east pennsboro elementary school€¦ · project manager mc:dlp attachments cc: file 405 . ... job...
TRANSCRIPT
EAST PENNSBORO AREA SCHOOL DISTRICT
Additions and Renovations to
EAST PENNSBORO ELEMENTARY SCHOOL 840 Panther Parkway, Enola, PA 17025
WEST CREEK HILLS ELEMENTARY SCHOOL
400 Erford Road, Camp Hill, PA 17011
PROGRESS REPORT #3
November 2019 RC Project No. 19-1716
Prepared by:
West Creek Hills Elementary School
East Pennsboro Elementary School
December 10, 2019 Dr. Donna Dunar Superintendent East Pennsboro Area School District 890 Valley Street Enola, PA 17025 RE: East Pennsboro Area School District Additions and Renovations for East Pennsboro and
West Creek Hills Elementary Schools RC Project No. 19-1761 November 2019 – Monthly Report #3 Dear Dr. Dunar, Attached, for your use and information, is Reynolds Construction’s November 2019 Monthly Progress Report #3 for the above-referenced project. If you have any questions or comments regarding this report, please do not hesitate to contact me. Sincerely, REYNOLDS CONSTRUCTION, LLC Mike Cline Project Manager MC:dlp Attachments cc: File 405
Table of Contents Executive Summary ........................................................................................................................ 1
Contractor Updates ....................................................................................................................... 2
Contract No. 301 – General Construction / eciConstruction, LLC .......................................................... 2 Contract No. 302 – Fire Protection / S. A. Comunale, Inc. ..................................................................... 2
Pay Requisition Summary ............................................................................................................. 3
Change Management .................................................................................................................... 4
Change Order Summary .......................................................................................................................... 4 Change Order Log.................................................................................................................................... 5
Project Schedule ............................................................................................................................ 6
Project Considerations ................................................................................................................. 21
Project Photos ..............................................................................................................................22
East Pennsboro Area School District East Pennsboro Elementary School West Creek Hills Elementary School Progress Report #3-November 2019
1 | P a g e
Executive Summary The additions at both East Pennsboro Elementary School (EPE) and West Creek Hills Elementary School (WCH) have been under construction for seven (7) weeks since the Notice to Proceed issued on October 11, 2019. Substantial Completion date for additions and renovations is August 4, 2020. With regards to administrative progress, Reynolds has been assisting the District with administrative work for land easements at WCH. Schrader Group Architects, K & W Engineers and Reynolds have been diligent in reviewing and processing submittals and shop drawings for materials and equipment which will be required in the next few months. Requests for information (RFIs) from all contractors are being processed in a timely manner. On site progress to date includes that foundations for new construction at EPE are nearly complete. Excluding the gymnasium at EPE, concrete slabs on grade at both sites should be completed before the first of the year. Weather has been pleasing for late fall construction.
West Creek Hills Elementary School
East Pennsboro Elementary School
East Pennsboro Area School District East Pennsboro Elementary School West Creek Hills Elementary School Progress Report #3-November 2019
2 | P a g e
Contractor Updates Contract No. 301 – General Construction / eciConstruction, LLC
Work Completed through November 2019: East Pennsboro Elementary School
➢ Job Trailer – 80% ➢ Addition Footings and Foundation – 100%
West Creek Hills Elementary School
➢ Job Trailer – 100% ➢ Modular Classroom Demolition – 100% ➢ Addition Footings – 100%
Contract No. 302 – Fire Protection / S. A. Comunale, Inc.
Work Completed Through October 2019:
➢ Administrative documents – 100% ➢ No work onsite to date
East Pennsboro Area School District East Pennsboro Elementary School West Creek Hills Elementary School Progress Report #3-November 2019
3 | P a g e
Pay Requisition Summary
Contract
Number Contractor Name
Period
To
App
Num
Original
Contract
Net Change by
Change Order
Contract Sum to
Date
Total Compl +
Stored To Date Retainage
Total Earned
Less Retain.
Previous
Applications
Current
Payment Due
Balance To Finish
+ Retain.
Pct
Comp
301 eciConstruction, LLC 7,304,500.00$ -$ 7,304,500.00$ -$ -$ -$ -$ -$ 7,304,500.00$ 0.0%
302 S. A. Comunale, Inc. 217,580.00$ -$ 217,580.00$ -$ -$ -$ -$ -$ 217,580.00$ 0.0%
7,522,080.00$ -$ 7,522,080.00$ -$ -$ -$ -$ -$ 7,522,080.00$ 0.0%Summary Totals:
Requisition Summary Totals
By ContractEPASD
Job No:19-1716
East Pennsboro Elementary School & West Creek Hills Elementary School
Additions and Renovations
East Pennsboro Area School District East Pennsboro Elementary School West Creek Hills Elementary School Progress Report #3-November 2019
4 | P a g e
Change Management Change Order Summary
East Pennsboro Area School District East Pennsboro & West Creek Hills Elementary Schools
Construction Contingency $261,810.00
Total of all Executed Change Orders $0.00
Total of all November Change Orders ($7,287.00)
Remaining Contingency Balance $269,097.00
Approved Change Orders, please see attached log. Currently the following Potential Change Orders are under review and/or processing.
1. Delete furnishing and installing one batting cage at EPE 2. Remove plaster ceiling above suspended ceiling at connector at WCH 3. Storm water outfall redesign at WCH
East Pennsboro Area School District East Pennsboro Elementary School West Creek Hills Elementary School Progress Report #3-November 2019
