

eng.19 Fire Alarm Devices 5 0% 5 Jun-04-20 Jun-11-20 0

eng.22 Install Folding Partition 2 0% 2 Jun-05-20 Jun-09-20 15

eng.23 Walk Off Mats 3 0% 3 Jun-05-20 Jun-10-20 33

eng.24 Final Coat Paint 5 0% 5 Jun-05-20 Jun-12-20 12

eng.25 Casework and Cabinetry 5 0% 5 Jun-09-20 Jun-16-20 7

eng.26 Light Fixtures, Speakers, Receptacles, Security Devices 10 0% 10 Jun-11-20 Jun-25-20 0

eng.27 Basketball Backboards and Rims 3 0% 3 Jun-12-20 Jun-17-20 14

eng.28 Toilet Partitions 4 0% 4 Jun-12-20 Jun-18-20 27

eng.29 Retractable Batting Cages 5 0% 5 Jun-12-20 Jun-19-20 12

eng.30 Remove Temporary Lighting and Power 5 0% 5 Jun-12-20 Jun-19-20 93

eng.31 Toilet Accessories 3 0% 3 Jun-15-20 Jun-18-20 27

eng.32 ATC Wiring 5 0% 5 Jun-15-20 Jun-22-20 23

eng.33 VCT Flooring 5 0% 5 Jun-16-20 Jun-23-20 7

eng.36 Fire Protection Hydro Testing, Inspection of New System Piping 1 0% 1 Jun-17-20 Jun-18-20 14

eng.34 Low Voltage Fixtures and Devices 5 0% 5 Jun-18-20 Jun-25-20 9

eng.37 Ceiling Tile 10 0% 10 Jun-18-20 Jul-02-20 14

eng.35 Mechanical Fixtures and Devices 15 0% 15 Jun-18-20 Jul-10-20 10

eng.38 Staircase Handrail 3 0% 3 Jun-19-20 Jun-24-20 19

eng.41 Corridor Tack Strips 4 0% 4 Jun-23-20 Jun-29-20 20

eng.43 Doors and Hardware 10 0% 10 Jun-23-20 Jul-08-20 7

eng.40 Solid Surfaces 3 0% 3 Jun-25-20 Jun-30-20 9

eng.39 Epoxy Coated Concrete 3 0% 3 Jun-25-20 Jun-30-20 19

eng.42 Gym Sound Panels 8 0% 8 Jun-25-20 Jul-08-20 0

eng.44 Plumbing Fixtures 10 0% 10 Jun-30-20 Jul-15-20 9

N Dec Jan F Mar Apr M J Jul A S Oct N D

2020

Hang and Finish Drywall

Primer and First Coat Paint

Electrical In Wall Rough Ins

Plumbing In Wall Rough Ins

Electrical Cable Trays

Resinous Epoxy Flooring

Mechanical In Wall Rough Ins

Fire Protection In Wall Rough Ins

Ceiling Grid

Sprinkler Heads

Fire Alarm Devices

Install Folding Partition

Walk Off Mats

Final Coat Paint

Casework and Cabinetry

Light Fixtures, Speakers

Basketball Backboards and Rims

Toilet Partitions

Retractable Batting Cages

Remove Temporary Ligh

Toilet Accessories

ATC Wiring

VCT Flooring

Fire Protection Hydro Tes

Low Voltage Fixtures and Devices

Ceiling Tile

Mechanical Fixtures a

Staircase Handrail

Corridor Tack Strips

Doors and Hardware

Solid Surfaces

Epoxy Coated Concrete

Gym Sound Panels

Plumbing Fixtures

East Pennsboro Elementary School

Construction Schedule (1716e r1a)Data Date Nov-19-19

Schedule ID 1716e r1a

Run Date Dec-09-19

Page 3 of 9

Page 13: EAST PENNSBORO ELEMENTARY SCHOOL€¦ · Project Manager MC:dlp Attachments cc: File 405 . ... Job Trailer – 80% Addition Footings and Foundation – 100% West Creek Hills Elementary

. Description DaysPlan

Dur %Comp

DaysLeft

Start Finish TotalFloat

eng.45 Tackboards and Whiteboards 3 0% 3 Jul-02-20 Jul-08-20 14

eng.47 Room Signage 2 0% 2 Jul-08-20 Jul-10-20 7

eng.46 Gym Rubber Flooring 10 0% 10 Jul-08-20 Jul-22-20 0

eng.48 Overhead Grille and Counter Door 3 0% 3 Jul-10-20 Jul-15-20 7

eng.49 Fire Cabinets and Extinguishers 2 0% 2 Jul-15-20 Jul-17-20 7

eng.50 Gym Wall Pads 2 0% 2 Jul-22-20 Jul-24-20 2

eng.51 Staircase Rubber Flooring 4 0% 4 Jul-22-20 Jul-28-20 0

eng.52 Final Cleaning 5 0% 5 Jul-28-20 Aug-04-20 0

eng.53 Air Balancing 5 0% 5 Aug-04-20 Aug-11-20 57

eng.54 Punchlist 10 0% 10 Aug-04-20 Aug-18-20 52

First Floor - AdditionFirst Floor - AdditionFirst Floor - AdditionFirst Floor - AdditionFirst Floor - AdditionFirst Floor - AdditionFirst Floor - AdditionFirst Floor - Addition

en1.1 Interior Masonry Walls and Chases 20 0% 20 Mar-17-20 Apr-14-20 8

en1.2 Aluminum Wall Panels 10 0% 10 Mar-27-20 Apr-10-20 70

en1.3 Staircase Handrail 3 0% 3 Apr-14-20 Apr-17-20 66

en1.4 Electrical Overhead Rough In / Labeling 10 0% 10 Apr-21-20 May-05-20 3

en1.5 Plumbing Overhead Rough In / Insulation / Labeling 10 0% 10 Apr-22-20 May-06-20 3

en1.6 Install Mechanical Interior Unit 5 0% 5 Apr-23-20 Apr-30-20 3

en1.7 Mechanical Pipe and Duct Overhead Rough In / Insulation / Tagging 20 0% 20 Apr-23-20 May-21-20 3

en1.8 Fire Protection Overhead Rough In / Labeling 10 0% 10 Apr-30-20 May-14-20 3

