earth system science chair integrated water management group

71
Earth System Science Chair Integrated Water Management group “Unveiling rules-in-use in eco-engineering projects” Andrea Juarez 860319413070 MSc. Climate Studies Supervisors: dr. ir. Erik van Slobbe Earth System Science Group Wageningen University MSc. Debora de Block Earth System Science Group Wageningen University March 2013

Upload: others

Post on 15-Jan-2022

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Earth System Science Chair Integrated Water Management group

Earth System Science Chair Integrated Water Management group

“Unveiling rules-in-use in eco-engineering projects”

Andrea Juarez 860319413070

MSc. Climate Studies Supervisors: dr. ir. Erik van Slobbe Earth System Science Group Wageningen University MSc. Debora de Block Earth System Science Group Wageningen University

March 2013

Page 2: Earth System Science Chair Integrated Water Management group

2

Table of Contents Table of Contents ...................................................................................................................................................................................... 2

List of Figures ............................................................................................................................................................................................. 4

List of Tables ............................................................................................................................................................................................... 4

1 Summary .............................................................................................................................................................................................. 5

2 Introduction ........................................................................................................................................................................................ 6

2.1 Background .............................................................................................................................................................................. 7 2.2 Problem statement ............................................................................................................................................................... 7 2.3 Purpose of the study ............................................................................................................................................................ 7

3 Theoretical framework .................................................................................................................................................................. 9

4 Research Questions ...................................................................................................................................................................... 13

5 Methodology .................................................................................................................................................................................... 14

5.1 Case study .............................................................................................................................................................................. 14 5.2 Data collection techniques ............................................................................................................................................. 15

5.2.1 Primary data collection ......................................................................................................................................... 15 5.2.2 Secondary data collection .................................................................................................................................... 15

5.3 Data Process ......................................................................................................................................................................... 16 5.4 Analysis ................................................................................................................................................................................... 16

5.4.1 Rules in-use analysis .............................................................................................................................................. 16 5.4.2 Traditional versus eco-engineering approach rules in-use analysis ................................................ 16

6 Results ................................................................................................................................................................................................ 17

6.1 ‘Rambla del Poyo’ in Valencia, Spain ......................................................................................................................... 17 6.1.1 Actors ............................................................................................................................................................................ 18 6.1.2 Action situations ....................................................................................................................................................... 19

6.2 The ‘Noordwaard’ Polder................................................................................................................................................ 26 6.2.1 Actors ............................................................................................................................................................................ 26 6.2.2 Action situations ....................................................................................................................................................... 28

7 Analysis .............................................................................................................................................................................................. 37

7.1 ‘Rambla del Poyo’: Rules in-use ................................................................................................................................... 37 7.1.1 Boundary rules .......................................................................................................................................................... 37 7.1.2 Position rules ............................................................................................................................................................. 39 7.1.3 Choice rules ................................................................................................................................................................ 41 7.1.4 Information rules ..................................................................................................................................................... 42 7.1.5 Payoff rules ................................................................................................................................................................. 43

7.2 The ‘Noordwaard’ Polder: Rules in-use .................................................................................................................... 44 7.2.1 Boundary rules .......................................................................................................................................................... 44 7.2.2 Position rules ............................................................................................................................................................. 44 7.2.3 Choice rules ................................................................................................................................................................ 47 7.2.4 Information rules ..................................................................................................................................................... 48 7.2.5 Payoff rules ................................................................................................................................................................. 49

7.3 Rules in-use and eco-engineering approaches: perspectives from case studies ................................... 50 7.3.1 Rules in-use influencing interaction and outcomes in eco-engineering and vice versa........... 50 7.3.2 Traditional versus eco-engineering approaches: lessons learned ..................................................... 55 7.3.3 Rules in-use in eco-engineering and the SESs framework .................................................................... 56

8 Discussion ......................................................................................................................................................................................... 57

8.1 Rules in-use and eco-engineering ............................................................................................................................... 57 8.1.1 The complexity of the rules in-use in eco-engineering ........................................................................... 57 8.1.2 The new and changed rules in-use compared to traditional approaches ....................................... 57 8.1.3 Comparing the ‘Rambla del Poyo’ and ‘Noordwaard’ governance systems ................................... 58

8.2 Application of the IAD and SESs framework .......................................................................................................... 58 8.2.1 Challenges when facing different action situations and levels of rules in-use ............................. 58

Page 3: Earth System Science Chair Integrated Water Management group

3

8.2.2 The usefulness of the IAD and SESs frameworks in Eco-engineering .............................................. 59 8.2.3 Underpinning the IAD and SESs frameworks .............................................................................................. 59

8.3 Methods and techniques ................................................................................................................................................. 60 8.3.1 Criteria for selection of case studies and key actors interviews ......................................................... 60 8.3.2 Data processing methods ..................................................................................................................................... 61

9 Conclusions ...................................................................................................................................................................................... 62

9.1 Related to the research questions............................................................................................................................... 62 9.2 Rules in-use and eco-engineering ............................................................................................................................... 63 9.3 Related to the SESs and IAD framework and eco-engineering ...................................................................... 63 9.4 Related to research methods ........................................................................................................................................ 63

10 Recommendations ...................................................................................................................................................................... 64

10.1 Key points for future research .................................................................................................................................. 64 10.2 Related to the methods and techniques ................................................................................................................ 64 10.3 Future development of eco-engineering .............................................................................................................. 65

11 References...................................................................................................................................................................................... 66

12Annexes ................................................................................................................................................................................................. 69

Page 4: Earth System Science Chair Integrated Water Management group

4

List of Figures Figure 1. A multitier framework for analysing SESs. Source: E. Ostrom (2007b) ....................................................... 9

Figure 2. The IAD framework in the background and the inner-workings of an action situation in the

foreground. The rules influencing the action situation’s component parts are listed around its

boundary Source: (Mincey et al., 2013) ......................................................................................................................... 10

Figure 3. The linkages amongst levels of rules-in-use and decision/action situations. Source: G. Cowie & S.

Borrett (2005) ........................................................................................................................................................................... 11

Figure 4. Geographical location of the ‘Rambla del Poyo’ Basin. Source: Camarasa et al. (2011) .................... 17

Figure 5. Timeline of relevant events leading to eco-engineering projects in ‘Rambla del Poyo’. .................... 20

Figure 6. Location of eco-engineering projects in the ‘Rambla del Poyo’. Source: modified from BOE

(2012). .......................................................................................................................................................................................... 24

Figure 7. Geographical location of the 'Noordwaard' polder. Source: van den Brink (2009) . ........................... 26

Figure 8. Timeline of relevant events leading to the eco-engineering project in the ‘Noordwaard’ Polder. 29

Figure 9. Overview of PKB procedure and EIA for the Room for the River Programme. Source: Middelkamp

(2011). .......................................................................................................................................................................................... 30

Figure 10. Landscape Plan for depoldering (eco-engineering) the ‘Noordwaard’. Source: modified from

Ruimte voor de Rivier (2009). ........................................................................................................................................... 35

Figure 11. Rules in-use influencing components of action situations at constitutional, collective-choice and

even operational level leading to eco-engineering projects in ‘Rambla del Poyo’...................................... 38

Figure 12. Map of actors and their relations leading to eco-engineering in ‘Rambla del Poyo’. Both formal

and informal relations are represented by dashed lines; continuous lines represent only formal

relations. ...................................................................................................................................................................................... 39

Figure 13. Rules in-use influencing components of action situations at constitutional, collective-choice and

operational level for depoldering the ‘Noordwaard’. .............................................................................................. 45

Figure 14. Map of actors and their relations leading to eco-engineering in ‘Noordwaard’ Polder. Both

formal and informal relations are represented by dashed lines; continuous lines represent only

formal relations. ....................................................................................................................................................................... 46

Figure 15. Rules in-use influencing interactions and outcomes in eco-engineering and vice versa. ............... 51

Figure 16. Facilitated process approach for ‘Rambla del Poyo’. ....................................................................................... 52

Figure 17. Facilitated process approach for ‘Noordwaard Polder’. ................................................................................. 53

List of Tables Table 1. Second-tier variables in framework for analysing SESs. Source: E. Ostrom (2007b) .............................. 9 Table 2. Types of rules influencing action arenas. Source: Ostrom (2007a) and Polski & Ostrom (1999) ... 12 Table 3. List of actors relevant in the process leading to eco-engineering projects in ‘Rambla del Poyo’.

Source: BOE (2012); interviews; newspaper articles. ............................................................................................. 18 Table 4. Description of proposed solutions: eco-engineering projects in ‘Rambla del Poyo’ basin. Source:

AMINSA (2006). ........................................................................................................................................................................ 23 Table 5. List of actors relevant in the process leading to the eco-engineering project in ‘Noordwaard’

Polder. Source: Middelkamp (2011); Huisman et al., (2004); Paassen et al., (2011); Schut et al., (2010); interviews. .................................................................................................................................................................. 27

Table 6. Lessons learned from eco-engineering approaches versus traditional approaches.............................. 55

Page 5: Earth System Science Chair Integrated Water Management group

5

1 Summary This research aimed to analyse the rules in-use influencing eco-engineering approaches and vice versa.

The term eco-engineering was used to refer to projects in flood risk management, that included the use of

natural resources to increase structure functionality or to create structures (DELTARES, 2009).

Furthermore, projects that considered multiple objectives, different designs and decision-making

processes compared to traditional approaches. Rules in-use have been described as values defining

human strategies and behaviours, when a group of actors interact to produce different outcomes (Hess &

Ostrom, 2005; Polski & Ostrom, 1999). Rules in-use may formally be described in the form of a law, policy

or procedure; or may emerge informally as norms, operating practices, strategies or habits (Polski &

Ostrom, 1999). In addition, rules in-use constitute variables of governance system (Ostrom, 2007a, 2009).

To analyse the mutual influence of rules in-use and eco-engineering approaches, two case studies were

selected: the ‘Rambla del Poyo’ in Valencia, Spain, and the ‘Noordwaard’ Polder in the Netherlands. For the

first case the consented eco-engineering projects consisted of afforestation activities to increase local

water retention; green-ways to collect and conduct storm water run-off; and the restoration of floodplains

to accommodate water after high peak events. For the second case the final eco-engineering project

consisted of depoldering the area, in order to convert it into a multifunctional space with different

flooding frequencies. The methods to develop the research consisted of semi-structured interviews to key

actors and literature reviews. To process the collected data the approach was to construct a timeline of

relevant events. The developments of a timeline of events for each study case facilitated the identification

of action situations, were interactions and outcomes were produced. Once particular action situations

were identified the rules in-use were identified and analysed. This was done by using Ostrom’s Ostrom

(2009) Institutional Analysis and Development Framework. Based on this framework the rules in-use

depending on the types of action situations they related to, were identified as boundary, position, choice,

information or payoff rules. In addition, rules in-use were also identified as constitutional, collective-

choice or operational.

The main results and analysis evidenced the complexity of the governance systems in both case studies. A

polycentric type of governance characterized both cases. This means that different actors, at different

levels and from different sectors interacted to produce particular outcomes. This polycentric condition led

to the findings of different action situations, therefore, different types of rules in-use. Furthermore, to

identify rules in-use at different levels (constitutional, collective-choice and operational). The action

situations found consisted of the prescription and application of national and regional policies and

regulations (constitutional level). Action situations and consequently rules in-use found at the collective-

choice and operational levels, consisted mainly of informal lobbying, conflict resolution, and information

activities between project developers and local actors.

Both case studies evidenced that eco-engineering projects were triggered by the influence of new

regulations and policies at the constitutional level (i.e. EU Directives and regional flood safety policies). At

collective-choice and operational levels, new or changed boundary, position, and choice rules were found

influencing actors’ networks. In addition, actors’ perceptions of roles and their level of participation.

Furthermore, such were found influencing informal procedures (facilitated processes). Informational type

of rules influenced a strategic learning between concerning actors and the use of multiple discourses. For

both case studies the mutual influence of rules in-use and eco-engineering approaches resulted from

distinctive interactions. Such interactions were characterized by a top and bottom-up interchange

between actors, a distributed decision-making and the establishment of strategic alliances. As a result the

outcomes produced consisted of projects characterized by their integral design, their technical and

governance innovation, the provision of ecosystem services, and overall by enabling an integrated and

multifunctional flood risk management in the respective areas.

Page 6: Earth System Science Chair Integrated Water Management group

6

2 Introduction Flooding is a frequent, widespread and increasing natural hazard in many regions (Levy, Gopalakrishnan,

& Lin, 2005). Climate change and increasing sea levels are expected to augment the intensity and

frequency of flood related risks around the world (IPCC, 2007). In densely populated areas where flooding

is perceived undesirable, defences are considered indispensable and traditionally have consisted of hard

structures such as dikes, breakwaters, or dams (van Slobbe et al., 2012). In the light of current social, legal

and economic concerns, the overall effectiveness and resilience of these approaches have been questioned

(Levy et al., 2005). The need for innovative and sustainable solutions, with measures that offer

possibilities to enhance ecosystem functioning, has led to the development of new approaches (Borsje et

al., 2011).

New approaches in flood defence with an ecosystem basis have been referred to as ‘Eco-engineering’,

‘Building with Nature (BwN)’ or ‘Room for the River’ (Mitsch & Jørgensen, 2003; van Slobbe et al., 2012).

In general, it can be stated that such approaches consist of an integrated understanding of elements in

both the social and ecological systems. They comprise a chosen vision given the ecological and flood

protection possibilities and preferences, and a design plan for their realization given the particular

governance context where they are to be implemented. In Europe there is already knowledge and

experience with the implementation of such approaches (BwN, 2012; EcoShape, 2011; EU, 2011). Still

most of them need further efforts in addressing and socializing their potential (Naumann et al., 2011). In

the case of successful initiatives new opportunities can be identified or even motivate their development

in other regions. But also better understandings of such new approaches can evidence if indeed they

represent effective solutions in the ways they addressed both the social and ecological systems.

In this thesis report an analysis is presented of the mutual influence of rules in-use and eco-engineering

approaches. Rules in-use can be understood as ‘the values defining the behaviour of actors when they

interact to produce different outcomes’ (Polski & Ostrom, 1999). Therefore, analysing how rules in-use

influenced the interactions and outcomes in eco-engineering approaches and vice versa, provided with a

better understanding of their governance system, but also on how these new approaches unfolded. Two

case studies were analysed in which the technical design, objectives and the actors’ roles to develop

engineering projects, represented paradigm shifts compared to traditional approaches in flood defence

management.

The first case analysed was the ‘Rambla del Poyo’ in Valencia, Spain. Natural water retention areas, green-

ways and floodplains restoration constituted the final consented eco-engineering projects. The second

case analysed was the ‘Noordwaard’ Polder in the Netherlands. For this case the final eco-engineering

project was to create spaces with different flooding frequencies to accommodate water after high peak

events. First an identification of the action situations was developed. This in order to identify the ‘values’

(rules in-use) influencing such situations based on Ostrom’s (2009) Institutional Analysis and

Development Framework. The analysis of the rules in-use evidenced how the rules influenced interactions

and outcomes in eco-engineering approaches and vice versa. Such rules in-use were found to be common

in principle but with different values in both study cases. In addition, that based on the case studies such

rules in-use represented mainly the differences compared to traditional approaches and can be

considered as lessons learned from the governance systems.

Page 7: Earth System Science Chair Integrated Water Management group

7

2.1 Background In Europe examples of BwN or eco-engineering can be found in the United Kingdom with the managed

realignment approach. This approach consists of a cost-effective response aimed to create intertidal

habitats against increasing wave activity and sea-level rise (French, 2006; Turner, Burgess, Hadley,

Coombes, & Jackson, 2007). In the Netherlands new approaches have been institutionalized in flood

defence polices with projects such as ‘living with water’ and ‘increasing the resilience of our flood

defences’(van Slobbe et al., 2012). Another example can be found in Spain where initiatives to improve

local infiltration in urban areas, are being considered as local retention measures against flooding

(Francés, García-Bartual, Ortiz, Salazar, & Miralles, 2008). Different assessments (e.g. ecological, technical,

economic) of these new approaches in flood defence have been made (Francés et al., 2008; French, 2006;

Turner et al., 2007). But other types of assessments (e.g. outcomes and lessons learned) for example of

eco-engineering type of projects can also be found in the literature (EU, 2011). These have evidenced the

importance of accounting both the natural and social systems, when assessing BwN or eco-engineering

approaches.

Berkes & Folke (1998) have appointed the term socio-ecological systems (SESs) to analyse the integrated

concept of humans and nature. By framing two BwN projects in The Netherlands as SESs, van Slobbe et al.,

(2012), evaluated their resilience, social learning and the use of ecosystem services. Following this scope

the analysis allowed an exploration of the subsystems relevant to the BwN approach. The ‘natural system’

composed by the hydro-morphological processes (i.e., sedimentation, erosion) and the ecological

processes (i.e., food webs). The ‘engineering system’ composed by the human interventions influencing

the natural system (i.e., dams, reclamation projects), and the ‘societal system’ composed by the informal

and formal institutions operating in the projects (i.e., laws, stakeholder involvement, networks, practices).

(van Slobbe et al., 2012)

Particularly, the governance system in BwN approaches has been assessed in projects located in the

Netherlands. These have focussed in analysing stakeholders’ networks, regulatory and knowledge

contexts, and their realization frameworks. Thus, preliminary overviews and lessons learned with respect

to the governance elements embedded in such initiatives have been outlined (Wiki 2012).

2.2 Problem statement

There is still a need to learn about initiatives following eco-engineering approaches with regards to their

management, governance and monitoring activities. Better understandings and assessments of such new

approaches are needed to facilitate their future implementation or even identify niches for innovations.

(Apitz, Elliott, Fountain, & Galloway, 2006; van Slobbe et al., 2012; Waltner-Toews & Kay, 2005)

As relevant as it is to understand how these initiatives operate, it is important to know what were the

processes that facilitated their development. Therefore, there is still room and a growing interest from

scholars, policymakers and project developers, to learn about the governance systems in particular with

regards to the policies, strategies, or the norms used in eco-engineering approaches.

2.3 Purpose of the study The main purpose of the research was to analyse how rules in-use influenced interactions and outcomes

in eco-engineering approaches and vice versa. The specific objectives were to define the action situations

that led to eco-engineering projects in the selected case studies. Also, to identify the main actors involved

and the rules in-use. Furthermore, to compare rules in-use in eco-engineering approaches to the

traditional approaches.

Page 8: Earth System Science Chair Integrated Water Management group

8

Another purpose of this research was to contribute in exploring the use of Ostrom’s (2007b) multitier

framework for analysing socio-ecological systems, and Ostrom’s (2009) Institutional Analysis and

Development (IAD) framework. Especially by applying it to eco-engineering projects in the field of flood

management. The framework has traditionally been used to analyse socio-ecological systems, in which

there is clearly a distinguished ‘common pool resource’ (Ostrom, 2007b). Some examples are found in the

fields of forest management, agriculture (grazing and crops production), and in the water sector but

mainly related to irrigation systems, fisheries and pollution of water bodies (Janssen, Anderies, & Ostrom,

2007; Ostrom, 2007b, 2009; Ostrom & Cox, 2010).

The holistic representation of both the social and ecological systems, with the set of variables and their

sub-variables proposed to analyse them (Ostrom, 2007b, 2009), provided sufficient grounds for this

framework to be suitable in the attempt to understand the complexity of eco-engineering projects.

Therefore, with the application of the SESs and IAD frameworks and by analysing specifically the rules in-

use, this research contributed in providing insights about the governance system of eco-engineering

initiatives. Also in providing with new scopes in how to apply such frameworks and also assess such new

approaches.

Page 9: Earth System Science Chair Integrated Water Management group

9

3 Theoretical framework Ostrom (2007b) provides a nested framework to diagnose SESs, in order to achieve more coherent and

cumulative understandings of a system. The framework conceptually decomposes SESs into higher tier

levels with defined inter-linkages and boundaries (Figure 1). The variables of these higher tier levels are

the resource system (i.e. forest, fishery, lake, grazing area), the governance system (i.e. network

structures, rules), resource units (i.e. trees, fish, water, fodder), and the users of that system (Ostrom,

2009). These are related to action arenas where interactions take place that in turn produce outcomes and

feedbacks to the system (Ostrom, 2007b, 2009).

Figure 1. A multitier framework for analysing SESs. Source: E. Ostrom (2007b)

According to this framework each of these levels can further be partitioned into second tier levels (Table

1) which can relatively be considered as separate and independent subsystems (Ostrom, 2007b). This

level of variables allows exploration of parts of the system and are the ones directly conditioning action

arenas (Ostrom, 2009). A third aspect of the framework highlights the condition of ‘non-decomposability’

and ‘non-linearity’ of SESs, denoting that regardless the partitioning of different tier levels, the variables

across scales still interconnect and affect each other’s performance (Ostrom, 2007b).

Table 1. Second-tier variables in framework for analysing SESs. Source: E. Ostrom (2007b)

Page 10: Earth System Science Chair Integrated Water Management group

10

The application of Ostrom’s framework in new flood management approaches for example, will imply that

subject to a particular context the resource system (e.g. flood prone area), resource units (e.g. space for

flood protection), governance system (e.g. flood safety policies, polycentric networks, rules in-use), and

involved users (e.g. government bodies, project developers, organized groups, farmers, residents), have

led to particular interactions and outcomes (e.g. eco-engineering projects) that in turn produce feedbacks

in both the social and ecological systems. Thus, particular variables from the highest and second level tiers

in the system can be analysed to depict how these influence action arenas operating in the system.