5 | P a g e
Change Order Log
Change
Management #
Contract
or COR #
Scho
ol Description
Cost Issue
Received Date
Proposed/Quoted
Amount
Negotiated
Amount
Architect
Approval
Final Change Order
Amount Status
CO Amount to
Contractor CO # Date Issued
ECI SAC
1 1 EPE Delete furnishing & installing one Batting Cage (8,769.00)$ 10.31.19 (8,769.00)$ (8,769.00)$ 11.05.19 (8,769.00)$ OFS (8,769.00)$ 01-01 11.05.19
2 1 WCH Remove plaster ceiling above suspended ceiling at connector 1,482.00$ 12.03.19 1,482.00$ 1,482.00$ 12.06.19 1,482.00$ OFS 1,482.00$ 01-02 12.09.19
3 1 WCH Storm w ater outfall redesign
Project Totals (7,287.00)$ -$ (7,287.00)$ (7,287.00)$ (7,287.00)$ (7,287.00)$
ECI original Contract Sum = $7,304,500.00 7,297,213.00$ BEING NEGOTIATED BN
SAC original Contract Sum = $217,580.00 217,580.00$ OUT FOR SIGNATURE OFS
FULLY EXECUTED FE
VOID/REJECTED V
CLOSED C
Errors & Omissions E&O
KEY
Contractor
Additions and Renovations to East Pennsboro & West Creek Hills Elementary Schools
19-1716-EPE & 19-1716-WCH
C O S T I S S U E S U M M A R Y
East Pennsboro Area School District East Pennsboro Elementary School West Creek Hills Elementary School Progress Report #3-November 2019
6 | P a g e
Project Schedule
Substantial Completion dates for each phase are as follows:
Phase 1 (Construct New Additions & Erosion Control) .........................................August 4, 2020 Phase 2 (Perform Renovations & Final Sitework) .................................................August 4, 2020
. Description DaysPlan
Dur %Comp
DaysLeft
Start Finish TotalFloat
East Pennsboro Elementary SchoolEast Pennsboro Elementary SchoolEast Pennsboro Elementary SchoolEast Pennsboro Elementary SchoolEast Pennsboro Elementary SchoolEast Pennsboro Elementary SchoolEast Pennsboro Elementary SchoolEast Pennsboro Elementary School
ec.sc Substantial Completion - Area C Renovations - NLT Aug-4-20 0 0% 0 Jul-29-20* 4
en.sc Substantial Completion - Addition - NLT Aug-4-20 0 0% 0 Aug-04-20* 0
ea.sc Substantial Completion - Area A Renovations - NLT Aug-4-20 0 0% 0 Aug-04-20* 0
General Mobilization and Start UpGeneral Mobilization and Start UpGeneral Mobilization and Start UpGeneral Mobilization and Start UpGeneral Mobilization and Start UpGeneral Mobilization and Start UpGeneral Mobilization and Start UpGeneral Mobilization and Start Up
eg.2 Temporary Lighting and Power 5 0% 5 Nov-20-19 Nov-26-19* -7
eg.6 Last Day of School 1 0% 1 Jun-08-20* Jun-08-20 0
Site WorkSite WorkSite WorkSite WorkSite WorkSite WorkSite WorkSite Work
es.7 Survey and Layout 3 70% 1 Nov-12-19 A Nov-20-19 0
es.5 Demo Stormwater System 5 0% 5 Jun-09-20 Jun-15-20 2
es.6 Install Fire Hydrant Pipe and Structure 5 0% 5 Jun-09-20* Jun-15-20 17
es.13 Concrete Pads, Stairs, Walkways, Ramps, and Curbs 10 0% 10 Jun-09-20 Jun-22-20 7
es.14 Infiltration Basin Work 15 0% 15 Jun-09-20 Jun-29-20 7
es.10 Install Stormwater Pipes and Structures 10 0% 10 Jun-16-20 Jun-29-20 2
es.16 Handrail Systems 4 0% 4 Jun-23-20 Jun-26-20 24
es.17 Grading and Topsoil 5 0% 5 Jun-30-20 Jul-07-20 2
es.18 Grass Seeding / Landscape 5 0% 5 Jul-08-20 Jul-14-20 2
es.19 Steel Bollards 3 0% 3 Jul-15-20 Jul-17-20 10
es.21 Remove Field Offices and Storage Trailers 5 0% 5 Jul-15-20* Jul-21-20 2
es.20 Reinstall Benches, Picnic Tables 2 0% 2 Jul-20-20 Jul-21-20 10
es.22 Paving Base and Wear Coats 5 0% 5 Jul-22-20 Jul-28-20 2
es.15 4" Chain Link Fence and Gate 5 0% 5 Jul-22-20 Jul-28-20 5
es.12 Basketball Rims, Posts, and Backboards 3 0% 3 Jul-29-20* Jul-31-20 2
es.23 Paving Striping: Handicap, Parking, Basketball 3 0% 3 Jul-29-20 Jul-31-20 2
New Addition (Area C)New Addition (Area C)New Addition (Area C)New Addition (Area C)New Addition (Area C)New Addition (Area C)New Addition (Area C)New Addition (Area C)
Building EnclosureBuilding EnclosureBuilding EnclosureBuilding EnclosureBuilding EnclosureBuilding EnclosureBuilding EnclosureBuilding Enclosure
ene.1 Prep and Pour Foundations 20 30% 14 Nov-14-19 A Dec-12-19 0
ene.2 Foundation Masonry Walls 20 0% 20 Nov-21-19 Dec-23-19 0
ene.3 Underground Sanitary Rough In and Backfill 15 0% 15 Nov-22-19 Dec-17-19 0
ene.4 Underground Electrical Rough In and Backfill 5 0% 5 Nov-25-19 Dec-04-19 0
ene.5 Underground Fire Protection Rough In and Backfill 5 0% 5 Nov-26-19 Dec-05-19 0
ene.6 Roof Drain Pipe Rough In and Backfill 10 0% 10 Nov-27-19 Dec-13-19 0
ene.7 Insulate and Backfill Foundation Walls 5 0% 5 Dec-13-19 Dec-20-19 0
ene.8 CMU Door Frames 3 0% 3 Dec-20-19 Dec-26-19 17
N Dec Jan F Mar Apr M J Jul A S Oct N D
2020
Substantial Compl
Substantial Comp
Substantial Comp
Temporary Lighting and Power
Last Day of School
Survey and Layout
Demo Stormwater System
Install Fire Hydrant Pipe a
Concrete Pads, Stairs, W
Infiltration Basin Work
Install Stormwater Pipe
Handrail Systems
Grading and Topsoil
Grass Seeding / Landscape
Steel Bollards
Remove Field Office
Reinstall Benches, P
Paving Base and Wear Coats
4" Chain Link Fenc
Basketball Rims, P
Paving Striping: H
Prep and Pour Foundations
Foundation Masonry Walls
Underground Sanitary Rough In and Backfill
Underground Electrical Rough In and Backfill
Underground Fire Protection Rough In and Backfill
Roof Drain Pipe Rough In and Backfill
Insulate and Backfill Foundation Walls
CMU Door Frames
East Pennsboro Elementary School
Construction Schedule (1716e r1a)Data Date Nov-19-19
Schedule ID 1716e r1a
Run Date Dec-09-19
Page 1 of 9
. Description DaysPlan
Dur %Comp
DaysLeft
Start Finish TotalFloat
ene.9 CMU Walls to Steel Bearing 20 0% 20 Dec-20-19 Jan-21-20 0
ene.10 Prep and Pour Slab on Grade - LGI and Other Areas 5 0% 5 Jan-21-20 Jan-28-20 0
ene.11 Folding Partition Steel 3 0% 3 Jan-28-20 Jan-31-20 7
ene.12 Bar Joists, Columns, and Decking 10 0% 10 Jan-28-20 Feb-11-20 0
ene.13 Parapet Walls 5 0% 5 Feb-11-20 Feb-18-20 7
ene.15 Prep and Pour Slab on Grade - Gym 5 0% 5 Feb-11-20 Feb-18-20 27
ene.18 Roof Curbing 5 0% 5 Feb-11-20 Feb-18-20 27
ene.16 Exterior Metal Framing 8 0% 8 Feb-11-20 Feb-21-20 0
ene.17 Roof Drains 8 0% 8 Feb-11-20 Feb-21-20 24
ene.19 Roof System and Walking Pads 20 0% 20 Feb-18-20 Mar-17-20 7
ene.20 Brick Veneer and Insulation 25 0% 25 Feb-21-20 Mar-27-20 0
ene.22 Stair Case Metal Pans 5 0% 5 Mar-03-20 Mar-10-20 27
ene.23 Pour Concrete at Staircase 5 0% 5 Mar-10-20 Mar-17-20 27
