earned value analysis - eva

29
AACE International 1265 Suncrest Towne Centre Drive Morgantown, WV 26505‐1876 USA. Technical Paper for CCC Examination A Technical Paper is submitted to AACEI in partial fulfillment of the requirements for recognition as Certified Cost Consultant. Earned Value Analysis – EVA A Project Management Tool Ahmed Bin Ali Bamasdoos Candidate Constituent Number 66828 (Exam Calendar 8 th March, 2012) Date: 2 nd January, 2012

Upload: ahmed-bamasdoos

Post on 18-Jul-2015

209 views

Category:

Engineering


5 download

TRANSCRIPT

I  

   

AACE International 1265 Suncrest Towne Centre Drive Morgantown, WV 26505‐1876 USA.    Technical Paper for CCC Examination A Technical Paper is submitted to AACEI in partial fulfillment of the requirements for recognition as Certified Cost Consultant. 

   Earned Value Analysis – EVA 

A Project Management Tool   

    

Ahmed Bin Ali Bamasdoos  

Candidate Constituent Number 66828 (Exam Calendar 8th March, 2012) 

  

Date: 2nd January, 2012  

 

 

Earned Value Analysis ‐ EVA    

II  

 

Table of Contents 

List of Tables & Figures………………………………….………………………………………………………………..……III 

Abstract…………………………………………..…………………………………………….........................................IV 

1. Introduction…………………………………………………………………………………………………….……..……....1   

2. EVM History, Rewards & Recognitions………………………………………………………..……………….……2 

3. EVM Objectives…………………………………………………………………………………………….…………….……3 

4. What is EVM .......................................................................................................................3 

5. Why use EVM......................................................................................................................3 

6. EVM Advantages & Disadvantages………………………….……………………………………….……………….4 

7. Earned Value Analysis EVA Presentation, Definitions & Explanation 

7.1. EVM Definitions……………………………………………………………………….……………………………..……….5 

7.2. Earned Value Analysis (EVA)……………………………………………………………………………..……………..5 

7.3. EVA Terminology……………………………………………………………………………………………………………..6 

7.4. EVA Formulas & Interpretation………………………………………………………………………………………..7 

7.5. EVA Key Dimension & Other Elements……………………………………………………………………………..8 

7.5.1 Planned Value (PV)……………………………………………………………………………………………………………8 

7.5.2 Earned Value (EV)……………………………………………………………………………………………………………..9 

7.5.3 Actual Cost (AC)…………………………………………………………………………………………………………………10 

7.5.4 Schedule Variance (SV)…………………………………………………………………………………………………....11 

7.5.5 Cost Variance (CV)…………………………………………………………………………………………………………….12 

7.5.6 Schedule Performance Index (SPI)…………………………………………………………………………………...12 

7.5.7 Cost Performance Index (CPI)…………………………………………………………………………………………..13 

7.5.8 Budget at Completion (BAC) …………………………………………………………….……………………………...13 

Earned Value Analysis ‐ EVA    

III  

7.5.9 Estimate at Completion (EAC)…………………………………………………………………………….……………..13 

7.5.10  Estimate to Completion (ETC)………………………………………………………………………….….…………….14 

7.5.11  Variance at Completion (VAC)……………………………………………………………………….………………….15 

8. Illustrative explanation of Earned Value Analysis……………………………………….…….…….………....15 

8.1 Calculation of Variations (SV & CV)…………………………………………………………………….……………………16 

8.2 Calculation of Variations % (SV % & CV %)……………………………………………………….……………….…….16 

8.3 Calculation of Index (SPI & CPI)…………………………………………………………………………………………......17 

8.4 Calculation of Forecast (EAC, BAC, ETC, VAC & TCPI)………………………………………..……………………..18 

9. Earned Value Analysis (EVA) Graphical Presentation 

9.1. EVA “ Unde Budget  & Behind Schedule”. ………………………………………………………….…….…………..19 

9.2. EVA “Over Budget & Behind Schedule”………………………………………………………………….….…………..20 

9.3. EVA “Under Budget & Ahead Schedule”………………………………………………………………….….…………20 

9.4. EVA “Over Budget & Ahead Schedule”………………………………………………………………………….…….…21 

10. Conclusion……………………………………………………………………………………………………………….……..22 

11. Summary………………………………………………………………………………………………………………….……..23 

12. Bibliography & References……………………………………………………………………………………….……..24 

 

 

 

 

 

 

 

Earned Value Analysis ‐ EVA    

IV  

 

List of Tables 

Table 1.1: Earned Value Analysis Terminology…………………………………………………………………..………6 

Table 1.2: Earned Value Analysis Formulas & Interpretation………………………………………………………7  

Table 2.1: EVA KEY DIMENSION (PV, EV & AC) table for a project ABC………………………………….…. 15 

Table 2.2: Calculation of Variations (Schedule Variance & Cost Variance) for Project ABC………...16 