en1.9 Interior Metal Framing 8 0% 8 May-07-20 May-19-20 3

en1.10 Wood Blocking 5 0% 5 May-13-20 May-20-20 3

en1.11 Interior Door Frames, Windows, Storefronts 4 0% 4 May-14-20 May-20-20 27

en1.12 Hang and Finish Drywall 10 0% 10 May-15-20 Jun-01-20 3

en1.13 Electrical In Wall Rough Ins 10 0% 10 May-20-20 Jun-04-20 27

en1.14 Plumbing In Wall Rough Ins 10 0% 10 May-21-20 Jun-05-20 27

en1.15 Primer and First Coat Paint 8 0% 8 May-22-20 Jun-04-20 4

en1.16 Mechanical In Wall Rough Ins 10 0% 10 May-22-20 Jun-08-20 27

en1.17 Fire Protection In Wall Rough Ins 10 0% 10 May-26-20 Jun-09-20 27

en1.18 Electrical Cable Trays 5 0% 5 Jun-01-20 Jun-08-20 3

en1.19 Ceiling Grid 5 0% 5 Jun-03-20 Jun-10-20 3

en1.20 Fire Alarm Devices 5 0% 5 Jun-04-20 Jun-11-20 4

en1.21 Sprinkler Heads 10 0% 10 Jun-04-20 Jun-18-20 13

en1.22 ATC Wiring 5 0% 5 Jun-09-20 Jun-16-20 27

en1.23 Casework and Cabinetry 10 0% 10 Jun-10-20 Jun-24-20 3

N Dec Jan F Mar Apr M J Jul A S Oct N D

2020

Tackboards and Whiteboards

Room Signage

Gym Rubber Flooring

Overhead Grille and

Fire Cabinets and Ex

Gym Wall Pads

Staircase Rubber Flooring

Final Cleaning

Air Balancing

Punchlist

Interior Masonry Walls and Chases

Aluminum Wall Panels

Staircase Handrail

Electrical Overhead Rough In / Labeling

Plumbing Overhead Rough In

Install Mechanical Interior Unit

Mechanical Pipe and Duct Ov

Fire Protection Overhead Rou

Interior Metal Framing

Wood Blocking

Interior Door Frames, Windo

Hang and Finish Drywall

Electrical In Wall Rough Ins

Plumbing In Wall Rough Ins

Primer and First Coat Paint

Mechanical In Wall Rough Ins

Fire Protection In Wall Rough Ins

Electrical Cable Trays

Ceiling Grid

Fire Alarm Devices

Sprinkler Heads

ATC Wiring

Casework and Cabinetry

East Pennsboro Elementary School

Construction Schedule (1716e r1a)Data Date Nov-19-19

Schedule ID 1716e r1a

Run Date Dec-09-19

Page 4 of 9

Page 14: EAST PENNSBORO ELEMENTARY SCHOOL€¦ · Project Manager MC:dlp Attachments cc: File 405 . ... Job Trailer – 80% Addition Footings and Foundation – 100% West Creek Hills Elementary

. Description DaysPlan

Dur %Comp

DaysLeft

Start Finish TotalFloat

en1.24 Light Fixtures, Speakers, Receptacles, Security Devices 15 0% 15 Jun-11-20 Jul-02-20 4

en1.25 Remove Temporary Lighting and Power 5 0% 5 Jun-12-20 Jun-19-20 93

en1.26 VCT Flooring 10 0% 10 Jun-17-20 Jul-01-20 3

en1.27 Fire Protection Hydro Testing, Inspection of New System Piping 1 0% 1 Jun-18-20 Jun-19-20 13

en1.28 Ceiling Tile 10 0% 10 Jun-19-20 Jul-06-20 13

en1.29 Doors and Hardware 10 0% 10 Jun-24-20 Jul-09-20 6

en1.30 Low Voltage Fixtures and Devices 5 0% 5 Jun-25-20 Jul-02-20 4

en1.31 Mechanical Fixtures and Devices 15 0% 15 Jun-25-20 Jul-17-20 5

en1.32 Resinous Epoxy Flooring 5 0% 5 Jul-01-20 Jul-09-20 3

en1.33 Solid Surfaces 3 0% 3 Jul-02-20 Jul-08-20 4

en1.34 Room Signage 2 0% 2 Jul-09-20 Jul-13-20 6

en1.35 Install Folding Partition 2 0% 2 Jul-09-20 Jul-13-20 11

en1.36 Walk Off Mats 3 0% 3 Jul-09-20 Jul-14-20 10

en1.37 Epoxy Coated Concrete 3 0% 3 Jul-09-20 Jul-14-20 10

en1.38 Final Coat Paint 5 0% 5 Jul-09-20 Jul-16-20 4

en1.39 Plumbing Fixtures 10 0% 10 Jul-09-20 Jul-23-20 3

en1.40 Overhead Grille and Counter Door 3 0% 3 Jul-13-20 Jul-16-20 6

en1.41 Fire Cabinets and Extinguishers 2 0% 2 Jul-16-20 Jul-20-20 6

en1.42 Tackboards and Whiteboards 3 0% 3 Jul-16-20 Jul-21-20 5

en1.43 Corridor Tack Strips 4 0% 4 Jul-16-20 Jul-22-20 4

en1.44 Toilet Partitions 4 0% 4 Jul-16-20 Jul-22-20 4

en1.45 Staircase Rubber Flooring 4 0% 4 Jul-16-20 Jul-22-20 4

en1.46 Toilet Accessories 3 0% 3 Jul-17-20 Jul-22-20 4

en1.47 Final Cleaning 5 0% 5 Jul-23-20 Jul-30-20 3

en1.48 Air Balancing 5 0% 5 Jul-30-20 Aug-06-20 60

en1.49 Punchlist 10 0% 10 Jul-30-20 Aug-13-20 55

Second Floor - AdditionSecond Floor - AdditionSecond Floor - AdditionSecond Floor - AdditionSecond Floor - AdditionSecond Floor - AdditionSecond Floor - AdditionSecond Floor - Addition

en2.1 Prep and Pour 2nd Floor Concrete Floor 10 0% 10 Feb-11-20 Feb-25-20 21

en2.2 Interior Masonry Walls and Chases 20 0% 20 Mar-17-20 Apr-14-20 8

en2.3 Aluminum Wall Panels 10 0% 10 Apr-10-20 Apr-24-20 60

en2.4 Staircase Handrail 3 0% 3 Apr-14-20 Apr-17-20 66

en2.5 Electrical Overhead Rough In / Labeling 10 0% 10 Apr-21-20 May-05-20 3

en2.6 Plumbing Overhead Rough In / Insulation / Labeling 10 0% 10 Apr-22-20 May-06-20 3

en2.7 Install Mechanical Interior Unit 5 0% 5 Apr-23-20 Apr-30-20 3

N Dec Jan F Mar Apr M J Jul A S Oct N D

2020

Light Fixtures, Speake

Remove Temporary Ligh

VCT Flooring

Fire Protection Hydro Te

Ceiling Tile

Doors and Hardware

Low Voltage Fixtures a

Mechanical Fixtures

Resinous Epoxy Flooring

Solid Surfaces

Room Signage

Install Folding Partition

Walk Off Mats

Epoxy Coated Concrete

Final Coat Paint

Plumbing Fixtures

Overhead Grille and

Fire Cabinets and Ex

Tackboards and Whiteboards

Corridor Tack Strips

Toilet Partitions

Staircase Rubber Flooring

Toilet Accessories

Final Cleaning

Air Balancing

Punchlist

Prep and Pour 2nd Floor Concrete Floor

Interior Masonry Walls and Chases

Aluminum Wall Panels

Staircase Handrail

Electrical Overhead Rough In / Labeling

Plumbing Overhead Rough In

Install Mechanical Interior Unit

East Pennsboro Elementary School

Construction Schedule (1716e r1a)Data Date Nov-19-19

Schedule ID 1716e r1a

Run Date Dec-09-19

Page 5 of 9

Page 15: EAST PENNSBORO ELEMENTARY SCHOOL€¦ · Project Manager MC:dlp Attachments cc: File 405 . ... Job Trailer – 80% Addition Footings and Foundation – 100% West Creek Hills Elementary