ene.14 HVAC RTU Steel 5 0% 5 Mar-17-20 Mar-24-20 83
ene.21 Set HVAC RTUs 3 0% 3 Mar-24-20 Mar-27-20 83
ene.24 Exterior Windows 12 0% 12 Mar-25-20 Apr-10-20 0
ene.25 Aluminum Roof Coping and Metal Caps 10 0% 10 Mar-27-20 Apr-10-20 60
ene.26 Building Weathertight 1 0% 1 Apr-10-20 Apr-13-20 0
ene.27 Temporary Lighting and Power in Place 4 0% 4 Apr-13-20 Apr-17-20 0
ene.28 Temporary Heating and Dehumidifying In Place 2 0% 2 Apr-17-20 Apr-21-20 0
ene.29 Pre-Fab Canopies 5 0% 5 Apr-24-20 May-01-20 60
ene.30 Permanent Electrical Power in Place 2 0% 2 Jun-10-20 Jun-12-20 29
ene.31 HVAC Rooftop and Interior Unit Start Up 2 0% 2 Jul-17-20 Jul-21-20 5
GymGymGymGymGymGymGymGym
eng.1 Interior Masonry Walls and Chases 20 0% 20 Mar-17-20 Apr-14-20 7
eng.2 Aluminum Wall Panels 10 0% 10 Apr-10-20 Apr-24-20 60
eng.4 Mechanical Pipe and Duct Overhead Rough In / Insulation / Tagging 20 0% 20 Apr-20-20 May-18-20 0
eng.3 Electrical Overhead Rough In / Labeling 8 0% 8 Apr-21-20 May-01-20 2
eng.5 Install Mechanical Interior Unit 5 0% 5 May-01-20 May-08-20 2
eng.7 Fire Protection Overhead Rough In / Labeling 8 0% 8 May-08-20 May-20-20 2
eng.8 Interior Metal Framing 4 0% 4 May-15-20 May-21-20 2
eng.6 Paint Gym Ceiling 5 0% 5 May-15-20 May-22-20 0
eng.9 Wood Blocking 2 0% 2 May-20-20 May-22-20 2
eng.10 Interior Door Frames, Windows, Storefronts 4 0% 4 May-20-20 May-27-20 23
N Dec Jan F Mar Apr M J Jul A S Oct N D
2020
CMU Walls to Steel Bearing
Prep and Pour Slab on Grade - LGI and Other Areas
Folding Partition Steel
Bar Joists, Columns, and Decking
Parapet Walls
Prep and Pour Slab on Grade - Gym
Roof Curbing
Exterior Metal Framing
Roof Drains
Roof System and Walking Pads
Brick Veneer and Insulation
Stair Case Metal Pans
Pour Concrete at Staircase
HVAC RTU Steel
Set HVAC RTUs
Exterior Windows
Aluminum Roof Coping and Metal Caps
Building Weathertight
Temporary Lighting and Power in Place
Temporary Heating and Dehumid
Pre-Fab Canopies
Permanent Electrical Power in Place
HVAC Rooftop and
Interior Masonry Walls and Chases
Aluminum Wall Panels
Mechanical Pipe and Duct Ov
Electrical Overhead Rough In / Labeling
Install Mechanical Interior Unit
Fire Protection Overhead Ro
Interior Metal Framing
Paint Gym Ceiling
Wood Blocking
Interior Door Frames, Windo
East Pennsboro Elementary School
Construction Schedule (1716e r1a)Data Date Nov-19-19
Schedule ID 1716e r1a
Run Date Dec-09-19
Page 2 of 9
. Description DaysPlan
Dur %Comp
DaysLeft
Start Finish TotalFloat
eng.12 Hang and Finish Drywall 5 0% 5 May-21-20 May-29-20 2
eng.11 Primer and First Coat Paint 8 0% 8 May-22-20 Jun-04-20 0
eng.13 Electrical In Wall Rough Ins 10 0% 10 May-27-20 Jun-10-20 23
eng.14 Plumbing In Wall Rough Ins 10 0% 10 May-28-20 Jun-11-20 23
eng.15 Electrical Cable Trays 5 0% 5 May-29-20 Jun-05-20 7
eng.16 Resinous Epoxy Flooring 5 0% 5 May-29-20 Jun-05-20 12
eng.17 Mechanical In Wall Rough Ins 10 0% 10 May-29-20 Jun-12-20 23
eng.18 Fire Protection In Wall Rough Ins 10 0% 10 Jun-01-20 Jun-15-20 23
eng.20 Ceiling Grid 5 0% 5 Jun-02-20 Jun-09-20 7
eng.21 Sprinkler Heads 10 0% 10 Jun-03-20 Jun-17-20 14
eng.19 Fire Alarm Devices 5 0% 5 Jun-04-20 Jun-11-20 0
eng.22 Install Folding Partition 2 0% 2 Jun-05-20 Jun-09-20 15
eng.23 Walk Off Mats 3 0% 3 Jun-05-20 Jun-10-20 33
eng.24 Final Coat Paint 5 0% 5 Jun-05-20 Jun-12-20 12
eng.25 Casework and Cabinetry 5 0% 5 Jun-09-20 Jun-16-20 7
eng.26 Light Fixtures, Speakers, Receptacles, Security Devices 10 0% 10 Jun-11-20 Jun-25-20 0
eng.27 Basketball Backboards and Rims 3 0% 3 Jun-12-20 Jun-17-20 14
eng.28 Toilet Partitions 4 0% 4 Jun-12-20 Jun-18-20 27
eng.29 Retractable Batting Cages 5 0% 5 Jun-12-20 Jun-19-20 12
eng.30 Remove Temporary Lighting and Power 5 0% 5 Jun-12-20 Jun-19-20 93
eng.31 Toilet Accessories 3 0% 3 Jun-15-20 Jun-18-20 27
eng.32 ATC Wiring 5 0% 5 Jun-15-20 Jun-22-20 23
eng.33 VCT Flooring 5 0% 5 Jun-16-20 Jun-23-20 7
eng.36 Fire Protection Hydro Testing, Inspection of New System Piping 1 0% 1 Jun-17-20 Jun-18-20 14
eng.34 Low Voltage Fixtures and Devices 5 0% 5 Jun-18-20 Jun-25-20 9
eng.37 Ceiling Tile 10 0% 10 Jun-18-20 Jul-02-20 14
eng.35 Mechanical Fixtures and Devices 15 0% 15 Jun-18-20 Jul-10-20 10
eng.38 Staircase Handrail 3 0% 3 Jun-19-20 Jun-24-20 19
eng.41 Corridor Tack Strips 4 0% 4 Jun-23-20 Jun-29-20 20
eng.43 Doors and Hardware 10 0% 10 Jun-23-20 Jul-08-20 7
eng.40 Solid Surfaces 3 0% 3 Jun-25-20 Jun-30-20 9
eng.39 Epoxy Coated Concrete 3 0% 3 Jun-25-20 Jun-30-20 19
eng.42 Gym Sound Panels 8 0% 8 Jun-25-20 Jul-08-20 0
eng.44 Plumbing Fixtures 10 0% 10 Jun-30-20 Jul-15-20 9
N Dec Jan F Mar Apr M J Jul A S Oct N D
2020
Hang and Finish Drywall
Primer and First Coat Paint
Electrical In Wall Rough Ins
Plumbing In Wall Rough Ins
Electrical Cable Trays
Resinous Epoxy Flooring
Mechanical In Wall Rough Ins
Fire Protection In Wall Rough Ins
Ceiling Grid
Sprinkler Heads
Fire Alarm Devices
Install Folding Partition
Walk Off Mats
Final Coat Paint
Casework and Cabinetry
Light Fixtures, Speakers
Basketball Backboards and Rims
Toilet Partitions
Retractable Batting Cages
Remove Temporary Ligh
Toilet Accessories
ATC Wiring
VCT Flooring
Fire Protection Hydro Tes
Low Voltage Fixtures and Devices
Ceiling Tile
Mechanical Fixtures a
Staircase Handrail
Corridor Tack Strips
Doors and Hardware
Solid Surfaces
Epoxy Coated Concrete
Gym Sound Panels
Plumbing Fixtures
East Pennsboro Elementary School
Construction Schedule (1716e r1a)Data Date Nov-19-19
Schedule ID 1716e r1a
Run Date Dec-09-19
Page 3 of 9
. Description DaysPlan
Dur %Comp
DaysLeft
Start Finish TotalFloat
eng.45 Tackboards and Whiteboards 3 0% 3 Jul-02-20 Jul-08-20 14
eng.47 Room Signage 2 0% 2 Jul-08-20 Jul-10-20 7
eng.46 Gym Rubber Flooring 10 0% 10 Jul-08-20 Jul-22-20 0
eng.48 Overhead Grille and Counter Door 3 0% 3 Jul-10-20 Jul-15-20 7
eng.49 Fire Cabinets and Extinguishers 2 0% 2 Jul-15-20 Jul-17-20 7
eng.50 Gym Wall Pads 2 0% 2 Jul-22-20 Jul-24-20 2
eng.51 Staircase Rubber Flooring 4 0% 4 Jul-22-20 Jul-28-20 0
eng.52 Final Cleaning 5 0% 5 Jul-28-20 Aug-04-20 0
eng.53 Air Balancing 5 0% 5 Aug-04-20 Aug-11-20 57
eng.54 Punchlist 10 0% 10 Aug-04-20 Aug-18-20 52
First Floor - AdditionFirst Floor - AdditionFirst Floor - AdditionFirst Floor - AdditionFirst Floor - AdditionFirst Floor - AdditionFirst Floor - AdditionFirst Floor - Addition