An action arena is composed of an action situation and involved actors, but for simplification motives only

the produced interactions and outcomes are depicted in the SESs framework (Ostrom, 2011). A key part of

this framework is the identification of an action situation (Figure 2) and by looking at its internal

components the researcher can specify how actors are being analysed (Ostrom, 2011). The internal

components of an action situation consist of actors in positions that decide amongst diverse actions; based

on the information and control they possess about how actions are related to potential outcomes with the

costs and benefits assigned, respectively (Ostrom, Gardner, & Walker, 2006).

Based on the Institutional Analysis and Development (IAD) framework the internal structure of an action

situation is conditioned by the external variables such as the biophysical conditions, attributes of the

community and the rules in-use (Ostrom, 2011). This representation (Figure 2) was considered in this

research, since the main purpose was to study the mutual influence of rules in-use and action arenas.

Notwithstanding, while the framework for diagnosing SESs considers rules in-use (constitutional,

collective-choice and operational rules) as second tier variables of the governance system, the IAD

framework provides the basis to analyse in more detail the action arenas and the influences of the rules

in-use.

Figure 2. The IAD framework in the background and the inner-workings of an action situation in the

foreground. The rules influencing the action situation’s component parts are listed around its boundary

Source: (Mincey et al., 2013)

Page 11: Earth System Science Chair Integrated Water Management group

11

In previous sections the term rules in-use has been defined as ‘the values defining the behaviour of actors

when they interact to produce different outcomes’ (Polski & Ostrom, 1999). However, the term can also be

understood as the ‘shared normative understandings about what a participant in a position must, must not,

or may do in a particular action situation’ (Hess & Ostrom, 2005). Rules in-use are those usually known,

enforced and create opportunities and constrains for those involved. They are frequently nested and can

be crafted at three levels: operational, collective choice, and constitutional (Hess & Ostrom, 2005; Polski &

Ostrom, 1999). Each of these three levels of rules incorporates arrangements and situations (

Figure 3) where choices are made and actions are taken (Cowie & Borrett, 2005). Therefore, they are

useful to explain policy or decision-making situations, interactions and outcomes (Polski & Ostrom, 1999).

At the operational level rules determine actions, patterns of interactions, and outcomes in the physical

world. Collective-choice rules determine who is eligible to participate and how rules at the operation level

should be governed. Similarly, rules at the constitutional level determine the crafting of rule sets but

instead at the collective choice level. Although higher levels bound lower levels of decision situations,

rules at the operation level are the ones directly affecting action situations where the outcomes of the

resource use are generated. Furthermore, such outcomes may in turn feedback situations at different

levels, or within specific level feedbacks may also influence situations and arrangements (Figure 3).

(Cowie & Borrett, 2005; Polski & Ostrom, 1999).

Figure 3. The linkages amongst levels of rules-in-use and decision/action situations. Source: G. Cowie & S. Borrett (2005)

Furthermore, Ostrom (2007a) has stated that in the effort to bring some order to the different rules that

one could analyse, these have been clustered into seven broad types depending on the action situation and

its internal components they relate to. Such types of rules may influence action situations present at any of

the three already mentioned levels and have been referred as: boundary, position, choice, aggregation,

information, payoff, and scope rules (Table 2; Figure 2).

Page 12: Earth System Science Chair Integrated Water Management group

12

Table 2. Types of rules influencing action arenas. Source: Ostrom (2007a) and Polski & Ostrom (1999)

Type of rule Definition

Boundary Rules that determine which participants can enter or leave (under what conditions)

a particular situation. These are also known as the exit and entry rules by specifying

who is eligible to participate and how they do so.

Position Rules that create the positions that participants hold. Such rules specify the number

and type of participants who hold each position.

Choice Rules that assign action sets to the positions filed by the participants. In other words

the possible actions a participant can choose to perform given the position it holds.

Aggregation Rules that affect the level of control that individual participants exercise at a linkage

within or across situations. These rules basically determine how decisions are

lobbied and made in an action situation.

Information Rules concerning the level of information available to participants about actions and

between actions and outcomes linkages. They refer to the amount and type of

information accessible to participants.

Payoff Rules that affect the benefits and costs assigned to participants in light of the

outcomes achieved.

Scope Rules that affect which outcomes may, must, or must not be affected within a

situation

Page 13: Earth System Science Chair Integrated Water Management group

13

4 Research Questions

General research question:

How do rules in-use influence interactions and outcomes in eco-engineering approaches and vice

versa?

Based on the SESs framework there are different external variables (i.e. users, resource units, governance

system and the resource system) that could influence and become influenced in return by projects

developed under an eco-engineering approach. This general question therefore defines the specific values

that were analysed in this research. In this case these constituted the ‘rules in-use’ in eco-engineering

projects. Based on the SESs and IAD frameworks the question also takes into account the ‘context’ (action

arenas: interactions and outcomes) and the feedbacks between both rules in-use and eco-engineering

approaches.

Specific research questions:

What are the main events and processes (action situations) leading to eco-engineering initiatives?

Based on the SESs and IAD frameworks one should first define which are the action situations (e.g.

prescription and application of policies, monitoring and enforcing, lobbying, conflict resolution and

information sharing activities) and the levels that are going to be the subject of analysis.

Who are the actors involved in these action situations?

Again based on the SESs and IAD frameworks, to look at action situations consequently one should also

analyze the actors that are participating.

What boundary, position, choice, information or payoff rules were applied in these action

situations?

When performing an institutional analysis the values embedded in the different procedures, norms,

regulations and strategies, can be of different domains or be affecting different action situations and their

internal components. Thus, the IAD framework provides with a classification of such rules in order to

facilitate their analysis and achieve a better understanding of how these relate to the action situations

being studied.

What are differences between rules in-use in traditional versus eco-engineering approaches?

By looking at the different interactions and outcomes, actors and rules in-use in eco-engineering projects

an analysis can be made over new or changed rules compared to traditional approaches in flood defense

management.

Page 14: Earth System Science Chair Integrated Water Management group

14

5 Methodology In this section the methods used to develop the research are presented. The first step consisted of defining

the criteria for the case study selection. Then the methods used to collect and process the information and

the frameworks and structure considered for the analysis.

5.1 Case study

The case study is a research strategy which focuses on understanding the dynamics or interventions

present within particular settings (Eisenhardt, 1989). This research strategy typically combines data

collection methods such as literature reviews, interviews, focus groups, questionnaires and observations

(Eisenhardt, 1989; Hartley, 2004). Case studies can be used to provide description, generate theory or to

illustrate the theoretical issues being studied (Eisenhardt, 1989). In addition, depending on the purpose of

the research the case study design can also be mainly descriptive (i.e. describe interventions in real-life

settings), explanatory (i.e. explain casual links in real-life interventions), exploratory (i.e. evaluate

interventions with no clear set of outcomes) or comparative (i.e. multiple cases with similar or contrasting

results based on a theory) (Baxter & Jack, 2008). Therefore, this research approach was selected to

analyse the rules in-use and eco-engineering approaches. It was considered suitable since the main

interest was lo learn from particular settings and theories, where the analysis of the interventions or

dynamics between the social and natural systems came from real-life contexts. Furthermore, in this

research the comparative case study design was chosen to be both explanatory and comparative, as

lessons learned were drawn from the analysis and two cases were selected. In order to define which

particular cases were going to be addressed the following criteria was defined:

- Eco-engineering examples within the European context

- Eco-engineering examples in which their devising process comprised new objectives and

procedures

- Eco-engineering examples in which the devised project has been officially consented

- Eco-engineering examples from which literature was available and accessible

The first criteria came from developing the research within the boundaries of the Project ‘Working with

Nature, ecosystem engineering in coastal and river engineering1’ which placed its focus on European

countries. Project partners in the Netherlands and in Spain were key in narrowing the scope to these two

particular countries for the selection of cases. This allowed a familiarization with the background of the

potential regions of study and later on the introduction to actors and other sources of information when

performing the interviews and analysis. Following the other two criteria the ‘Rambla del Poyo’ in Valencia,

Spain, and the ‘Noordwaard’ Polder in The Netherlands came to be the selected study cases.

It is worth mentioning that what could be perceived as differences between the cases according to their

stage (approval, implementation) and scale (regional, local), such factors were not accounted for their

selection. The main principle relied in focusing on the processes themselves, which led to consented

projects under an eco-engineering approach. This was also due to considering as a premise that the

governance contexts between the two study cases are different. Therefore, institutions, procedures and

rules leading to eco-engineering projects were expected to be different (operating at different levels or

even scales).

1 The Project ‘Working with nature, ecosystem engineering in coastal and river engineering’ was funded by the Knowledge and Innovation Communities (KICs) (created by the European Institute of Innovation and Technology). Its main objective: ‘to define eco-engineering products and services and to map and create business opportunities for eco-engineering-working with nature- approaches along rivers and coasts in Europe as green adaptation method’. It was developed by the following project partners: Imperial College, UK; ARCADIS, DELTARES, and Wageningen University, The Netherlands; and the Technical University of Valencia, Spain.

Page 15: Earth System Science Chair Integrated Water Management group

15

5.2 Data collection techniques

5.2.1 Primary data collection

First-hand information consists of data originally collected for the purpose of the research (M. Schut,

2012). Stakeholder’s analysis methods have been seen as ‘a way of generating information on relevant

actors to understand their behaviour, interests, agendas, and influence on decision-making processes’ (Reed

et al., 2009). In addition, ‘interviewing is one of the most used data collection techniques within the case

study approach’(M. Schut, 2012). Therefore, for this research a stakeholder’s analysis method was used for

the primary data collection. The selected method consisted of performing key informant interviews in

both case studies (Annex 1 and Annex 2). This allowed the identification of the different actors and the

collection of their insights for a multi-perspective understanding of the issue at stake, based on the actors’

views with respect to the strategies, choices and the roles they played. Key informant interviews were also

performed to construct the process that unfolded and to validate the information gathered between

interviews and literature reviews.

In order to select the key informants a preliminary list of involved actors was made in collaboration with

experts acquainted with the study cases. The principle was to include representatives of actors from the

different groups (e.g. project developers, government, local authorities, farmers, etc.). As the collection of

information unfolded other actors were identified (snowball sampling). A semi-structured interview

format was also chosen since a guideline of questions was developed (Annex 4); but by using this

technique enough flexibility was allowed to engage in a more dynamic interaction with the interviewees.

For example, specific and particular inputs could be elaborated in more detail; the tone could be moulded

according to the position of the interviewee; or the interviewee could be guided based on the storyline

relevant for the research, but still discuss about new inputs considered relevant. The interviews

performed were not recorded but notes taken were transcribed.

As previously mentioned the snowball sampling was also used as other interviews became possible as a

result of recommendations and contacts provided by the initial key interviewed actors. This technique

proved to be a good strategy when performing the data collection activities. By referring to the person

that identified the new or potential interviewee, this built a kind of ‘trust’ facilitating the access, openness

and sometimes the sharing of other sources of information (e.g. reports, documents, etc.). It is worth

mentioning that in the attempt of arranging personal meetings to perform the interviews, although

personal meetings couldn’t be arranged, general information was still provided by performing then ‘phone

call interviews’ (Annex 3). More broadly insights of such actors during the process were collected but still

became useful and thus considered.

5.2.2 Secondary data collection

Ideally in performing this type of research, insights from each group of actors combined with a

representative sample, provide a better and balanced representation of their understandings and insights

in relation to the process. In order to have a better insight of the other relevant actors, supporting

methods for data collection were considered. These consisted of the use of secondary sources of

information consisting mainly of: newspaper articles and blogs, scientific papers, thesis, legislation and

legislative procedures, studies on alternative proposals, technical and official government reports,

brochures and factsheets, plans and maps, power point presentations, etc. This literature review aided the

construction of the cases and was also used to triangulate and validate data from the interviews and

between these different sources. Interviewees provided most of these supporting sources of information,

but others were found using web academic finders.

Page 16: Earth System Science Chair Integrated Water Management group

16

5.3 Data Process

To process the information collected particular categories were identified in which the data could be

grouped. These consisted in identifying and classifying the information which could be associated with the

context previous to the eco-engineering projects, the process for devising the projects, describing the

projects, and input data that could be directly linked for the analysis of the rules in-use. Once the

information was organized the next step consisted in constructing a timeline of critical events. This in

order to depict which constituted the main actions situations in both case studies leading to the e final

consented eco-engineering projects. Thus, the values (rules in-use) around such critical events could be

particularly identified and analysed in the next stages.

5.4 Analysis

In general the data collected from both primary and secondary sources was analyzed following the

‘grounded research approach’. This analytical method was used as it enables the researcher to adapt when

collected data follows and interactive process, and the researcher becomes more grounded to the

information as the case study unfolds (Marc Schut, Leeuwis, & van Paassen, 2010).

5.4.1 Rules in-use analysis

The IAD framework was used for the rules in-use analysis in both case studies. Since actions situations

were being analysed, the seven types of rules that relate to such situations were used to classify the

identified values and strategies. Also, since the processes leading to eco-engineering projects were

analysed, rules were found operating at different levels (constitutional, collective-choice and operational)

and affecting different actions situations at different moments. However, for representation motives these

were all grouped and simultaneously presented following the same outline of the framework. This choice

was made as it is not clear based on the works done with the framework, how to represent schematically

such information when an institutional change analysis is being performed (considering different levels

and types of rules across time). Nevertheless, such distinction was made and properly described. Although

the research focused in the governance system in particular to the rules in-use, considering the aspect of

non-decomposability of Ostrom’s (2007) framework, the resource system, units and users (actors) were

also addressed to aid the analysis. However, these were not elaborated into detail, but still were included

since after all eco-engineering approaches in this research are being framed as SESs.

5.4.2 Traditional versus eco-engineering approach rules in-use analysis

By identifying the process that unfolded and the rules in-use in eco-engineering approaches, this made it

possible to also analyse which of these rules influenced or became influenced in return. To develop this

analysis the approach consisted in distinguishing the grounds in which identified new and changed rules

were influencing action situations, consequently interactions and outcomes and vice versa. This in order

to draw general understandings (lessons learned) and then compared them to the traditional approaches.

Since considering as a premise that the governance systems between the two case studies were different,

mainly contrasting results were expected. As it turned out common denominators where found.

Therefore, by considering the common denominators from both case studies a general comparison

between the new (eco-engineering) and traditional approaches was made, but the description of the

values composing the common denominators according to each case was also included.

Page 17: Earth System Science Chair Integrated Water Management group

17

6 Results

In chapter 3 it was mentioned that action arenas are composed of action situations and the actors involved

(Ostrom, 2011). Action situations are defined as “the social spaces where individuals interact, exchange

goods and services, engage in appropriation and provision of activities, solve problems, or fight.”... “In field

settings, it is hard to tell where one situation ends and another begins” (Ostrom et al., 2006).

When looking at the rules in-use influencing these ‘social spaces’, it is necessary to understand first what

are these situations and what are their main attributes. Therefore, in this chapter the actors involved and

the action situations that were analysed as part of this research are presented. For both the case studies

these constitute in general the prescription and application of national and regional policies and

regulations, but also information sharing, deliberation processes, conflict-resolution, investment and

lobbying activities. Such action situations led to particular interactions and outcomes (eco-engineering

projects). Since actions arenas are described in this section, the actors who became involved are also

presented.

In this research the term eco-engineering refers to ‘the use of engineering solutions, which improve

traditional structures using natural resources to increase the structure functionality, or the use of natural

materials (flora and fauna) to create structures’ (DELTARES, 2009). But also to refer to projects, solutions

or alternatives, in which safety against floods played a central role, and additional values (environmental,

recreational, and economical) also took a central core in their design.

6.1 ‘Rambla del Poyo’ in Valencia, Spain

The ‘Rambla del Poyo’ basin located in the East coast of Spain, is an example of a Mediterranean

ephemeral stream system (Camarasa et al., 2011; Francés et al., 2008). Mediterranean ‘ramblas’ and

‘barrancos’ are known as relatively small basins (several hundred km2) with steep slopes, wide valleys,

scarce vegetation and poorly

developed soils (Camarasa et al.,

2011; Camarasa & Tilford, 2002).

Despite remaining dry for most of the

year, these systems react over

intense, heavy and irregularly

distributed rain (Camarasa et al.,

2011). Thus, become subject to rapid

and unpredictable flash floods

(Camarasa & Segura, 2001). The

‘Rambla del Poyo’ is characterized by

a semiarid climate and has an area of

380km2 (Francés et al., 2008). It

comprises the region south of

Valencia city between the Turia and

Jucar rivers, which drains into the

‘Albufera’ coastal lagoon (Figure 4)

(Camarasa et al., 2011; Camarasa &

Tilford, 2002; Francés et al., 2008). It

is composed by three main

tributaries: the ‘Barranco Grande’,

the ‘Barranco de la Cueva Morica’

and the ‘Rambla de Gallo-Chiva’

(Camarasa & Tilford, 2002).Fure 4

Figure 4. Geographical location of the ‘Rambla del Poyo’ Basin.

Source: Camarasa et al. (2011).

Page 18: Earth System Science Chair Integrated Water Management group

18

6.1.1 Actors

There were several actors who became involved as result of the new approach (eco-engineering projects)

in the ‘Rambla del Poyo’. These in general consisted of various governmental units, 32 municipalities, the

Technical University of Valencia, a number of environmental groups, the platform ‘Per un Barranc Viu’

(For a Living Ravine), consultancy groups, and the European Commission, Directorate-General of

Environment as an international body (Table 3).

Table 3. List of actors relevant in the process leading to eco-engineering projects in ‘Rambla del Poyo’. Source: BOE (2012); interviews; newspaper articles.

Government Units Municipalities -Ministry of Natural, Rural and Marine Environment: General administrative institution, with its competent bodies at a regional level (see others). Its functional attribution is to monitor and evaluate activities related to water resources, biodiversity, protection of natural and marine environments, amongst others. Also, to ensure that required procedures, regulations, objectives and standards are met. -Hydrological Confederation of Jucar: Regional autonomous body, under the Ministry of Natural, Rural and Marine Environment. It is the governmental manager of all the hydraulic and hydrological initiatives that take place in the area. -Others: -Generalitat Valenciana (Provincial Authority) -General Directorate of Biodiversity (Ministry of Environment) -General Directorate of Environmental Management (Counselling of Territory and Housing, Generalitat Valenciana) -General Directorate of Environmental Quality (Counselling of Territory and Housing, Generalitat Valenciana) -General Directorate of Spatial Planning (Counselling of Territory and Housing, Generalitat Valenciana) -General Directorate of Public Works (Counselling of Infrastructure and Transport, Generalitat Valenciana) -General Directorate of Fishing and Alimentation (Generalitat Valenciana) -General Directorate of Landscape and Territory (Generalitat Valenciana) -Environmental Evaluation Area of the Autonomy Secretary of Territory and Environment (Generalitat Valenciana) -General Directorate of Railways (Ministry of Development) -Counselling of Tourism, Culture and Sports (Generalitat Valenciana)

The 32 municipalities located within the basin or next to the flood prone areas. These are the basic units of governmental authority, with the principal attribution to ensure and protect the local territory and people’s interests, amongst others. -Municipality of Alaquás -Municipality of Aldaia -Municipality of Alfafar -Municipality of Benetússer

-Municipality of Chiva -Municipality of Loriguilla

-Municipality of Manisses

-Municipality of Massanassa

-Municipality of Paiporta -Municipality of Picanya -Municipality of Quart de Poblet

-Municipality of Siete Aguas

-Municipality of Xirivella -Municipality of Cheste -Municipality of Alabal -Municipality of Alborache

-Municipality of Beniparrell -Municipality of Buñol -Municipality of Catarroja -Municipality of Gestalgar -Municipality of Godelleta -Municipality of Mislata -Municipality of Monserrat -Municipality of Montroy -Municipality Picassent -Municipality of Riba-Roja de Turia

-Municipality of Sedavi -Municipality of Silla -Municipality of Torrent -Municiapility of Turis -Municipality of Valencia -Municipality of Vilamarxant

Universities Environmental groups -The Polytechnic University of Valencia (PUV): Educational and research institute, in this case a knowledge provider in the field of Hydraulics.

Organized groups that represent the environmental interests and engage in activities related to the conservation, maintenance and protection of the natural heritage in the area. -Ecologists in Action-Agro -ADENA -SEO -Study Group and Defense of the Environment ‘Rocandell’ -ENEBRO-Environmental Group of Chiva-Ege -Ecologists in Action-Alicante -Ecologic Group ‘L’Aber-ea’ -Friends of Wetlands of South Alicante Association - ‘Xúquer’ -Coordinador in Defense of the Forests

Platforms Consultancies -‘Per un Barranc Viu’ (For a Living Ravine): Organized platform of local actors in reaction to the first project developed (1991-1995). The principal function was to manifest and express their concerns over the environmental impacts of the first proposed projects in the area (1991-1995).

Civil engineering companies that offer expertise in designing and implementing projects in the field of Hydrology and Hydraulics, amongst others. -AMINSA -TYPSA

International Bodies Directorate-General for the Environment: Part of the European Commission that supervises Member States on their correct application of the EU Environmental Law.

Page 19: Earth System Science Chair Integrated Water Management group

19

6.1.2 Action situations

The final consented eco-engineering projects in the case of ‘Rambla del Poyo’, resulted from a process that

unfolded over the years, and was triggered by different levels of action situations and levels of rules

(constitutional and collective-choice). These particular action situations have consisted in the prescription

and application of national and regional policies and regulations (constitutional level), and in the

monitoring and enforcing of these activities in a formal context (collective-choice level). But actions at the

collective-choice level also included informal lobbying, conflict resolution and information processes with

local actors.