. Description DaysPlan

Dur %Comp

DaysLeft

Start Finish TotalFloat

en2.8 Mechanical Pipe and Duct Overhead Rough In / Insulation / Tagging 15 0% 15 Apr-23-20 May-14-20 3

en2.9 Fire Protection Overhead Rough In / Labeling 10 0% 10 Apr-30-20 May-14-20 3

en2.10 Interior Metal Framing 8 0% 8 May-07-20 May-19-20 3

en2.11 Wood Blocking 5 0% 5 May-13-20 May-20-20 3

en2.12 Interior Door Frames, Windows, Storefronts 4 0% 4 May-14-20 May-20-20 27

en2.13 Hang and Finish Drywall 10 0% 10 May-15-20 Jun-01-20 3

en2.14 Electrical In Wall Rough Ins 10 0% 10 May-20-20 Jun-04-20 27

en2.15 Plumbing In Wall Rough Ins 10 0% 10 May-21-20 Jun-05-20 27

en2.16 Primer and First Coat Paint 8 0% 8 May-22-20 Jun-04-20 4

en2.17 Mechanical In Wall Rough Ins 10 0% 10 May-22-20 Jun-08-20 27

en2.18 Fire Protection In Wall Rough Ins 10 0% 10 May-26-20 Jun-09-20 27

en2.19 Electrical Cable Trays 5 0% 5 Jun-01-20 Jun-08-20 3

en2.20 Ceiling Grid 5 0% 5 Jun-03-20 Jun-10-20 3

en2.21 Fire Alarm Devices 5 0% 5 Jun-04-20 Jun-11-20 4

en2.22 Sprinkler Heads 10 0% 10 Jun-04-20 Jun-18-20 13

en2.23 ATC Wiring 5 0% 5 Jun-09-20 Jun-16-20 27

en2.24 Casework and Cabinetry 10 0% 10 Jun-10-20 Jun-24-20 3

en2.25 Light Fixtures, Speakers, Receptacles, Security Devices 15 0% 15 Jun-11-20 Jul-02-20 4

en2.26 Remove Temporary Lighting and Power 5 0% 5 Jun-12-20 Jun-19-20 93

en2.27 VCT Flooring 10 0% 10 Jun-17-20 Jul-01-20 3

en2.28 Fire Protection Hydro Testing, Inspection of New System Piping 1 0% 1 Jun-18-20 Jun-19-20 13

en2.29 Ceiling Tile 10 0% 10 Jun-19-20 Jul-06-20 13

en2.30 Doors and Hardware 10 0% 10 Jun-24-20 Jul-09-20 6

en2.31 Low Voltage Fixtures and Devices 5 0% 5 Jun-25-20 Jul-02-20 4

en2.32 Mechanical Fixtures and Devices 15 0% 15 Jun-25-20 Jul-17-20 5

en2.33 Resinous Epoxy Flooring 5 0% 5 Jul-01-20 Jul-09-20 3

en2.34 Solid Surfaces 3 0% 3 Jul-02-20 Jul-08-20 4

en2.35 Room Signage 2 0% 2 Jul-09-20 Jul-13-20 6

en2.36 Install Folding Partition 2 0% 2 Jul-09-20 Jul-13-20 78

en2.37 Walk Off Mats 3 0% 3 Jul-09-20 Jul-14-20 10

en2.38 Epoxy Coated Concrete 3 0% 3 Jul-09-20 Jul-14-20 10

en2.39 Final Coat Paint 5 0% 5 Jul-09-20 Jul-16-20 4

en2.40 Plumbing Fixtures 10 0% 10 Jul-09-20 Jul-23-20 3

en2.41 Overhead Grille and Counter Door 3 0% 3 Jul-13-20 Jul-16-20 6

N Dec Jan F Mar Apr M J Jul A S Oct N D

2020

Mechanical Pipe and Duct Ov

Fire Protection Overhead Rou

Interior Metal Framing

Wood Blocking

Interior Door Frames, Windo

Hang and Finish Drywall

Electrical In Wall Rough Ins

Plumbing In Wall Rough Ins

Primer and First Coat Paint

Mechanical In Wall Rough Ins

Fire Protection In Wall Rough Ins

Electrical Cable Trays

Ceiling Grid

Fire Alarm Devices

Sprinkler Heads

ATC Wiring

Casework and Cabinetry

Light Fixtures, Speake

Remove Temporary Ligh

VCT Flooring

Fire Protection Hydro Te

Ceiling Tile

Doors and Hardware

Low Voltage Fixtures a

Mechanical Fixtures

Resinous Epoxy Flooring

Solid Surfaces

Room Signage

Install Folding Partition

Walk Off Mats

Epoxy Coated Concrete

Final Coat Paint

Plumbing Fixtures

Overhead Grille and

East Pennsboro Elementary School

Construction Schedule (1716e r1a)Data Date Nov-19-19

Schedule ID 1716e r1a

Run Date Dec-09-19

Page 6 of 9

Page 16: EAST PENNSBORO ELEMENTARY SCHOOL€¦ · Project Manager MC:dlp Attachments cc: File 405 . ... Job Trailer – 80% Addition Footings and Foundation – 100% West Creek Hills Elementary

. Description DaysPlan

Dur %Comp

DaysLeft

Start Finish TotalFloat

en2.42 Fire Cabinets and Extinguishers 2 0% 2 Jul-16-20 Jul-20-20 6

en2.43 Tackboards and Whiteboards 3 0% 3 Jul-16-20 Jul-21-20 5

en2.44 Staircase Rubber Flooring 4 0% 4 Jul-16-20 Jul-22-20 4

en2.45 Toilet Partitions 4 0% 4 Jul-16-20 Jul-22-20 4

en2.46 Corridor Tack Strips 4 0% 4 Jul-16-20 Jul-22-20 4

en2.47 Toilet Accessories 3 0% 3 Jul-17-20 Jul-22-20 4

en2.48 Final Cleaning 5 0% 5 Jul-23-20 Jul-30-20 3

en2.49 Air Balancing 5 0% 5 Jul-30-20 Aug-06-20 60

en2.50 Punchlist 10 0% 10 Jul-30-20 Aug-13-20 55

Renovations - Ground Floor Area CRenovations - Ground Floor Area CRenovations - Ground Floor Area CRenovations - Ground Floor Area CRenovations - Ground Floor Area CRenovations - Ground Floor Area CRenovations - Ground Floor Area CRenovations - Ground Floor Area C