Table 2.3: Calculation of Index (SPI & CPI) for Project ABC…………………………………………………….….17 

Table 2.4: Calculation of Forecast (EAC, BAC, ETC, VAC & TCPI) for Project ABC…………….…………..18  

 

List of Figures 

 

  Figure 1.1: Cumulative PV Curve for Project XYZ…………………………………………………………….……..9 

  Figure 1.2: Cumulative PV vs. EV Curves for Project XYZ………………………………………………………..10 

  Figure 1.3: Cumulative PV vs. EV vs. AC Curves for Project XYZ……………………………………………..11 

  Figure 2.1: Cumulative Curves for PV, EV, AC & EAC. (Under Budget & Behind Schedule)………19 

  Figure 2.2: Cumulative Curves for PV, EV, AC & EAC. (Over Budget & Behind Schedule)………...20 

  Figure 2.3: Cumulative Curves for PV, EV, AC & EAC. (Under Budget & Ahead Schedule)……….20 

  Figure 2.4: Cumulative Curves for PV, EV, AC & EAC. (Over Budget & Ahead Schedule)………….21 

Earned Value Analysis ‐ EVA    

V  

 

Abstract 

“Earned Value Management  (EVM)” helps the project team to measure project performance.  It  is a 

systematic project management process used to find variances in projects based on the comparison of 

worked performed and work planned. EVM is used on the cost and schedule control and can be very 

useful  in project forecasting. The project baseline  is an essential component of EVM and serves as a 

references point for all EVM related activities.  

          Earned Value Analysis is a best method of calculation to integrates cost, 

schedule and scope and can be used to forecast future performance and project completion dates. It 

is an “early warning” program / project management  tool  that enable project  team  to  identify and 

control the problems before they become insurmountable, it allows projects to be managed better – 

on time, on budget. 

Key Words:  (Earned Value Analysis), (Project Control), (Project Management) 

 

 

 

 

   

Earned Value Analysis ‐ EVA    

1  

 

1. Introduction 

 “Earned  Value  Management  (EVM)”  is  a  program  management  technique  that  used  “work  in 

progress”  to  indicate  what  will  happened  to  work  in  the  future.  EVM  is  an  enhancement  over 

traditional  accounting  progress  measure.  Traditional  methods  focus  on  planned  accomplishment 

(expenditure)  and  actual  cost.  Earned  Value  Analysis  goes  one  step  further  and  examines  actual 

accomplishment. This gives  to project  team a greater  insight  into potential  risk areas. With  clearer 

picture, project team can create risk mitigation plans based on the actual cost, schedule and technical 

progress  of  the  work,  it  is  an  “early  warning”  program/project  management  tool  that  enables 

managers to identify and control problems before they become insurmountable. It allows projects to 

be managed better – on time on budget. EVM System is not a specific system or tool set, but rather, a 

set of guidelines that guide a company’s management control system. 

 

   

Earned Value Analysis ‐ EVA    

2  

 

2. EVM History, Reward & Recognition 

Ref: DoD USA, “Earned Value Management Implementation” Guide Oct, 2006”,  Signed by “KEITH D. ERNST” Director Defense Contract Management Agency). 

 

According to the NASA headquarters library, the first version of Earned Value Management was 

developed by the Department of Defense (DoD) USA in 1967, to established the Cost/Schedule 

Control System Criteria (C/SCSC) to standardize contractor requirements for reporting cost and 

schedule performance on major contracts. Since 2005, EVM has been a part of general federal project 

risk management. Today EVM is a mandatory requirement of the US government. The Office of 

Management and Budget (OMB). Promotes use of EVM as a preferred performance‐based 

management system to manage software projects. EVM is also used in the private sector by 

companies in a variety of industries, consulting firms and educational establishments.  

Some of the most well known organizations practicing EVM are: 

• NASA 

• Project Management Institute (PMI) 

• Society of Cost Estimating and Analysis 

• Federal Acquisition Institute 

•  Acquisition Management (UK) 

Based  on  reports  of  the  General  Accounting  Office  (GAO)  in  August  1996  a  memorandum  of 

understanding  concerning  common  cost  and  schedule management  for  acquisitions was  signed by 

Australia, Canada, and the Unites States. This gives  international recognition to EVM worldwide. The 

NASA  Office  of  Chief  Engineer  is  sponsoring  an  “Earned  Value  Management  AVM  Award  of 

Excellence” to present at the NASA PM Challenge Conference.  

 

Earned Value Analysis ‐ EVA    

3  

 

3. EVM Objective 

The Main objective  for  EVM  is  tool  to  “measuring  a project’s progress  at  any  given point  in  time, 

forecasting it’s a completion date and final cost”, and analyzing variances in the schedule and budget 

as  the  project  proceeds.  It  compares  the  planned  amount  of  work  with  what  has  actually  been 

completed, to determine if the cost, schedule, and work accomplished are progressing in accordance 

with the plan. As work is completed, it is considered as “Earned”.  