Despite actions situations in these case were found mainly at the collective-choice level, in a way these

became also influenced from the expected operational action situations that they seek to define. In

particular when the potential actors at operational levels were somehow included in the definition of

rules for the projects. In order to provide with a general overview about these processes, a timeline of

events with the identified key elements of these actions was elaborated (Figure 5). In this figure shaded

circles indicate where particular actions (formal and informal) became interrelated.

Relevant events and initial flood defence actions in ‘Rambla del Poyo’

Over the last few decades the ‘Rambla del Poyo’ basin has been subject to an increased human occupation

and land use change, that has led to a pattern of flood risk highly dependent on exposure (Camarasa et al.,

2011). Flooding problems in the area have led to the canalization of final branches of the rivers, but risks

have persisted as urban expansion continues (Camarasa et al., 2011) and new environmental and social

concerns emerge (AMINSA, 2006). Records of extreme floods in the ‘Rambla del Poyo’ date back to 1949,

1957 and 1983 (Segura, Sanjaume, & Meyer, 1985). The event of 1949 mainly affected the community of

‘Chiva’ and was aggravated by demolition and waste materials which after the Civil War, were dumped

into the ravine and hindered the free flow of water (Segura et al., 1985). The event of 1957 although didn’t

cause severe damages within the basin, was also mentioned by interviewed actors as the most relevant,

because it coincided with the rise of the Turia River that caused the ‘Great Flood of Valencia City’

(Camarasa et al., 2011; Segura et al., 1985). This led to the Turia River’s diversion to the south where it

now occupies part of the ‘Rambla del Poyo’s plains (Camarasa et al., 2011).

The event of 1983 is relevant since it affected different areas and sectors along the basin. Most

importantly, because it outlined the implications of urban infrastructure located in natural drains and the

lack of adequate channels, which have increased the risks to floods (Segura et al., 1985). Up until this point

the state of actions against floods in the area have been almost exclusively structural engineering

solutions (PATRICOVA, 2002). Nonetheless, it was around this decade that relevant efforts emerged at a

regional and national level, to promote non-structural, management, political, and legal initiatives towards

flood defence [i.e. the 2508/1975 Decree about intervention measures in floodplains for a return period of

500 years, the Automatic System of Hydrological Information (SAIH) finalized in 1990 for Júcar Basin, the

National Hydrological Plan approved in 1992, and the Planning Guideline of Civil Protection against Flood

Risk approved in 1995 (Berga, 1993; PATRICOVA, 2002)].

Despite these efforts were gaining momentum, other extreme events were recorded in 1988, 1989, 1998,

and most recently in 2000 (with a peak flow of 500m3/s) (AMINSA, 2006; Francés et al., 2008). The

political momentum and reactive responses taken during these years can be outlined then, as the point in

time where initial steps influenced and started to pave the path towards new approaches. The interviewee

from AMINSA Consultancy, who stressed that changes in the traditional approaches paved their way

around this time, also supported this argument.

Page 20: Earth System Science Chair Integrated Water Management group

20

Figure 5. Timeline of relevant events leading to eco-engineering projects in ‘Rambla del Poyo’.

Page 21: Earth System Science Chair Integrated Water Management group

21

Moving from a traditional civil-engineering approach to an eco-engineering approach

When looking particularly to the first initiative preceding the eco-engineering projects in the area, this can

be referred to a process initiated in 1991 by ‘Confederación Hidrográfica del Júcar’ (Hydrological

Confederation of Júcar -HCJ-). This consisted of a study for the artificial restitution of about 42 km

channels along the basin, which basically followed a traditional engineering approach (AMINSA, 2006).

The proposed solutions from this project became official in 1995, but the Environmental Impact

Declaration (EID), issued in 1996 by the ‘Generalitat Valenciana’ (Provincial Authority), conditionally

approved its realization (AMINSA, 2006; TYPSA, 2009a). This declaration required the evaluation mainly

of other environmental studies and complementary documentation (AMINSA, 2006). Despite these

conditions, the bidding process for developing the original proposal of Phase I of the project continued in

1998, and the requests of the 1996’s EID were only presented to the competent authorities until 2000

(AMINSA, 2006). Although these requirements were met, in 1999 the European Commission (DG of

Environment) published a complaint, of a possible misapplication by the Spanish Authorities of the EU

Birds and Habitats Directives (TYPSA, 2009b). The response submitted to this accusation was based on

the amends presented in 2000, which the European Commission considered insufficient (AMINSA, 2006).

Therefore, in late 2000 the Provincial Authority commissioned a new EID requiring a new series of

conditions applicable for Phase I and the rest of the project (AMINSA, 2006; TYPSA, 2009a). Given this in

2001 the General Directorate of Hydraulic Works and Water Quality of the Ministry of Environment called

for new approaches. It also authorized the drafting of a new project named: Environmental suitability and

drainage of Poyo Basin to the Albufera (Valencia) (TYPSA, 2009b). The Dictatorate in addition stated that

this project should be submitted to a new EID, except for Phase I for which amends were made and

approved (AMINSA, 2006; TYPSA, 2009a). This then led to a process where the flooding problems in the

basin started to be discussed between actors and relevant institutions, resulting in the exploration of

possible solutions that can best contribute to an integrated flood management, while complying with the

new required environmental objectives (AMINSA, 2006). This process was also highlighted by the

interviewee from AMINSA and by one of the interviewees from the Polytechnic University of Valencia

(PUV). As a result of these informal discussions and dialogues that were held between key actors, a study

that contained the different possible solutions was published in 2005 (TYPSA, 2009b). After this the HCJ

decided to invest more efforts that could assist in the selection of the best alternatives (AMINSA, 2006;

TYPSA, 2009a).

Interviewees from AMINSA and TYPSA Consultancy, the PUV and from the HCJ, mentioned that to explore

which could then be the most viable solutions, the first approach was to evaluate them from a technical

point of view. Therefore, the hydraulic functioning of the watershed was studied according to the possible

alternatives which were: retaining water in the landscape via afforestation, micro-ponds, and micro-

reservoirs, the establishment of green-ways and the restoration of floodplains. The behaviour and

response of these alternatives in different locations and scenarios (events for a period of return of 100,

300 and 500 years) was quantified both separately and together, with the use of the latest hydraulic

models available at that time: RAINGEN stochastic model, TETIS model, and the SOBEK RURAL model

(AMINSA, 2006).

According to the interviewees of AMINSA and HCJ based on this analysis, which was closely developed by

AMINSA and the Polytechnic University of Valencia, but supervised and monitored by HCJ, the solutions

were again shared with relevant actors of the area to receive feedbacks but also to consider local interests.

During this second round of informal dialogues and information sharing, the potential actors that would

be affected with the implementation of the alternatives were reached. This became an initiative of HCJ

accompanied by AMINSA, in which based on the interviewees (AMINSA and HCJ), consisted of targeted

individual and group meetings.

Page 22: Earth System Science Chair Integrated Water Management group

22

The motivation was to create a communication channel where the concerned actors and the authorities

could manifest particular interests, express their posture in relation to the projects, but also bargain and

concede over the benefits and costs. Based on the AMINSA’s interviewee the principle for the authority

(HCJ) to promote these actions was to further define the best solutions now considering the parameters of

land use and the property rights. Additionally, to have feedbacks over the alternatives to discard those

that represented most controversy and low acceptance, or to even consider other options. These actions

were managed strategically focusing mainly on those municipalities in which their territorial boundaries

were going to be affected, held political power, or manifested conflicting positions towards the

development of the projects. The same principle was applied for the environmental groups, focusing in

those who were seeking after the environmental quality of the area. The interviewee from AMINSA also

pointed out that these meetings and presentations were held on an irregular basis and were led by the

HCJ.

Notwithstanding, the interviewed government officials and consultancies’ engineers highlighted these

interactions at different moments throughout the planning process, as one of the most relevant steps

taken compared to traditional approaches. This because it allowed during an early stage the participation

of different actors in order to reach for consented actions, thus facilitating the subsequent stages. On the

other hand based on other sources of information (newspaper articles and blogs) to collect insights from

the other stakeholders, it can be stated that certain local actors also engaged in relevant actions that in a

way influenced the devising of the final eco-engineering projects. These consisted of the creation of a local

Platform called ‘Per un Barranc Viu’ (For a Living Ravine) to manifest the local concerns in relation to the

environmental impacts of the 1995’s project. In addition, it was found that the environmental group of

Ecologists in Action-Agro were responsible in taking their complaints to the EU DG of Environment.

Continuing with the process, once the solutions were concretized in 2006 (AMINSA, 2006), the efforts to

perform the official informative process and final drafting of the project took place from 2007 to 2009

(TYPSA, 2009b). This process was led by another consultancy, TYPSA, but still monitored by the HCJ.

Based on the interviews, stakeholders where again strategically reached, following the same principles, to

discuss the set of alternatives and their complementary studies (i.e. social, economic and environmental).

But also, to hold dialogues on the basis of received official allegations or requested clarifications. After this

process a favourable EID was issued in 2012, making the alternative of ‘solutions for a period of return of

100-500 years and without flow transfer between the Pozalet and Poyo ravines’ the officially consented

choice (BOE, 2012).

The consented eco-engineering projects

Since the request for a new project in 2000, clear objectives were defined in response to comply mainly

with the environmental and flood safety polices and regulation both at a regional and national level.

Therefore, these can be called out as the main drivers with regard to the process, which were also

mentioned by all interviewees. So the defined objectives were: ‘i) virtually eliminate the impact of flooding

in urban areas up to a return period of 5002 years, ii) promote hydraulic planning so that future impacts of

land use change and runoff diversion are reduced, iii) protect the Albufera National Park against clogging

processes and ecosystem degradation, iv) and to restore environmentally the river systems and create

ecological corridors, while promoting a territorial integration through the planned activities’ (AMINSA,

2006). Nonetheless, interviewees from the government and consultancies also mentioned that the range

of possible alternatives were also evaluated and prioritized based on economic terms, and minimum land

expropriation and occupation.

2 Return period of 500 years in this case is a term used to refer to the average time frame for a high peak flow to display at least in one occasion (PATRICOVA, 2002).

Page 23: Earth System Science Chair Integrated Water Management group

23

The approved set of solutions or eco-engineering projects (Table 4 and Figure 6) consists of a group of

measures to perform upstream, middle-stream and downstream the basin. It includes the construction of

green-ways between the Pozalet, Poyo and Gallego Ravines, with the criteria of rural areas having a level

of protection up to 100 years (TYPSA, 2009a). Therefore, in the Pozalet Ravine a green way should be

constructed for a peak discharge of 240m3/s (based on a return period of 500 years), with a restored

floodplain in the Municipality of Aldaia (TYPSA, 2009a). In the Poyo and Gallego Ravines green-ways are

proposed for a level of protection of 1,000m3/s, allowing room for extreme peaks to overflow, in order to

prevent a downstream flow not greater of 1,200m3/s (TYPSA, 2009a). This is viable since even for a

return period of 500 years, the total downstream flow could reach up to 1,500m3/s, a value that is still

compatible with the current capacity of the ravine (TYPSA, 2009a). In addition, the Poyo-Turia green-way

was also suggested for a flow up to 700m3/s, to meet the flow capacity of 800m3/s that continues its

course into the Albufera Lake (TYPSA, 2009a).

Based on the interviews, these actions are yet to be implemented once public funds are allocated.

However, it is relevant to mention that Phase I of the initial project started in 2001 with works finalized in

2005. These consisted of returning the channel downstream the basin between the Albufera Lake and the

Municipality of Paiporta to a capacity of about 800m3/s (TYPSA, 2009b). But also other measures

discussed as part of the process have been implemented (2005-2008). This have consisted of the

reforestation of 755 hectares upstream the basin, as a stabilization measure to improve water retention,

reduce soil erosion, improve the ecological conditions, and prevent forest fires through management

practices (BOE, 2012; TYPSA, 2009c).

Table 4. Description of proposed solutions: eco-engineering projects in ‘Rambla del Poyo’ basin. Source: AMINSA (2006).

Eco-engineering alternative Description

Afforestation Activities of afforestation in areas upstream the basin without

vegetation and potentially high erosion levels. This solution aims to

stabilize soils acting on run-off coefficients, in order to reduce peak

flows and sediment transportation downstream, while enhancing

the environmental quality.

Micro-ponds and Micro-

reservoir3

Activities upstream concerning the creation of a lamination area,

with sufficient capacity to hold natural run-off, thus reducing peak

discharges downstream the basin.

Green-way Activities concerning the conditioning of areas to collect and

conduct storm water run-off, characterized by a natural vegetation

cover, and also functioning as recreational spaces.

Floodplain restoration Activities concerning the creation of green zones that will be

allowed to flood after peak flows but will remain dry otherwise.

These areas will hold natural vegetation associated with riverine

ecosystems.

3 These alternatives were discarded in the final consent.

Page 24: Earth System Science Chair Integrated Water Management group

24

Figure 6. Location of eco-engineering projects in the ‘Rambla del Poyo’. Source: modified from BOE (2012).

Page 25: Earth System Science Chair Integrated Water Management group

25

Costs and benefits associated with the eco-engineering projects

In the previous sections it was mentioned that in a way costs and benefits associated with the alternatives

were discussed among the concerned actors. In this section this aspect is further elaborated. Interviewees

from government and consultancies mentioned that there was one particular strategy used to aid the

socialization of alternatives with other actors. This was taken from the guidelines provided by the regional

action plan, PATRICOVA, in which the concept of ‘units of impact’ is introduced. A unit of impact is defined

by the spatial combination of risk and vulnerabilities; where the calculated cost of one unit was estimated

in 2 euros average for annual damage. The principle was to estimate the total of current units of impact at

a municipal level and in the area in general (16,086,254 units). This to have an estimation of the total costs

(32 million euros/year) if measures were not implemented. Also to depict which municipalities pose the

greatest impacts and costs, highlighting as such the Municipality of Aldaia, Xirivella, and Quart de Poblet in

the top three. An estimation was also made in relation to the effect the alternatives will have in reducing

the units of impacts, to support even more these propositions. In relation to other estimation of costs

considered or evaluated in the process, these basically consisted of the costs of land to be expropriated by

the implementation of the projects (18,223,478 euros), the costs of materials and works (221,433,058

euros) which add up to a total of 239,656, 536 euros (TYPSA, 2009b).

On the other hand, according to the interviews, the main benefit was mainly attributed to the provision of

flood safety in the area. This was seconded by the estimation in a way of the saved costs if measures are

implemented which are stated to reduce in total the units of impact. Other mentioned benefits were that

with the process, steps in building a more integrated water management was initiated since it allowed for

a more comprehensive hydrographical planning. Environmental benefits are also expected once the

projects are implemented such as the protection of the Albufera Lake from sediments, the functional

recovery of ecosystems and riverbanks, and the gains associated with the creation of biological corridors

that will result from the green-ways. Other benefits include the creation of recreational areas for public

use, and the construction of bike lanes and pedestrian sideways to connect inhabitants from neighbouring

settlements. Concrete estimations of such benefits were not performed.

Parallel influential initiatives

The ideas to move from traditional civil engineering to new approaches were also influenced by new

policies and regulations that became official in parallel to the previously described process. These were

mentioned by interviewees from the PUV. The most relevant is the Territorial Action Plan on Flood

Hazard Prevention in the Valencian Community (PATRICOVA) published in 2002. The PATRICOVA was

one of the management tools developed according to the 6/1989 Law of Spatial planning in the Valencian

Community, which provided the principles and recommendations of actions under a quantified evaluation

of flood risk impacts (return period of 100 to 500 years), and proposed a set of requirements to achieve

their maximum reduction, amongst other features (PATRICOVA, 2002).

The Hydrological Plan of Júcar includes the actions already taken in the area according to Phase I, but it is

also relevant as it became a regional tool that reinforced the general guidelines and objectives projects

should meet in terms of safety and environmental concerns (TYPSA, 2009b). Other important policies

mentioned that are related with the process were also the EU Floods Directive (2007), the Spatial

Planning and Landscape Protection Law, published in 2004, and the 2006 Valencian Community

Landscape Regulation. In addition, the Water Programme created to prevent siltation and ensure the

quality of inputs to the Albufera Lake, but also to promote upstream reforestations and to develop flood

control measures in the area.

Page 26: Earth System Science Chair Integrated Water Management group

26

6.2 The ‘Noordwaard’ Polder

The ‘Noordwaard’ is an agricultural polder of 2,050 hectares (Figure 7), established in the Biesbosch tidal

system south west of Werkendam in the Netherlands (Pleijte, Schut, & During, 2011; Marc Schut et al.,

2010). The term polder in the Netherlands is used to refer to the low-lying areas, which by the use of

pumps, canals or flood defences (embankments or dikes), were reclaimed from either the sea or rivers

(Marc Schut et al., 2010; Stijnen, Kanning, Jonkman, & Kok, 2013). Before the current conditions the area

was characterized by consisting of a fine network of creeks in the higher alluvial parts (Rijsdorp, Adegeest,

de Kuijer, de Koning, & Gaastra, 2006). Former creeks are still visible however, due to the presence of

small dikes and differences in the terrain heights (Middelkamp, 2011). Livestock and farming became only

possible in the area after the broader creeks were cut off and the flows of water interrupted, with the

embankments of the surrounding rivers, the establishment of dikes, and the stepwise location of polders

(Rijsdorp et al., 2006).

The ‘Noordwaard’ is specifically located between the rivers banks of the ‘Nieuwe Merwede’ in the north

and the ‘Bergsche Maas’ in the south, both part of the Rhine river Delta (Huisman, van de Rotten, Sanders,

Yan, & Xia, 2004; Marc Schut et al., 2010). In 2005 there were a total of 200 inhabitants, 49 houses and 26

farms (RWS, 2009). The farms

were diverse consisting of arable,

dairy, horse and even mixtures

between dairy and arable

designated lands (Middelkamp,

2011). Based on Schut et al.,

(2010) the National Park

Biesbosch also borders the

south-west part of the polder.

This area declared a Natura 2000

site consists of willow woods and

wide creeks (Middelkamp, 2011).

In 2008 a project to convert 600

hectares of the polder’s

agricultural land to nature was

completed. This deserves special

mention as it resulted in the

promise made by the Brabant

Province to the farmers, of not to

expropriate anymore land in the

near future (Marc Schut et al.,

2010). However, as it will be

explained in the following

sections, the final consented eco-

engineering project (part of the

Room for the River) included

such measures.

6.2.1 Actors

The same as with the previous case, there were several actors who became involved in the process that

led to the particular final consented eco-engineering project for this area. These in general constituted

governmental units, local authorities, universities, several platforms, local farmers and inhabitants,

amongst others (Table 5).

Figure 7. Geographical location of the ‘Noordwaard’ polder.

Source: van den Brink (2009).

Page 27: Earth System Science Chair Integrated Water Management group

27

Table 5. List of actors relevant in the process leading to the eco-engineering project in ‘Noordwaard’ Polder. Source: Middelkamp (2011); Huisman et al., (2004); Paassen et al., (2011); Schut et al., (2010); interviews.

Government Units Regional and Local Authorities -Dutch Government: The parliament is responsible of supervising the plan for room for the river projects while the Cabinet makes the final decision (PKB). -Ministry of Transport and Water Management (V&M): Policy makers and implementers of initiatives in the field of flood protection. Other relevant ministries: -Ministry of Housing, Spatial Planning and the Environment (VROM) -Ministry of Agriculture, Nature Management and Fisheries (LNV) -‘Rijkswaterstaat’ South-Holland: This is the Dutch Directorate of General Transport, Public Works and Water Management (RWS). They are the managers of the Dutch river systems and responsible for the definition of the expected water levels. Supervisors of the Project Group ‘Ruimte voor de Rivieren’. -‘Ruimte voor de Rivieren’ (Room for the Rivers): Project group that includes the designers of the sustainable and safe solutions (eco-engineering projects) that should meet with the required or established objectives. Composed also by the ‘Bureau Benedenrivieren’ (Bureau Lower River Region) and the ‘Bureau Bonenrivieren’ (Bureau upper River Region).

-Water Board Rivierenland: Developers of the master plan for the area. Supervisors of the safety of the dykes amongst other attributions. -Hoogheemraadschap: responsible for the flood defence system. Other relevant authorities: -Province of Noord-Brabant -Municipality of Werkendam

Universities Environmental groups -TU Delft University: The hydraulic engineering and water management group assisted in the process by generating alternative projects based on natural, hydraulic, socio-cultural, legal and economic criteria. -Wageningen University: Scientists became involved and performed a research through the university’s ‘science-shop’ funds. Alternative solutions were developed based on a qualitative landscape ecological system analysis with an strategic insight of the democratic procedures.

Environmental groups: pressure groups fighting for the conservation of the environment.

Organized groups, Boards and Platforms Citizens -‘Bewonersvereninging Bandijk’ (Residents Association): Platform composed by the residents of the area. This group is known to have agreed to the proposal presented by the Rijkswaterstaat. -‘Klankbordgroep’ Noordwaard (Advisory Board): Established board with representatives of entrepreneurs, residents, nature groups, recreation and the ZLTO. The board is responsible to provide with advise, support and feedbacks over the interests and results in relation to the realization of the project. -Platform ‘Behoud Noordwaard’ (Platform Save the Noordward): Group of farmers and inhabitants opposing the plans of the Rijkswatersaat. Advised by the Faculty of Hydraulic Engineering of Delft University and Wageningen University. -Southern Netherlands Farmers’ Organization (ZLTO): Organization of farmers to provide with knowledge and support for the collective interests and concerns.