ec.02 Electrical Demo / Patch 5 0% 5 Jun-09-20 Jun-15-20 4

ec.03 Mechanical Demo / Patch 5 0% 5 Jun-09-20 Jun-15-20 4

ec.08 Plumbing Demo / Patch 5 0% 5 Jun-09-20 Jun-15-20 4

ec.01 Selective Demo / Patch 10 0% 10 Jun-09-20* Jun-22-20 4

ec.05 Electrical Rough Ins 8 0% 8 Jun-16-20 Jun-25-20 4

ec.09 Plumbing Rough Ins and Finishes 8 0% 8 Jun-18-20 Jun-29-20 4

ec.04 Mechanical Rough Ins 8 0% 8 Jun-22-20 Jul-01-20 4

ec.19 Steel Members, Decking, Concrete 5 0% 5 Jun-23-20 Jun-29-20 6

ec.06 ATC Wiring 3 0% 3 Jun-26-20 Jun-30-20 7

ec.13 Install Door and Frame 3 0% 3 Jun-30-20 Jul-02-20 6

ec.07 Cable Tray 3 0% 3 Jul-02-20 Jul-07-20 4

ec.14 Painting 8 0% 8 Jul-08-20 Jul-17-20 4

ec.10 Reinstall Ceiling Grid and Tile 5 0% 5 Jul-13-20 Jul-17-20 4

ec.20 Plumbing Fixtures 1 0% 1 Jul-20-20 Jul-20-20 5

ec.21 Electrical Finishes 4 0% 4 Jul-20-20 Jul-23-20 4

ec.11 Install Handrail System 5 0% 5 Jul-20-20 Jul-24-20 4

ec.12 Toilet Accessories 3 0% 3 Jul-21-20 Jul-23-20 5

ec.22 Mechanical Finishes 4 0% 4 Jul-21-20 Jul-24-20 4

ec.15 Final Cleaning 3 0% 3 Jul-27-20 Jul-29-20 4

ec.17 Air Balancing 5 0% 5 Jul-30-20 Aug-05-20 61

ec.16 Punchlist 10 0% 10 Jul-30-20 Aug-12-20 56

Renovations - First Floor Area ARenovations - First Floor Area ARenovations - First Floor Area ARenovations - First Floor Area ARenovations - First Floor Area ARenovations - First Floor Area ARenovations - First Floor Area ARenovations - First Floor Area A

ea.01 Remove Kitchen Equipment 3 0% 3 Jun-09-20* Jun-11-20 0

ea.02 Selective Demo 5 0% 5 Jun-09-20 Jun-15-20 0

N Dec Jan F Mar Apr M J Jul A S Oct N D

2020

Fire Cabinets and Ex

Tackboards and Whiteboards

Staircase Rubber Flooring

Toilet Partitions

Corridor Tack Strips

Toilet Accessories

Final Cleaning

Air Balancing

Punchlist

Electrical Demo / Patch

Mechanical Demo / Patch

Plumbing Demo / Patch

Selective Demo / Patch

Electrical Rough Ins

Plumbing Rough Ins an

Mechanical Rough Ins

Steel Members, Decking

ATC Wiring

Install Door and Frame

Cable Tray

Painting

Reinstall Ceiling Grid and Tile

Plumbing Fixtures

Electrical Finishes

Install Handrail System

Toilet Accessories

Mechanical Finishes

Final Cleaning

Air Balancing

Punchlist

Remove Kitchen Equipment

Selective Demo

East Pennsboro Elementary School

Construction Schedule (1716e r1a)Data Date Nov-19-19

Schedule ID 1716e r1a

Run Date Dec-09-19

Page 7 of 9

Page 17: EAST PENNSBORO ELEMENTARY SCHOOL€¦ · Project Manager MC:dlp Attachments cc: File 405 . ... Job Trailer – 80% Addition Footings and Foundation – 100% West Creek Hills Elementary

. Description DaysPlan

Dur %Comp

DaysLeft

Start Finish TotalFloat

ea.03 Plumbing Demo 5 0% 5 Jun-09-20 Jun-15-20 2

ea.04 Electrical Demo 5 0% 5 Jun-09-20 Jun-15-20 2

ea.05 Mechanical Demo 5 0% 5 Jun-09-20 Jun-15-20 2

ea.07 Metal Wall Framing 8 0% 8 Jun-15-20 Jun-24-20 0

ea.06 Fire Protection Pipe for Area A & Riser 5 0% 5 Jun-16-20 Jun-22-20 2

ea.09 Plumbing Rough In 10 0% 10 Jun-16-20 Jun-29-20 0

ea.11 Low Voltage Rough In 5 0% 5 Jun-17-20 Jun-23-20 6

ea.10 Electrical Rough In 8 0% 8 Jun-17-20 Jun-26-20 1

ea.12 Mechanical Rough In 15 0% 15 Jun-17-20 Jul-08-20 0

ea.16 Hollow Metal Door Frames and Windows 4 0% 4 Jun-19-20 Jun-24-20 2

ea.08 Wood Blocking 3 0% 3 Jun-22-20 Jun-24-20 0

ea.42 Wire New Fire Alarm Devices, Ensure Monitoring 1 0% 1 Jun-23-20 Jun-23-20 80

ea.17 Hang and Finish Drywall 8 0% 8 Jun-23-20 Jul-02-20 0

ea.43 Final Fire Protection Inspection / Testing 1 0% 1 Jun-24-20 Jun-24-20 80

ea.13 Thermostat Wiring 3 0% 3 Jun-24-20 Jun-26-20 21

ea.22 Electrical Devices: Lights, Receptacles, Devices 8 0% 8 Jun-29-20 Jul-09-20 1