 

4. What is Earned Value Management (EVM)? 

• Earned  Value  Management  (EVM)  is  an  incremental  methodology  for  measuring  project 

performance  by  determining  cost  and  schedule  performance  of  a  project  by  comparing 

“planned” worked with “accomplished” work in terms of the dollar value assigned to the work, 

and determining the need to recommend corrective actions. 

• EVM is a “Management Tool” which provides a snapshot of project performance at a point in 

time. And compares where the project is now with previous work accomplished and where the 

project was planned to be. And also it serves as an “early warning” system to detect deficient 

or endangered progress. 

 

5. Why use Earned Value Management (EVM)? 

• When you manage project performance by just comparing planned to actual results, you could 

easily be on time but overspend according to your plan. 

Earned Value Analysis ‐ EVA    

4  

• Using EVM is a better method because it integrates cost, time and work done and can be used 

to forecast future performance and project completion dates and costs. 

• Earned value analysis results should be a major part of project reporting. 

• EVM is the basis for course correction and will lead to new forecasted completion cost, change 

requests and other items that will need to communicate. 

• EVM provides an accurate picture of contract status and supports mutual goals of contractors 

and customer. 

 

6. EVM Advantages & Disadvantages: 

S.No.  Descriptions  EVM Advantages  EVM Disadvantages 

1 VARIANCE ANALYSIS 

Shows Current Status in term of Cost & Schedule. 

Time consuming and requires experienced effort to measure and analyze the performance. 

2  FORECASTING It enables predictions of cost at completion and completion date. 

It depends on reliable measurements that can be difficult to achieve for some cost types. 

3  EFFICIENCY 

Provides performance indices identifying area under of ever performing and enquiring corrective action. 

Past performance is not necessarily an indication of future performance.

4 ESTIMATING ACCURACY 

Provides feedback of the actual performance against the baseline estimates 

It does not take into account risks and uncertainties 

5  DECESIONS  Provides triggers for escalating problems and helps in taking sudden decisions.  

It Requires a compatible cost tracking system and it will be never 100% accurate. So sometimes decision can take wrongly. 

 

 

Earned Value Analysis ‐ EVA    

5  

 

7. Earned Value Analysis Definitions, Presentation & Explanation 

 

7.1    Earned Value Definitions: (Ref: “Projectsmart.co.uk” By Duncan Haughty, PMP) 

NASA defines it as, "An integrated management control system for assessing, understanding 

and quantifying what a contractor or field activity is achieving with program dollars. EVM 

provides project management with objective, accurate and timely data for effective decision 

making." 

  Englert and Associates, Inc define it as, "A method for measuring project performance. It 

compares the amount of work that was planned with what was actually accomplished to 

determine if cost and schedule performance is as planned." 

7.2    Earned Value Analysis (EVA) 

Earned Value Analysis is an industry standard method of measuring a project’s progress at any 

given point in time, forecasting its completion date and final cost, and analyzing variances in 

the schedule and budget as the project proceeds. It compare the planned amount of work with 

has actually been completed, to determine if the cost, schedule and work accomplished are 

progressing in accordance with the plan. As work is complete, it is considered as “Earned”. 

 

 

Earned Value Analysis ‐ EVA    

6  

 

7.3    Earned Value Analysis Terminology – Table 1.1        (Ref: “PMI PMstudy Targeting Success” PMstudy.com) 

Acronym  Term  Description PV  Planned Value  The authorized budget assigned to the schedule 

work to be accomplished for a schedule activity or WBS component. 

 (BCWS)  (Budget Cost of Work Scheduled) 

EV  Earned Value  The value of work performed expressed in terms of the approved budget assigned to that work for a schedule activity or WBS component. 

(BCWP)  (Budget Cost of Work Performed) 

AC Actual Cost (Actual Budget 

Work Performed) Actual Cost of work completed that is incurred and recorded 

SV  Schedule Variance A measure of the schedule performance on a project. (Negative SV: Behind the Schedule) (Positive SV: Ahead of schedule) 

CV  Cost Variance A measure of the cost performance on a project. (Negative CV: Over Budget) (Positive CV: Under Budget) 

CPI  Cost Performance Index A measure of cost efficiency on a project. The value got for 1 $ of actual cost 

SPI  Schedule Performance Index A measure of schedule efficiency on a project. Progress as a % of Planned Progress 

EAC  Estimate at Completion The expected total cost when the defined scope of work will be completed. 