en1.1 Interior Masonry Walls and Chases 20 0% 20 Mar-17-20 Apr-14-20 8
en1.2 Aluminum Wall Panels 10 0% 10 Mar-27-20 Apr-10-20 70
en1.3 Staircase Handrail 3 0% 3 Apr-14-20 Apr-17-20 66
en1.4 Electrical Overhead Rough In / Labeling 10 0% 10 Apr-21-20 May-05-20 3
en1.5 Plumbing Overhead Rough In / Insulation / Labeling 10 0% 10 Apr-22-20 May-06-20 3
en1.6 Install Mechanical Interior Unit 5 0% 5 Apr-23-20 Apr-30-20 3
en1.7 Mechanical Pipe and Duct Overhead Rough In / Insulation / Tagging 20 0% 20 Apr-23-20 May-21-20 3
en1.8 Fire Protection Overhead Rough In / Labeling 10 0% 10 Apr-30-20 May-14-20 3
en1.9 Interior Metal Framing 8 0% 8 May-07-20 May-19-20 3
en1.10 Wood Blocking 5 0% 5 May-13-20 May-20-20 3
en1.11 Interior Door Frames, Windows, Storefronts 4 0% 4 May-14-20 May-20-20 27
en1.12 Hang and Finish Drywall 10 0% 10 May-15-20 Jun-01-20 3
en1.13 Electrical In Wall Rough Ins 10 0% 10 May-20-20 Jun-04-20 27
en1.14 Plumbing In Wall Rough Ins 10 0% 10 May-21-20 Jun-05-20 27
en1.15 Primer and First Coat Paint 8 0% 8 May-22-20 Jun-04-20 4
en1.16 Mechanical In Wall Rough Ins 10 0% 10 May-22-20 Jun-08-20 27
en1.17 Fire Protection In Wall Rough Ins 10 0% 10 May-26-20 Jun-09-20 27
en1.18 Electrical Cable Trays 5 0% 5 Jun-01-20 Jun-08-20 3
en1.19 Ceiling Grid 5 0% 5 Jun-03-20 Jun-10-20 3
en1.20 Fire Alarm Devices 5 0% 5 Jun-04-20 Jun-11-20 4
en1.21 Sprinkler Heads 10 0% 10 Jun-04-20 Jun-18-20 13
en1.22 ATC Wiring 5 0% 5 Jun-09-20 Jun-16-20 27
en1.23 Casework and Cabinetry 10 0% 10 Jun-10-20 Jun-24-20 3
N Dec Jan F Mar Apr M J Jul A S Oct N D
2020
Tackboards and Whiteboards
Room Signage
Gym Rubber Flooring
Overhead Grille and
Fire Cabinets and Ex
Gym Wall Pads
Staircase Rubber Flooring
Final Cleaning
Air Balancing
Punchlist
Interior Masonry Walls and Chases
Aluminum Wall Panels
Staircase Handrail
Electrical Overhead Rough In / Labeling
Plumbing Overhead Rough In
Install Mechanical Interior Unit
Mechanical Pipe and Duct Ov
Fire Protection Overhead Rou
Interior Metal Framing
Wood Blocking
Interior Door Frames, Windo
Hang and Finish Drywall
Electrical In Wall Rough Ins
Plumbing In Wall Rough Ins
Primer and First Coat Paint
Mechanical In Wall Rough Ins
Fire Protection In Wall Rough Ins
Electrical Cable Trays
Ceiling Grid
Fire Alarm Devices
Sprinkler Heads
ATC Wiring
Casework and Cabinetry
East Pennsboro Elementary School
Construction Schedule (1716e r1a)Data Date Nov-19-19
Schedule ID 1716e r1a
Run Date Dec-09-19
Page 4 of 9
. Description DaysPlan
Dur %Comp
DaysLeft
Start Finish TotalFloat
en1.24 Light Fixtures, Speakers, Receptacles, Security Devices 15 0% 15 Jun-11-20 Jul-02-20 4
en1.25 Remove Temporary Lighting and Power 5 0% 5 Jun-12-20 Jun-19-20 93
en1.26 VCT Flooring 10 0% 10 Jun-17-20 Jul-01-20 3
en1.27 Fire Protection Hydro Testing, Inspection of New System Piping 1 0% 1 Jun-18-20 Jun-19-20 13
en1.28 Ceiling Tile 10 0% 10 Jun-19-20 Jul-06-20 13
en1.29 Doors and Hardware 10 0% 10 Jun-24-20 Jul-09-20 6
en1.30 Low Voltage Fixtures and Devices 5 0% 5 Jun-25-20 Jul-02-20 4
en1.31 Mechanical Fixtures and Devices 15 0% 15 Jun-25-20 Jul-17-20 5
en1.32 Resinous Epoxy Flooring 5 0% 5 Jul-01-20 Jul-09-20 3
en1.33 Solid Surfaces 3 0% 3 Jul-02-20 Jul-08-20 4
en1.34 Room Signage 2 0% 2 Jul-09-20 Jul-13-20 6
en1.35 Install Folding Partition 2 0% 2 Jul-09-20 Jul-13-20 11
en1.36 Walk Off Mats 3 0% 3 Jul-09-20 Jul-14-20 10
en1.37 Epoxy Coated Concrete 3 0% 3 Jul-09-20 Jul-14-20 10
en1.38 Final Coat Paint 5 0% 5 Jul-09-20 Jul-16-20 4
en1.39 Plumbing Fixtures 10 0% 10 Jul-09-20 Jul-23-20 3
en1.40 Overhead Grille and Counter Door 3 0% 3 Jul-13-20 Jul-16-20 6
en1.41 Fire Cabinets and Extinguishers 2 0% 2 Jul-16-20 Jul-20-20 6
en1.42 Tackboards and Whiteboards 3 0% 3 Jul-16-20 Jul-21-20 5
en1.43 Corridor Tack Strips 4 0% 4 Jul-16-20 Jul-22-20 4
en1.44 Toilet Partitions 4 0% 4 Jul-16-20 Jul-22-20 4
en1.45 Staircase Rubber Flooring 4 0% 4 Jul-16-20 Jul-22-20 4
en1.46 Toilet Accessories 3 0% 3 Jul-17-20 Jul-22-20 4
en1.47 Final Cleaning 5 0% 5 Jul-23-20 Jul-30-20 3
en1.48 Air Balancing 5 0% 5 Jul-30-20 Aug-06-20 60
en1.49 Punchlist 10 0% 10 Jul-30-20 Aug-13-20 55
Second Floor - AdditionSecond Floor - AdditionSecond Floor - AdditionSecond Floor - AdditionSecond Floor - AdditionSecond Floor - AdditionSecond Floor - AdditionSecond Floor - Addition
en2.1 Prep and Pour 2nd Floor Concrete Floor 10 0% 10 Feb-11-20 Feb-25-20 21
en2.2 Interior Masonry Walls and Chases 20 0% 20 Mar-17-20 Apr-14-20 8
en2.3 Aluminum Wall Panels 10 0% 10 Apr-10-20 Apr-24-20 60
en2.4 Staircase Handrail 3 0% 3 Apr-14-20 Apr-17-20 66
en2.5 Electrical Overhead Rough In / Labeling 10 0% 10 Apr-21-20 May-05-20 3
en2.6 Plumbing Overhead Rough In / Insulation / Labeling 10 0% 10 Apr-22-20 May-06-20 3
en2.7 Install Mechanical Interior Unit 5 0% 5 Apr-23-20 Apr-30-20 3
N Dec Jan F Mar Apr M J Jul A S Oct N D
2020
Light Fixtures, Speake
Remove Temporary Ligh
VCT Flooring
Fire Protection Hydro Te
Ceiling Tile
Doors and Hardware
Low Voltage Fixtures a
Mechanical Fixtures
Resinous Epoxy Flooring
Solid Surfaces
Room Signage
Install Folding Partition
Walk Off Mats
Epoxy Coated Concrete
Final Coat Paint
Plumbing Fixtures
Overhead Grille and
Fire Cabinets and Ex
Tackboards and Whiteboards
Corridor Tack Strips
Toilet Partitions
Staircase Rubber Flooring
Toilet Accessories
Final Cleaning
Air Balancing
Punchlist
Prep and Pour 2nd Floor Concrete Floor
Interior Masonry Walls and Chases
Aluminum Wall Panels
Staircase Handrail
Electrical Overhead Rough In / Labeling
Plumbing Overhead Rough In
Install Mechanical Interior Unit
East Pennsboro Elementary School
Construction Schedule (1716e r1a)Data Date Nov-19-19
Schedule ID 1716e r1a
Run Date Dec-09-19
Page 5 of 9
. Description DaysPlan
Dur %Comp
DaysLeft
Start Finish TotalFloat
en2.8 Mechanical Pipe and Duct Overhead Rough In / Insulation / Tagging 15 0% 15 Apr-23-20 May-14-20 3
en2.9 Fire Protection Overhead Rough In / Labeling 10 0% 10 Apr-30-20 May-14-20 3
en2.10 Interior Metal Framing 8 0% 8 May-07-20 May-19-20 3
en2.11 Wood Blocking 5 0% 5 May-13-20 May-20-20 3
en2.12 Interior Door Frames, Windows, Storefronts 4 0% 4 May-14-20 May-20-20 27
en2.13 Hang and Finish Drywall 10 0% 10 May-15-20 Jun-01-20 3
en2.14 Electrical In Wall Rough Ins 10 0% 10 May-20-20 Jun-04-20 27