ea.18 Primer and First Coat Paint 5 0% 5 Jun-30-20 Jul-07-20 0

ea.23 Mechanical Finishes 8 0% 8 Jun-30-20 Jul-10-20 12

ea.21 Ceiling Grid 5 0% 5 Jul-02-20 Jul-09-20 0

ea.14 Install Mechanical Interior Units 3 0% 3 Jul-06-20 Jul-08-20 14

ea.33 Resinous Kitchen Epoxy Flooring 10 0% 10 Jul-07-20 Jul-16-20 0

ea.34 Bathroom Epoxy Flooring 5 0% 5 Jul-08-20 Jul-14-20 2

ea.24 Plumbing Finishes 8 0% 8 Jul-08-20 Jul-17-20 0

ea.25 Cabinetry and Casework 5 0% 5 Jul-10-20 Jul-16-20 0

ea.15 Mechanical Unit Start Up 2 0% 2 Jul-13-20 Jul-14-20 12

ea.35 VCT Flooring 5 0% 5 Jul-15-20 Jul-21-20 2

ea.27 Install Kitchen Equipment 5 0% 5 Jul-17-20 Jul-23-20 0

ea.29 Electrical Kitchen Equipment Connections 8 0% 8 Jul-17-20 Jul-28-20 0

ea.30 Plumbing Kitchen Equipment Connections 8 0% 8 Jul-17-20 Jul-28-20 0

ea.31 Mechanical Kitchen Equipment Connections 8 0% 8 Jul-17-20 Jul-28-20 0

ea.19 Toilet Partitions 4 0% 4 Jul-20-20 Jul-23-20 0

ea.36 Room Signage 2 0% 2 Jul-22-20 Jul-23-20 3

ea.28 Doors and Hardware 5 0% 5 Jul-22-20 Jul-28-20 2

ea.38 Final Coat Paint 2 0% 2 Jul-24-20 Jul-27-20 1

N Dec Jan F Mar Apr M J Jul A S Oct N D

2020

Plumbing Demo

Electrical Demo

Mechanical Demo

Metal Wall Framing

Fire Protection Pipe for

Plumbing Rough In

Low Voltage Rough In

Electrical Rough In

Mechanical Rough In

Hollow Metal Door Fram

Wood Blocking

Wire New Fire Alarm Dev

Hang and Finish Drywall

Final Fire Protection Ins

Thermostat Wiring

Electrical Devices: Lig

Primer and First Coat Paint

Mechanical Finishes

Ceiling Grid

Install Mechanical Interior Units

Resinous Kitchen Ep

Bathroom Epoxy Flooring

Plumbing Finishes

Cabinetry and Casework

Mechanical Unit Start Up

VCT Flooring

Install Kitchen Equipment

Electrical Kitchen E

Plumbing Kitchen

Mechanical Kitchen

Toilet Partitions

Room Signage

Doors and Hardware

Final Coat Paint

East Pennsboro Elementary School

Construction Schedule (1716e r1a)Data Date Nov-19-19

Schedule ID 1716e r1a

Run Date Dec-09-19

Page 8 of 9

Page 18: EAST PENNSBORO ELEMENTARY SCHOOL€¦ · Project Manager MC:dlp Attachments cc: File 405 . ... Job Trailer – 80% Addition Footings and Foundation – 100% West Creek Hills Elementary

. Description DaysPlan

Dur %Comp

DaysLeft

Start Finish TotalFloat

ea.20 Toilet Accessories 3 0% 3 Jul-24-20 Jul-28-20 2

ea.26 Handrails 5 0% 5 Jul-24-20 Jul-30-20 0

ea.32 Ceiling Tile 5 0% 5 Jul-24-20 Jul-30-20 0

ea.37 Privacy Curtains 2 0% 2 Jul-28-20 Jul-29-20 1

ea.39 Final Cleaning 3 0% 3 Jul-31-20 Aug-04-20 0

ea.41 Air Balancing 5 0% 5 Aug-05-20 Aug-11-20 57

ea.40 Punchlist 10 0% 10 Aug-05-20 Aug-18-20 52

N Dec Jan F Mar Apr M J Jul A S Oct N D

2020

Toilet Accessories

Handrails

Ceiling Tile

Privacy Curtains

Final Cleaning

Air Balancing

Punchlist

East Pennsboro Elementary School

Construction Schedule (1716e r1a)Data Date Nov-19-19

Schedule ID 1716e r1a

Run Date Dec-09-19

Page 9 of 9

Page 19: EAST PENNSBORO ELEMENTARY SCHOOL€¦ · Project Manager MC:dlp Attachments cc: File 405 . ... Job Trailer – 80% Addition Footings and Foundation – 100% West Creek Hills Elementary

. Description DaysPlan

Dur %Comp

DaysLeft

Start Finish TotalFloat

West Creek Hills Elementary SchoolWest Creek Hills Elementary SchoolWest Creek Hills Elementary SchoolWest Creek Hills Elementary SchoolWest Creek Hills Elementary SchoolWest Creek Hills Elementary SchoolWest Creek Hills Elementary SchoolWest Creek Hills Elementary School

sc.2b Substantial Completion - Renovations - NLT Aug-4-20 0 0% 0 Jul-20-20* 10

sc.2as Substantial Completion - Sitework - NLT Aug-4-20 0 0% 0 Jul-28-20* 4

sc.2a Substantial Completion - Addition - NLT Aug-4-20 0 0% 0 Jul-29-20* 5

Site WorkSite WorkSite WorkSite WorkSite WorkSite WorkSite WorkSite Work

ws.3 Erosion Control 3 90% 0 Oct-23-19 A Nov-20-19 5

ws.11 North Playground Demolition 5 90% 1 Oct-29-19 A Nov-20-19 6

ws.6 Temporary Sediment Trap 3 75% 1 Nov-04-19 A Nov-21-19 6

ws.8 Stormwater Piping - Track Area 10 0% 10 Nov-20-19 Dec-06-19 5

ws.10 Existing Storm System Demolition 3 0% 3 Nov-21-19 Nov-26-19 11

ws.13 Underground Sanitary and Sewer Rough-in 10 0% 10 Dec-06-19 Dec-20-19 5

ws.14 Remove Lines - Front Parking Lot 1 0% 1 Jun-09-20 Jun-09-20 34

ws.15 Prep Subbase for Asphalt and Concrete Sidewalks 5 0% 5 Jun-09-20 Jun-15-20 14

ws.16 Prep Subbase for Emergency Access Lane 5 0% 5 Jun-09-20 Jun-15-20 14

ws.17 Prep Soft Play Area - Coordinate with Playround Installer 5 0% 5 Jun-09-20 Jun-15-20 32

ws.18 Remove Trailers and Laydown Area - Move Inside 10 0% 10 Jun-09-20 Jun-22-20 4

ws.19 Seal Coat Front Parking Lot 1 0% 1 Jun-10-20 Jun-10-20 34

ws.20 Base Pave - Walkways 1 0% 1 Jun-16-20 Jun-16-20 14

ws.21 Base Pave - Emergency Access Road 1 0% 1 Jun-16-20 Jun-16-20 14

ws.22 2B Stone Play Area 1 0% 1 Jun-16-20 Jun-16-20 32

ws.23 Pour Concrete Sidewalks - Building Addition and Front Parking Lot 1 0% 1 Jun-16-20 Jun-16-20 33