-Farmers: Farmers living in the polder whose land are affected by the proposals of the Rijkswaterstaat. Main growing products: potatoes, beets, grains, vegetables and grass seed. -Public companies (drinking water and electricity company) -Association for inland shipping -Residents

Other Advisory Bodies - Investigation and Verification Office of the Senate (Research and Verification Commission): Commission that advises and supports the Dutch government through research and by assessing research offered to the government.

Page 28: Earth System Science Chair Integrated Water Management group

28

6.2.2 Action situations

As previously mentioned in the particular case of the ‘Noordwaard’ the final consented solution was

depoldering. This will turn the area into a multifunctional space with differential flooding frequencies to

ensure the safety in the surroundings (RWS, 2009). To reach such solution a process of several years

influenced by different levels of action situations influenced by particular rules in-use (constitutional,

collective-choice and operational) preceded. The same as in the ‘Rambla del Poyo’ case, during the process

both formal and informal actions were engaged. The process consisted of the prescription and application

of national policies and rules, and there was clearly a participation of actors to be involved at the

operational level, in action situations where rules in the collective-choice level were being defined (Figure

8). The same as in the previous case, shaded circles denote formal and informal actions that became

intertwined during the process.

Relevant floods events and initial procedures

The Dutch are widely known for their long history in water management and flood control strategies

(Klijn, van Buuren, & van Rooij, 2004). However, the 1953 flood event in the southwest of the Netherlands

is relevant, as it influenced significantly the way water is currently dealt in the country (Marc Schut et al.,

2010). After this flooding event the Delta Committee was installed (Gerritsen, 2005). With the generation

of The Delta Plan, hydrological measures were suggested and a normative protection system based on

flood risk was established (Gerritsen, 2005; Klijn et al., 2004; Marc Schut et al., 2010).

Despite these settings, the water periods of 1993 and 1995 questioned the flood protection measures

against high peak discharges in the Rhine and Meuse (Klijn et al., 2004; Marc Schut et al., 2010). It is not a

surprise why interviewed actors also recall these particular events, as over 250,000 people were

evacuated when water levels flowed in areas with or close to human settlements (Marc Schut et al., 2010).

These events showed that dyke’s stability in polders could not be guaranteed based on the current

discharge design (15,000m3/s for once every 1,250 years); also that such events translated in great

economic losses (Huisman et al., 2004; Klijn et al., 2004; Marc Schut et al., 2010). Interviewees and the

literature highlight these moments as a turning point in the Dutch flood control strategies. It was

mentioned that it triggered the political momentum to readdress the subject but under new approaches

and considerations.

So after the 1995’s flood peak event, the normative discharge of the Rhine River was intensified and

extended to include climate change scenarios (Klijn et al., 2004). This led to a change from the discharge

regime of 15,000m3/s (with a probability of 1/1,250 years) at the Lobith, to new water discharge

capacities of 16,000 m3/s (2015-2050) to 18,000 m3/s in the long term (2050-2100) (Klijn et al., 2004;

Marc Schut et al., 2010). But in order to cope with the higher discharge norms, rising the dykes was not

considered a feasible choice. This because houses in the country were built already in or near dykes. Also

because if water levels are to surpass higher dykes, this can result in increased flow velocities that can

cause more damage. (Huisman et al., 2004)

Therefore, these contexts led to the creation of a new Policy by the Dutch Ministry of Public Works and

Transport, aiming to explore how to meet the new safety levels (Huisman et al., 2004; Middelkamp, 2011).

This was how the ‘Ruimte voor de Rivier’ (Room for the River) concept was introduced. Between this time

the Commission Water Policy for the 21st century (Commission WB21) published a study, where in

addition of recommending strengthening of the dykes, the government should explore spatial measures to

allocate water while increasing the spatial quality of the rivers’ area (Marc Schut et al., 2010). Also, that

such measures should include during the planning the integration of the general public to create

awareness and support (Marc Schut et al., 2010). This is important to mention as in outlined what would

become latter the main guidelines for developing the Room for the River Programme and the devising of

the eco-engineering project for the ‘Noordwaard’ polder.

Page 29: Earth System Science Chair Integrated Water Management group

29

Figure 8. Timeline of relevant events leading to the eco-engineering project in the ‘Noordwaard’ Polder.

Page 30: Earth System Science Chair Integrated Water Management group

30

From vertical to horizontal solutions: making it happen

The concept of Room for the River in itself represented a paradigm shift by moving from vertical

protection measures (dykes) to horizontal solutions (create space for water). In order to make it a reality

a ‘Planologische KernBeslissing’ (PKB) or Spatial Planning Key Decision procedure was organized to

ensure a decentralized policy process (Middelkamp, 2011; Schielen, 2006; Marc Schut et al., 2010). This

procedure was highlighted by one interviewee and in the literature of consisting of formal actions

mandated by law where four steps can be identified: 1) the government publishes a set of coherent

measures (proposal), 2) a consultation process is developed to gather formal reactions of the public, 3) a

publication of adapted plans is elaborated which then leads to the development of the official Cabinet’s

point of view, 4) and based on this proposition the Parliament and Senate discusses and approves the

plans, resulting in a final formal government decision (Middelkamp, 2011; Schielen, 2006; Marc Schut et

al., 2010).

But it was also found in the literature and one interviewee mentioned the connection of developing in

parallel an Environmental Impact Assessment (EIA) (Middelkamp, 2011; Marc Schut et al., 2010). This

procedure (Figure 9) was also consulted formally with the general public and the outcomes presented to

the Parliament for final approval (Middelkamp, 2011). It can be stated that this particular process is

comparable in a way to the processes developed during the latter stage in the case of the ‘Rambla del

Poyo’, when the proposals from the regional authorities were also put to test through formal consultation

processes before official approval.

Figure 9. Overview of PKB procedure and EIA for the Room for the River Programme. Source: Middelkamp

(2011).

In this case, however, the official government proposal (PKB 1) was a result of a process that started

earlier (2001), and consisted of government initiatives aimed to explore the opportunities and

possibilities of translating the concept of Room for the River into practical measures. Based on Schut et al.,

(2010) and his interview, a national resilience study was developed (2000-2002) that included 600

potential measures based on three criteria: 1) sustainable safety (based on a discharge capacity of 18,000

m3/s), 2) spatial quality based on the government’s Fifth National Policy Document on Spatial Planning, and

3) a cost-benefit analysis. These measures were ranked based on scores assigned to each indicator. The

study in addition included the use of a hydraulic model called ‘blokkendoos’ (box of blocks) to test the

hydraulic effects of combined measures. (Marc Schut et al., 2010)

During this time depoldering the ‘Noordwaard’ was not officially considered in the first list of measures.

Instead in the region the development of two green rivers for the longer term were proposed (Marc Schut

et al., 2010). In this case green rivers are measures similar to the green-ways described in the previous

case. These according to van den Brink (2009) consist of two channels in the landscape where water can

flow after a high peak event. Despite these measures were considered hydraulically effective, they were at

the same time controversial due to their social and environmental impact (Marc Schut et al., 2010).

Interviewees also elaborated over this point by stating that such measures were not feasible due to the

characteristics of the landscape and peat characteristics of the soils.

Page 31: Earth System Science Chair Integrated Water Management group

31

The resilience study, however, was not the only initiative developed by the government during this phase.

Mentioned by interviewees and in the literature, interactive design and planning sessions were also

organized to prepare the regional advice and define more concretely the possible measures (Middelkamp,

2011; Marc Schut et al., 2010; van den Brink, 2009). In doing so, the steering group ‘Ruimte voor de Rivier’

(Room for the River) together with the ‘Bureau Benedenrivieren’ (Bureau Lower River Region) engaged in

a negotiation process with different actors. These consisted of national, provincial, and local governments,

water boards, representatives of farmers, residents and other groups; with a degree of organization and

representation (Huisman et al., 2004; van den Brink, 2009). The principle behind it was now to ‘zoom in

the scope’. In order to facilitate cooperation the box of blocks model was also used primarily as

communicative tool. In general, this can be referred then as specifically the moment in time when

dialogues and negotiations moved to local contexts, resulting for the ‘Noordwaard’ comprising area in the

preliminary definition of possible projects.

Depoldering, a possiblity in the ‘Noordwaard’?

There was a clear strategy in developing the initial approach for the lower river region, were the case

study is located. The interviewee, who became involved in such procedures from the government side,

expressed that the main criteria was to focus on measures for the longer-term discharge (18,000m3/s). He

argued that “measures to comply with such a standard in the future will have to be developed anyway...

therefore, why not take it as a guiding principle and do it properly from the beginning”. Another mentioned

criteria was to consider the local interests of actors (farming, nature development, ecological demands,

economic development based on water recreation) (Edelenbos, Roth, & Winnubst, 2013). This

interviewee mentioned in addition that the challenge relied then in getting the local actors to understand

this was a wise approach.

The overall process comprising the initial interactive design sessions and planning process was outlined

by the government interviewee, of consisting of both formal and informal activities. Part of the formal

activities based on the interviews and literature review refer to the initial four step-wise design sessions

that were officially developed during 2002-2004. These aimed to determine specific working areas and a

general vision for the region (Edelenbos et al., 2013). The first of this sessions was conducted to explore

with actors, different ideas which were translated into maps (Marc Schut et al., 2010). During the second

session the maps were re-discussed resulting in 42 potential measures for the lower region (Marc Schut et

al., 2010). At this moment short and long term measures were discussed, but the adequacy of short-term

measures to comply with future safety objectives was brought into question (van den Brink, 2009). As a

result of how strategically the long-term vision was handled by the facilitators in the region, two

interviewees pointed out that actors realized after this process, that a major spatial measure might be

preferable. Interviewees also mentioned that although it was not considered formally, this was when local

actors started to consider depoldering the ‘Noordwaard’ as possible option. The other long-term solution

was the development of a green river through the Land van Heusden en Altena, but according to one

interviewee between this two, depoldering was by then preferred by most actors.

Based on Schut et al., (2010), after these two design sessions the 42 measures were presented to the

regional steering committee for the lower region. This resulted at the end in a classification of depoldering

the ‘Noodwaard’ as a controversial measure (Marc Schut et al., 2010). From this event what is important

to mention is that it brought the idea of depoldering to the formal discussions. Interviewees highlighted

that many actors despite recognizing its potential, at the same were concerned in relation to the promise

made by the Brabant Province and how such a measure will affect the activities and actors living in the

area. However, as the two last design sessions continued and negotiations proceeded, depoldering the

‘Noordwaard’ was changed at the end from controversial measure to the officially preferred solution

(Marc Schut et al., 2010).

Page 32: Earth System Science Chair Integrated Water Management group

32

Based on interviews at this moment most of the actors had agreed on such a measure but not all were

sharing the same position. In addition, such alternative was preferred under the condition that it became

part of the short-term policy programme (forerunner status: clarity given in two years); residents and

farmers will remain living and performing their regular activities; or if reallocated that reasonable

compensation will be granted; and that they will be involved in the planning process (Edelenbos et al.,

2013). So after this process a subsequent planning procedure continued to develop more specifically the

project and to devise how it will be implemented. Based on the interviews this process consisted again of

formal public meetings and design workshops to discuss the plans with the local and regional actors. The

RWS served as an initiator and it was during these discussions that the ‘Belangenvereniging Bandijk’

platform and the ‘Klankbordgroep’ were established. This latter with the main objective to inform the

different parties, monitor and evaluate the activities, resolve conflicts, and to become a communication

platform between institutions.

The sessions developed between 2005-2006 aimed to discuss three alternative projects for the

‘Noordwaard’ to start elaborating their respective Environmental Impact Assessment (EIA). The sessions

consisted of workshops with farmers, residents, the Southern Netherlands Farmers’ Organization (ZLTO),

and interest groups. From 2006-2007 the EIA and the drafting of the design vision was carried out in more

detail. This included another consultation round with several design workshops and residents meetings.

Informally field visits, citizen evenings, and ‘kitchen-table’ talks with residents and farmers were

developed to discuss their opinions and individual land living preferences after depoldering. The output

from this process was presented to the State Secretary in 2007 as the regional alternative. The EIA was

also finished around the same time. It was now left to the State Secretary to decide if the devised vision

would become the preferred alternative of the EIA and thus the National Project Decision. (van den Brink,

2009)

Based on the government facilitator interview at that time, having one-on-one dialogues with farmers and

other actors in an informal setting, contributed in building trust and information sharing. This helped

lobbying the different ideas and building channels of communication where local concerns and interests

could be shared. He also mentioned that even during the formal activities strategies were carefully

considered in how the workshops were handled. For example, all actors sit on a same working table to

create an atmosphere of equality and approacheness. During these phases it has been stated that the

cooperation between actors was enabled by the strategies chosen in how information was managed (open

and full information provided by facilitators; local actors wanted to be informed as soon as possible)

(Edelenbos et al., 2013).

Following these actions during 2007-2010 discussions were held in relation to the real estate strategy and

the compensation for loss value and opportunities to continue with agricultural activities (implementation

plan). This process took time which in turn translated in farmers and local residents to increase their

uncertainty about the process (van den Brink, 2009). This became a product from a change in the way

negotiations were dealt. During these years the government facilitators were changed and the process

became less open and even closed. From the government point of view the innovative way the facilitators

were handling the earlier process represented a change in traditional procedures (set first a course for a

certain result and then involve the social enrollment). It has been stated that the government before

committing and not being able to comply, chose to follow more a risk avoidance approach for the

remaining part of the process. This meant changing back to ‘normal’ procedures, which translated in a

limited access to local actors during the definition of rules for the compensation, damage and compulsory

purchase. The approach changed because such decisions could set implications for the other Room for the

River projects. (Edelenbos et al., 2013)

Page 33: Earth System Science Chair Integrated Water Management group

33

According to the interviews and supported by the literature, however, around the time when the process

to develop more specifically the project started, there was a group of farmers and residents who believed

their interests were not taken into consideration and that the exploration of other solutions was

undermined in the previous process. This motivated them to establish the ‘Platform Behoud Noordwaard’

(Platform Save De Noordwaard) in 2004. The objective of the platform was to convey their interests and

opposition to the government’s plan in a constructive way. This was done by elaborating alternatives,

which could also meet the Room for the River’s objectives. To do so they partnered with specialists who

could assist them in this case. This was how TU-Delf University and Wageningen University became

involved in the process. (Middelkamp, 2011; Pleijte et al., 2011; Marc Schut et al., 2010; van den Brink,

2009)

The platform mobilized a first research in cooperation first with TU-Delf University (Pleijte et al., 2011;

Marc Schut et al., 2010). A research project was conducted where alternatives to depoldering were

evaluated based on natural, hydraulic, cultural, legal, and economic conditions (Huisman et al., 2004). The

outputs showed a more cost-effective alternative (€100 million) compared to others (€280-360 million)

including the government’s proposal at that time. This particular alternative measure consisted of an inlet

and outlet structure that will allow flooding in the area only when necessary (with a probability of once in

500 years). In addition, such measure will make the area able to maintain its current living and

agricultural conditions. (Huisman et al., 2004) Based on Schut et al., (2010) despite this research created

space to reopen dialogue, it didn’t’ translate into anything tangible in the region. However, interviewed

farmers and the literature mentioned that in 2005 another strategic cooperation by the platform was

established with Wageningen University. This was made possible by the habilitation of funds to perform a

new research via the University’s ‘science-shop’. (Pleijte et al., 2011; Marc Schut et al., 2010)

The strategy to develop this research was based on “1) underpinning the Platform’s alternative with a

qualitative landscape ecological system analysis, 2) critically reviewing the government’s hydraulic model

and its basic assumptions, and 3) criticizing the democratic process and finding ways to penetrate political

agendas” (Pleijte et al., 2011). As result of this process “the platform’s alternative was proactively defended

by providing with answers to arguments the Ministry would use to contest the alternative plan” (Marc Schut

et al., 2010). However, mentioned by interviewees and in the literature, the possibilities of such efforts in

translating into other tangible alternatives for the area were again hindered by several events and factors:

1) The PKB procedure (phases 1, 2 and 3) had started already in 2005 based on the government’s

proposals

2) The project was also granted a ‘Forerunner Status’ in 2005 (speed up the process)

3) The unity of members in the Platform weakened as members were asked by the BLRR to become

co-operative with other local actors who were willing to comply with the other on-going efforts.

In addition, that clarity soon will be given with regards on the reallocation of houses,

expropriation of land, and functional activities in the area. (Pleijte et al., 2011)

4) Despite a research was performed in 2006 by the Investigation and Verification Office of the

Senate to evaluate the Platform’s alternative against the government’s proposal, the new

alternative was found to general to compare. Although the Commission agreed on some of the

findings, the process formally was already too advanced to change the on-going course. This

initiative was a result from a clarification hearing organized after the received contestations from

the Ministry of Transport, Public Works and Water Management and BLRR over the proposed

alternative developed by Wageningen University and the Platform. (Pleijte et al., 2011; Marc

Schut et al., 2010)

Between the last semester of 2006, the Room for the River became approved by the Parliament and the

Senate, leading to the final approval by the government in 2007 (PKB 4). The final specific project decision

of depoldering the ‘Noorwaard’ was made officially in 2009 and its implementation started in 2011 to be

finished in 2014 (RWS, 2009).

Page 34: Earth System Science Chair Integrated Water Management group

34

The consented eco-engineering project

As previously mentioned the final project consists of transforming the ‘Noordwaard’ polder into a

multifunctional area with differential flooding frequencies (RWS, 2009). High peak water discharges from

the ‘Nieuwe Merwede’ will be allowed to flow through the area in the direction to the ‘Hollands Diep’

(RWS, 2009). But in order to allow such functions, the project was elaborated to comply with the following

objectives: 1) reach a minimal hydraulic water level reduction of 30 cm at Gorinchem, 2) include a

sustainable perspective for farmers, 3) current inhabits are allowed to stay, 4) and improve the spatial

quality of the area (RWS, 2007). This led to the development of a new safety design where housing and

infrastructure, became adjusted to open channels with tidal influence and flooding during high waters,

without endangering the people, goods and livestock. In addition, such design allowed the creation of

opportunities to strengthen Natura 2000, via the creation of nature and recreational areas. (RWS, 2009)

The core of this particular design relied in finding a safety layout acceptable for all the affected (private

sector, people, families, entrepreneurs, farmers, administrators and public decision makers), while

considering that part of the area will flood several times a year, and other might be flooded under a

frequency of once every 100 years or up to 1000 years (RWS, 2009). The ultimate design (Figure 10)

includes the location of high-diked polders in the northwest and southeast part of the ‘Noordwaard’.

These will be used for living and agriculture. New houses in this area are planned to be located at the edge

of the polder. In the northeast the flow-through area will become the intertidal zone. Low dikes will bind

the intertidal polders, and dwelling mounds are planned on which new houses will be built. In the eastern

part of the flow-through area the polders will be turned into wet grasslands and these will be used for

nature development and cattle (which can flee to special areas during high waters). Other polders in this

area will consist of dry grassland, which can be mainly used by cattle and will be well drained. Creeks will

separate the polders in order to return in a way the spatial layout of the area to its historical condition. On

the banks of the creeks vegetation will be established consisting of trees and reeds. A sloped dike

surrounded by a willow field will protect a historical landmark in the area consisting of a fort. Some areas

will not face any change and will be used as grassland for cattle. (Middelkamp, 2011)

In the area currently 6 to 7 farmers (polders) are staying compared to the original 26. It was mentioned in

the interviews that a new initiative was created to explore the possibilities and define the ‘rules’ for the

future use (agriculture, cattle), organization and management (e.g. criteria for allocation, valuation of

landyield capacity, monitoring, rent fees) of the new intertidal polders. With this regard it is worth

mentioning in general that by far the most preferred alternative for the organization and management is

to implement a model that will allow collective collaboration to grow. It was also mentioned that now as

the implementation phase has started RWS, ‘Klankbordgroep’ and the ZLTO continue to oversee the local

operational activities and engage in regularly meetings with other concerned actors to discuss emerging

collective interests or problems.

Page 35: Earth System Science Chair Integrated Water Management group

35

Figure 10. Landscape Plan for depoldering (eco-engineering) the ‘Noordwaard’. Source: modified from Ruimte voor de Rivier (2009).

Page 36: Earth System Science Chair Integrated Water Management group

36

Costs and benefits associated with the eco-engineering project

Based on the interviews the option was given to the farmers to either move or stay in the area. However,

to stay implied that some areas would be allowed to flood several times a year. This meant that

agricultural possibilities would be compromised. These conditions led some farmers to consider that

moving could then result in their best option. It was mentioned that due to the forerunner status of the

project, some farmers believed for example they could get better off by receiving an extra ‘bonus’ for

providing safety to others. Overall, the expropriation and compensation process in the end was perceived

very subjectively. While for some it was mentioned to be relatively fair for others it could have been

developed better as higher expectations were raised. The fact that this process took several years, created

an atmosphere of uncertainty and doubt, turning into an emotional process to the local people.

Interviewees mentioned that if chosen to move voluntarily, farmers received compensation over the value

of their land. However, if chosen to stay then the government will run the costs of reallocation or for the

works to provide safety to their houses and buildings (if needed). In addition, for those farmers staying it

was agreed that they would benefit from a special insurance. This accounts for the retribution over

possible damages caused by future floods. However, this insurance was granted over the basis that only

the holder of the land could claim. This could be inherited but not transferred over selling the land. The

total budget assigned to the project was of € 300,000 million (RWS, 2007).

In relation to the benefits based on the interviewees the idea was to enhance the spatial quality of the area

by restoring old creaks and the natural environment. Local actors mentioned that this will attract tourists

and it can open new possibilities for them. It was mentioned for example that new small business could be

created by renting canoes, selling their growing products, enable vacation houses or floating houses.