en2.15 Plumbing In Wall Rough Ins 10 0% 10 May-21-20 Jun-05-20 27
en2.16 Primer and First Coat Paint 8 0% 8 May-22-20 Jun-04-20 4
en2.17 Mechanical In Wall Rough Ins 10 0% 10 May-22-20 Jun-08-20 27
en2.18 Fire Protection In Wall Rough Ins 10 0% 10 May-26-20 Jun-09-20 27
en2.19 Electrical Cable Trays 5 0% 5 Jun-01-20 Jun-08-20 3
en2.20 Ceiling Grid 5 0% 5 Jun-03-20 Jun-10-20 3
en2.21 Fire Alarm Devices 5 0% 5 Jun-04-20 Jun-11-20 4
en2.22 Sprinkler Heads 10 0% 10 Jun-04-20 Jun-18-20 13
en2.23 ATC Wiring 5 0% 5 Jun-09-20 Jun-16-20 27
en2.24 Casework and Cabinetry 10 0% 10 Jun-10-20 Jun-24-20 3
en2.25 Light Fixtures, Speakers, Receptacles, Security Devices 15 0% 15 Jun-11-20 Jul-02-20 4
en2.26 Remove Temporary Lighting and Power 5 0% 5 Jun-12-20 Jun-19-20 93
en2.27 VCT Flooring 10 0% 10 Jun-17-20 Jul-01-20 3
en2.28 Fire Protection Hydro Testing, Inspection of New System Piping 1 0% 1 Jun-18-20 Jun-19-20 13
en2.29 Ceiling Tile 10 0% 10 Jun-19-20 Jul-06-20 13
en2.30 Doors and Hardware 10 0% 10 Jun-24-20 Jul-09-20 6
en2.31 Low Voltage Fixtures and Devices 5 0% 5 Jun-25-20 Jul-02-20 4
en2.32 Mechanical Fixtures and Devices 15 0% 15 Jun-25-20 Jul-17-20 5
en2.33 Resinous Epoxy Flooring 5 0% 5 Jul-01-20 Jul-09-20 3
en2.34 Solid Surfaces 3 0% 3 Jul-02-20 Jul-08-20 4
en2.35 Room Signage 2 0% 2 Jul-09-20 Jul-13-20 6
en2.36 Install Folding Partition 2 0% 2 Jul-09-20 Jul-13-20 78
en2.37 Walk Off Mats 3 0% 3 Jul-09-20 Jul-14-20 10
en2.38 Epoxy Coated Concrete 3 0% 3 Jul-09-20 Jul-14-20 10
en2.39 Final Coat Paint 5 0% 5 Jul-09-20 Jul-16-20 4
en2.40 Plumbing Fixtures 10 0% 10 Jul-09-20 Jul-23-20 3
en2.41 Overhead Grille and Counter Door 3 0% 3 Jul-13-20 Jul-16-20 6
N Dec Jan F Mar Apr M J Jul A S Oct N D
2020
Mechanical Pipe and Duct Ov
Fire Protection Overhead Rou
Interior Metal Framing
Wood Blocking
Interior Door Frames, Windo
Hang and Finish Drywall
Electrical In Wall Rough Ins
Plumbing In Wall Rough Ins
Primer and First Coat Paint
Mechanical In Wall Rough Ins
Fire Protection In Wall Rough Ins
Electrical Cable Trays
Ceiling Grid
Fire Alarm Devices
Sprinkler Heads
ATC Wiring
Casework and Cabinetry
Light Fixtures, Speake
Remove Temporary Ligh
VCT Flooring
Fire Protection Hydro Te
Ceiling Tile
Doors and Hardware
Low Voltage Fixtures a
Mechanical Fixtures
Resinous Epoxy Flooring
Solid Surfaces
Room Signage
Install Folding Partition
Walk Off Mats
Epoxy Coated Concrete
Final Coat Paint
Plumbing Fixtures
Overhead Grille and
East Pennsboro Elementary School
Construction Schedule (1716e r1a)Data Date Nov-19-19
Schedule ID 1716e r1a
Run Date Dec-09-19
Page 6 of 9
. Description DaysPlan
Dur %Comp
DaysLeft
Start Finish TotalFloat
en2.42 Fire Cabinets and Extinguishers 2 0% 2 Jul-16-20 Jul-20-20 6
en2.43 Tackboards and Whiteboards 3 0% 3 Jul-16-20 Jul-21-20 5
en2.44 Staircase Rubber Flooring 4 0% 4 Jul-16-20 Jul-22-20 4
en2.45 Toilet Partitions 4 0% 4 Jul-16-20 Jul-22-20 4
en2.46 Corridor Tack Strips 4 0% 4 Jul-16-20 Jul-22-20 4
en2.47 Toilet Accessories 3 0% 3 Jul-17-20 Jul-22-20 4
en2.48 Final Cleaning 5 0% 5 Jul-23-20 Jul-30-20 3
en2.49 Air Balancing 5 0% 5 Jul-30-20 Aug-06-20 60
en2.50 Punchlist 10 0% 10 Jul-30-20 Aug-13-20 55
Renovations - Ground Floor Area CRenovations - Ground Floor Area CRenovations - Ground Floor Area CRenovations - Ground Floor Area CRenovations - Ground Floor Area CRenovations - Ground Floor Area CRenovations - Ground Floor Area CRenovations - Ground Floor Area C
ec.02 Electrical Demo / Patch 5 0% 5 Jun-09-20 Jun-15-20 4
ec.03 Mechanical Demo / Patch 5 0% 5 Jun-09-20 Jun-15-20 4
ec.08 Plumbing Demo / Patch 5 0% 5 Jun-09-20 Jun-15-20 4
ec.01 Selective Demo / Patch 10 0% 10 Jun-09-20* Jun-22-20 4
ec.05 Electrical Rough Ins 8 0% 8 Jun-16-20 Jun-25-20 4
ec.09 Plumbing Rough Ins and Finishes 8 0% 8 Jun-18-20 Jun-29-20 4
ec.04 Mechanical Rough Ins 8 0% 8 Jun-22-20 Jul-01-20 4
ec.19 Steel Members, Decking, Concrete 5 0% 5 Jun-23-20 Jun-29-20 6
ec.06 ATC Wiring 3 0% 3 Jun-26-20 Jun-30-20 7
ec.13 Install Door and Frame 3 0% 3 Jun-30-20 Jul-02-20 6
ec.07 Cable Tray 3 0% 3 Jul-02-20 Jul-07-20 4
ec.14 Painting 8 0% 8 Jul-08-20 Jul-17-20 4
ec.10 Reinstall Ceiling Grid and Tile 5 0% 5 Jul-13-20 Jul-17-20 4
ec.20 Plumbing Fixtures 1 0% 1 Jul-20-20 Jul-20-20 5
ec.21 Electrical Finishes 4 0% 4 Jul-20-20 Jul-23-20 4
ec.11 Install Handrail System 5 0% 5 Jul-20-20 Jul-24-20 4
ec.12 Toilet Accessories 3 0% 3 Jul-21-20 Jul-23-20 5
ec.22 Mechanical Finishes 4 0% 4 Jul-21-20 Jul-24-20 4
ec.15 Final Cleaning 3 0% 3 Jul-27-20 Jul-29-20 4
ec.17 Air Balancing 5 0% 5 Jul-30-20 Aug-05-20 61
ec.16 Punchlist 10 0% 10 Jul-30-20 Aug-12-20 56
Renovations - First Floor Area ARenovations - First Floor Area ARenovations - First Floor Area ARenovations - First Floor Area ARenovations - First Floor Area ARenovations - First Floor Area ARenovations - First Floor Area ARenovations - First Floor Area A
ea.01 Remove Kitchen Equipment 3 0% 3 Jun-09-20* Jun-11-20 0
ea.02 Selective Demo 5 0% 5 Jun-09-20 Jun-15-20 0
N Dec Jan F Mar Apr M J Jul A S Oct N D
2020
Fire Cabinets and Ex
Tackboards and Whiteboards
Staircase Rubber Flooring
Toilet Partitions
Corridor Tack Strips
Toilet Accessories
Final Cleaning
Air Balancing
Punchlist
Electrical Demo / Patch
Mechanical Demo / Patch
Plumbing Demo / Patch
Selective Demo / Patch
Electrical Rough Ins
Plumbing Rough Ins an
Mechanical Rough Ins
Steel Members, Decking
ATC Wiring
Install Door and Frame
Cable Tray
Painting
Reinstall Ceiling Grid and Tile
Plumbing Fixtures
Electrical Finishes
Install Handrail System
Toilet Accessories
Mechanical Finishes
Final Cleaning
Air Balancing
Punchlist
Remove Kitchen Equipment
Selective Demo
East Pennsboro Elementary School
Construction Schedule (1716e r1a)Data Date Nov-19-19
Schedule ID 1716e r1a
Run Date Dec-09-19
Page 7 of 9
. Description DaysPlan
Dur %Comp
DaysLeft
Start Finish TotalFloat
ea.03 Plumbing Demo 5 0% 5 Jun-09-20 Jun-15-20 2
ea.04 Electrical Demo 5 0% 5 Jun-09-20 Jun-15-20 2
ea.05 Mechanical Demo 5 0% 5 Jun-09-20 Jun-15-20 2
ea.07 Metal Wall Framing 8 0% 8 Jun-15-20 Jun-24-20 0
ea.06 Fire Protection Pipe for Area A & Riser 5 0% 5 Jun-16-20 Jun-22-20 2
ea.09 Plumbing Rough In 10 0% 10 Jun-16-20 Jun-29-20 0
ea.11 Low Voltage Rough In 5 0% 5 Jun-17-20 Jun-23-20 6
