earned value in agile: the definition of done in agile - kjetil strand

18
20.06.2011 © PROMIS AS 1 Earned Value in Agile: The Definition of done in Agile Software development EVA 16, London, June 14th – 15th Kjetil Strand, Promis AS

Upload: eva-in-theuk

Post on 01-Jul-2015

329 views

Category:

Business


0 download

DESCRIPTION

This is one of many excellent presentations given over the last three years of the eVa in the UK series. They can also be found in the archive at: http://evaintheuk.org/archive along with back-copy video footage in http://evaintheuk/pmchannel EVA19, the long established Earned Value conference, has this year described its theme as looking at a project management ‘ABC’ – Agile, Benefits and Complex. The four day event, which returns to the Armourers Hall, runs from the 19th to 22nd of May with the flagship conference being held on 20th and 21st May and workshops before and after. The conference will look at how this ‘ABC’ can be made to work within a portfolio and how agile fits into major and minor projects. It will investigate how to manage the relationship between portfolio benefits and project budgets, and whether complex projects even exist. Conference organiser and APM chairman, Steve Wake says: “Currently there is little evidence that this ‘ABC’ is being effectively deployed and managed. This conference aims to address that concern through EVA’s trademark blend of learning and professional development. Case studies and unusual presentations, delivered by top-notch speakers and experienced practitioners, will again engage and entertain the audience. We’ve used string quartets to illustrate points in the past and this year we will be using a Blues band for the first time.” Speakers across the two days include many familiar faces from the APM events programme including; Adrian Pyne of the APM ProgM SIG ‘Changing the project wasteland with a portfolio culture that works,’ APM Honorary Fellow Tim Banfield Director at the Major Projects Authority and Stephen Jones, Sellafield and Planning Monitoring and Control Specific Interest Group (PMC SIG) and Carolyn Limbert of the APM PMC SIG to talk about agile, benefits and complex. Peter Taylor, the Lazy Project Manager will be presenting on “The project manager who smiled” and the ever popular Stephen Carver will present the leadership lessons that can be learnt from Alfred the Great. In addition, there will be speakers from AIRBUS, TfL, Bloodhound, Heathrow T2 and London Tideway Tunnels. The conference will be supplemented by a number of workshops being held at the Chartered Institute of Arbitrators, Bloomsbury Square on Monday 19th and Thursday 22nd May 2014. 'eVa in the UK' http://evaintheuk.org is building a reputation, brand and a learning legacy for the Project Management Profession. The event series is now in its nineteenth year. It is almost as if it all kicked-off when Steve Wake was in short trousers and knights roamed the land on their chargers! #eva19 is an excellent example of Listening, Learning and Leading #apmLLL in action, and great opportunity for professional development. I would encourage anyone who is interested in 'Building a better Project Manager,' to take a look at the web site book your place and get involved.

TRANSCRIPT

Page 1: Earned Value in Agile: The Definition of Done in Agile - Kjetil Strand

20.06.2011 • © PROMIS AS 1

Earned Value in Agile:The Definition of done in Agile Software developmentEVA 16, London, June 14th – 15thKjetil Strand, Promis AS

Page 2: Earned Value in Agile: The Definition of Done in Agile - Kjetil Strand

20.06.2011 • © PROMIS AS 2

Outline of the talk

• Background – Earned Value Analysis in Agile • Work Breakdown Structure in Agile• A Project Execution Model based on PS2000 Agile• The Control Gate following each Sprint: Definition of Done• An Estimation Model based on the Execution Model• A practical example: Cashing in and Monitoring Earned Value

Page 3: Earned Value in Agile: The Definition of Done in Agile - Kjetil Strand

20.06.2011 • © PROMIS AS 3

Earned Value Analysis in Agile Projects

• Some resistance against Earned Value Analysis in the agile community• Some regard established project management knowledge areas as waterfall

(you have to establish a project budget)• This talk will demonstrate that Earned Value analysis fits well together with

agile practises• We present a framwork within which earned value could be monitored

throughout the history of agile software development projects

Page 4: Earned Value in Agile: The Definition of Done in Agile - Kjetil Strand

20.06.2011 • © PROMIS AS 4

Work Breakdown Structure in Agile

The two main levels in the project plan are epics and user storiesThe project scope is described by epics (high level user stories)The project budget is distributed on this epics levelFurther detailing on the user story level (product backlogs) and the sprint task levelsFull tracability top down and bottom up on cost and progress