ws.24 Wearing Course Pave - Walkways 1 0% 1 Jun-17-20 Jun-17-20 14

ws.25 Wearing Course Pave - Emergency Access Road 1 0% 1 Jun-17-20 Jun-17-20 14

ws.26 Mulch Play Area 1 0% 1 Jun-17-20 Jun-17-20 32

ws.27 Prep Track Subbase for Pavement 5 0% 5 Jun-23-20 Jun-29-20 4

ws.28 Base Pave Track 1 0% 1 Jun-30-20 Jun-30-20 4

ws.29 Wearing Course Pave - Track 1 0% 1 Jul-01-20 Jul-01-20 4

ws.30 Line Striping - Front Parking Lot and Track 1 0% 1 Jul-02-20 Jul-02-20 19

ws.31 Basketball Court Equipment 3 0% 3 Jul-02-20 Jul-07-20 19

ws.32 Replace Top Soil 5 0% 5 Jul-02-20 Jul-09-20 4

ws.33 Install Parking Bumpers 1 0% 1 Jul-06-20 Jul-06-20 19

ws.34 Site Signage 1 0% 1 Jul-07-20 Jul-07-20 19

ws.35 Final Seeding 3 0% 3 Jul-10-20 Jul-14-20 4

ws.36 Landscaping 3 0% 3 Jul-10-20 Jul-14-20 12

N D Jan F Mar Apr M Jun Jul A S Oct N D

2020

Substantial Comple

Substantial Comp

Substantial Comp

Erosion Control

North Playground Demolition

Temporary Sediment Trap

Stormwater Piping - Track Area

Existing Storm System Demolition

Underground Sanitary and Sewer Rough-in

Remove Lines - Front Parking Lot

Prep Subbase for Aspha

Prep Subbase for Emerg

Prep Soft Play Area - Coo

Remove Trailers and La

Seal Coat Front Parking Lot

Base Pave - Walkways

Base Pave - Emergency A

2B Stone Play Area

Pour Concrete Sidewalks

Wearing Course Pave - Walkways

Wearing Course Pave - E

Mulch Play Area

Prep Track Subbase fo

Base Pave Track

Wearing Course Pave - Track

Line Striping - Front P

Basketball Court Equipment

Replace Top Soil

Install Parking Bumpers

Site Signage

Final Seeding

Landscaping

West Creek Hills Elementary School

Construction Schedule (1716w r1a)Data Date Nov-19-19

Schedule ID 1716w r1a

Run Date Dec-09-19

Page 1 of 5

Page 20: EAST PENNSBORO ELEMENTARY SCHOOL€¦ · Project Manager MC:dlp Attachments cc: File 405 . ... Job Trailer – 80% Addition Footings and Foundation – 100% West Creek Hills Elementary

. Description DaysPlan

Dur %Comp

DaysLeft

Start Finish TotalFloat

ws.37 Convert Temporary Sediment Trap to Permanent Basin 5 0% 5 Jul-15-20 Jul-21-20 4

ws.38 Remove Erosion Controls 2 0% 2 Jul-22-20 Jul-23-20 7

ws.39 Permanent Site Fencing 5 0% 5 Jul-22-20 Jul-28-20 4

Classroom AdditionClassroom AdditionClassroom AdditionClassroom AdditionClassroom AdditionClassroom AdditionClassroom AdditionClassroom Addition

wa.1 Excavate & Pour Footers 10 10% 9 Nov-18-19 A Dec-06-19 6

wa.2 Foundation Walls and Shear Walls 15 0% 15 Dec-04-19 Dec-26-19 6

wa.3 Plumbing Undergrounds 5 0% 5 Dec-20-19 Dec-30-19 5

wa.5 Backfill Foundation Walls 5 0% 5 Dec-24-19 Jan-02-20 6

wa.4 Stone Under Slab 5 0% 5 Dec-26-19 Jan-03-20 5

wa.6 Pour Slab on Grade 3 0% 3 Jan-03-20 Jan-08-20 5

wa.8 Load Bearing Wall Framing 8 0% 8 Jan-08-20 Jan-20-20 5

wa.7 Set Columns and Corridor Tube Steel 5 0% 5 Jan-20-20 Jan-27-20 5

wa.10 Electric Exterior Wall Rough-In 5 0% 5 Jan-20-20 Jan-27-20 39

wa.11 Plumbing Exterior Wall Rough-In 5 0% 5 Jan-20-20 Jan-27-20 39

wa.12 Exterior Wall Insulation 10 0% 10 Jan-20-20 Feb-03-20 43

wa.9 Set Roof Steel 10 0% 10 Jan-27-20 Feb-10-20 5

wa.13 HM Frames 3 0% 3 Jan-29-20 Feb-03-20 15

wa.14 Interior Wall Layout and Framing 15 0% 15 Feb-03-20 Feb-24-20 15

wa.15 Roof Decking 5 0% 5 Feb-10-20 Feb-17-20 5

wa.16 Plumbing Interior Wall Rough-In 15 0% 15 Feb-10-20 Mar-02-20 29

wa.17 Roof Insulation 5 0% 5 Feb-11-20 Feb-18-20 9

wa.18 Roof Drains 3 0% 3 Feb-13-20 Feb-18-20 9

wa.19 Roof Blocking and Curbs 5 0% 5 Feb-17-20 Feb-24-20 5

wa.20 Electrical Interior Wall Rough-in 15 0% 15 Feb-17-20 Mar-09-20 24

wa.21 Low Voltage Interior Wall Rough-In 15 0% 15 Feb-17-20 Mar-09-20 24

wa.22 Membrane Roofing 10 0% 10 Feb-24-20 Mar-09-20 5

wa.31 Wall Rough In Inspection 1 0% 1 Mar-09-20 Mar-10-20 24

wa.23 Set Roof Top HVAC Equipment 1 0% 1 Mar-09-20 Mar-10-20 42

wa.24 Sprinkler Rough In 15 0% 15 Mar-09-20 Mar-30-20 5

wa.25 Masonry Veneer 30 0% 30 Mar-09-20 Apr-20-20 18

wa.26 Set Cabinet Unit Heaters/Wall Mounted Unit Heaters 5 0% 5 Mar-16-20 Mar-23-20 43

wa.27 Overhead Plumbing 10 0% 10 Mar-16-20 Mar-30-20 28

wa.28 HVAC Piping and Duct Rough-In 22 0% 22 Mar-16-20 Apr-15-20 5

wa.29 Electrical Above Ceiling Rough-In 10 0% 10 Mar-23-20 Apr-06-20 5

N D Jan F Mar Apr M Jun Jul A S Oct N D

2020

Convert Temporary

Remove Erosion Controls

Permanent Site Fencing

Excavate & Pour Footers

Foundation Walls and Shear Walls

Plumbing Undergrounds

Backfill Foundation Walls

Stone Under Slab

Pour Slab on Grade

Load Bearing Wall Framing

Set Columns and Corridor Tube Steel

Electric Exterior Wall Rough-In

Plumbing Exterior Wall Rough-In

Exterior Wall Insulation

Set Roof Steel

HM Frames

Interior Wall Layout and Framing

Roof Decking

Plumbing Interior Wall Rough-In

Roof Insulation

Roof Drains

Roof Blocking and Curbs

Electrical Interior Wall Rough-in

Low Voltage Interior Wall Rough-In

Membrane Roofing

Wall Rough In Inspection

Set Roof Top HVAC Equipment

Sprinkler Rough In

Masonry Veneer

Set Cabinet Unit Heaters/Wall Mount

Overhead Plumbing

HVAC Piping and Duct Rough-In

Electrical Above Ceiling Rough-In

West Creek Hills Elementary School

Construction Schedule (1716w r1a)Data Date Nov-19-19

Schedule ID 1716w r1a

Run Date Dec-09-19

Page 2 of 5

Page 21: EAST PENNSBORO ELEMENTARY SCHOOL€¦ · Project Manager MC:dlp Attachments cc: File 405 . ... Job Trailer – 80% Addition Footings and Foundation – 100% West Creek Hills Elementary