     

1. Original estimated assumptions no longer valid 2. Current variance are a typical, similar variances will not occur in the future 3. Current variances are typical, Similar variances may occur in future 4. EAC taking both CPI and SPI into account 

BAC  Budget at Completion  Budget for the whole project 

ETC  Estimate to Completion From a particular point in time, how much more time is required to complete the project 

VAC  Variance at Completion  Over or Under Budget 

TCPI To Complete Performance 

Index The work remaining divided by the funds remaining,  

      1. Equation Expressed in terms of EAC: 

      2. Equation Expressed in terms of BAC: 

 

 

Earned Value Analysis ‐ EVA    

7  

 

7.4    Earned Value Analysis Formulas & Interpretation – Table 1.2        (Ref: “PMI PMstudy Targeting Success” PMstudy.com) 

Acronym  Formula  Analysis PV 

  What is the estimated value of the work planned to be done?  (BCWS) 

EV   

What is the estimated value of the work actually accomplished? (BCWP) 

AC     What is the actual cost incurred? 

SV  EV – PV NEGATIVE is behind the Schedule (or) POSITIVE is ahead the Schedule. 

CV  EV – AC NEGATIVE is over the budget (or) POSITIVE is under the budget. 

CPI  EV/AC = BAC/EAC LESS THAN 1.0 is over the budget (or) GREATER THAN 1.0 is under the budget. 

SPI  EV/PV LESS THAN 1.0 is behind the Schedule (or) GREATER THAN 1.0 is ahead the Schedule. 

EAC       

Note: There are many ways to calculate EAC 

 

AC + ETC Actually Cost plus new estimate cost for remaining work. Used when original estimate was fundamentally flawed. 

AC + BAC – EV Actual cost plus remaining budget. Used when current variances are atypical. 

AC + {(BAC ‐ EV)/CPI} OR BAC/CPI Actual cost plus remaining budget modified by performance. Used when current variances are atypical. 

AC + {(BAC ‐ EV)/(CPI*SPI) Actual cost plus remaining budget modified by performance. While both taken into account CPI & SPI 

BAC  EAC * CPI  How much did you BUDGET for the TOTAL PROJECT 

ETC  EAC – AC  How much more will the project Cost? 

VAC  BAC – EAC  How much over budget will we be at the end of project? 

TCPI     

  PROJECTED VALUE LESS THAN 1.0 is Over the Budget (or) PROJECTED VALUE GREATER THAN 1.0 is Under the Budget. 

(BAC‐EV) / (EAC ‐ AC) 

(BAC‐EV) / (BAC ‐ AC) 

Earned Value Analysis ‐ EVA    

8  

 

7.5   Earned Value Analysis Key Dimensions  

EVA develops and monitors three key dimensions for each work package and control account: 

7.5.1 BCWS = Planned Value (PV) 

7.5.2  BCWP = Earned Value (EV) 

7.5.3  ACWP = Actual Cost (AC) 

As of first quarter of year 2002 there is shifting in using the below terms as above. 

7.5.1    Budgeted Cost of Work Schedule (BCWS) 

7.5.2    Budgeted Cost of Work Performed (BCWP)   

7.5.3    Actual Cost of Work Performed (ACWP)         

 

7.5.1 Planned Value (PV) or (BCWS) (Ref: “PMI PMBOK GUIDE” Fourth Edition) 

Planned value (PV) is the authorized budget assigned to the work to be accomplished for 

an activity or work breakdown structure component. It includes the detailed authorized 

work, plus the budget for such authorized work, allocated by phase over the life of the 

project. The total of the PV is sometimes referred to as the performance measurement 

baseline (PMB). The total PV for the project is also known as Budget at Completion (BAC). 

Planned Value is usually charted showing the cumulative resources budgeted across the 

project schedule. Figure 1.1 shows the Planned Value S‐curve for Project XYZ. 

 

 

Earned Value Analysis ‐ EVA    

9  

1040

64

96

134

176

220236

256 268284

300

0

50

100

150

200

250

300

350

Jan‐11 Feb‐11 Mar‐11 Apr‐11 May‐11 Jun‐11 Jul‐11 Aug‐11 Sep‐11 Oct‐11 Nov‐11 Dec‐11

P…

 

 

   Figure 1.1 ‐ Cumulative Planned Value for Project XYZ.  

7.5.2 Earned Value (EV) or (BCWP) (Ref: “PMI PMBOK GUIDE” Fourth Edition) 

Earned value (EV) is the value of work performed expressed in terms of the approved 

budget assigned to the work for an activity or work breakdown structure component. It is 

the authorized work that has been completed, plus the authorized budget for such 

completed work. The EV being measured must be related to the PV baseline (PMB), and 

the EV measured cannot be greater than the authorized PV budget for a component. The 

term EV is often used to describe the percentage completion of a project. Project 

Managers monitor EV, both incrementally to determine current status and cumulatively to 

determine the long term performance trends. Figure 2.2 Shows the Earned Value for the 

project XYZ at the month of July 2011 mark, and indicates that less work executed than 

planned has been accomplished. 