There are already entrepreneurs in the area, one who owns a campsite and another one with a horse

stable that could benefit. The creation of bike lanes was also mentioned as another positive value. In

addition, with the habilitation of the middle polders opportunities are going to be created to develop more

agricultural activities for those who choose to stay. In this sense, already initial attempts have been

developed to assign rent and management fees. These have been established based on the different types

of polders and the yielding capacity of the soils, ranging from the highest to the lowest: dry low quay

polders, wet low quay polders, inter tidal flat, and inter tidal creek areas. Furthermore, it was mentioned

from the interviews that other benefits are associated with supporting the Natura 2000 network, as the

area is adjacent to the National Park De Biesbosh.

Page 37: Earth System Science Chair Integrated Water Management group

37

7 Analysis In Chapter 3 the IAD framework was described as a nested arrangement of action situations and rules in-

use where the broader scope of activities basically aims to identify more collective behaviours or actions

at the subsequent levels (M. D. McGinnis, 2011). In both case studies rules in-use were found at the

constitutional, collective-choice and even operational levels. These are related to the different action

situations (described in Chapter 6) that made up the process leading to the final and consented eco-

engineering project(s). In the following sections the identified rules in-use for both case studies are

presented.

7.1 ‘Rambla del Poyo’: Rules in-use In this section the rules in-use for the ‘Rambla del Poyo’ are described. In this case those rules correspond

mainly to constitutional and collective-choice action arenas. Nonetheless, despite rules at this latter level

are meant to define operational level action arenas, it can be expected that operational rules will be

further defined once implementation of projects commence. In order to represent the identified rules in

this case, these were classified according to the types of rules (Figure 11) that directly affect the

components or types of action situations they relate to (boundary, position, choice, information and payoff

rules).

7.1.1 Boundary rules

There are several actors that became part of the process. In the case of the governmental authorities

(regional and provincial) what determined their involvement and role in the process, comes from the

principles of their own constitution and institutionalization. Nonetheless, it can be stated that there were

formal4 and informal rules that in a way had an influence and also determined the approach this

institutions took as the crafting of solutions developed. These also determined the actors that during the

process were considered, and how or to which extent their participation was included.

In terms of formal rules the 1985 Directive on the assessment of the effects of certain public and private

projects on the environment, with its consecutive appropriation by the Spanish authorities, is relevant to

the case. This because it made it a requisite that a project that impose significant effects over the

environment, should meet specific environmental requirements and be summited to a public information

process before an Environmental Impact Declaration (EID) is emitted. As a result of this regulation, when

the first proposal (1995-1996) became conditioned, this significantly influenced the scope and the

approach the competent authorities decided to implement onwards. In addition, this regulation also

defined in a way the actors and sectors, that became part both during the formal and informal dialogues.

This since one of its mandates indicates that concerned actors of a particular project should be consulted

through a formal public information process. Thus, municipalities, environmental groups, inhabitants,

farmers, public services, amongst others became involved (Annex 5).

Another platform that in a way allowed the possibility of a particular actor (in this case the environmental

groups) to enter the process and engage a more formal participation, was the European Commission of

Environment, when the complaints from this group were made official. But yet one more formal rule that

helped the shaping of the positions and roles of those who became involved was the PATRICOVA. The

main objectives included in this plan stressed the need to develop measures for a return period of 100-

500 years, in addition, to develop measures that would impose the least environmental impact. Therefore,

it also influenced the approaches taken by both the authorities and the consultancies (AMINSA and

TYPSA).

4 ‘Formal rules are those backed by the law, implying enforcement of rules by the state, while informal rules are upheld by mutual agreement, or by relations of power or authority, and rules are thus enforced endogenously’(Cousins, 1997).

Page 38: Earth System Science Chair Integrated Water Management group

38

Figure 11. Rules in-use influencing components of action situations at constitutional, collective-choice and even operational level leading to eco-engineering

projects in ‘Rambla del Poyo’.

Page 39: Earth System Science Chair Integrated Water Management group

39

In the light to develop solutions that would comply with the objectives of this Plan, it can also be stated

that this motivated the inclusion of another important actor who could provide with further technical

assistance, the Technical University of Valencia. Based on the interviews, for the informal negotiations and

dialogues held to explore and define the best alternatives, the criteria to define who should be the main

actors to include was based on:

Municipalities that based on the first exploration of solutions, where identified with the highest

flooding risks and economic impacts

Secondly, actors whose territorial boundaries would become affected (expropriation) with the

implementation of the alternatives

Municipalities with high political weight because of the pressure they receive from influential

organized groups (i.e. farmers downstream the basin)

And actors who during the process took a more active role (i.e. Municipality of Cheste)

7.1.2 Position rules

In the area traditionally the national, provincial and regional state authorities hold the main interest and

responsibility to administrate and control the initiatives related to hydraulic projects. Since 1934 the main

institution responsible has been the Hydrological Confederation of Júcar (HCJ), a body under the Ministry

of Environment. Despite this organism still remains the central authority at a regional level, since the

1980’s the administrative framework has experienced a series of changes. New policies and regulations

were introduced or amended and new bodies institutionalized. This has resulted in a polycentric level of

governance in relation to any type of hydraulic initiative in the area. Currently authorities from different

levels (i.e. municipalities and other sate bodies and ministries) and types (i.e. environmental, landscape,

and transport sectors) have now a particular role, set of positions and responsibilities. In addition, other

actors have become part of the process (i.e. university, environmental groups, etc.). As a result from the

positions or roles taken by the actors, but also from the previously explained action situations in which

they interacted, the actors involved established distinctive relations between each other. Such relations

can even be depicted as those that developed from the formal or informal rules influencing the action

situations in which they interacted (Figure 12).

Figure 12. Map of actors and their relations leading to eco-engineering in ‘Rambla del Poyo’. Both formal

and informal relations are represented by dashed lines; continuous lines represent only formal relations.

Page 40: Earth System Science Chair Integrated Water Management group

40

Before the eco-engineering projects in the area the development of projects in this field followed mainly a

unidirectional and top-down approach. Regional and provincial governmental authorities were the main

and responsible actors, with possibly consultancies assisting in the development and realization. Other

actors were rarely considered if not included throughout the process. With the development of the eco-

engineering projects the start of the process followed the same line. But it changed as new regulations

became official and new objectives were established. This changed the positions for some the actors, in

addition of involving new actors with particular roles or influences during the process.

As previously mentioned the HCJ has been the governmental authority, responsible of leading and

monitoring the execution of hydraulic projects. In the beginning the role of the institution was to lead and

monitor the process according to procedures and current regulations: public call to develop the project,

public information process, tender process once approval from EID and execution. When new regulations

enter into force and new objectives or modifications were required, the institution took an additional role

and that was to facilitate and promote platforms to include other actors in discussions and negotiations to

explore new solutions. In addition, the HCJ served an important role in channelling the state funds that

enabled the process.

The Ministry of Natural, Rural and Marine Environment was also a key actor in the process, in terms of

ensuring that objectives are met, environmental requirements fulfilled and other relevant legal and social

conditions were indeed formally addressed. The evaluation, resolution and recommendations are

presented via the EID. Therefore, as part of the process it has been the institution that ultimately has hold

the power of either conditioning (fist project) or approving its realization (Phase I of initial project, and

the final eco-engineering projects).

The European Commission of Environment deserves special mention as for the process it had a relevant

position. In this case by fulfilling its mandate of investigating complaints presented by civil society, where

possible European Union law has been infringed. When the complaint was made it reinforced the

redirection of the approaches taken, more specific with the definition of clearer environmental objectives

the projects should meet. This action was the result of the role environmental groups adopted during the

process, in ensuring that the natural and ecological values were protected with the implementation of the

project. Concerned of the consequences of the first project (1991-1995) one particular environmental

group (Ecologists in Action-Agro) took action by presenting the allegations to the European Commission

and therefore posed a very influential role.

Once the settings were in place for the search of new projects, the civil engineering consultancies

(AMINSA and TYPSA) took also a different position. For the region the government authorities lack of

sufficient capacity to develop themselves these tasks. Therefore, they rely on private consultancies that

before would be in charge of drafting the projects based mainly on a technical-hydraulic basis, with their

respective environmental impact study. In the search of solutions that could comply with new safety

standards and environmental objectives, these actors were then faced to work on a broader basis. Both

consultancies now had to work considering other social preferences and the requirements of new

regulations. They also became involved with relevant actors (farmers, municipalities and environmental

groups), as part of a strategy to discuss the interests and concerns in the search of defining the best

solutions. In the case of AMINSA a key opportunity was found by working with the Polytechnic University

of Valencia (PUV), when testing the effects of the possible solutions with use of the latest hydraulic

models. Therefore, the PUV in this case introduced a new role in the process: the role of research in

decision-making.

There are 32 municipalities in the area, however, not all became involved or had a particular role in the

process. Their position was to ensure that the conditions and space for development growth within their

limits was not compromised. In this sense they looked after the land affected by the projects and how this

would affect the interests of other local actors.

Page 41: Earth System Science Chair Integrated Water Management group

41

They also seek to explore for alternatives that would bring them other benefits (such as recreational

spaces and bike lanes to go along the solutions). In most cases the municipalities exercised a passive role,

in the sense that they became involved up to the extent, the developers of the projects included them

during the conducted informal dialogues. In other cases, they exercised a more active role throughout the

process by manifesting their concerns; putting pressures and requesting further clarifications and

dialogues. This was for example the case of the municipality of ‘Cheste’ by having influenced at the end the

complete discard of the reservoir as a possible solution. Also, the actions taken by the platform ‘per un

Barranc Viu’ supported by the municipality of ‘Paiporta’, when works for Phase I initiated and the locals

wanted to ensure a more ecologically sound approach instead of the original ‘hard-works’ approach.

It is worth mentioning that as the negotiations with the municipalities were developed, the interviewed

actors in charge of the project indicated that in most of the cases there was an identifiable change of

perspective in some municipalities. Through the negotiations and dialogues, the municipalities came to a

better understanding of the interconnections of the different proposed solutions, their relevance and the

consequences of not implementing them. This facilitated the negotiations when they were too reserved

about the proposals. In the other hand, some municipalities hold the posture that even with the informal

dialogues throughout the process, they were still left with the impression that because it was a State

initiative, the projects will be developed anyway despite their full consent. For them these platforms for

negotiations were not entirely inclusive as not for all the cases the interests were truly considered. As for

other municipalities they claimed not becoming too involved, as the proposed solutions didn’t affected

directly their boundaries. A clear change in the position of municipalities in the crafting of new solutions

compared to traditional ways is therefore evident through their participation in the informal discussions.

However, during these actions as previously mentioned not all municipalities became involved and their

position to the extent of how much they were included or became influential is relative. During the formal

information process, pretty much the positions by the actors remained the same as before: authorities

published the project, actors have a 30 day term to present allegations, authorities respond and then make

if necessary the amends.

As mentioned before, during the processes leading to eco-engineering projects took place, new regulations

and requirements became official. This made it then a more complex process as new institutions adopted

a role in terms of becoming responsible in dictating if the requirements are met by the project (planning

and execution). These are to name the most relevant: the General Directorate of Territory and Landscape,

the General Directorate of the Environmental Management, and the Department of Natural Areas of

Conservation, all from the Provincial Authority (Generalitat Valenciana). Furthermore, as for the other

actors involved (other sectorial government authorities), their position became clear during the formal

information processes. The presented allegations were to ensure that the preventive and corrective

measures when implementing the project were to be fulfilled.

7.1.3 Choice rules

When looking at the main actions taken for this case, clear choice rules at the collective level (influencing

operational levels) can be outlined. These consisted of the new objectives (flood safety standards,

hydraulic planning, environmental quality and costs/benefits) selected as the main ruling criteria for the

devising of the new projects proposals. After the 2000’s EID which conditioned the initial proposal and in

the light of new regional regulations (PATRICOVA), this scenario motivated the regional authorities (HCJ)

to change their scope and also to set new rules in how the process should be developed. In relation to the

process new choice rules consisted in developers of proposals, partnering with the UPV for technical

assistance, as well as promoting a stepwise process to preliminarily discuss the alternatives with other

local actors. For the steering process the choices were to explore first possible solutions with local actors

and then evaluate them from a technical perspective (UPV assistance).

Page 42: Earth System Science Chair Integrated Water Management group

42

Then based on this assessment preliminary alternatives were again discussed with relevant actors for

feedbacks and to further define them. After these procedures the official drafting or the projects started

which included another round of informal consultation with local actors to discuss specific details before

the formal consultation procedure. In addition, this process included the generation of supplementary

studies and information, which according to official regulations and current law, had to be submitted also

to a formal consultation process.

So during this process there was one clear choice and that was to develop both formal and informal

procedures to engage with the different actors. Informal actions consisted of the facilitation of dialogues

with other actors in order to socialize and negotiate the solutions. As one interviewee mentioned these

actions were developed by choosing a simple pragmatic principle: “to inform about the ideas for the

possible alternatives, that had been already assessed, but still be flexible enough by allowing room for

negotiation”. Following this line, such particular actions were ruled by choosing an ‘informational’ or even

‘consultation’ level of participation with the actors. Another criteria chosen was to dialogue mainly

individually with those actors with power in opinion or that represented a strong opposition. Therefore,

specific interests or concerns were strategically targeted. This action was also realized by the

consultancies, which accompanied the process and were responsible to convey further explanations

regarding the proposed solutions.

Due to the nature of the type of ‘participatory’ process that was developed during the planning and design

phase, some environmental groups and municipalities choose to engage in more active process to express

their opinion and defend interests. This was done by using platforms such as the European Commission of

Environment, as well as pronouncing statements in the media. Also based on the interviews performed to

some Municipalities, by addressing directly the authority (HCJ) and requesting further explanations or

justifications to their proposals. But in general, these groups together with farmers, irrigators and other

competent state bodies, although relatively participated during the planning, their actions were mostly

relegated to analyse the proposals that were presented to them. Also, to manifest their suggestions or

recommendations, in some cases alternative proposals, via written allegations during the formal public

information process. Another strategy other actors [platform ‘per un Barranc Viu’ (For a living Ravine)]

chose to express their opinion, was through manifestations on the constructions sites when works for

Phase I of the project were to initiate. Finally, other main choice rules relate to following the formal

governmental procedures (official evaluation, verification and approval of projects). These mainly were

led and performed by the competent governmental authorities.

7.1.4 Information rules

In this case the channels for communication and information between actors was also governed by clear

identified rules. The overall principle selected by the steering actors was to inform local actors about the

flood safety, costs and benefits, and the environmental considerations embedded in the selection of

potential alternatives. The main strategy for information sharing and generation was to mainly follow one

level (top down) approach. This is supported because although actors were addressed during the initial

planning phase, their participation remained mainly consultative. It has also been stated that during this

phase a stepwise process was developed, since despite according to interviewees local participation was

not truly enabled, still several rounds of informal consultations were developed. The formal consultation

process preceded and so the final projects became officially selected. With the application of such strategy,

therefore, both formal and informal platforms for communication, information transfer and feedbacks

were created. The informal channels mainly consisted of meetings and one-one consultations, which were

aided by the use of indicative tools such as maps. In terms of the level of detail and clarity about the

information during this process it can be stated that this remained somehow restrained.

Page 43: Earth System Science Chair Integrated Water Management group

43

It is important to mention that also only after official documentation was published, that detailed

information about the project proposals was accessible for the public. So specific strategies that defined

how information was shared and divulgated among actors consisted in final official documents and

reports of public access and other informational documents (e.g. meetings minutes, outputs from informal

interactions). However, their ‘public access’ condition was put into question as these were not easily

obtained and the process to access them still remains bureaucratic. This leads to the assumption that for

this case, either the bureaucratic conditions behind the governance context is a limiting factor, or

strategically certain information was kept from the public (during the process and currently).

Furthermore, that particularly the informational inputs provided by external assistance (research

institutions) was used to develop and aid the devising of the government proposals. Since local

participation was somehow limited during the initial phase, some actors used the social media to convey

and inform other actors about their positions.

7.1.5 Payoff rules

There was a clear strategy in evaluating the payoff rules in this case. This consisted in devising a

methodology to evaluate the costs of future impacts if actions are not taken. The outputs from this

approach let to the definition of the cost of damage of one unit of impact (2 euros average annual damage).

From this value an estimation of the total units of impacts and costs was done for each municipality

resulting in a total impact cost for the area of 32 million euros/year. Based on this definition the

municipalities with the most costs were identified and this outline was used to target them with priority

during the negotiations. This approach helped to communicate the ideas in terms of the annual costs that

could be saved if solutions are implemented, aiding then somehow the cooperation of actors.

Another value considered as part of this rules was the estimation of the total costs of implementing the

solutions (including land expropriation, development of the environmental monitoring plan, and the

security and health study). With regards of the values assigned to the benefits that will be gained from the

implementation of the projects, these can be summarized as: the protection against flood risk,

hydrographical planning, functional environmental recovery, protection of the Albufera, river areas for

public use (recreational spaces) and the creation of biological corridors. Clear environmental benefits are

distinguished, however, in this case these have not yet been quantified or further evaluated.

Page 44: Earth System Science Chair Integrated Water Management group

44

7.2 The ‘Noordwaard’ Polder: Rules in-use

In this section the overview of the identified rules in-use for the ‘Noordwaard’ case is presented. The same

as in the previous case, constitutional and collective-choice but also operational rules, are all grouped and

represented according to the types of rules influencing the components or types of action situations.

Therefore, the rules in-use described in the following sections basically refer to the values the involved

actors considered, their positions and choices, information exchanged and the costs and benefits

evaluated at these levels (Figure 13).

7.2.1 Boundary rules

In this case there were also multiple actors that became part of the process from the principles of their

own constitution and institutionalization. In addition, actors who also became involved by the defined

formal and informal rules during the process, which dictated who were allowed to enter action arenas,

their duties and procedures. In terms of formal rules, the 1985/337CEE Directive, with its amend by

97/11/EC, relative to the Environmental Impact Assessment, became also relevant to the case. This

boundary rule allowed the participation of different actors during formal consultation processes. In

addition, since the Environmental Impact Assessment (EIA) for the government proposals were developed

in line with the ‘devised vision’, it not only supported this process but it also allowed the integration and

interaction with other actors during this phase. Worth noting, in this case compared to the ‘Rambla del

Poyo’, this rule was not merely the main driving principle defining the scope, sectors and actors to include

in the process.

Formally what could be mentioned was the main driver for this case in changing paradigms and defining

which actors became part of the process, was the 4th National Policy on Water Management (Policy

Guideline for Room for the River) and the Spatial Planning Key Procedure (PKB). Informal rules

contributed such as the Commission WB21’s advice to include actors’ participation during early planning,

and the State Secretary decision to prepare a regional advice, based on a preliminary consent at local

levels for possible solutions. These elements defined which actors together with their positions were to be

considered or installed (advisory groups).

It is important to mention that for the ‘Noordwaard’ case once the design phase and implementation

started, there were also criteria that defined which should be the main actors to include. This was based

on considering actors of the area that will become directly affected with the project (land expropriation,

reallocation, or with concerned interests). Furthermore, there was also and additional informal criteria

that can be said allowed other actors to enter action arenas. This were the strategies opted by the

Platform Save the ‘Noordwaard’ in searching external, non-governmental assistance to generate

alternative proposals.

7.2.2 Position rules

The same as in the previous case, traditionally national, provincial and regional authorities hold the main

interest and responsibility in relation to flood and water management in the Netherlands. Despite in this

case a type of polycentric governance was already in place, the analysis of the process for depoldering the

‘Noordwaard’, showed that new policies and regulations also changed the roles and positions of installed

institutions. Although the initiation and final decision still remained a government attribution at the

national level, the planning and design process included the integration and participation of different

levels of authorities (province, municipality, water board and other ministries and government bodies)

and other actors at regional and local levels (ZLTO, farmers, residents and others). This represented a

change in terms of how projects to provide national-wide flood safety were developed; in which both top-

down and bottom-up approaches were combined to define the final alternatives.

Page 45: Earth System Science Chair Integrated Water Management group

45

Figure 13. Rules in-use influencing components of action situations at constitutional, collective-choice and operational level for depoldering the ‘Noordwaard’.

Page 46: Earth System Science Chair Integrated Water Management group

46

The same as in the ‘Rambla del Poyo’ as a result from the positions or roles taken by the actors, but also

from the previously explained action situations in which they interacted, the actors involved in the

‘Noordwaard’ case also established distinctive relations between each other. Such relations were also

depicted as those that developed from the formal or informal rules influencing the action situations in

which they interacted (Figure 14).

Figure 14. Map of actors and their relations leading to eco-engineering in ‘Noordwaard’ Polder. Both

formal and informal relations are represented by dashed lines; continuous lines represent only formal

relations.

For the Dutch government a change in positions compared to traditional approaches, relied in initiating a

process were legitimacy was given space. Therefore, this led to the development of activities to explore

possible measures first at the national level. Then to define strategies for steering processes that could

provide with a consented regional advice on more concrete measures. With this approach new roles were

assigned to the RWS (‘Rijkswaterstaat’) and the BLRR (Bureau Lower River Region) where in addition of

their technical positions, these actors also engaged new responsibilities such as becoming facilitators and

negotiators with actors. Thus, this implied that such actors were faced to devise particular strategies to

thrive during the negotiations.