ea.10 Electrical Rough In 8 0% 8 Jun-17-20 Jun-26-20 1
ea.12 Mechanical Rough In 15 0% 15 Jun-17-20 Jul-08-20 0
ea.16 Hollow Metal Door Frames and Windows 4 0% 4 Jun-19-20 Jun-24-20 2
ea.08 Wood Blocking 3 0% 3 Jun-22-20 Jun-24-20 0
ea.42 Wire New Fire Alarm Devices, Ensure Monitoring 1 0% 1 Jun-23-20 Jun-23-20 80
ea.17 Hang and Finish Drywall 8 0% 8 Jun-23-20 Jul-02-20 0
ea.43 Final Fire Protection Inspection / Testing 1 0% 1 Jun-24-20 Jun-24-20 80
ea.13 Thermostat Wiring 3 0% 3 Jun-24-20 Jun-26-20 21
ea.22 Electrical Devices: Lights, Receptacles, Devices 8 0% 8 Jun-29-20 Jul-09-20 1
ea.18 Primer and First Coat Paint 5 0% 5 Jun-30-20 Jul-07-20 0
ea.23 Mechanical Finishes 8 0% 8 Jun-30-20 Jul-10-20 12
ea.21 Ceiling Grid 5 0% 5 Jul-02-20 Jul-09-20 0
ea.14 Install Mechanical Interior Units 3 0% 3 Jul-06-20 Jul-08-20 14
ea.33 Resinous Kitchen Epoxy Flooring 10 0% 10 Jul-07-20 Jul-16-20 0
ea.34 Bathroom Epoxy Flooring 5 0% 5 Jul-08-20 Jul-14-20 2
ea.24 Plumbing Finishes 8 0% 8 Jul-08-20 Jul-17-20 0
ea.25 Cabinetry and Casework 5 0% 5 Jul-10-20 Jul-16-20 0
ea.15 Mechanical Unit Start Up 2 0% 2 Jul-13-20 Jul-14-20 12
ea.35 VCT Flooring 5 0% 5 Jul-15-20 Jul-21-20 2
ea.27 Install Kitchen Equipment 5 0% 5 Jul-17-20 Jul-23-20 0
ea.29 Electrical Kitchen Equipment Connections 8 0% 8 Jul-17-20 Jul-28-20 0
ea.30 Plumbing Kitchen Equipment Connections 8 0% 8 Jul-17-20 Jul-28-20 0
ea.31 Mechanical Kitchen Equipment Connections 8 0% 8 Jul-17-20 Jul-28-20 0
ea.19 Toilet Partitions 4 0% 4 Jul-20-20 Jul-23-20 0
ea.36 Room Signage 2 0% 2 Jul-22-20 Jul-23-20 3
ea.28 Doors and Hardware 5 0% 5 Jul-22-20 Jul-28-20 2
ea.38 Final Coat Paint 2 0% 2 Jul-24-20 Jul-27-20 1
N Dec Jan F Mar Apr M J Jul A S Oct N D
2020
Plumbing Demo
Electrical Demo
Mechanical Demo
Metal Wall Framing
Fire Protection Pipe for
Plumbing Rough In
Low Voltage Rough In
Electrical Rough In
Mechanical Rough In
Hollow Metal Door Fram
Wood Blocking
Wire New Fire Alarm Dev
Hang and Finish Drywall
Final Fire Protection Ins
Thermostat Wiring
Electrical Devices: Lig
Primer and First Coat Paint
Mechanical Finishes
Ceiling Grid
Install Mechanical Interior Units
Resinous Kitchen Ep
Bathroom Epoxy Flooring
Plumbing Finishes
Cabinetry and Casework
Mechanical Unit Start Up
VCT Flooring
Install Kitchen Equipment
Electrical Kitchen E
Plumbing Kitchen
Mechanical Kitchen
Toilet Partitions
Room Signage
Doors and Hardware
Final Coat Paint
East Pennsboro Elementary School
Construction Schedule (1716e r1a)Data Date Nov-19-19
Schedule ID 1716e r1a
Run Date Dec-09-19
Page 8 of 9
. Description DaysPlan
Dur %Comp
DaysLeft
Start Finish TotalFloat
ea.20 Toilet Accessories 3 0% 3 Jul-24-20 Jul-28-20 2
ea.26 Handrails 5 0% 5 Jul-24-20 Jul-30-20 0
ea.32 Ceiling Tile 5 0% 5 Jul-24-20 Jul-30-20 0
ea.37 Privacy Curtains 2 0% 2 Jul-28-20 Jul-29-20 1
ea.39 Final Cleaning 3 0% 3 Jul-31-20 Aug-04-20 0
ea.41 Air Balancing 5 0% 5 Aug-05-20 Aug-11-20 57
ea.40 Punchlist 10 0% 10 Aug-05-20 Aug-18-20 52
N Dec Jan F Mar Apr M J Jul A S Oct N D
2020
Toilet Accessories
Handrails
Ceiling Tile
Privacy Curtains
Final Cleaning
Air Balancing
Punchlist
East Pennsboro Elementary School
Construction Schedule (1716e r1a)Data Date Nov-19-19
Schedule ID 1716e r1a
Run Date Dec-09-19
Page 9 of 9
. Description DaysPlan
Dur %Comp
DaysLeft
Start Finish TotalFloat
West Creek Hills Elementary SchoolWest Creek Hills Elementary SchoolWest Creek Hills Elementary SchoolWest Creek Hills Elementary SchoolWest Creek Hills Elementary SchoolWest Creek Hills Elementary SchoolWest Creek Hills Elementary SchoolWest Creek Hills Elementary School
sc.2b Substantial Completion - Renovations - NLT Aug-4-20 0 0% 0 Jul-20-20* 10
sc.2as Substantial Completion - Sitework - NLT Aug-4-20 0 0% 0 Jul-28-20* 4
sc.2a Substantial Completion - Addition - NLT Aug-4-20 0 0% 0 Jul-29-20* 5
Site WorkSite WorkSite WorkSite WorkSite WorkSite WorkSite WorkSite Work
ws.3 Erosion Control 3 90% 0 Oct-23-19 A Nov-20-19 5
ws.11 North Playground Demolition 5 90% 1 Oct-29-19 A Nov-20-19 6
ws.6 Temporary Sediment Trap 3 75% 1 Nov-04-19 A Nov-21-19 6
ws.8 Stormwater Piping - Track Area 10 0% 10 Nov-20-19 Dec-06-19 5
ws.10 Existing Storm System Demolition 3 0% 3 Nov-21-19 Nov-26-19 11
ws.13 Underground Sanitary and Sewer Rough-in 10 0% 10 Dec-06-19 Dec-20-19 5
ws.14 Remove Lines - Front Parking Lot 1 0% 1 Jun-09-20 Jun-09-20 34
ws.15 Prep Subbase for Asphalt and Concrete Sidewalks 5 0% 5 Jun-09-20 Jun-15-20 14
ws.16 Prep Subbase for Emergency Access Lane 5 0% 5 Jun-09-20 Jun-15-20 14
ws.17 Prep Soft Play Area - Coordinate with Playround Installer 5 0% 5 Jun-09-20 Jun-15-20 32
ws.18 Remove Trailers and Laydown Area - Move Inside 10 0% 10 Jun-09-20 Jun-22-20 4
ws.19 Seal Coat Front Parking Lot 1 0% 1 Jun-10-20 Jun-10-20 34
ws.20 Base Pave - Walkways 1 0% 1 Jun-16-20 Jun-16-20 14
ws.21 Base Pave - Emergency Access Road 1 0% 1 Jun-16-20 Jun-16-20 14
ws.22 2B Stone Play Area 1 0% 1 Jun-16-20 Jun-16-20 32
ws.23 Pour Concrete Sidewalks - Building Addition and Front Parking Lot 1 0% 1 Jun-16-20 Jun-16-20 33
ws.24 Wearing Course Pave - Walkways 1 0% 1 Jun-17-20 Jun-17-20 14
ws.25 Wearing Course Pave - Emergency Access Road 1 0% 1 Jun-17-20 Jun-17-20 14
ws.26 Mulch Play Area 1 0% 1 Jun-17-20 Jun-17-20 32
ws.27 Prep Track Subbase for Pavement 5 0% 5 Jun-23-20 Jun-29-20 4
ws.28 Base Pave Track 1 0% 1 Jun-30-20 Jun-30-20 4
ws.29 Wearing Course Pave - Track 1 0% 1 Jul-01-20 Jul-01-20 4
ws.30 Line Striping - Front Parking Lot and Track 1 0% 1 Jul-02-20 Jul-02-20 19
ws.31 Basketball Court Equipment 3 0% 3 Jul-02-20 Jul-07-20 19
ws.32 Replace Top Soil 5 0% 5 Jul-02-20 Jul-09-20 4
ws.33 Install Parking Bumpers 1 0% 1 Jul-06-20 Jul-06-20 19
ws.34 Site Signage 1 0% 1 Jul-07-20 Jul-07-20 19
ws.35 Final Seeding 3 0% 3 Jul-10-20 Jul-14-20 4
ws.36 Landscaping 3 0% 3 Jul-10-20 Jul-14-20 12
N D Jan F Mar Apr M Jun Jul A S Oct N D
2020
Substantial Comple
Substantial Comp
Substantial Comp
Erosion Control
North Playground Demolition
Temporary Sediment Trap
Stormwater Piping - Track Area
Existing Storm System Demolition
Underground Sanitary and Sewer Rough-in
Remove Lines - Front Parking Lot
Prep Subbase for Aspha
Prep Subbase for Emerg
Prep Soft Play Area - Coo
Remove Trailers and La
Seal Coat Front Parking Lot
Base Pave - Walkways
Base Pave - Emergency A