Page 5: Earned Value in Agile: The Definition of Done in Agile - Kjetil Strand

20.06.2011 • © PROMIS AS 5

The execution model in PS2000 Agile

Analysis of Needs

Approvalphase

Detailed planningAnalysis and design

Testing Development

Progress

Iterative construction phase

Cg1

Cgn

Cg2

PMS 0Epics ready for analysis

SolutionDescription

PMS 1User stories ready for construction-

PMS 2User stories ready for approval

PMS 3User stories in production

• 4 Principal Milestones (PMS 0 – 3)

• A Control gate (Cgn) for each iteration

Page 6: Earned Value in Agile: The Definition of Done in Agile - Kjetil Strand

20.06.2011 • © PROMIS AS 6

Large projects: The Execution Modelis repeated for each release

R1 R2 R3 R4Releases

Time

Analysis of Needs

Approval phase

Progress

IterativeConstruction phase

Cg

CgCg

PMS 0

Solution Description

PMS 1User stories

ready for construction

PMS 2User stories

ready for approval

PMS 3User stories

in productionEpics

ready for analysis

Page 7: Earned Value in Agile: The Definition of Done in Agile - Kjetil Strand

20.06.2011 • © PROMIS AS 7

SCRUM: Each sprint is an iteration

Page 8: Earned Value in Agile: The Definition of Done in Agile - Kjetil Strand

20.06.2011 • © PROMIS AS 8

Detailed planning, analysis and design

Testing

Development

The Anatomy of the Sprint in PS2000 Agile

-What did you do?

-What will you do?

-Any obstacles?24 h

Sprint Backlog

Planning Decomposed by the team

The delivery in the Control gate –running software and definition of done

Prioritized Product Backlog

Cg

Page 9: Earned Value in Agile: The Definition of Done in Agile - Kjetil Strand

20.06.2011 • © PROMIS AS 9

The Control gate

• By the end of the sprint, the teams demonstrate running software to the product owner(s)

• Furthermore, to check if a user story meets Definition of done, it must pass a Control gate

The sprint

Cg

• The Control gate meeting is usually executed 2-4 working days after sprint demo (by this time, the teams have already executed sprint planning for the next sprint)

• In the Control gate process and the Control gate meeting a lot of representatives from the Customer side are participating: Product Owners, Test, Architecture, Operations, and project management

• In the Control gate meeting the Customer gives feedback on all parameters of ‘Done’ to the Vendor

Page 10: Earned Value in Agile: The Definition of Done in Agile - Kjetil Strand

20.06.2011 • © PROMIS AS 10

Definition of Done

• The user stories are verified on a stable test environment

• Do the user stories meet the acceptance criteria?

• Is the software well documented (user documentation, system documentation, installation and operations documentation)?

The sprint

Cg

• Are the tests documented?• Is the code of good quality?• Are other architectural constraints and guidelines met?• All these requirements should be fulfilled to meet the definition of done• The control gate meeting itselt may handle a number of delivered user

stories in a relatively short time (e.g., 30 user stories in 15 minutes)

Page 11: Earned Value in Agile: The Definition of Done in Agile - Kjetil Strand

20.06.2011 • © PROMIS AS 11

An Estmation Model with Build Estimate as the Main Driver

Build Estimate

Analysis and detailed design

System and integration testing

Bug fixing

Scrum seremonies

Functional guidance

30 %

30 %

20 %

10 %

10 %

Analysis of Needs

Solution Description

Approval and Completion

Construction

Sum construction

22 %

22 %

16 %

System implementation – X % of project cost

Administration and Management – Y % of project cost

Technical support, environments – Z % of project cost

Sum hours derived from

Build

Duration

Sum hours derived

Sum hoursBuild = Development, Unit testing, deployment and documentation

Page 12: Earned Value in Agile: The Definition of Done in Agile - Kjetil Strand

20.06.2011 • © PROMIS AS 12

An implementation of the Estimation Model

Page 13: Earned Value in Agile: The Definition of Done in Agile - Kjetil Strand

20.06.2011 • © PROMIS AS 13

Mapping the estimation model to earned value in the principal milestones

Earned value in each principal milestone is computed according to the estimation modelNothing else than progress on epics and user stories count as earned valueOther activities in the project are considered useful only to the degree that they support progress on epics and user stories