Duration in Months

PROJECT XYZ – Planned Value

Data Date 

Earned Value Analysis ‐ EVA    

10  

10

4064

96

134

176

220236

256268

284300

176

0

50

100

150

200

250

300

350

Jan‐11 Feb‐11 Mar‐11 Apr‐11 May‐11 Jun‐11 Jul‐11 Aug‐11 Sep‐11 Oct‐11 Nov‐11 Dec‐11

PV

EV

 

 

 

 Figure 1.2 ‐ Cumulative Planned Value and Earned Value for Project XYZ.  

7.5.3 Actual Cost (AC) or (ACWP) (Ref: “PMI PMBOK GUIDE” Fourth Edition) 

Actual  Cost  (AC)  is  the  total  cost  actually  incurred  and  recorded  in  accomplishing work 

performed  for  an  activity  or work  breakdown  structure  component.  It  is  the  total  cost 

incurred  in accomplishing  the work  that  the EV measured. The AV has  to  correspond  in 

definition  to whatever was budgeted  for  in  the PV and measured  in  the EV.  (e.g. direct 

hours only, direct costs only, or all costs including indirect costs). The AC will have no upper 

limit; whatever  is spend to achieve the EV will be measured. Figure 1.3 shows the Actual 

Cost for Project XYZ at the month of July, 2011 mark, and  indicates that the organization 

has spent  less  than  it planned  to spend,  to achieve  the work performed  to date but  it  is 

more than work executed. 

 

Duration in Months

PROJECT XYZ – Planned Value & Earned Value 

Data Date 

Earned Value Analysis ‐ EVA    

11  

1040

64

96

134

176

220236

256 268284

300

176200

0

50

100

150

200

250

300

350

Jan‐11 Feb‐11 Mar‐11 Apr‐11 May‐11 Jun‐11 Jul‐11 Aug‐11 Sep‐11 Oct‐11 Nov‐11 Dec‐11

PV

EV

   

  Figure 1.3 ‐ Cumulative Planned Value and Earned Value for Project XYZ.  

7.5.4 Schedule Variance (SV) (Ref: “PMI PMBOK GUIDE” Fourth Edition) 

Schedule Variance (SV) is a measured of schedule performance on a project. It is equal to 

the earned value (EV) minus the planned value (PV). The EVM schedule variance is a useful 

metric  in  that  it  can  indicate  a  project  falling  behind  its  baseline  schedule.  The  EVM 

schedule variance will ultimately equal zero when the project is completed because all the 

planned values will have been earned. EVM SVs are best used  in conjunction with critical 

path methodology (CPM) scheduling and risk management. Equation: SV = EV – PV 

 

 

 

 

Duration in Months

PROJECT XYZ – Planned & Earned Values & Actual Cost 

Data Date 

Earned Value Analysis ‐ EVA    

12  

 

7.5.5 Cost Variance (CV) (Ref: “PMI PMBOK GUIDE” Fourth Edition) 

Cost Variance (CV) is a measured of cost performance on a project. It is equal to the earned 

value (EV) minus the actual cost (AC). The cost variance at the end of the project will be the 

difference between the budget at completion (BAC) and the actual amount spent. The EVM 

CV  is particularly critical because  it  indicates  the  relationship of physical performance  to 

the costs spent. Any negative EVM CV is often non‐recoverable to the project.  

Equation: CV = EV ‐ AC 

The SV and CV can be converted to efficiency indicators to reflect the cost and schedule 

performance of any project for comparison against all other projects or within a portfolio 

of projects. The variances and indices are useful for determining project status and 

providing a basis for estimating project cost and schedule outcome. 

 

7.5.6 Schedule Performance Index (SPI) (Ref: “PMI PMBOK GUIDE” Fourth Edition) 

Schedule Performance Index (SPI) is a measure of progress achieved compared to progress 

planned on a project. It is sometimes used in conjunction with the cost performance index 

(CPI) to forecast the final project completion estimates. An SPI value less than 1.0 indicates 

less work was completed  than was planned, An SPI greater  than 1.0  indicates  that more 

work  was  completed  than  was  planned.    Since  the  SPI measure  all  project  work,  the 

performance on the critical path must also be analyzed to determine whether the project 

Earned Value Analysis ‐ EVA    

13  

will finish ahead of or behind its planned finish date. The SPI is equal to the ration of the EV 

to the PV. Equation: SPI = EV / PV. 

 

7.5.7 Cost Performance Index (CPI) (Ref: “PMI PMBOK GUIDE” Fourth Edition) 

Cost Performance  Index  (CPI)  is a measure of  the value of work completed compared  to 

the  actual  cost or progress made on  the project.  It  is  considered  the most  critical  EVM 

metric and measure  the cost efficiency  for  the work complete. A CPI value  less  than 1.0 

indicates a cost overran for work completed. A CPI value greater than 1.0 indicates a cost 

under  run  of  performance  to  date.  The  CPI  is  equal  to  the  ratio  of  the  EV  to  the  AC.  