. Description DaysPlan

Dur %Comp

DaysLeft

Start Finish TotalFloat

wa.30 Domestic Piping Insulation 10 0% 10 Mar-30-20 Apr-13-20 28

wa.33 Pull Data Cable 15 0% 15 Apr-06-20 Apr-27-20 5

wa.34 Pull Wires 15 0% 15 Apr-06-20 Apr-27-20 5

wa.32 HVAC Piping and Duct Insulation 10 0% 10 Apr-15-20 Apr-29-20 16

wa.37 Hang and Finish Drywall 25 0% 25 Apr-16-20 May-21-20 5

wa.35 Composite Metal Panels 5 0% 5 Apr-20-20 Apr-27-20 20

wa.36 Windows 10 0% 10 Apr-20-20 May-04-20 18

wa.38 Aluminum Store Fronts - Vestibules 3 0% 3 Apr-27-20 Apr-30-20 20

wa.39 Masonry Caulking 5 0% 5 May-04-20 May-11-20 60

wa.40 Painting 15 0% 15 May-07-20 May-29-20 5

wa.41 Acoustical Ceiling Grid 10 0% 10 May-14-20 May-29-20 5

wa.42 Sprinkler Heads 3 0% 3 May-18-20 May-21-20 12

wa.43 Speakers, Exit Signs, Smoke Heads 3 0% 3 May-18-20 May-21-20 12

wa.44 HVAC GRDs 3 0% 3 May-18-20 May-21-20 13

wa.45 Lighting 10 0% 10 May-18-20 Jun-02-20 5

wa.61 Fire Protection Hydro Testing 1 0% 1 May-21-20 May-22-20 12

wa.47 Set Classroom Unit Ventilators 5 0% 5 May-29-20 Jun-05-20 31

wa.48 Switches, Receptacles, Data and Fire Alarm Devices 5 0% 5 May-29-20 Jun-05-20 32

wa.49 Above Ceiling Inspection 1 0% 1 Jun-02-20 Jun-03-20 5

wa.50 Acoustical Ceiling Tile 8 0% 8 Jun-03-20 Jun-15-20 5

wa.51 HVAC Startup 1 0% 1 Jun-05-20 Jun-08-20 31

wa.52 Classroom Casework 10 0% 10 Jun-05-20 Jun-19-20 7

wa.53 Resinous Flooring Bathrooms 5 0% 5 Jun-15-20 Jun-22-20 5

wa.54 Classroom VCT 15 0% 15 Jun-15-20 Jul-07-20 6

wa.55 Corridor Terrazzo 15 0% 15 Jun-15-20 Jul-07-20 8

wa.56 Plumbing Fixtures 10 0% 10 Jun-22-20 Jul-07-20 5

wa.57 Doors and Hardware 10 0% 10 Jun-29-20 Jul-14-20 6

wa.46 Visual Display Boards 3 0% 3 Jul-07-20 Jul-10-20 8

wa.62 Toilet Partitions 5 0% 5 Jul-07-20 Jul-14-20 5

wa.58 Accessories and Signage 5 0% 5 Jul-07-20 Jul-14-20 6

wa.63 Toilet Accessories 2 0% 2 Jul-13-20 Jul-15-20 5

wa.59 Final Cleaning 10 0% 10 Jul-15-20 Jul-29-20 5

wa.60 Balancing 10 0% 10 Jul-29-20 Aug-12-20 57

Building RenovationsBuilding RenovationsBuilding RenovationsBuilding RenovationsBuilding RenovationsBuilding RenovationsBuilding RenovationsBuilding Renovations

N D Jan F Mar Apr M Jun Jul A S Oct N D

2020

Domestic Piping Insulation

Pull Data Cable

Pull Wires

HVAC Piping and Duct Insulation

Hang and Finish Drywall

Composite Metal Panels

Windows

Aluminum Store Fronts - Vestibules

Masonry Caulking

Painting

Acoustical Ceiling Grid

Sprinkler Heads

Speakers, Exit Signs, Smoke Heads

HVAC GRDs

Lighting

Fire Protection Hydro Testing

Set Classroom Unit Ventilators

Switches, Receptacles, Da

Above Ceiling Inspection

Acoustical Ceiling Tile

HVAC Startup

Classroom Casework

Resinous Flooring Bathrooms

Classroom VCT

Corridor Terrazzo

Plumbing Fixtures

Doors and Hardware

Visual Display Boards

Toilet Partitions

Accessories and Signage

Toilet Accessories

Final Cleaning

Balancing

West Creek Hills Elementary School

Construction Schedule (1716w r1a)Data Date Nov-19-19

Schedule ID 1716w r1a

Run Date Dec-09-19

Page 3 of 5

Page 22: EAST PENNSBORO ELEMENTARY SCHOOL€¦ · Project Manager MC:dlp Attachments cc: File 405 . ... Job Trailer – 80% Addition Footings and Foundation – 100% West Creek Hills Elementary

. Description DaysPlan

Dur %Comp

DaysLeft

Start Finish TotalFloat

wr.1 Summer Start Date 0 0% 0 Jun-09-20* 4

wr.2 Remove Music Practice A004 and Boys Restoom A106 Ceiling Grid and Tile for Sanitary Line1 0% 1 Jun-09-20 Jun-09-20 31

wr.3 Domestic Water Line Taps for Addition 1 0% 1 Jun-09-20 Jun-09-20 38

wr.4 Remove Corridor and Classroom Ceiling Grid and Tile for Sprinkler and Power Feeds2 0% 2 Jun-09-20 Jun-10-20 20

wr.5 Install New Sanitary Line from Addition to Restroom Chase 3 0% 3 Jun-10-20 Jun-12-20 31

wr.11 Reconfigure Existing Sprinkler Riser, Add to New Riser 2 0% 2 Jun-11-20 Jun-12-20 20

wr.7 Replace Music Practice A004 and Boys Restroom A106 Ceiling Grid and Tile1 0% 1 Jun-15-20 Jun-15-20 31

wr.6 Install New Sprinkler Main - Tie In at Addition 5 0% 5 Jun-15-20 Jun-19-20 20

wr.12 Wire New Fire Alarm Devices, Ensure Monitoring 1 0% 1 Jun-22-20 Jun-22-20 26

wr.8 Install New Electrical Power Feeder - Tie In at Addition 5 0% 5 Jun-22-20 Jun-26-20 20

wr.13 Fire Protection Final Inspection / Testing 1 0% 1 Jun-23-20 Jun-23-20 28

wr.9 Replace Corridor and Classroom Ceiling Grid and Tile 2 0% 2 Jun-29-20 Jun-30-20 20

wr.10 Final Clean 3 0% 3 Jul-16-20 Jul-20-20 10

Nurse's AreaNurse's AreaNurse's AreaNurse's AreaNurse's AreaNurse's AreaNurse's AreaNurse's Area

wrn.1 Demo Nurses Area Toilet Room Wall 3 0% 3 Jun-09-20 Jun-11-20 13

wrn.2 Demo Existing Sink Base - Exam Room 1 0% 1 Jun-12-20 Jun-12-20 13

wrn.3 Demo Existing Window - Nurses Office 1 0% 1 Jun-15-20 Jun-15-20 13

wrn.4 Install New ADA Sink Base 2 0% 2 Jun-15-20 Jun-16-20 29

wrn.5 Install New Aluminum Storefront Window - Nurses Of fice 1 0% 1 Jun-16-20 Jun-16-20 28