2B Stone Play Area
Pour Concrete Sidewalks
Wearing Course Pave - Walkways
Wearing Course Pave - E
Mulch Play Area
Prep Track Subbase fo
Base Pave Track
Wearing Course Pave - Track
Line Striping - Front P
Basketball Court Equipment
Replace Top Soil
Install Parking Bumpers
Site Signage
Final Seeding
Landscaping
West Creek Hills Elementary School
Construction Schedule (1716w r1a)Data Date Nov-19-19
Schedule ID 1716w r1a
Run Date Dec-09-19
Page 1 of 5
. Description DaysPlan
Dur %Comp
DaysLeft
Start Finish TotalFloat
ws.37 Convert Temporary Sediment Trap to Permanent Basin 5 0% 5 Jul-15-20 Jul-21-20 4
ws.38 Remove Erosion Controls 2 0% 2 Jul-22-20 Jul-23-20 7
ws.39 Permanent Site Fencing 5 0% 5 Jul-22-20 Jul-28-20 4
Classroom AdditionClassroom AdditionClassroom AdditionClassroom AdditionClassroom AdditionClassroom AdditionClassroom AdditionClassroom Addition
wa.1 Excavate & Pour Footers 10 10% 9 Nov-18-19 A Dec-06-19 6
wa.2 Foundation Walls and Shear Walls 15 0% 15 Dec-04-19 Dec-26-19 6
wa.3 Plumbing Undergrounds 5 0% 5 Dec-20-19 Dec-30-19 5
wa.5 Backfill Foundation Walls 5 0% 5 Dec-24-19 Jan-02-20 6
wa.4 Stone Under Slab 5 0% 5 Dec-26-19 Jan-03-20 5
wa.6 Pour Slab on Grade 3 0% 3 Jan-03-20 Jan-08-20 5
wa.8 Load Bearing Wall Framing 8 0% 8 Jan-08-20 Jan-20-20 5
wa.7 Set Columns and Corridor Tube Steel 5 0% 5 Jan-20-20 Jan-27-20 5
wa.10 Electric Exterior Wall Rough-In 5 0% 5 Jan-20-20 Jan-27-20 39
wa.11 Plumbing Exterior Wall Rough-In 5 0% 5 Jan-20-20 Jan-27-20 39
wa.12 Exterior Wall Insulation 10 0% 10 Jan-20-20 Feb-03-20 43
wa.9 Set Roof Steel 10 0% 10 Jan-27-20 Feb-10-20 5
wa.13 HM Frames 3 0% 3 Jan-29-20 Feb-03-20 15
wa.14 Interior Wall Layout and Framing 15 0% 15 Feb-03-20 Feb-24-20 15
wa.15 Roof Decking 5 0% 5 Feb-10-20 Feb-17-20 5
wa.16 Plumbing Interior Wall Rough-In 15 0% 15 Feb-10-20 Mar-02-20 29
wa.17 Roof Insulation 5 0% 5 Feb-11-20 Feb-18-20 9
wa.18 Roof Drains 3 0% 3 Feb-13-20 Feb-18-20 9
wa.19 Roof Blocking and Curbs 5 0% 5 Feb-17-20 Feb-24-20 5
wa.20 Electrical Interior Wall Rough-in 15 0% 15 Feb-17-20 Mar-09-20 24
wa.21 Low Voltage Interior Wall Rough-In 15 0% 15 Feb-17-20 Mar-09-20 24
wa.22 Membrane Roofing 10 0% 10 Feb-24-20 Mar-09-20 5
wa.31 Wall Rough In Inspection 1 0% 1 Mar-09-20 Mar-10-20 24
wa.23 Set Roof Top HVAC Equipment 1 0% 1 Mar-09-20 Mar-10-20 42
wa.24 Sprinkler Rough In 15 0% 15 Mar-09-20 Mar-30-20 5
wa.25 Masonry Veneer 30 0% 30 Mar-09-20 Apr-20-20 18
wa.26 Set Cabinet Unit Heaters/Wall Mounted Unit Heaters 5 0% 5 Mar-16-20 Mar-23-20 43
wa.27 Overhead Plumbing 10 0% 10 Mar-16-20 Mar-30-20 28
wa.28 HVAC Piping and Duct Rough-In 22 0% 22 Mar-16-20 Apr-15-20 5
wa.29 Electrical Above Ceiling Rough-In 10 0% 10 Mar-23-20 Apr-06-20 5
N D Jan F Mar Apr M Jun Jul A S Oct N D
2020
Convert Temporary
Remove Erosion Controls
Permanent Site Fencing
Excavate & Pour Footers
Foundation Walls and Shear Walls
Plumbing Undergrounds
Backfill Foundation Walls
Stone Under Slab
Pour Slab on Grade
Load Bearing Wall Framing
Set Columns and Corridor Tube Steel
Electric Exterior Wall Rough-In
Plumbing Exterior Wall Rough-In
Exterior Wall Insulation
Set Roof Steel
HM Frames
Interior Wall Layout and Framing
Roof Decking
Plumbing Interior Wall Rough-In
Roof Insulation
Roof Drains
Roof Blocking and Curbs
Electrical Interior Wall Rough-in
Low Voltage Interior Wall Rough-In
Membrane Roofing
Wall Rough In Inspection
Set Roof Top HVAC Equipment
Sprinkler Rough In
Masonry Veneer
Set Cabinet Unit Heaters/Wall Mount
Overhead Plumbing
HVAC Piping and Duct Rough-In
Electrical Above Ceiling Rough-In
West Creek Hills Elementary School
Construction Schedule (1716w r1a)Data Date Nov-19-19
Schedule ID 1716w r1a
Run Date Dec-09-19
Page 2 of 5
. Description DaysPlan
Dur %Comp
DaysLeft
Start Finish TotalFloat
wa.30 Domestic Piping Insulation 10 0% 10 Mar-30-20 Apr-13-20 28
wa.33 Pull Data Cable 15 0% 15 Apr-06-20 Apr-27-20 5
wa.34 Pull Wires 15 0% 15 Apr-06-20 Apr-27-20 5
wa.32 HVAC Piping and Duct Insulation 10 0% 10 Apr-15-20 Apr-29-20 16
wa.37 Hang and Finish Drywall 25 0% 25 Apr-16-20 May-21-20 5
wa.35 Composite Metal Panels 5 0% 5 Apr-20-20 Apr-27-20 20
wa.36 Windows 10 0% 10 Apr-20-20 May-04-20 18
wa.38 Aluminum Store Fronts - Vestibules 3 0% 3 Apr-27-20 Apr-30-20 20
wa.39 Masonry Caulking 5 0% 5 May-04-20 May-11-20 60
wa.40 Painting 15 0% 15 May-07-20 May-29-20 5
wa.41 Acoustical Ceiling Grid 10 0% 10 May-14-20 May-29-20 5
wa.42 Sprinkler Heads 3 0% 3 May-18-20 May-21-20 12
wa.43 Speakers, Exit Signs, Smoke Heads 3 0% 3 May-18-20 May-21-20 12
wa.44 HVAC GRDs 3 0% 3 May-18-20 May-21-20 13
wa.45 Lighting 10 0% 10 May-18-20 Jun-02-20 5
wa.61 Fire Protection Hydro Testing 1 0% 1 May-21-20 May-22-20 12
wa.47 Set Classroom Unit Ventilators 5 0% 5 May-29-20 Jun-05-20 31
wa.48 Switches, Receptacles, Data and Fire Alarm Devices 5 0% 5 May-29-20 Jun-05-20 32
wa.49 Above Ceiling Inspection 1 0% 1 Jun-02-20 Jun-03-20 5
wa.50 Acoustical Ceiling Tile 8 0% 8 Jun-03-20 Jun-15-20 5
wa.51 HVAC Startup 1 0% 1 Jun-05-20 Jun-08-20 31
wa.52 Classroom Casework 10 0% 10 Jun-05-20 Jun-19-20 7
wa.53 Resinous Flooring Bathrooms 5 0% 5 Jun-15-20 Jun-22-20 5
wa.54 Classroom VCT 15 0% 15 Jun-15-20 Jul-07-20 6
wa.55 Corridor Terrazzo 15 0% 15 Jun-15-20 Jul-07-20 8
wa.56 Plumbing Fixtures 10 0% 10 Jun-22-20 Jul-07-20 5
wa.57 Doors and Hardware 10 0% 10 Jun-29-20 Jul-14-20 6
wa.46 Visual Display Boards 3 0% 3 Jul-07-20 Jul-10-20 8
wa.62 Toilet Partitions 5 0% 5 Jul-07-20 Jul-14-20 5
wa.58 Accessories and Signage 5 0% 5 Jul-07-20 Jul-14-20 6
wa.63 Toilet Accessories 2 0% 2 Jul-13-20 Jul-15-20 5
wa.59 Final Cleaning 10 0% 10 Jul-15-20 Jul-29-20 5
wa.60 Balancing 10 0% 10 Jul-29-20 Aug-12-20 57
Building RenovationsBuilding RenovationsBuilding RenovationsBuilding RenovationsBuilding RenovationsBuilding RenovationsBuilding RenovationsBuilding Renovations
N D Jan F Mar Apr M Jun Jul A S Oct N D
2020
Domestic Piping Insulation
Pull Data Cable
Pull Wires
HVAC Piping and Duct Insulation
Hang and Finish Drywall
Composite Metal Panels
Windows
Aluminum Store Fronts - Vestibules
Masonry Caulking
Painting
Acoustical Ceiling Grid
Sprinkler Heads
Speakers, Exit Signs, Smoke Heads
HVAC GRDs
Lighting
Fire Protection Hydro Testing
Set Classroom Unit Ventilators
Switches, Receptacles, Da
Above Ceiling Inspection