Equation:  CPI = EV/AC. 

 

7.5.8 Budget at Completion (BAC)  

Budget at Completion (BAC) is the sum of the entire budget value that has been previously 

established for the work to be performed on a project, or on components within a project 

such as schedule activity or WBS component. The budget at completion also called as the 

total planned value of the project. 

Equation: BAC = EAC * CPI 

 

7.5.9 Estimate at Completion (EAC)  

Estimate at Completion (EAC) is an input output device that is used to measure the 

expected total cost of a particular schedule activity, a WBS component or of the project as 

a whole. It is a forecast of most likely total project costs based on project performance and 

Earned Value Analysis ‐ EVA    

14  

risk quantification. At the start of the project BAC and EAC will be equal. EAC will vary from 

BAC only when AC varies from PV. Most common forecasting techniques are some of: 

7.5.9.1   EAC = Actual cost to date plus new estimate for all remaining work. This 

approach is most often used when past performance shows that the original 

estimating assumptions were fundamentally flawed, or they are no longer 

relevant to a change in conditions. 

7.5.9.2   EAC = Actual Cost to date plus remaining budget. This approach is most 

often used when current variances are seen as atypical and the project 

management team expectations are that similar variance will not occur in the 

future. 

7.5.9.3   EAC = Actual Cost to date plus the remaining budget modified by a 

performance factor, Often the cumulative cost performance index (CPI). This 

approach is most often used when current variances are seen as typical of 

future variances 

7.5.9.4   EAC = BAC modified by performance factor, cumulative cost performance 

index (CPI). This approach is most often used when no variances from BAC 

have occurred. 

 

7.5.10 Estimate to Complete (ETC)  

Estimate to Complete the difference between Estimate at Completion (EAC) and Actual 

Cost (AC), this is the estimated additional cost to complete the project form any given 

time.  Equation: ETC = EAC – AC 

Earned Value Analysis ‐ EVA    

15  

 

7.5.11 Variance at Completion  (VAC)  

The difference between Budget at Completion (BAC) and Estimate at Completion (EAC). 

This is the dollar value by which the project will over or under the budget.  

Equation: VAC = BAC – EAC 

 

8 Illustrative explanation of Earned Value Analysis. 

The information given below for Project ABC cumulative PV, EV & AC and project duration is 12 months. 

Earned Value Analysis (PV, EV & AC) for Project ABC “As of July, 2011 – Table 2.1 

DESCRIPTION Jan‐11 

Feb‐11 

Mar‐11 

Apr‐11 

May‐11 

Jun‐11 

Jul‐11 

Aug‐11 

Sep‐11 

Oct‐11 

Nov‐11 

Dec‐11 

DIM

ENSIONS  Planned Value(PV)  10  50  114  210  344  520  740 980  1,236  1,504 1,788 2,000

Earned Value (EV)  8  45  110  200  310  490  610               

Actual Cost (AC)  11  48  112  205  320  505  650               

 

Planned Value (PV) = 2,000 

Earend Value (EV) = 610 

Actual Cost (AC) = 650 

EVA Data Date = July, 2011 

 

 

 

 

Earned Value Analysis ‐ EVA    

16  

 

8.1 Calucuation of Variations: 

a. Scheduel Variance (SV) = Earned Value ‐ Planned Value (AV ‐ PV)  

b. Cost Variance (CV) = Earned Value ‐ Actual Cost (EV ‐ AC)  

 

Earned Value Analysis (SV & CV) for Project ABC “As of July, 2011 – Table 2.2 

DESCRIPTION  Formula  Jul‐11 

VARIATIONS 

Schedule Variance (SV)  

=610‐740 ‐130 

Cost Variance (CV)  =610‐650  ‐40 

 

 

8.2    Calcualation of Varinces %: 

a. Schedule Variance SV%  =  SV/PV  =  ‐130/740 = 18% Behind the Schedule.  

b. Cost Variance CV%  =  CV/EV = ‐40/610 = 7% Overrun  

The above table 2.2 shows a clear picture of the actual status of the work done and cost. Currently 

shows the schedule variance of $‐130. It was sheduled to be completed $740 of work, and have only 

completed for $610.  In addition, the work that was completed for $610 has cost more than we had 

planned $650, creating a cost variance of $‐40.  It means project  is running   “Behind the Schedule by 

18%  & Over the Budget by 7%”. 

 

 

 

Earned Value Analysis ‐ EVA    

17  

 

8.3  Calucuation of Index: 

a. Scheduel Performance Index (SPI) = Earned Value/Planned Value (EV/ PV) 

b. Cost Performance Index (CPI) = Earned Value/Actual Cost (EV/AC)  

 

Earned Value Analysis (SPI & CPI) for Project ABC “As of July, 2011 – Table 2.3 

DESCRIPTION  Formula  Jul‐11 

INDEX

  Schedule Performance Index (SPI)  =610/740  0.82 

Cost Performance Index (CPI)  =610/650  0.94 

 

 The Above table 2.3 shows a clear index for actual wok done status based on time and cost. Currently 

SPI  is 0.82. as it is less than 1.0 means the project is running “Behind the Schedule”. In addition, the 

CPI is 0.94. as it is also less than 1.0 means the project running “Over the Budget”. 