wrn.6 Install New Wall Nurses Area - Rework Devices 5 0% 5 Jun-16-20 Jun-22-20 13

wrn.7 Install New Casework - Exam Room 1 0% 1 Jun-17-20 Jun-17-20 29

wrn.8 Remove Fixtures Nurses Area Toilet Room 2 0% 2 Jun-17-20 Jun-18-20 15

wrn.9 Patch and Paint Nurse's Area Walls 3 0% 3 Jun-23-20 Jun-25-20 13

wrn.10 Rework Grid and Install New Ceiling Tile - Cot Room & Nurses Toilet Room3 0% 3 Jun-26-20 Jun-30-20 13

wrn.11 Install Epoxy Floor Over Existing Flooring (Nurse's Toilet) 5 0% 5 Jul-01-20 Jul-08-20 13

wrn.12 Install New Fixtures in Nurse's Toilet Room 1 0% 1 Jul-09-20 Jul-09-20 13

wrn.13 Install Nurses Area Occupancy Switches 1 0% 1 Jul-10-20 Jul-10-20 13

wrn.14 Install Bathroom Accessories 2 0% 2 Jul-14-20 Jul-15-20 10

Gang Restrooms and Toilet RoomsGang Restrooms and Toilet RoomsGang Restrooms and Toilet RoomsGang Restrooms and Toilet RoomsGang Restrooms and Toilet RoomsGang Restrooms and Toilet RoomsGang Restrooms and Toilet RoomsGang Restrooms and Toilet Rooms

wrg.1 Remove Fixtures Kitchen Toilet Room Gang Restroom Area A (Gym) 2 0% 2 Jun-09-20 Jun-10-20 10

wrg.2 Remove Fixtures Gang Restroom Area A (Gym) 2 0% 2 Jun-09-20 Jun-10-20 14

wrg.3 Demo Partitions 5 0% 5 Jun-09-20 Jun-15-20 11

wrg.4 Remove Fixtures Gang Restroom Area B 2 0% 2 Jun-11-20 Jun-12-20 10

wrg.5 Remove Fixtures Staff Toilet Rooms 2 0% 2 Jun-11-20 Jun-12-20 12

N D Jan F Mar Apr M Jun Jul A S Oct N D

2020

Summer Start Date

Remove Music Practice A

Domestic Water Line Taps

Remove Corridor and Cla

Install New Sanitary Line

Reconfigure Existing Spr

Replace Music Practice A

Install New Sprinkler Ma

Wire New Fire Alarm De

Install New Electrical Po

Fire Protection Final Ins

Replace Corridor and C

Final Clean

Demo Nurses Area Toilet

Demo Existing Sink Base

Demo Existing Window -

Install New ADA Sink Base

Install New Aluminum St

Install New Wall Nurses

Install New Casework - Exam Room

Remove Fixtures Nurses

Patch and Paint Nurse'

Rework Grid and Insta

Install Epoxy Floor O

Install New Fixtures i

Install Nurses Area O

Install Bathroom Accessories

Remove Fixtures Kitchen

Remove Fixtures Gang R

Demo Partitions

Remove Fixtures Gang R

Remove Fixtures Staff To

West Creek Hills Elementary School

Construction Schedule (1716w r1a)Data Date Nov-19-19

Schedule ID 1716w r1a

Run Date Dec-09-19

Page 4 of 5

Page 23: EAST PENNSBORO ELEMENTARY SCHOOL€¦ · Project Manager MC:dlp Attachments cc: File 405 . ... Job Trailer – 80% Addition Footings and Foundation – 100% West Creek Hills Elementary

. Description DaysPlan

Dur %Comp

DaysLeft

Start Finish TotalFloat

wrg.6 Remove Fixtures Gang Restroom Area C 2 0% 2 Jun-15-20 Jun-16-20 10

wrg.7 Patch and Paint Restroom / Toilet Room Walls 3 0% 3 Jun-17-20 Jun-19-20 10

wrg.8 Install Epoxy Floor Over Existing Flooring (Restrooms) 10 0% 10 Jun-22-20 Jul-06-20 10

wrg.9 Install New Fixtures in Restrooms / Toilet Rooms 3 0% 3 Jul-07-20 Jul-09-20 80

wrg.10 Modify Gang Restroom Partitions 5 0% 5 Jul-07-20 Jul-13-20 10

wrg.11 Install Bathroom Accessories 2 0% 2 Jul-14-20 Jul-15-20 10

N D Jan F Mar Apr M Jun Jul A S Oct N D

2020

Remove Fixtures Gang R

Patch and Paint Restroo

Install Epoxy Floor O

Install New Fixtures i

Modify Gang Restro

Install Bathroom Accessories

West Creek Hills Elementary School

Construction Schedule (1716w r1a)Data Date Nov-19-19

Schedule ID 1716w r1a

Run Date Dec-09-19

Page 5 of 5

Page 24: EAST PENNSBORO ELEMENTARY SCHOOL€¦ · Project Manager MC:dlp Attachments cc: File 405 . ... Job Trailer – 80% Addition Footings and Foundation – 100% West Creek Hills Elementary

East Pennsboro Area School District East Pennsboro Elementary School West Creek Hills Elementary School Progress Report #3-November 2019

21 | P a g e

Project Considerations The following major items are being tracked for resolution:

NO. ITEM RESP. RESOLUTION

DATE STATUS

01 Storm water outfall re-design at WCH K&W Engineers Jan. 2, 2020 In progress

02

03

04

05

Page 25: EAST PENNSBORO ELEMENTARY SCHOOL€¦ · Project Manager MC:dlp Attachments cc: File 405 . ... Job Trailer – 80% Addition Footings and Foundation – 100% West Creek Hills Elementary

East Pennsboro Area School District East Pennsboro Elementary School West Creek Hills Elementary School Progress Report #3-November 2019

22 | P a g e

Project Photos

EPE Pier

EPE Foundation

Page 26: EAST PENNSBORO ELEMENTARY SCHOOL€¦ · Project Manager MC:dlp Attachments cc: File 405 . ... Job Trailer – 80% Addition Footings and Foundation – 100% West Creek Hills Elementary

East Pennsboro Area School District East Pennsboro Elementary School West Creek Hills Elementary School Progress Report #3-November 2019

23 | P a g e

EPE Grading

Page 27: EAST PENNSBORO ELEMENTARY SCHOOL€¦ · Project Manager MC:dlp Attachments cc: File 405 . ... Job Trailer – 80% Addition Footings and Foundation – 100% West Creek Hills Elementary

East Pennsboro Area School District East Pennsboro Elementary School West Creek Hills Elementary School Progress Report #3-November 2019

24 | P a g e

WCH Footings

Page 28: EAST PENNSBORO ELEMENTARY SCHOOL€¦ · Project Manager MC:dlp Attachments cc: File 405 . ... Job Trailer – 80% Addition Footings and Foundation – 100% West Creek Hills Elementary

East Pennsboro Area School District East Pennsboro Elementary School West Creek Hills Elementary School Progress Report #3-November 2019

25 | P a g e

WCH Foundations

WCH Column