Acoustical Ceiling Tile
HVAC Startup
Classroom Casework
Resinous Flooring Bathrooms
Classroom VCT
Corridor Terrazzo
Plumbing Fixtures
Doors and Hardware
Visual Display Boards
Toilet Partitions
Accessories and Signage
Toilet Accessories
Final Cleaning
Balancing
West Creek Hills Elementary School
Construction Schedule (1716w r1a)Data Date Nov-19-19
Schedule ID 1716w r1a
Run Date Dec-09-19
Page 3 of 5
. Description DaysPlan
Dur %Comp
DaysLeft
Start Finish TotalFloat
wr.1 Summer Start Date 0 0% 0 Jun-09-20* 4
wr.2 Remove Music Practice A004 and Boys Restoom A106 Ceiling Grid and Tile for Sanitary Line1 0% 1 Jun-09-20 Jun-09-20 31
wr.3 Domestic Water Line Taps for Addition 1 0% 1 Jun-09-20 Jun-09-20 38
wr.4 Remove Corridor and Classroom Ceiling Grid and Tile for Sprinkler and Power Feeds2 0% 2 Jun-09-20 Jun-10-20 20
wr.5 Install New Sanitary Line from Addition to Restroom Chase 3 0% 3 Jun-10-20 Jun-12-20 31
wr.11 Reconfigure Existing Sprinkler Riser, Add to New Riser 2 0% 2 Jun-11-20 Jun-12-20 20
wr.7 Replace Music Practice A004 and Boys Restroom A106 Ceiling Grid and Tile1 0% 1 Jun-15-20 Jun-15-20 31
wr.6 Install New Sprinkler Main - Tie In at Addition 5 0% 5 Jun-15-20 Jun-19-20 20
wr.12 Wire New Fire Alarm Devices, Ensure Monitoring 1 0% 1 Jun-22-20 Jun-22-20 26
wr.8 Install New Electrical Power Feeder - Tie In at Addition 5 0% 5 Jun-22-20 Jun-26-20 20
wr.13 Fire Protection Final Inspection / Testing 1 0% 1 Jun-23-20 Jun-23-20 28
wr.9 Replace Corridor and Classroom Ceiling Grid and Tile 2 0% 2 Jun-29-20 Jun-30-20 20
wr.10 Final Clean 3 0% 3 Jul-16-20 Jul-20-20 10
Nurse's AreaNurse's AreaNurse's AreaNurse's AreaNurse's AreaNurse's AreaNurse's AreaNurse's Area
wrn.1 Demo Nurses Area Toilet Room Wall 3 0% 3 Jun-09-20 Jun-11-20 13
wrn.2 Demo Existing Sink Base - Exam Room 1 0% 1 Jun-12-20 Jun-12-20 13
wrn.3 Demo Existing Window - Nurses Office 1 0% 1 Jun-15-20 Jun-15-20 13
wrn.4 Install New ADA Sink Base 2 0% 2 Jun-15-20 Jun-16-20 29
wrn.5 Install New Aluminum Storefront Window - Nurses Of fice 1 0% 1 Jun-16-20 Jun-16-20 28
wrn.6 Install New Wall Nurses Area - Rework Devices 5 0% 5 Jun-16-20 Jun-22-20 13
wrn.7 Install New Casework - Exam Room 1 0% 1 Jun-17-20 Jun-17-20 29
wrn.8 Remove Fixtures Nurses Area Toilet Room 2 0% 2 Jun-17-20 Jun-18-20 15
wrn.9 Patch and Paint Nurse's Area Walls 3 0% 3 Jun-23-20 Jun-25-20 13
wrn.10 Rework Grid and Install New Ceiling Tile - Cot Room & Nurses Toilet Room3 0% 3 Jun-26-20 Jun-30-20 13
wrn.11 Install Epoxy Floor Over Existing Flooring (Nurse's Toilet) 5 0% 5 Jul-01-20 Jul-08-20 13
wrn.12 Install New Fixtures in Nurse's Toilet Room 1 0% 1 Jul-09-20 Jul-09-20 13
wrn.13 Install Nurses Area Occupancy Switches 1 0% 1 Jul-10-20 Jul-10-20 13
wrn.14 Install Bathroom Accessories 2 0% 2 Jul-14-20 Jul-15-20 10
Gang Restrooms and Toilet RoomsGang Restrooms and Toilet RoomsGang Restrooms and Toilet RoomsGang Restrooms and Toilet RoomsGang Restrooms and Toilet RoomsGang Restrooms and Toilet RoomsGang Restrooms and Toilet RoomsGang Restrooms and Toilet Rooms
wrg.1 Remove Fixtures Kitchen Toilet Room Gang Restroom Area A (Gym) 2 0% 2 Jun-09-20 Jun-10-20 10
wrg.2 Remove Fixtures Gang Restroom Area A (Gym) 2 0% 2 Jun-09-20 Jun-10-20 14
wrg.3 Demo Partitions 5 0% 5 Jun-09-20 Jun-15-20 11
wrg.4 Remove Fixtures Gang Restroom Area B 2 0% 2 Jun-11-20 Jun-12-20 10
wrg.5 Remove Fixtures Staff Toilet Rooms 2 0% 2 Jun-11-20 Jun-12-20 12
N D Jan F Mar Apr M Jun Jul A S Oct N D
2020
Summer Start Date
Remove Music Practice A
Domestic Water Line Taps
Remove Corridor and Cla
Install New Sanitary Line
Reconfigure Existing Spr
Replace Music Practice A
Install New Sprinkler Ma
Wire New Fire Alarm De
Install New Electrical Po
Fire Protection Final Ins
Replace Corridor and C
Final Clean
Demo Nurses Area Toilet
Demo Existing Sink Base
Demo Existing Window -
Install New ADA Sink Base
Install New Aluminum St
Install New Wall Nurses
Install New Casework - Exam Room
Remove Fixtures Nurses
Patch and Paint Nurse'
Rework Grid and Insta
Install Epoxy Floor O
Install New Fixtures i
Install Nurses Area O
Install Bathroom Accessories
Remove Fixtures Kitchen
Remove Fixtures Gang R
Demo Partitions
Remove Fixtures Gang R
Remove Fixtures Staff To
West Creek Hills Elementary School
Construction Schedule (1716w r1a)Data Date Nov-19-19
Schedule ID 1716w r1a
Run Date Dec-09-19
Page 4 of 5
. Description DaysPlan
Dur %Comp
DaysLeft
Start Finish TotalFloat
wrg.6 Remove Fixtures Gang Restroom Area C 2 0% 2 Jun-15-20 Jun-16-20 10
wrg.7 Patch and Paint Restroom / Toilet Room Walls 3 0% 3 Jun-17-20 Jun-19-20 10
wrg.8 Install Epoxy Floor Over Existing Flooring (Restrooms) 10 0% 10 Jun-22-20 Jul-06-20 10
wrg.9 Install New Fixtures in Restrooms / Toilet Rooms 3 0% 3 Jul-07-20 Jul-09-20 80
wrg.10 Modify Gang Restroom Partitions 5 0% 5 Jul-07-20 Jul-13-20 10
wrg.11 Install Bathroom Accessories 2 0% 2 Jul-14-20 Jul-15-20 10
N D Jan F Mar Apr M Jun Jul A S Oct N D
2020
Remove Fixtures Gang R
Patch and Paint Restroo
Install Epoxy Floor O
Install New Fixtures i
Modify Gang Restro
Install Bathroom Accessories
West Creek Hills Elementary School
Construction Schedule (1716w r1a)Data Date Nov-19-19
Schedule ID 1716w r1a
Run Date Dec-09-19
Page 5 of 5
East Pennsboro Area School District East Pennsboro Elementary School West Creek Hills Elementary School Progress Report #3-November 2019
21 | P a g e
Project Considerations The following major items are being tracked for resolution:
NO. ITEM RESP. RESOLUTION
DATE STATUS
01 Storm water outfall re-design at WCH K&W Engineers Jan. 2, 2020 In progress
02
03
04
05
East Pennsboro Area School District East Pennsboro Elementary School West Creek Hills Elementary School Progress Report #3-November 2019
22 | P a g e
Project Photos
EPE Pier
EPE Foundation
East Pennsboro Area School District East Pennsboro Elementary School West Creek Hills Elementary School Progress Report #3-November 2019
23 | P a g e
EPE Grading
East Pennsboro Area School District East Pennsboro Elementary School West Creek Hills Elementary School Progress Report #3-November 2019
24 | P a g e
WCH Footings
East Pennsboro Area School District East Pennsboro Elementary School West Creek Hills Elementary School Progress Report #3-November 2019
25 | P a g e
WCH Foundations
WCH Column