 

8.4  Calucuation of Forecast: 

a. Estimate at Completion (EAC) =  AC + {(BAC ‐ EV)/(CPI*SPI) 

b. Budget at Completion (BAC) = EAC * CPI 

c. Estimate to Complete (ETC) = EAC – AC 

d. Variance at Completion (VAC) = BAC – EAC 

e. Total Complete Performance Index (TCPI) = (BAC‐EV) / (EAC ‐ AC) 

 

 

 

Earned Value Analysis ‐ EVA    

18  

 

Earned Value Analysis (EAC, BAC, ETC, VAC & TCPI) for Project ABC “As of July, 2011) – Table 2.4 

DESCRIPTION  Formula  Jul‐11 

FORE

CAST 

Estimate at Completion (EAC)  =650+(2000‐610)/(0.94*0.82)  2,447 

Budget at Completion (BAC)  =2,447*0.94  2,296 

Estimate to Complete (ETC)  =2,477‐650  1,797 

Variance at Completion (VAC)  =2,296‐2,447  ‐151 

Total Complete Performance Index (TCPI)  =(2,296/610)/(2,447‐650)  0.94 

 

The above table 2.4 currently it shows the following: 

a.  “Estimate at Completion”  shows $2,447, where as it was scheduled based on time and cost to 

be completed the work for $2,000.  

b. The “Budget at Completion” shows $2,296 where as it was budgeted based on time & cost to 

be compelted the work for $2,000.  

c. The “Estimate to Complete” shows as follows: 

• Cost Based: $1,797 is the projected cost for future work to be executed. 

• Time Based: (BAC/SPI)/(BAC/12) = 14.5 Months will be total project duration. 

d. The “Variance at Completion” shows $‐151 as over budgeted at end of project. 

e. The “Total Complete Performance Index” shows 0.94. as  it  is  less than 1.0 this proejct will be 

overbudget at end fo the project. 

Based on the above calculations, Project ABC will be cost $2,447 & 14.5 Months to complete. 

 

Earned Value Analysis ‐ EVA    

19  

 

9   EVA Graphical presentation for common scenarios as following: 

9.1 EVA “ Unde Budget  & Behind Schedule”.  

9.2 EVA “Over Budget & Behind Schedule”. 

9.3 EVA “Under Budget & Ahead Schedule”. 

9.4 EVA “Over Budget & Ahead Schedule”. 

 

9.1 EVA “Under Budgt & Behind Schedule”. 

 Figure 2.1 – Cumulative Curves for PV, EV, AC & EAC. (Under Budget & Behind Schedule) 

 

 

 

 

 

 

 

$2,000PV

$1,800 AC

$1,600 EV

$1,400EAC

$1,200

$1,000

$800

$600

$400

$200

$0 Jan‐11 Feb‐11 Mar‐11 Apr‐11 May‐11 Jun‐11 Jul‐11 Aug‐11 Sep‐11 Oct‐11 Nov‐11 Dec‐11 Jan‐12 Feb‐12 Mar‐12

Resources

EXECUTED WORK PROJECTED WORK

Duration in Months

X

SlipagePlanned Vs Projected 

Completion

Earned Value Analysis ‐ EVA    

20  

 

9.2     EVA “Over Budget & Behind Schedule”. 

 Figure 2.2 – Cumulative Curves for PV, EV, AC & EAC. (Over Budget & Behind Schedule)  

 

 

9.3   EVA  “Under Budget & Ahead Schedule”.  

 Figure 2.3 – Cumulative Curves for PV, EV, AC & EAC. (Under Budget & Ahead Schedule) 

$2,500PV

$2,200 AC

$2,000 EV

$1,800EAC

$1,600

$1,400

$1,200

$1,000

$800

$600

$400

$200

‐      Jan‐11 Feb‐11 Mar‐11 Apr‐11 May‐11 Jun‐11 Jul‐11 Aug‐11 Sep‐11 Oct‐11 Nov‐11 Dec‐11 Jan‐12 Feb‐12 Mar‐12

Duration in Months

Resources

Completion Variation

EXECUTED WORK PROJECTED WORK

X

Cost Variation

$2,000PV

$1,800 AC

$1,600 EV

$1,400EAC

$1,200

$1,000

$800

$600

$400

$200

$0 Jan‐11 Feb‐11 Mar‐11 Apr‐11 May‐11 Jun‐11 Jul‐11 Aug‐11 Sep‐11 Oct‐11 Nov‐11 Dec‐11

EXECUTED WORK PROJECTED WORK

Duration in Months

X

Cost Variation

Earned Value Analysis ‐ EVA    

21  

  

 9.4   EVA “Over Budget & Ahead Schedule”. 

 Figure 2.4 – Cumulative Curves for PV, EV, AC & EAC. (Over Budget & Ahead Schedule) 

 

Explaination: 

In the above figures commonly represented the curves as follows: 

• Green curve shown as Planned Value (PV) form the project start to finish dates 

• Blue curve showsn as Actual Cost (AC) from the project start to data date end of July, 2011. 