Local and regional authorities for the ‘Noordwaard’ project, apart from engaging in cooperative decision-

making, in general did not engage in major changes in roles. Nonetheless, they had an important position

during the initial phases. They became mainly the first addressed actors when measures at regional levels

started to be considered and negotiated. To get them to understand the interdependencies of water

management countrywide was key in order to facilitate further cooperation and dialogues (at subsequent

levels and phases). Other ministries (VROM and LNV) became also involved mainly as other verification,

evaluation and support bodies to ensure that other sectorial interests were not compromised (i.e.

environmental impact assessments). For the ‘Noordwaard’ case universities became also part of the

process but their role was different. They took a position of contra-expertise providers with the

development of alternative proposals. Also, local residents and farmers in this case took new and different

roles.

Page 47: Earth System Science Chair Integrated Water Management group

47

Instead of being relegated to express only their positions through the formal consultation processes, they

became involved in planning and design activities, thus, assuming a role of negotiators. Some opposing the

government proposals assumed an additional role and that was of strategically partnering with the

universities to become independent proponents of alternative projects as previously mentioned. Key

actors such as the ZLTO and the Advisory board that was established took the main positions of looking

after collective interests and supporters for the different actors involved during the negotiation process.

7.2.3 Choice rules

In general by looking at the process several relevant choice rules can be identified that shaped the main

actions engaged by the involved actors. To briefly mention the most relevant found at a constitutional

level these are: the change of the discharge normative capacity (16,000m3/s to 18,000m3/s in the long

term); new policy approach for water management (moving from vertical to spatial solutions); and initial

exploration at a national level in translating the concept of Room for the River to concrete measures

(resilience study). At the collective-choice level relevant choice rules can be said consisted of the initiative

by the State Secretary for a regional advice consisting of a regional and local steering process. This led for

the lower river region to choose as a tactical approach or strategy, to negotiate with actors measures

based on local interests for the long-term discharge (18,000m3/s).

Depoldering the ‘Noordwaard’ was chosen as a regional measure, under the conditions that local actors

will be given the choice to stay in the area and that clarity over its design and implementation will be

provided in the short term (granting forerunner status). This led to the definition of rules that shaped the

criteria (objectives) for the project, but also the process to develop its design vision and later on its

implementation (include actors in planning and design). As a result of this choice rules all actors became

somehow (based on their positions) involved in actions aiming to discuss and devise alternatives that

complied with the defined objectives and criteria. In addition, they engaged in negotiation and dialogue

activities to reach consensus or exchange information. Furthermore, based on these rules and the choices

made in defining the level (placation and partnership) and processes (formal and informal) for the

participation of actors, these were also allowed to engage in such activities to convey their opinions,

interests, oppositions or recommendations.

In this particular point is worth highlighting the choice made by opposing farmers and residents to the

government proposals. Mentioned already their main choices consisted of forming an organized group,

seek expertise assistance from universities, and manifest their interests and propositions in a constructive

way by presenting alternative measures. To elaborate on this point is worth mentioning a choice made by

the government in response to the alternative proposals presented by this platform. This consisting of the

development of a research by the Investigation and Verification Office of the Senate to evaluate such

proposals against the government’s, as result from the hearing requested by the concerned parties. One

relevant choice rule that determined this process worth highlighting was the selection of closing down the

open negotiations with actors, in relation to the real state, expropriation and compensation discussions. In

this sense the process turned again into a top down approach. The government made this choice since

decisions at this point could set precedents for other Room for the River projects, but also to have more

control about the process and follow again more closely traditional procedures.

Summarizing, choice rules defined the RWS and the BLRR in their positions to exert the main action of

socializing, negotiating and initiating with strategic actors the project planning and design for the region.

The advisory group, ZLTO and residents association were chosen or included to provide support during

these processes. Local and regional authority bodies were approached or came together initially to discuss

preliminary ideas and to explore potential projects. Then other local and regional actors became included

as negotiations progressed and more detailed discussions about the project were being realized.

Page 48: Earth System Science Chair Integrated Water Management group

48

Finally, other main activities that took place during the process consisted of the formal and official

evaluation, verification and approval of projects, ruled by the formal governmental procedures. These

mainly led and performed by the national government (Parliament, Cabinet), except for the formal

consultation process were the public again could convey their positions by presenting formal allegations

or reactions.

7.2.4 Information rules

There were clear strategies during the process in relation to what and how information was shared

between the involved actors. For example, from the initiators of the process the principle was to get across

information that will enable the understanding of involved actors, that a change in the approach for flood

safety was needed, and that in doing so cooperation and collaboration was essential. This led to the

generation of strategies aimed to convey the objectives and criteria selected to achieve such scope.

Furthermore, the mentioned principle was also composed of enabling the participation of actors to ensure

a legitimate process where local interests, preferences and positions were considered. Therefore, this also

defined the strategies that allowed the collection and integration of such informational feedbacks.

In this case it can be stated that during the initial planning activities information was conveyed following a

top down approach. A list of potential measures (national resilience study) was developed first for their

consecutive socialization with other actors at subsequent levels. To do so, indicative and visual tools (box

of blocks and maps) were developed to aid the information transfer. After this initial step the process

changed into a bottom up approach, as even focusing initially at regional levels, the strategy followed a

stepwise process that allowed the exchange and generation of information. The information handled at

this moment focused on the discharge normative capacity (for the ‘Noordwaard’ case the long term value)

and the other defined criteria (spatial quality and cost/benefit). The stepwise approach consisted in first

exploring and collecting ideas with actors and translating them into maps. Then these ideas were re

discussed and presented to the regional steering committee for their evaluation. At this moment

information was strategically handled, as depoldering was being discussed and considered, but due to its

controversy was not yet included ‘officially’ nor discarded. Interviewees mentioned that such strategies

created the space and momentum for it to be readdressed in the latter stages. As the stepwise negotiation

process continued, a decision had to be made and based on agreed choices and how the local interests

were strategically handled, it then resulted in depoldering becoming officially one of the projects for the

region.

This process and the consecutive (devise vision for depoldering) became only possible with the setting up

of formal and informal channels of communication, and platforms for information transfer and feedbacks.

These consisted of planning and design sessions, meetings, workshops, fields and personal visits, living-

room talks, official consultation processes. These became supported by the strategic definition of the

working groups, advisory or organized groups, which facilitated the lobbying and managing of

information transfer and feedbacks. Interviewees mentioned that during the initial planning and design

process there were also strategies chosen in how the information was conveyed. For example during

workshops and sessions, facilitators tried to accommodate and engage with actors by creating a setting of

equality, reliability, and approacheness.

Strategies that defined how information was also shared and divulgated among actors consisted in

documents, brochures, minutes, official reports, outputs from design and planning sessions, and other

research studies with alternative measures. Some actors also used the media to express and inform about

their positions, while others also used such statements as elements to steer the process. It can also be

mentioned that organized actors (Platform Save the ‘Noordwaard’) used research as a mechanism to

convey and inform about local knowledge, their interests and positions. In general information during the

first and initial phases aimed to be transparent, open and accessible. This contributed in building trust and

confidence between the actors about the process.

Page 49: Earth System Science Chair Integrated Water Management group

49

Therefore, cooperation and consents were enabled. However, once the mayor agreements and decisions

were made, when it was time to discuss about the real estate, compensation and reallocation mechanisms,

this turned back to traditional procedures of information generation and sharing. Information was not

conjunctly created with local actors and it was only shared after the government made the preliminary

proposition.

7.2.5 Payoff rules

In relation to this type of rules it can be mentioned that values were given to the costs incurred during the

planning and design process and to the expenses for its implementation (300,000 million Euros). Worth

highlighting, also values were given to the costs of moving, reallocation and expropriation of land. A

relevant payoff rule that was settled between the government and the remaining actors in the area was

the grant of the special life insurance.

Interviewees highlighted that values assigned to benefits consequently rely in the provision of flood safety

(nationwide) and enhanced quality in the area. However, values have been also given to new

opportunities that can be created as a consequence of the expected increase of tourism (e.g. sell products,

rent canoes), and the possibilities of expanding agricultural activities with the use of the middle inter tidal

polders. Since implementation of the project has already begun, interviewees stated that although the

previous mentioned benefits are potentially considered, only in time their true applicability,

accountability and efficiency could properly be assessed and thus such benefits in practice obtained.

Page 50: Earth System Science Chair Integrated Water Management group

50

7.3 Rules in-use and eco-engineering approaches: perspectives from case

studies

In this section the analysis of the rules in-use for both case studies is presented. The analysis is structured

by describing in general how rules in-use influenced interactions and outcomes in eco-engineering and

vice versa. The analysis is then elaborated in further details for each study case. Finally, the analysis

between traditional versus eco-engineering approaches is described.

7.3.1 Rules in-use influencing interaction and outcomes in eco-engineering and vice versa

In the previous sections rules in-use were identified according to the action situations (interactions and

outcomes) they relate to. It was mentioned that such action situations were found at the constitutional

level (i.e. application and enforcement of formal rules), collective-choice and operational level (i.e.

informal lobbying, conflict resolution and information sharing). For both case studies rules in-use found at

the constitutional level were the EU Directives (i.e. Birds, Habitats, EIA), and the national or regional

regulations and policies (i.e. PATRICOVA, PKB, 4th National Policy on Water Management). These

influenced the actors who became involved and their relations (actors’ networks). This depiction was

made based on how it is embedded in such regulations and policies, who are the actors responsible for

their application and to which other actors they apply. However, choice rules were also found that

influenced how such regulations and policies were enforced. For both case studies these consisted in the

choices of considering multifunctional objectives and the flood protection and environmental standards to

develop the potential projects.

At collective-choice and operational level, rules in-use (boundary, position and choice) were also found

influencing the actors’ networks and coalitions (i.e. criteria considered to include actors for preliminary

consent, coalitions for external expertise support). In addition, such rules were found influencing the

positions for some actors by changing their perceptions of roles (e.g. project developers now facilitators).

Also, the level of participation of actors in terms of the extent to which their interests and influences were

considered (e.g. informative or inclusive). Furthermore, these rules in-use (boundary, position and choice)

were found influencing informal procedures consisting of the facilitated or steering processes that

unfolded.

In relation to the information type of rules, it can be stated that these were found to be influencing a

‘negotiated knowledge’ to devise and approve the potential projects. The term negotiated knowledge is

used in this case to refer to the clear strategies that were selected with regards to the mechanisms and the

extent to which information was available between the actors (i.e. establishment of working or advisory

groups, workshops, meetings, etc.). Also, with regards to the type of information shared and considered

through the use of multiple discourses: costs/benefits, environmental, flood safety or local and regional

perspectives. Furthermore, to how the information was developed through a strategic learning approach,

consisting of a process with multiple feedbacks, open or closed, top down/bottom up.

In both case studies information rules were found closely linked to payoff and choice rules (informal

procedures and level of participation) through the negotiated knowledge. Information rules accounted as

information issues those related to flood protection, the potential projects themselves (planning/design),

the costs and benefits assigned, but also the exchange of interests, oppositions and concerns amongst

actors. Therefore, it was mainly through the information sharing that also conflicts, lobbying and informal

decisions were addressed.

Page 51: Earth System Science Chair Integrated Water Management group

51

In the previous paragraphs it has been described how the mutual influence between rules in-use and

interactions in eco-engineering approaches became reflected in relation to the rules in-use. In terms of

how such mutual influences reflected in the interactions, it can be mentioned that these reflected in a top

and bottom-up interchange and a distributed decision-making between actors. In addition, by interactions

developing over a time frame consisting of 10 years in average, denoting that rules in-use and eco-

engineering projects didn’t developed suddenly but rather as a long time process. Furthermore, such

influences were reflected in the strategic alliances that were established between the actors. As a result

the outcomes produced consisted of projects characterized by their integral design, their technical and

governance innovation, the provision of ecosystem services, and overall by enabling an integrated and

multifunctional flood risk management in the respective areas (Figure 15).

Figure 15. Rules in-use influencing interactions and outcomes in eco-engineering and vice versa.

Rules in-use: influencing networks and coalitions, role perceptions and level of participation in case studies

When analysing the influences of rules in-use and eco-engineering approaches in relation to the actors’

networks, the main changes were found in how the actors related to each other with regards to the

planning, design and decision making for the projects. A top down approach was identified in ‘Rambla del

Poyo’ and a top down/bottom up approach for the ‘Noordwaard’. The level of participation was different

in both cases. This lead to define a new balance between the actors’ interests and influences, were in both

cases it became broader but remained still constrained. For the ‘Rambla’ case it was mainly informative

and consultative. In the ‘Noordwaard’ the extent to which local actors influenced the process and their

interests were considered, was comparably larger and consisted of two phases: initial (inclusive,

placation, partnership) and final (mainly informative).

Both case studies also showed that developers of projects (government bodies, contractors or working

groups) assumed new roles by becoming facilitators and negotiators. In addition, as new actors became

involved clear strategies determined who was in and who was out (formal rules and criteria for

preliminary consents: actors with stakes or with added resources such as the provision of expertise).

Specific strategies were evidenced in terms of how these new actors also choose to interact in the light of

their new found roles or to establish coalitions. Particular coalitions from the case studies worth

highlighting are the partnerships between local actors and research institutes for contra-expertise

support in ‘Noordwaard’. In ‘Rambla’ on the contrary such partnerships were established between project

developers and the research institute.

Page 52: Earth System Science Chair Integrated Water Management group

52

Rules in-use: influencing multifunctional objectives, environmental and flood safety standards in case studies

In the ‘Rambla del Poyo’ the regulations and policies influencing the environmental and flood safety

standards were the EU Directives (Birds and Habitats→Natura 2000, EIA, Floods), PATRICOVA, and the

new flood safety regime (return period of 500 years). The new multifunctional objectives and criteria to

comply with such norms and regulations was set to achieve a level of flood safety (based on the safety

regime), develop measures with technical-hydraulic basis, include socio-economic interests, and improve

the ecological quality of the area.

On the other hand for the ‘Noordwaard’ case the policies and regulations consisted of the 4th National

Policy on Water Management, PKB procedure, the EU Directives (Birds and Habitats→Natura 2000, EIA)

and the new flood defence regime (16,000m3/s to 18,000m3/s in the long term). The new objectives and

criteria were developed at two levels: National (sustainable safety, spatial quality, cost/benefit) and local

(specific water level reduction target, farmers allowed to stay, spatial quality and local sustainability).

Rules in-use: influencing informal procedures (facilitated processes) in case studies

The facilitated or steering process in the ‘Rambla del Poyo’ (Figure 16) was characterized by consisting of

a one-directional approach with several phases each consisting of informal feedbacks (between regional

and local level actors). In this case, project developers also defined rules over the extent to which local

actors had an influence or power over the preliminary decisions made (level of participation). This was

mainly limited and to an extent restricted.

Figure 16. Facilitated process approach for ‘Rambla del Poyo’.

For the ‘Noordwaard’ case the steering process (Figure 17) consisted of a multi-layered steering

approach. It initiated at the national level to enable first a regional advice. Then the process moved to the

local context when the design vision of the project was being realized. Each ‘layer’ consisted of their own

set of rules and in both regional and local steering levels; several rounds of informational ‘feedbacks’

followed a bottom up approach. Project developers in this case engaged an open, interactive and

innovative steering process. In this particular case despite steering processes were developed before the

official consultation, discussions continued with regards of the implementation of the project. When the

real state affairs were to be defined, the process changed and the strategies went back to more traditional,

closed and formal procedures. Local actors were not involved in such planning phase.

Phase 1:

Regional authority starts the process by tendering a project to deliver potential solutions.

-1st round of 'local and informal' feedbacks

Phase 2:

Potential solutions are tested and decisions are made over preferred options.

-2nd round of 'local and informal' feedbacks

Phase 3:

Regional authority tenders project for the drafting of preferred

solutions

-3rd round of 'local and informal' feedbacks

Phase 4:

Preferred solutions and EIA submited to formal

consultation process

Page 53: Earth System Science Chair Integrated Water Management group

53

Figure 17. Facilitated process approach for ‘Noordwaard Polder’.

Rules in-use: influencing the negotiated knowledge, strategic learning and use of multiple discourse in case studies

In relation to the mutual influences between interactions in eco-engineering and the rules in-use, the

negotiated knowledge consisted for both cases in clear communication strategies. In the ‘Rambla’ the

pragmatic approach by having a careful control over the information shared and the actors targeted,

reflects that such approach still remained close to traditional practices. In the ‘Noordwaard’ case such

strategies indeed represented a significant change, as comparably local actors during the initial phase

were reached and included to a greater extent. The strategy in this case consisted of building strong bonds

of trust and reducing the uncertainties with regards to the process. This was done through clear and

prompt information sharing agreements, which then clearly denotes that this became a key factor that

facilitated cooperation. The strategies in this case also included a broader set of activities and even

platforms or working groups to support the negotiations and dialogues with the local actors. In both cases

it was found that the use of social media played a role in how it was used to convey interests and positions

between the actors.

In relation to the use of multiple discourses both case studies showed that a key strategy was found in

taking into account the different perceptions of actors’. In doing so, project developers engaged in the use

of multiple discourses to strive a strategic learning among actors that could also facilitate their

cooperation and consent. For the ‘Rambla del Poyo’ environmental, cost/benefits and flood safety

discourses where used. For the ‘Noordwaard’ case this even resulted not only in the consideration but also

in integration of local and cross-sectorial discourses. These constituted the use of the long-term flood

safety, local interests, and ecosystem services discourse.

In order to achieve such negotiated knowledge new rules were established to aid a strategic learning

amongst actors. The strategies chosen in each case were different and these become closely related to the

facilitated processes described in the previous section. Overall the mutual influences resulting from the

rules in-use and the interactions with regards to the informational situations constitute one of the main

mechanisms in which different levels of rules interconnected to define subsequent levels, or feedback each

other throughout the process. As mentioned previously, these action situations not only allowed

information and knowledge sharing at subsequent levels and vice versa, but in addition they became

spaces were actors could deliberate, negotiate, and reach for decisions. Therefore, allowing feedbacks or

interconnections between different levels of action situations (collective-choice and operational) with

regards to these other interactions. It is worth mentioning that despite these action situations were found

to be the most relevant mechanisms, it is acknowledge that they did not constitute the only mechanisms

were feedbacks took place (i.e. in the ‘Noordwaard’ case when parallel activities were developed in

devising alternative project proposals).

Page 54: Earth System Science Chair Integrated Water Management group

54

Interactions: influencing top down and bottom up interchange, distributed decision making, time frame, and strategic

alliances in case studies

For both case studies the influencing top down and bottom up interchange, the distributed decision-

making, and the strategic coalitions, resulted from how the interactions amongst actors consequently

developed from the mutual influence between rules shaping particular action situations and vice versa.

Such conditions became reflected for both case studies, in relation to the information, conflict-resolutions,

and lobbying interactions.

The process leading to eco-engineering projects in ‘Rambla del Poyo’ consisted of about 11 years total. The

‘Noordwaard’ case consisted of process of 9 years. This distinction was relevant to depict as it meant that

the different interactions unfolded through a long time span. The interactions became then multiple and

were changing as for example new rules in-use were placed or as different actions situations were being

developed. It reflects also that eco-engineering projects based on the case studies, have the particular

condition of requiring of processes consisting of at least several years in order to be developed.

Outcomes: flood defence strategy, innovations, ecosystem services, and multifunctional and integrated flood

management in case studies

As a result of rules in-use shaping or being shaped by eco-engineering approaches, this leads to denote

particular characteristics in the ultimate achieved flood defence strategy. In both cases such attributes

were found in the integral design of the measures, which not only included multiple objectives but also a

broader spatial scale (e.g. national, regional) and ecosystems interconnectivity (e.g. Natura 2000). In

addition, the connections between different eco-engineering projects, representing a major change in how

such are not being developed isolated.

In relation to the creation of new social and environmental opportunities, such as ecosystem services, new

agricultural opportunities, tourism, etc. These particular aspect remains however a big question in both

cases. This since despite environmental criteria was used as a discourse during negotiations; the general

and vague set objectives in this matter may have resulted in different interpretations by the involved

actors and thus favouring collaboration. Only through their implementation and within time the so-called

new creation of these opportunities can be in fact evaluated and accounted. Nevertheless, the outcomes

produced account for the development of a multifunctional river flood management in the respective

areas.

Furthermore, the design vision for the ‘Noordwaard’ case represents in itself an innovative flood defence

project from a technical perspective. Edelenbos et al., (2013) has already pointed out that this case in

particular shows how innovative approaches in design, may develop in informal and trust-building

cooperation and negotiation. This not only denotes the role of influential or changed rules in triggering

innovation, but also the challenges in how formal structures, processes and procedures, should then

enable more the generation of innovative ideas in such contexts. In other words, this highlights how

innovation in the governance system can translate into technical innovation and vice versa.

Page 55: Earth System Science Chair Integrated Water Management group

55

7.3.2 Traditional versus eco-engineering approaches: lessons learned

Regardless of the types and levels or rules found in both case studies, new or changed rules became

evident compared to ‘traditional approaches’. To provide with an overview and comprehensiveness of

changes, these are represented on the basis of the main influences identified between the rules in-use and

eco-engineering approaches. This since overall despite differences in the governance systems between the

study cases, the most relevant influence of new or changed rules in-use was commonly found at these

contexts (Table 6).

Table 6. Lessons learned from eco-engineering approaches versus traditional approaches.

Traditional approach Eco-engineering approach

Multifunctional objectives, environmental and flood safety standards

Centralized or unbundled policy frameworks Comprehensive policy frameworks and policies (multilevel and

cross sectorial)

Flood defence regime: first definition of flood risk

thresholds (safety standards)

Flood defence regime: definition or modification of flood risk

thresholds (safety standards) under new scenarios (e.g.