Milestone Earned value

Epics not started on 0%

Epics ready for solution description (PMS 0) 11 %

User stories ready for construction (PMS 1) 31 %

User stories ready for approval (PMS 2) 86 %

User stories in production (PMS 3) 100%

Analysis of Needs

Approvalphase

Detailed planningAnalysis and design

Testing Development

Progress

Iterative construction phase

Cg1

CgnCg2

PMS 0Epics ready for analysis

SolutionDescription

PMS 1User stories ready for construction

-

PMS 2User stories ready for approval

PMS 3User stories in production

Page 14: Earned Value in Agile: The Definition of Done in Agile - Kjetil Strand

20.06.2011 • © PROMIS AS 14

Control gates verify that user stories are ‘Done’

• When approved of in the control gate, we may cash in 86% of the budgeted value of the user story (according to this implementation of the estimation model)

• User stories not approved of, are not cashed in• These user stories remain on EV = 31% of budgeted value, together with other

user stories still in construction• These user stories are returned to the product backlog and prioritized for the

ongoing or future sprints• Most commonly, the team will commit to deliver these user stories in the

ongoing sprint, in addition to the commitment from their sprint planning• When passing the control gate, only the approval phase and system

implementation remain – these activities are estimated to 14% of project cost (according to this implementation of the estimation model)

Page 15: Earned Value in Agile: The Definition of Done in Agile - Kjetil Strand

20.06.2011 • © PROMIS AS 15

The framework is applied in a large system development project• A project in the Norwegian public sector• Duration 2008 – 2012, worth more than 100 MILL €• 3 vendors, 13 parallell sprint teams• The execution model in this project is based on the PS2000 agile contracting

standard• The framework has been a partly success, but with some challenges

Page 16: Earned Value in Agile: The Definition of Done in Agile - Kjetil Strand

20.06.2011 • © PROMIS AS 16

Local CPI tends to vary from sprint to sprint

Page 17: Earned Value in Agile: The Definition of Done in Agile - Kjetil Strand

20.06.2011 • © PROMIS AS 17

The last 22 sprints in the aforementioned project

Date Sprint Local CPI

Accum-ulated CPI EAC

14.01.2010 31 1,717 1,072 905 239 41828.01.2010 32 1,239 1,081 900 386 43418.02.2010 33 0,971 1,075 908 533 35710.03.2010 34 1,059 1,074 907 062 51913.04.2010 35 0,803 1,060 910 828 36006.05.2010 36 1,066 1,060 908 928 97427.05.2010 37 0,843 1,051 912 736 25817.06.2010 38 0,762 1,040 918 163 24810.08.2010 39 0,545 1,009 931 881 30330.08.2010 40 0,520 0,994 939 354 71920.09.2010 41 0,254 0,967 953 541 64214.10.2010 42 1,491 0,992 934 825 41809.11.2010 43 1,275 1,001 929 130 55630.11.2010 44 0,625 0,990 935 510 85321.12.2010 45 1,401 1,002 949 578 12313.01.2011 46 0,823 0,997 953 357 00902.02.2011 47 1,008 0,998 961 012 90602.03.2011 48 1,307 1,006 955 300 37817.03.2011 49 0,732 0,999 959 641 41608.04.2011 50 1,029 1,000 957 193 63506.05.2011 51 0,700 0,992 962 920 38826.05.2011 52 1,399 1,002 955 401 148

Page 18: Earned Value in Agile: The Definition of Done in Agile - Kjetil Strand

20.06.2011 • © PROMIS AS 18

Pros & Cons of the presented framework

On the one hand… On the other…• The framework is easy to

implement and maintain• No special tools are needed:

• Budgeted hours on epics and user stories

• Issue tracking system like Jira to provide the status of epics and user stories after each sprint

• A time tracking system to gather the actual worked project hours on a weekly basis

• Robust enough to provide the information needed on project progress

• During sprints 37 - 41 from the previous slide, the local CPI deteriorated considerably

• This was mainly due to a prolonged approval phase of the largest release in the project

• Large variations in local CPI (and because of this, in the EAC), may be hard to communicate to the steering committee