• Black cuve shown as Earned Value (EV) from the project start to data date end of july, 2011. 

• Red Curve shown as Esimate at Completeion (EAC) future forecast from the data date to end of 

project 

• Figure 2.1:  Total cost of the project will be equal to BAC & Behind the Schedule & its variances. 

• Figure 2.2:  Total cost of the project will be more than BAC & Behind the Schedule & its variances. 

• Figure 2.3:  Total cost of the project will be equal to BAC & ahead the Schedule & its variances. 

• Figure 2.4: Total cost of the project will be more than BAC & ahead the schedule & its variances. 

___________________________________________________________________________________ 

$2,500PV

$2,200 AC

$2,000 EV

$1,800EAC

$1,600

$1,400

$1,200

$1,000

$800

$600

$400

$200

$0 Jan‐11 Feb‐11 Mar‐11 Apr‐11 May‐11 Jun‐11 Jul‐11 Aug‐11 Sep‐11 Oct‐11 Nov‐11 Dec‐11

EXECUTED WORK PROJECTED WORK

Resources

Completion Variation

Duration in Months

X

Cost Variation

Earned Value Analysis ‐ EVA    

22  

 

10. Conclusion: 

The simple analysis methods described in the paper illustrate one beneficial use of earned value data, 

evaluating the reasonableness of the contractors’s Estmate at Completeion.  EVA is a better mthod of 

ptorgram/project management  beacause  it  intigrates  cost  and  schedule,  can  be  used  to  forecast 

future  performace  and  prject  compelteion  dates.  It  is  an  “early  warning”  program/project 

management  tool  that  enables managers  to  identifly  and  control  problems  before  they  become 

insurmountable. It allwos projects to be amanged better on tme, on budtget. 

  The cost management report prepared from arned value data can provide project managers with 

valuable insight into cost and scheduel status of their project. When used properly, the variances and 

performances  indices  can  help  a  manager  focus  attention  on  merging  probleums.  The  cost 

management reprot is not a financail reprot, it’s a tool for proejct managers. 

 

 

 

 

 

 

 

 

 

Earned Value Analysis ‐ EVA    

23  

 

11. Summary: 

The Eearned Value Analysis is a management tool to measure the current performance of any project 

in terms of “Cost & Schedule”.  And also it helps in forecasting the remaining work in terms of “Cost & 

Schedule”.  EVA  is  a  usefull  tool  to  the  risk management,  it  shows  the  current  variances  and  gives 

“early warning”  to  the  project managers  for  the  future  risks  and  also  helps  in  taking  prompt  and 

accurate decessions to execute the remaining the work “under the budget & behind the schedule” or 

“On time & On Budget”. Its three key dimension are Planned Value, Earned Value & Actual Cost shows 

current status of the project by comparing PV v/s   EV v/s AC. Hence EVA gives the right direction to 

the project manageres to manage the project and meets the dealines in terms of “Cost & Schedule”.  

 

 

 

 

 

 

 

 

 

 

 

Earned Value Analysis ‐ EVA    

24  

 

 12. Bibliography / References 

1. Department of Defense. “Earned Value Management Implementation” Guide Oct, 2006  Signed by “KEITH D. ERNST” Director Defense Contract Management Agency, by DoD USA   

2. Practice standard for EARNED VALUE MANAGEMENT ISBN:1‐930699‐42‐5 Published by: PMI Inc. Four Campus Boulevard, Newtown Square, Pennsylvania USA. www.pmi.org 

 

3. A Guide to the “Project Management Body of Knowledge” (PMBOK Guide) 4th Edition,  ISBN: 978‐1‐933890‐51‐7 Published by: PMI Inc. Fourteen Campus Boulevard, Newtown Square, Pennsylvania USA.   

4. PMstudy Targeting Success ‐Project Cost management Guide to Mathematical Question,  Published by: PMI Inc. www.pmstudy.com   

5. Projectsmart.co.uk “ Earned Value Management Explained”  Date of visit (9th Dec, 2011)    

6. Earned Value Management, U.S.A Government NASA Date of visit (9th Dec, 2011)   

7. “http://project‐management‐knowledge.com Date of visit (20th Dec, 2011)   

8. “http://en.wikipedia.org/wiki/Earned_value_management Date of visit (25th Dec, 2011)