Climate Change)

Main objectives and criteria for projects: flood

safety, technical and hydraulic, cost/benefit

Definition of multilevel and functional objectives and criteria

for projects: flood safety, environmental and spatial quality,

socio-economic

Formal and Informal procedures (facilitated processes)

Independent sectorial implementation of regulation

and policies by formal procedures

Implementation of regulation and policies with cross-sector

coordination and integration by formal and informal

procedures

Top down planning, design and decision-making Top down and bottom up planning, design and decision-

making

Networks and coalitions, role perceptions and level of participation

Stakeholders’ integration only during formal

consultation procedures

Stakeholders’ integration (participation at different levels and

moments before formal consultation procedures)

Balance between interests and influences of

concerned stakeholders (mainly concentrated in

project developers)

Balance between interests and influences of concerned

stakeholders (broader to legitimate)

Developers of projects mainly with technical roles Developers of projects also facilitators and negotiators

Negotiated knowledge, strategic learning and use of multiple discourse

Communication strategies closed and hierarchical

following only formal consultation procedures

Communication strategies by steering processes, formal and

informal procedures, strategic lobbying groups and use of

social media

Implementation of negotiated knowledge narrower

and single discourse use. Result: innovation is

smothered

Implementation of ‘negotiated knowledge’ by the use of

multiple discourses, strategic knowledge transfer, and

coalitions between actors (expertise support: research with a

new role). Result: innovation is enabled

Outcomes

Independent project based design (accounting the

hydrological and hydraulic systems) → use of hard

engineering structures

Integral and spatial designs (accounting socio-ecological

systems and broader spatial scales) → use of natural resources

to increase structure functionality or the natural environment

to create structures

Opportunities:? New opportunities: flood safety, ecosystem services,

sustainability

River flood management Multifunctional river flood management

Page 56: Earth System Science Chair Integrated Water Management group

56

7.3.3 Rules in-use in eco-engineering and the SESs framework

Based on the analysis presented in the previous sections, if one considers the SESs framework and by

looking at the rules in-use found in eco-engineering approaches, links and influences between other sub

tiers of the governance system became evident (e.g. network structures). But these even translated in

integrating and influencing other higher level of tiers (users, resource system and resource units). Despite

not all these inter-linkages were fully addressed, it is worth highlighting such connections.

These links for example include the already described rules in-use (mutually) influencing the knowledge

of SES and mental nodes of users, in the context of the new/changed knowledge and information arenas.

But there are also the rules in-use (mutually) influencing the resource system and units (boundaries, size,

technology, predictability of dynamics, economic value, spatial and temporal distribution, interaction

among other units, etc.), in the context of the outcomes produced by the flood defence strategy. This

denotes again the complexity embedded in eco-engineering and supports the adequacy in framing such

approach after all as SESs.

Page 57: Earth System Science Chair Integrated Water Management group

57

8 Discussion

8.1 Rules in-use and eco-engineering

8.1.1 The complexity of the rules in-use in eco-engineering

The analysis of the rules in-use from the study cases reflects that there were multiple and different levels

of influential ‘values’ developing across time. Rules embedded in eco-engineering show that these

developed at constitutional, collective-choice and operational level. These were also (mutually)

influencing different action situations such as the generation and exchange of information, consultation,

lobbying and conflict resolution amongst involved actors. This denotes the complexity of the governance

system in the eco-engineering approach. These particular settings could account their origin partly from

the polycentric type of governance in place in both cases. But also by considering that developing an eco-

engineering approach was not a process that arose suddenly. For both study cases it took in average 10

years. It included a combination of the political momentum after high peak events, informal and formal

actions/decisions, parallel activities performed by the actors involved, the exploration of possible

alternatives (research), and the development of the project proposals themselves. Therefore, there were

multiple grounds from which traditional rules or changed strategies (at different levels and processes)

came into the picture influencing the approach.

8.1.2 The new and changed rules in-use compared to traditional approaches

In both cases it was found that the process leading to the ultimate eco-engineering projects, involved new

triggering rules; but at the same time rules mainly related to the traditional procedures, information

sharing and network arrangements being changed in return (feedbacks). The approach was somehow in-

between fostered and forced by the new constitutional regulatory and policy frameworks. Interviewees

from the ‘Rambla del Poyo’ case stated for example that the motivation to include environmental

objectives arose in order to comply with the normative requirements (i.e. EU Directives). In this sense

their integration didn’t result from perceiving them as opportunities rather obstacles.

As the process in both case studies unfolded, traditional rules related to decision-making procedures and

actors’ networks changed. These changes translated in allowing the integration and participation of new

actors with particular stakes. This scenario led actors to engage in new roles and choices. For each study

case choice rules were also established to define the extent and the ways actors’ interests and influences

were included. Another relevant change was reflected in the information sharing situations. New rules led

to facilitated processes and actions striving strategic understandings in the local actors.

In order to implement eco-engineering projects, the potential measures imply changes in land use.

Especially when initiatives are to affect land property or put interests at stake, processes tend to become

polemic. There is a common phrase that clearly summarizes the perceptions of local actors when it comes

to projects of this nature: ‘as long as it’s not in my backyard’. Therefore, by giving value on facilitating local

cooperation under these premises, this possibly can be accounted as the explaining factor for the changed

rules influencing the actors’ roles and networks as well as the negotiated knowledge.

In the ‘Rambla del Poyo’ the final consented projects although represented a ‘shift’, the procedures

remained partially close to traditional approaches (i.e. participation of local actors still limited). This was

due probably because the process was developed mainly to comply with new constitutional rules.

Therefore, in doing so placed rules were only bent to allow room enough for innovation that could help

meet such requirements. For the ‘Noordwaard’ case the final consented project represents a clear example

of how technical innovation was triggered by innovations in the governance system.

Page 58: Earth System Science Chair Integrated Water Management group

58

This case evidences that with the use of multiple discourses and by focusing on the opportunities of

combining multiple interests, objectives and requirements; not only the approach but also the final project

design became itself a new idea. This aspect highlights the importance of finding catalysts that can enable

such spaces, as they represent potential roads that could not only assist but also become a mean to further

improve eco-engineering approaches.

8.1.3 Comparing the ‘Rambla del Poyo’ and ‘Noordwaard’ governance systems

It is interesting to discuss that initially by looking at study cases with different governance contexts that a

comparison between the two would not be most suitable. The idea was to mainly outline and draw key

principles of what could be considered ‘lessons learned’. However, during the analysis common

denominators operating in both cases were found. This allowed the identification of the main contexts in

which rules in-use despite having different values in both cases, still were considered to be common. This

also facilitated the overall comparison of rules in-use embedded in eco-engineering and traditional

approaches. This leads into thinking that despite differences between the governance contexts, the study

cases owe partly their common links to the overarching frameworks in the European context such as the

EU Directives (i.e. EIA, Birds and Habitats). Therefore, such frameworks might be having a greater

influence in the shaping of these approaches than what one would expect. Nevertheless, different national

policies and regulations in each case were also playing a role, however, in principle these were also found

to be common (defining flood safety levels and more participatory processes).

Furthermore, in addition to formal rules (explained previously) the already mentioned premises

(property-rights systems; interests at stake) involved in projects of this nature, might also be the lead of

both cases developing for example steering processes that facilitated the cooperation among actors.

Another example is found in the consideration of multiple objectives and the need to devise projects that

could meet such standards (role of research). Therefore, it can be stated that the common principles found

in both the implications of developing eco-engineering type of projects and the overarching rules shaping

the projects, became mutually critical and laid the grounds for the findings of ‘similar in principle (e.g.

level of participation, informal procedures, negotiated knowledge) but yet differentiated (e.g. differences

in the levels of participation)’ rules in-use. It is worth mentioning that of course these common grounds

might also be accounted for other overlooked factors. Also, that despite these similitudes the values

assigned in both cases for such particular rules, represented at the same time core differences. This in

order to not overlook the importance of relevant differences also found in both study cases.

8.2 Application of the IAD and SESs framework

8.2.1 Challenges when facing different action situations and levels of rules in-use

The IAD framework has proven its usefulness in understanding institutions. Its tier-like nature depicts all

the possible inter-linkages to highlight the different elements constituting institutions given a particular

system. However, the framework was built to facilitate the analysis of exogenous variables at one

particular level of action situation. This means for example that a researcher can choose the level of rules

in-use (constitutional, collective-choice or operational) and how these relate to particular activities

(monitoring, sanctioning, conflict resolution, provision of information and infrastructure, appropriation

and policy-making). Based on the understanding that eco-engineering approaches integrate both the socio

and ecological systems, therefore, both the IAD and SESs framework was chosen to perform the research.

In both case studies rules in-use were found at the three levels and almost in all the mentioned activities.

This translated into faced challenges in how to address such differences and complexities. In other words

with multiple action situations and multiple levels of rules, questions arose in how under such conditions

the framework could best be applied to perform the analysis. The strategy used consisted then in using

the IAD framework mainly as a roadmap to guide the identification and categorization of the variables that

Page 59: Earth System Science Chair Integrated Water Management group

59

influenced the different interactions and outcomes produced. As a consequence the compilation of the

different action situations and levels of rules found were all schematically presented as an overall result.

In terms of analysing the information following this strategy, this allowed a better comprehension of the

rules in-use and the governance systems in both study cases. However, a downside was that particular

activities were not reflected in greater detail, and the information was schematically presented with no

distinction in time, situation or level or rules in-use. Therefore, such distinction had to be addressed and

described separately in the different sections. Nevertheless, an overall schematic representation of the

rules in-use was chosen since after all different activities at different levels were being analysed anyways.

Considering this complexity and in the attempt of addressing its integral comprehension, not sufficient

grounds were found in spreading it.

8.2.2 The usefulness of the IAD and SESs frameworks in Eco-engineering

Overall the framework represented a good approach when looking at eco-engineering approaches but its

implementation might still be better recommend when applied to specific actions situations at a defined

level of rules. This particular factor has become a main critic to the framework. The condition that it is

mostly fitted to perform an analysis of what could be called a snapshot in time of a situation, limits to a

certain extent the performance of an institutional change analysis as such changes cannot clearly be

reflected. This became then one of the major drawbacks in applying this framework in this research.

Suggestions on how this could be overcome could be in narrowing to a particular process and level the

activity of interest. Then chose two or the desired moments and apply the analysis. This could lead to

different snapshots that can then be comparable. However, in the light of looking at complex systems

(SESs) and for example considering eco-engineering approaches as in this case, key information will

logically be left out. Thus, this implies a compromise between simplicity to aid the analysis and achieving a

greater comprehension and integration of the system, which at the end represent the intrinsic

characteristic of eco-engineering approaches.

Another relevant observation is that when applying the IAD and SESs frameworks in eco-engineering with

regards of the types of rules, a clear distinction could be made over the constitutional rules. For both study

cases it was stated that the other rules in-use were found at the collective-choice level but it was difficult

to distinguish to a certain extent which of these were directly influencing operational levels. The

boundaries between these two became somehow blurry probably because throughout the process clear

feedbacks influencing both levels were identified. Furthermore, when it came to distinguishing between

the types of rules, by looking at the interactions in eco-engineering it became difficult to distinguish values

corresponding to choice, aggregation or information types of rules. In both case studies the action

situations related to information sharing, conflict resolution and lobbying activities were intertwined.

Therefore, the identification of clear boundaries thus the clear depiction of these types of rules was not

fully achieved. This supports the better use of the framework by focusing on one particular level or action

situation. Nevertheless, the root of these challenges might also be in the eco-engineering approaches

themselves. Especially as in terms of how these approaches account for a comprehensive integration

between and within the social and natural systems, resulting in blurry boundaries that become to identify.

8.2.3 Underpinning the IAD and SESs frameworks

The IAD framework was used to aid the analysis of the rules in-use. However, the SESs framework was

also included as one of the higher-level tier (governance system) depicts the different levels of rules as

sub-level tiers. Since the scope of the research was to focus on the rules, other tier variables were not

addressed in greater detail. However, in the last section of the analysis and overall reflection addressing

such links was included.

Page 60: Earth System Science Chair Integrated Water Management group

60

There are scholars (M.D. McGinnis, 2011; Mincey et al., 2013) who have underpinned the SESs and IAD

framework in the attempt of how to use the framework more ‘dynamically’ by depicting the connection

between outcomes coming from one action situation to another or the influences between different tier

variables level. One approach has been presented by McGinnis (2011) which allows the ‘spread’ but still

‘linked’ analysis of process which can also enable the identification of rules in-use influencing them.

Another approach presented by Mincey et al., (2013) considered the analysis of the rules in-use at

collective-choice and operational level by using the types of rules that relate to action situations. An

approach similar to the one presented in this research. However, these approaches have been mostly

exploratory. Nonetheless, their application could represent opportunities for future research in this field.

Following this line, in the literature there are multiple frameworks to assess institutional change, but the

extent to which they relate to SESs so that they fit when looking at eco-engineering approaches will have

to be evaluated.

8.3 Methods and techniques

8.3.1 Criteria for selection of case studies and key actors interviews

In relation to the methods some observations can be made over the criteria for selection. The phase of the

project was not included. This resulted in the case of the ‘Noordwaard’ that rules in-use were also found at

the operational level. The construction of the case became more complex as when performing the

interviews, most actors could elaborate more over the recent strategies in relation to the implementation

(more familiar with the current context) and not so much over the previous steps. This brings into

mention also the fact that processes in both cases took an average or 10 years and some interviewed

actors were engaged mainly at particular stages. This meant that their contribution remained sometimes

restricted to particular moments. In occasions it also became difficult for them to remember with specific

detail the initial processes. Furthermore, it was experienced that instead of providing with a storyline they

expected to be asked concerning particular events. Therefore, closing down the possibility of getting new

insights despite those already known and thus consulted.

To overcome these challenges the strategies used consisted in addressing the questions sometimes two or

even more times throughout the interview by framing them differently. This in order to validate

mentioned information, but also allow the interviewee to provide with new inputs that were not shared

previously. This strategy also proved effective, as once the interviewee got into context, information

flowed more naturally. Another strategy consisted in summarising the answers provided before moving to

the next questions to check if the information was understood correctly. In doing so, interviewees

sometimes elaborated more when realizing that key information for example has not yet been mentioned.

These in general represented the main advantages of having selected the semi-structure interview

technique.

On the other hand, drawbacks were found in particular with the Dutch case as the interviews were

performed in English. Not being the first language for both parties the meaning or particular information

might have been miss interpreted. The positions of interviewees and how the questions were articulated

might also lead to cross understandings. Interviewees might have for example understood the questions

in a particular way different from what it was expected from them to elaborate on; or in occasions

interviewees would refer to particular events or actions with different names making it difficult to

connect. Furthermore, it was found in particular when interviewing government officials that answers

might have been biased by referring or stressing issues that might translate mainly as ‘positive’ outcomes

from this research. This is what I would call the use of ‘political discourses’ in which statements are made

with regards of what the people expect to hear, and also that support the institutions they represent. To

face these challenges again readdressing and reframing the questions throughout the interviews became a

good strategy. Furthermore, the validation of first hand collected data with secondary source data also

supported the verification and processing of the information to perform the analysis.

Page 61: Earth System Science Chair Integrated Water Management group

61

For the interviews performed in each case in occasions procedures became bureaucratic. For example, in

the ‘Rambla del Poyo’ some municipalities required a formal procedure to perform the interviews. It

consisted of registering and then request the interview and the consultation of the file related to the case.

After the evaluation of the request answer will be given if the interview was going to be granted or not. In

the ‘Noordwaard’ to access the farmers first the ZLTO had to be approached. After having a briefing

meeting the contacts of farmers were provided.

Other difficulties experienced consisted of key identified actors longer being active (ecological groups in

the ‘Rambla’ case), or others became difficult to locate as the have already moved (farmers with

expropriated land in the ‘Noordwaard’ case). Therefore, the setting up of meetings became a challenging

process. To overcome these limitations by using previous references from interviewed actors and with the

support provided by experts for their contact, the arrangements of meetings became possible. The

snowball sampling technique proved effective, however, actors referencing other particular ones could

have meant a bias in the selection of interviewees. In addition, only a total of 14 interviews were possible.

Thus, in order to overcome such possible limitations and to achieve a greater representation of the

stakeholders’ perceptions, secondary sources of information were consulted. These mainly constituted

documents in Spanish (native language) and for the Dutch case literature in English, found in relatively

considerable amounts. These proved to be effective in contributing with the construction of the cases and

to perform the consequent analysis.

8.3.2 Data processing methods

The use of a timeline of critical events to process the information turned out to be an effective technique.

By doing so it was possible to analytically assess the compiled information and crosschecked the input

data. The overall description that was achieved for both cases facilitated their overall comprehension and

it also laid the ground for the development of the consecutive analysis. The studies showed that the eco-

engineering approach was a process that developed over several years. The techniques used to get a grip

over the process allowed the identification of which were new and change rules. Such changes led to a

final situation but they did not occur at the same time. If one only focuses on an identified starting point

and an end point, key changes in between can therefore become overlooked. Thus, not being able to grasp

a comprehensive analysis.

Page 62: Earth System Science Chair Integrated Water Management group

62

9 Conclusions

9.1 Related to the research questions What are the main events and processes (action situations) leading to eco-engineering initiatives?

Processes and events in eco-engineering initiatives mainly constituted the application of national and

regional policies, and the monitoring and enforcing of those activities in formal and informal contexts. But

also formal and informal information exchange, negotiation rounds, the exploration and crafting of

alternatives and formal consultation activities. These were found across scales (constitutional, collective-

choice and operational) or developing sometimes parallel with mutual feedbacks and across time.

Who are the actors involved in these action situations?

Actors involved in eco-engineering initiatives comprise a diverse and multiple group. These vary from

government units (national, regional, local) and authority bodies (regional, local), to expertise providers

(universities), environmental groups, other project developers (private consultancies), farmers, and

residents, to organized platforms, boards and strategic steering/working groups.

What boundary, position, choice, information or payoff rules were applied in these action situations?

Boundary rules in both case studies consisted of the national and regional policies (e.g. EU Directives,

PATRICOVA and PKB) and the rules related to the criteria to include particular actors in the preliminary

consents (e.g. actors affected by expropriation of land, with concerned interests, etc.). Position rules were

those defining the roles of actors (i.e. project developers decision makers and facilitators, local actors

decision-makers, universities as expertise providers). Choice rules consisted to the values related to the

definition of the multiple objectives for projects, related to the criteria to develop regional and local

steering processes, the level of stakeholders’ participation, and the formal and informal procedures.

Information types of rules consisted of those defining the information generation and sharing and the

strategies in how and the extent to which information was transferred. Payoff rules consisted of the

identified strategies defining the costs and benefits assigned to the eco-engineering projects.

What are differences between rules in-use in traditional versus eco-engineering approaches? Main differences between rules in-use in traditional versus eco-engineering approaches, were found

related to the influencing overarching policy and regulatory frameworks (EU Directives and new flood

defence policies). In the rules in-use that influenced actors’ networks and roles, the top down versus

bottom up decision-making, broader participation of local stakeholders, increased balance between

interests and influences of local actors. In addition, with regards to rules in-use influencing the new

platforms and communication strategies, the use of multiple discourses and processes to strive the

negotiated knowledge between actors.

How do rules in-use influence interactions and outcomes in eco-engineering approaches and vice versa?

The unveiled rules in-use in eco-engineering approaches consist of (mutually) influencing values at the

constitutional, collective-choice and operational levels. At the constitutional level both case studies

evidenced that eco-engineering projects were triggered by the influence of new regulations and policies at

(i.e. EU Directives and regional flood safety policies). At collective-choice and operational levels, new or

changed boundary, position, and choice rules were found influencing actors’ networks. In addition, actors’

perceptions of roles and their level of participation. Furthermore, such were found influencing informal

procedures (facilitated processes).

Page 63: Earth System Science Chair Integrated Water Management group

63

Informational type of rules influenced a strategic learning between concerning actors and the use of

multiple discourses. For both case studies the mutual influence of rules in-use and eco-engineering

approaches resulted from distinctive interactions. Such interactions were characterized by a top and

bottom-up interchange between actors, a distributed decision-making and the establishment of strategic

alliances. As a result the outcomes produced consisted of projects characterized by their integral design,

their technical and governance innovation, the provision of ecosystem services, and overall by enabling an

integrated and multifunctional flood risk management in the respective areas.

In addition, based on the SESs framework that the mutual influences became reflected also in other

elements composing the governance systems, and as a result of the ultimate reached flood defence

strategy to other elements in the ecological system as well.

9.2 Rules in-use and eco-engineering

Despite differences were found in both cases, similarities were also depicted which can be related to the

overarching frameworks. This could be pointed as the main influential factor; nonetheless, the role of

regional and local values assigned to rules in-use at a collective-choice and operation levels, were critical

in defining which actors became involved, their positions and their strategies. These conditions denote the

polycentric nature and complexity of the governance systems embedded in eco-engineering approaches.

Also, that if one seek to grasp a comprehensive understanding of such contexts it makes it almost

inevitable to look beyond scales, sectors and even time horizons. Furthermore, that both common found

principles became mutually influenced (feedbacks).

Broader and more open facilitating processes can trigger greater governance and technical innovation in

eco-engineering projects. Strategies should be devised in order to enable such opportunities. These could

be found in expanding the use of multiple discourses and incentivising interactive-information exchanges,

which at the same time can facilitate cooperation between actors’. Integrating actors’ participation at an

early stage, building trust, and striving a structured knowledge (preparing the grounds).

9.3 Related to the SESs and IAD framework and eco-engineering

The application of the SESs and most in particular the IAD framework proved to be adequate by assisting

the analysis of the rules in-use. However, weak points became evident when applying it to complex

governance settings such as those embedded in eco-engineering approaches. The frameworks themselves

are limited in allowing the clear depiction between levels of rules in-use and their (mutually) influencing

multiple actions arenas.

9.4 Related to research methods

The use of a timeline of critical events proved adequate in constructing the cases and exposing the

information that allowed the identification of relevant action arenas and rules in-use. The use of primary

and secondary data allowed their mutual validation to reduce biases and support their

representativeness.

Page 64: Earth System Science Chair Integrated Water Management group

64

10 Recommendations

10.1 Key points for future research

An analysis of the rules in-use, actors and action situations in eco-engineering approaches, using the

concept of ‘network of adjacent action situations (NAAS)’ provided by (M.D. McGinnis, 2011). The approach

underpins the IAD framework in order to assist its application to complex policy settings.

This might prove to be useful in the attempt to make clearer the interrelations between different action

situations and levels of rules.

The SESs and IAD framework could also be used to develop an assessment of eco-engineering approaches

by defining a specific level of rules (constitutional, collective-choice and operational), type of action

situations (monitoring, appropriation and provision) and moments in time. By narrowing the scope this

might unveil relevant findings that otherwise could have been overlooked. However, this ‘fragmented’

approach could also represent losing the overall understandings of the systems at stake.

A similar approach could also be developed but using other study cases to test if the similar ground

principles found, are indeed common denominators in initiatives following such approach. Other

examples in the European context could then be considered. Following this line it will be interesting to

compare even with cases found in developing countries.

Research aiming to look at in particular the new opportunities created by eco-engineering approaches is

also recommended. The different initiatives laid their core over the potential multi-sectorial benefits they

aim to produce. To look at for example the ecosystem services, tourism, and intertidal agriculture, such

analysis could deliver the inputs in the understandings of how the produced outcomes feedback the socio-

ecological systems. Furthermore, such new opportunities open the possibilities to perform other types of

research as for example assessments for the development of payment for ecosystem services schemes, or

even how the new socio-economic opportunities connect with the livelihoods of local people.

Research could also focus on the innovation elements found. Such works could aim for example in looking

at other experiences and identifying which were the elements triggering both governance and technical

innovation.

Other research could also focus on performing a discourse analysis. It was found in both case studies that

the use of a multiple discourse proved to be a key factor enabling cooperation and negotiation. This makes

it interesting to evaluate how for example taking one or all discourses; these are understood or framed by

the different involved stakeholders.

10.2 Related to the methods and techniques

With regards to the methods and techniques it is recommendable to target the key representatives of the

different stakeholders. The snowball sampling technique can result biased as for example particular

actors might consider only to recommend other actors that will have a particular view or position.

Therefore, one should account this factor and ensure such representativeness.

While performing this research the use of different sources of data proved to be effective. This since it

allowed the triangulation and verification of the input data. Therefore, it is recommendable when

performing this type of research to consider approaches that can enable the verification (multiple data

sources). Also, it is worthwhile to ask interviewees if they could provide with other supporting literature.

Key stakeholders have access to documents that are not easily if not impossible to obtain otherwise.

Page 65: Earth System Science Chair Integrated Water Management group

65

The use of the timeline of critical events is also recommendable to construct the cases when the ‘ground

research approach’ is used. To improve the use of this technique a ‘draft’ layout can be elaborated to share

with stakeholders during interviews. This might help them recall the process and give feedbacks. The

preliminary construction of a stakeholders map can also be developed as supporting material during the

interviews. This might enable the collection of further useful insights.

The use of the IAD and SESs such frameworks proved to be suitable and therefore recommended as

approaches for further analysis of eco-engineering. However, specific recommendations in their

application can be found as the mentioned in section 10.1.

10.3 Future development of eco-engineering

Project developers or managers could for example consider learning experiences from the two cases. To

engage in initiatives considering an eco-engineering approach, first a normative and regulatory

framework mapping should allow the identification of criteria and objectives the projects should target

for. Following this mapping stakeholders and engaging in activities to promote a steering process

(multiple discourse use and structured knowledge) could not only facilitate cooperation but at the same

time trigger technological innovation for the projects.

Page 66: Earth System Science Chair Integrated Water Management group

66

11 References AMINSA. (2006). Memoria Resumen de Impacto Ambiental Adecuación Ambiental y Drenaje de la Cuenca

del Poyo Vertiente a la Albufera (pp. 90). Valencia, España: Ministerio de Ambiente, Confederación Hidrográfica del Júcar, Programa AGUA Albufera.

Apitz, S., Elliott, M., Fountain, M., & Galloway, T. (2006). European environmental management: Moving to an ecosystem approach. Integrated Environmental Assessment and Management, 2(1), 80-85. doi: 10.1002/ieam.5630020114

Baxter, P., & Jack, S. (2008). Qualitative Case Study Methodology: Study Desing and Implementation for Novice Researchers. The Qualitative Report, 13(4), 544-559.

Berga, L. (1993). El Plan Hidrológico Nacional y la Problemática de las Inundaciones en España. Revista de Obras Públicas, 3.327. AÑO 140, 53-63.

Berkes, F., & Folke, C. (1998). Linking social and ecological systems: management practices and social mechanisms for building resilience. . Cambridge, Uk: Cambridge University Press.

Resolución de 16 de diciembre de 2011, de la Secretaría de Estado de Cambio Climático, por la que se formula declaración de impacto ambiental del proyecto Adecuación ambienal y drenaje de la cuenca del Poyo vertiente a la Albufera, Valencia. (2012).

Borsje, B. W., van Wesenbeeck, B. K., Dekker, F., Paalvast, P., Bouma, T. J., van Katwijk, M. M., & de Vries, M. B. (2011). How ecological engineering can serve in coastal protection. Ecological Engineering, 37(2), 113-122.

BwN. (2012). Pilots and cases 2012. from http://publicwiki.deltares.nl/display/BWN/EDD+-+Pilots+and+cases

Camarasa, A. M., López-García, M. J., & Soriano-García, J. (2011). Mapping temporally-variable exposure to flooding in small Mediterranean basins using land-use indicators. [Hazards]. Applied Geography, 31(1), 136-145. doi: http://dx.doi.org/10.1016/j.apgeog.2010.03.003

Camarasa, A. M., & Segura, F. (2001). Flood events in Mediterranean ephemeral streams (ramblas) in Valencia region, Spain. CATENA, 45(3), 229-249. doi: http://dx.doi.org/10.1016/S0341-8162(01)00146-1

Camarasa, A. M., & Tilford, K. A. (2002). Rainfall–runoff modelling of ephemeral streams in the Valencia region (eastern Spain). Hydrological Processes, 16(17), 3329-3344. doi: 10.1002/hyp.1103

Cousins, B. (1997). How Do Rights Become Real?: Formal and Informal Institutions in South Africa's Land Reform. IDS Bulletin, 28(4), 59-68. doi: 10.1111/j.1759-5436.1997.mp28004007.x

Cowie, G., & Borrett, S. (2005). Institutional perspectives on participation and information in water management. [Vulnerability of Water Quality in Intensively Developing Urban Watersheds]. Environmental Modelling & Software, 20(4), 469-483.

DELTARES. (2009). Eco-engineering, from http://www.innoverenmetwater.nl/upload/documents/Eco%20engineering%20(brochure).pdf

EcoShape. (2011). Projects Retrieved 15-10-2012, 2012, from http://www.ecoshape.nl/en_EN/environments.html

Edelenbos, J., Roth, D., & Winnubst, M. (2013). Dealing with uncertanties in the Dutch Room for the River programme: a comparison between the Overdiep polder and Noordwaard. In F. Warner, A. van Buuren & J. Edelengbos (Eds.), Making space for the river: Governance experiences with multifunctional river flood managemetn in the US and Europe (pp. 200). London, UK: IWA Publishing.

Eisenhardt, K. M. (1989). Building Theories from Case Study Research. The Academy of Management Review, 14(4), 532-550. doi: 10.2307/258557

EU. (2011). OURCOAST, Integrated Coastal Zone Management. The Netherlands: European Union. Francés, F., García-Bartual, R., Ortiz, E., Salazar, S., & Miralles, J. (2008). CRUE Research Report No I-6:

Efficiency of non-structural flood mitigation measures: "room for the river" and "retaining water in the landscape": CRUE Funding Initiative on Flood Risk Management Research.

French, P. (2006). Managed realignment – The developing story of a comparatively new approach to soft engineering. Estuarine, Coastal and Shelf Science, 67(3), 409-423.

Gerritsen, H. (2005). What happened in 1953? The Big Flood in the Netherlands in retrospect. Philosophical Transactions of the Royal Society A: Mathematical, Physical and Engineering Sciences, 363(1831), 1271-1291. doi: 10.1098/rsta.2005.1568

Hartley, J. (2004). Case Study Research. In C. Cassell & G. Symon (Eds.), Essential Guide to Qualitative Methods in Organizational Research (pp. 324-333). Great Britain: Athenaeum Press Ltd., Gateshead.

Page 67: Earth System Science Chair Integrated Water Management group

67

Hess, C., & Ostrom, E. (2005). A Framework for Analyzing the Knowledge Commons: a chapter from Understanding Knowledge as a Commons: from Theory to Practice: Library Publications. Paper 21.

Huisman, B., van de Rotten, P., Sanders, R., Yan, Y., & Xia, Y. (2004). Project Noordwaard (F. o. C. Engineering, Trans.) (pp. 109). Delft, The Netherlands: TU Delft University.

IPCC. (2007). Summary for Policy Makers. . Cambridge, United Kingdom and New York, NY, USA: Cambridge University Press.

Janssen, M., Anderies, J., & Ostrom, E. (2007). Robustness of Social-Ecological Systems to Spatial and Temporal Variability. Society & Natural Resources: An International Journal, 20(4), 307-322.

Klijn, F., van Buuren, M., & van Rooij, S. A. M. (2004). Flood-risk Management Strategies for an Uncertain Future: Living with Rhine River Floods in The Netherlands? [AMBIO: A Journal of the Human Environment]. AMBIO: A Journal of the Human Environment, 33(3), 141-147. doi: 10.1579/0044-7447-33.3.141

Levy, J., Gopalakrishnan, C., & Lin, Z. (2005). Advances in Decision Support Systems for Flood Disaster Management: Challenges and Opportunities. [International Journal of Water Resources Development]. International Journal of Water Resources Development, 21(4), 593-612. doi: 10.1080/07900620500258117

McGinnis, M. D. (2011). An Introduction to IAD and the Language of the Ostrom Workshop: A Simple Guide to a Complex Framework. Policy Studies Journal, 39(1), 169-183. doi: 10.1111/j.1541-0072.2010.00401.x

McGinnis, M. D. (2011). Networks of Adjacent Action Situations in Polycentric Governance. Policy Studies Journal, 39(1), 51-78. doi: 10.1111/j.1541-0072.2010.00396.x

Middelkamp, J. (2011). Public Participation: The influence of characteristics of projects on the role of stakeholders and design changes. (Master Degree), University of Twente, Enschede.

Mincey, S. K., Hutten, M., Fischer, B. C., Evans, T. P., Stewart, S., & Vogt, J. M. (2013). Structuring institutional analysis for urban ecosystems: A key to sustainable urban forest management. [Urban Ecosystems]. 1-19. doi: 10.1007/s11252-013-0286-3

Mitsch, W. J., & Jørgensen, S. E. (2003). Ecological engineering: A field whose time has come. [The Philosophy and Energence of Ecological Engineering]. Ecological Engineering, 20(5), 363-377.

Naumann, S., Anzaldua, G., Berry, P., Burch, S., McKenna, D., Frelih-Larsen, A., . . . Sanders, M. (2011). Assessment of the potential of ecoystem-based approaches to climate change adaptation and mitigation in Europe. . UK: Final report to the European Comission, DG Environment, Contract no. 070307/2010/580412/SER/B2, Ecologic institute and Environmental Change Institute, Oxford University Centre of the Environment.

Ostrom, E. (2007a). Developping a method for analyzing institutional change Workshop in Political Theory and Policy Analysis (pp. 56). Arizona, United States: Center for the Study of Institutional Diversity, Arizona State University.

Ostrom, E. (2007b). A diagnostic approach for going beyond panaceas. Proceedings of the National Academy of Sciences of the United States of America, 104(39), 15181-15187.

Ostrom, E. (2009). A General Framework for Analyzing Sustainability of Social-Ecological Systems. Science, 325(5939), 419-422. doi: 10.1126/science.1172133

Ostrom, E. (2011). Background on the Institutional Analysis and Development Framework. Policy Studies Journal, 39(1), 7-27. doi: 10.1111/j.1541-0072.2010.00394.x

Ostrom, E., & Cox, M. (2010). Moving beyond panaceas: a multi-tiered diagnostic approach for social-ecological analysis. Environmental Conservation, 37(04), 451-463. doi: doi:10.1017/S0376892910000834

Ostrom, E., Gardner, R., & Walker, J. (2006). Rules, games, and common-pool resources. United States of America: The University of Michigan Press.

PATRICOVA. (2002). Plan de Accion Territorial de caracter sectorial sobre Prevencion del Riesgo de Inundacion en la Comunidad Valenciana (Memoria) (Vol. 1, pp. 79). Valencia, España: Generalitat Valenciana-Dirección General de Urbanismo y Ordenación Territorial-.

Pleijte, M., Schut, M., & During, R. (2011). Reflexivity in action research: two spatial planning cases Knowledge in action (Vol. 11, pp. 221-245): Wageningen Academic Publishers.

Polski, M., & Ostrom, E. (1999). An Istitutional Framework for policy analysis and desing. Kelembagaandas.worldpress.

Reed, M., Graves, A., Dandy, N., Posthumus, H., Hubacek, K., Morris, J., . . . Stringer, L. (2009). Who's in and why? A typology of stakeholder analysis methods for natural resource management. Journal of Environmental Management, 90(5), 1933-1949.

Rijsdorp, A., Adegeest, A., de Kuijer, O., de Koning, R., & Gaastra, R. (2006). Ontwerpvisie Ontpoldering Noordwaard. In B. N. Rotterdam (Ed.), (pp. 71). The Netherlands: Room voor de rivier.

Page 68: Earth System Science Chair Integrated Water Management group

68

rivier, r. v. d. (Cartographer). (2009). Inrichtingsplan Onpoldering Noordwaard. RWS. (2007). De-poldering Noordwaard: Plan, process and procedure [Presentation]: Miniterie van

Verkeer en Waterstaat. RWS. (2009). National Programme: Integrated flood alleviation measures in the Netherlands. In R. R.

Ministerie van Verkeer en Waterstaat (Ed.). The Netherlands: Room for the River. Schielen, R. M. J. (2006). On the role of the civil society in 'Room for the River' in the Netherlands (pp. 3).

Arnhem, The Netherlands: Ministry of Transport, Public Works and Water Management, Department of Integral Water Management and Waste Water Treatment, University of Twente, Faculty of Engineering Technology.

Schut, M. (2012). Who cares about research?! : a study on the role of research in policy processes in competing claims contexts. (Proefschrift Wageningen

Met lit. opg. - Met samenvatting in het Engels, Nederlands en Portugees), s.n.], [S.l. Retrieved from http://edepot.wur.nl/202812

Schut, M., Leeuwis, C., & van Paassen, A. (2010). Room for the River: Room for Research? The case of depoldering De Noordwaard, the Netherlands. Science and Public Policy, 37(8), 611-627. doi: 10.3152/030234210x12767691861173

Segura, F., Sanjaume, E., & Meyer, M. J. (1985). Repercusiones de un fenómeno extraordinario en la Rambla de Chiva. Cuadernos de Investigación Geográfica, tomo XI, 137-148.

Stijnen, J. W., Kanning, W., Jonkman, S. N., & Kok, M. (2013). The technical and financial sustainability of the Dutch polder approach. Journal of Flood Risk Management, n/a-n/a. doi: 10.1111/jfr3.12022

Turner, R. K., Burgess, D., Hadley, D., Coombes, E., & Jackson, N. (2007). A cost-benefit appraisal of coastal managed realignment policy. Global Environmental Change, 17(3-4), 397-407.

TYPSA. (2009a). Estudio de Soluciones y Viabilidad de la Solución Propuesta -Proyecto Adecuación Ambiental y Drenaje de la Cuenca del Poyo Vertiente a la Albufera- (2 ed., pp. 90). Valencia, España: Ministerio de Ambiente, Confederación Hidrográfica del Júcar, Programa AGUA Albufera.

TYPSA. (2009b). Memoria Proyecto Informativo de Adecuación Ambiental y Drenaje de la Cuenca del Poyo Vertiente a la Albufera (pp. 52). Valencia, España: Ministerio de Ambiente, Confederación Hidrográfica del Júcar, Programa AGUA Albufera.

TYPSA. (2009c). Restauración Forestal -Proyecto Adecuación Ambiental y Drenaje de la Cuenca del Poyo Vertiente a la Albufera- (2 ed., pp. 44). Valencia, España: Ministerio de Ambiente, Confederación Hidrográfica del Júcar, Programa AGUA Albufera.

van den Brink, M. (2009). Rijkswaterstaat on the Horns of a Dilema. Delft, The Netherlands: Uitgeverij Eburon.

van Slobbe, E., de Vriend, H., Aarninkhof, S., Lulofs, K., de Vries, M., & Dircke, P. (2012). Building with Nature: in search of resilient storm surge protection strategies. Natural Hazards, 1-20. doi: 10.1007/s11069-012-0342-y

Waltner-Toews, D., & Kay, J. (2005). The Evolution of an Ecosystem Approach: the Diamond Schematic and an Adaptive Methodology for Ecosystem Sustainability and Health. Ecology and Society, 10(1), 38.

Page 69: Earth System Science Chair Integrated Water Management group

69

12 Annexes Annex 1. Interviewed actors involved in the processes leading to eco-engineering projects in ‘Rambla del Poyo’.

Actors Number of Interviewees

Hydrological Confederation of Jucar 2

Municipality of Xirivella 1

Municipality of Riba-Roja de Turia 1

The Polytechnic University of Valencia 2

Consultancies:

-TYPSA

-AMINSA

2

TOTAL 8

Annex 2. Interviewed actors involved in the processes leading to eco-engineering project in the

‘Noordwaard’ Polder.

Actors Number of Interviewees ‘Rijkswaterstaat’ and Room for the River project group 1 Farmers (members of the Platform ‘Behoud Noordwaard’) 2 ‘Klankbordgroep’ Noordwaard 1 Wageningen University 1 ZLTO 1

TOTAL 6 Annex 3. Phoned interviewed actors involved in the processes leading to eco-engineering projects in

‘Rambla del Poyo.

Actors Number of Interviewees

Municipality of Massanassa 1 Municipality of Quart de Poblet 1 Municipality of Cheste 1 Environmental group ENEBRO Chiva-Ege 1

TOTAL 4

Page 70: Earth System Science Chair Integrated Water Management group

70

Annex 4. Semi-structure questionnaire used for key informant interviews.

A. Introduction: explain academic background and the goals of the research B. Questions

1. Where does the idea come from (eco-engineering)? Initial starters: Events (high peak discharges,

regulations, laws, programmes, particular activities, other)

Criteria (approaches, guidelines,

objectives, motivations, principles,

other)

2. Which were the main events and processes that unfolded leading to eco-engineering projects?

3. How these processes developed?

Processes: Formal decisions and interactions Informal decisions and interactions Other events Criteria: Approaches, objectives, motivations,

other 4. Which were key actors interacting in such processes? 5. What defined their participation and roles? 6. What defined their strategies (choices) and

interactions with regard to the processes? 7. Which strategies and interactions were effective and

which weren’t?

Most important/influential actors in: Design/planning activities Conflict resolution

(intermediaries/consensus) Provision of information Decision-making Criteria: Approaches, strategies, motivations,

other 8. Which and how costs and benefits were accounted? Ecosystem services

Externalities Social networks Trust environment Costs: avoided damages,

implementation Other

9. What represented main changes from traditional approaches related to this field?

Processes: Formal decisions and interactions Informal decisions and interactions Actors involved and criteria

Page 71: Earth System Science Chair Integrated Water Management group

71

Annex 5. Actors involved in formal dialogues and consultation processes in ‘Rambla del Poyo’. Source: BOE (2012).

Government Units Municipalities Environmental groups -General Directorate of Biodiversity (Ministry of Environment) -Government Delegation in Valencia -Government Sub-delegation in Valencia -General Directorate of Environmental Management (Generalitat Valenciana) -Environmental Evaluation Area of the Autonomy Secretary of Territory and Environment (Generalitat Valenciana) -General Dictatorate of Environmental Quality (Generalitat Valenciana) -General Dictatorate of Spatial Planning (Generalitat Valenciana) -General Directorate of Public Works (Generalitat Valenciana) -General Directorate of Fishing and Alimentation (Generalitat Valenciana)

-Municipality of Alaquás -Municipality of Aldaia -Municpality of Alfafar -Municipality of Benetússer -Municipality of Chiva -Municipality of Loriquilla -Municipality of Manisses -Municipality of Massanassa -Municipality of Paiporta -Municipality of Picanya -Municipality of Quart de Poblet Municipality of Siete Aguas -Municipality of Xirivella

-ADENA -SEO -Study and Defense Group of Environment ‘Rocandell’ -ENEBRO Environmental Group of Chiva-Ege -Ecologists in Action-Alicante -Ecologic Group L’Aber-ea -Friends of the Wetlands of South Alicante Association - ‘Xúquer’ -Coordinador in Defense of the Forests